JPH0363640B2 - - Google Patents
Info
- Publication number
- JPH0363640B2 JPH0363640B2 JP58217298A JP21729883A JPH0363640B2 JP H0363640 B2 JPH0363640 B2 JP H0363640B2 JP 58217298 A JP58217298 A JP 58217298A JP 21729883 A JP21729883 A JP 21729883A JP H0363640 B2 JPH0363640 B2 JP H0363640B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- compaction
- vibrator
- jack
- detector
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Lining And Supports For Tunnels (AREA)
Description
【発明の詳細な説明】
本発明はシールドトンネル構築の場所打ちコン
クリートの締固め装置に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a compaction device for cast-in-place concrete for constructing shield tunnels.
シールドトンネル構築工法としては従来は一次
覆工、裏込め注入、二次覆工の三工程により構成
される複雑な工法が採用されていたが輓近に到り
上記の工法の欠点を改良し、場所打ちコンクリー
ト打設により1回のコンクリート打設によりトン
ネル覆工をおこなう工法が採用されている。この
場所打ちコンクリートにおいては一度に大量のコ
ンクリートが注入されるのでトンネル工事におけ
るこの覆工コンクリートの締固めはコンクリート
の強度維持ならびに品質上重要な要素となってい
る。 Conventionally, shield tunnel construction has been a complex method consisting of three steps: primary lining, backfill injection, and secondary lining. The tunnel lining is constructed using a single cast-in-place concrete casting method. In cast-in-place concrete, a large amount of concrete is injected at once, so compaction of the lining concrete during tunnel construction is an important factor in maintaining the strength and quality of the concrete.
従来このトンネルにおける覆工コンクリートの
締固めは、その型枠に取付けられたバイブレータ
により行なわれているのが殆んどであり、またそ
の締固め時間も経験的な値が採用されている。従
って(1)型枠の表面付近にのみ締固めが集中するこ
と、(2)充分に締固められたか否かの定量的な把握
が困難であること、などの欠点を有していた。 Conventionally, the compaction of concrete lining in tunnels has mostly been carried out using vibrators attached to the formwork, and empirical values have also been adopted for the compaction time. Therefore, it has disadvantages such as (1) compaction is concentrated only near the surface of the formwork, and (2) it is difficult to quantitatively determine whether or not compaction has been sufficiently achieved.
本発明は、以上のような従来の欠点を改良する
とともに効率のよい締固めをおこない得るコンク
リートの締固め装置を提供することを目的とする
ものであり、その構成は場所打ちコンクリートに
よるシールドトンネルの覆工コンクリートの締固
めに用いられる装置であつて、バイブレータの入
力電流を検知する検知器と、バイブレータジヤツ
キの挿入、引抜き制御をおこなうパワーユニツト
および電磁弁と、上記検知器よりの信号にもとづ
きバイブレータの作動時間の算出およびバイブレ
ータジヤツキによる挿入、引抜きを制御する制御
機構とから構成せられたコンクリートの締固め装
置であり、これを実施例の図面について説明する
と、第1図は装置の構成及び作用をあらわす略断
面および制御のブロツク図であり、1はトンネル
掘削のシールドマシンのスキンプレート、2はト
ンネル覆工の型枠であり3は既に打設が完了した
個所のコンクリート覆工部、4はコンクリート注
入が行なわれたばかりの未締固め部であり、これ
は妻型枠5によりコンクリートがトンネル内部に
流出するのを防止している。第2図はこの妻型枠
5の正面部分図であり妻型枠5の正面部には注入
されたコンクリート締固め用のバイブレータを挿
入するためにその円周に適宜間隔を維持して塞ぎ
板6が取付けられている。塞ぎ板6は例えば硬質
ゴムの如くある程度の強度を有し、且弾性のある
材質にて作られ、第3図の如くその中央部に切込
み7を設けることにより内部に注入されたコンク
リートの流出は充分に防止する強度は有している
が、バイブレータなどの剛性を有する突き棒など
は挿入容易となっている。バイブレータの突き棒
8はこの塞ぎ板6の弾性部の切込み7よりコンク
リートの未締固め部4に挿入される。バイブレー
ターは突き棒8、電動力による発振器9および液
圧または空圧などにより推進および引抜き制御さ
れるバイブレータジヤツキ10により構成され
る。11は電源であり、検知器12を介して発振
器9および計算機構13を介してバイブレータジ
ヤツキ10用パワーユニツト14に電力が供給さ
れる。検知器12は発振器9に送られる電力の電
流値を検知し、この電流信号を計算機構13に送
る。計算機構13は前記の電流信号に基づき電磁
弁15を作動させバイブレータジヤツキ10の推
進および引抜きの制御をおこなうとともに発振器
9の負荷電流値より締固め時間を算出する機構を
有している。 The object of the present invention is to provide a concrete compaction device that can improve the above-mentioned conventional drawbacks and perform efficient compaction. A device used for compacting lining concrete, which includes a detector that detects the input current of the vibrator, a power unit and a solenoid valve that control the insertion and withdrawal of the vibrator jack, and a signal from the above detector. This is a concrete compaction device that is composed of a control mechanism that calculates the operating time of a vibrator and controls insertion and withdrawal by a vibrator jack. 1 and 2 are schematic cross-sectional and control block diagrams showing the operation, in which 1 is a skin plate of a shield machine for tunnel excavation, 2 is a formwork for tunnel lining, 3 is a concrete lining part where pouring has already been completed, Reference numeral 4 indicates an uncompacted area where concrete has just been poured, and the gable formwork 5 prevents the concrete from flowing into the tunnel. Fig. 2 is a partial front view of the end formwork 5, and the front part of the end formwork 5 has a closing plate with an appropriate interval maintained around its circumference in order to insert a vibrator for compacting the poured concrete. 6 is installed. The closing plate 6 is made of a material that has a certain degree of strength and elasticity, such as hard rubber, and has a notch 7 in its center as shown in Figure 3 to prevent the concrete poured inside from flowing out. Although it has sufficient strength to prevent this, it is easy to insert a rigid push rod such as a vibrator. The vibrator thrust rod 8 is inserted into the uncompacted portion 4 of the concrete through the notch 7 in the elastic portion of the closing plate 6. The vibrator is composed of a thrust rod 8, an electric oscillator 9, and a vibrator jack 10 whose propulsion and extraction are controlled by hydraulic or pneumatic pressure. Reference numeral 11 denotes a power source, and power is supplied to a power unit 14 for the vibrator jack 10 via a detector 12, an oscillator 9, and a calculation mechanism 13. The detector 12 detects the current value of the power sent to the oscillator 9 and sends this current signal to the calculation mechanism 13. The calculation mechanism 13 has a mechanism for operating the electromagnetic valve 15 based on the above-mentioned current signal to control the propulsion and extraction of the vibrator jack 10, and for calculating the compaction time from the load current value of the oscillator 9.
以上の如く構成されている装置においてこれを
作動せしめる場合は先づバイブレータの突き棒8
がバイブレータジヤツキ10により推進され塞ぎ
板6部より打設されたコンクリートの未締固め部
4に挿入され発振器9により振動が突き棒8に伝
えられ締固めが開始される。この場合突き棒が8
が充分にコンクリート中に挿入されていない過程
ならびにコンクリートの締固めが不充分な過程に
おいては発振器9の負荷電流は小さく、つぎに突
き棒8が充分にコンクリート中に挿入されかつ締
固めが進行するとともに発振器9の負荷電流は大
きくなる。従つてここで検知器12により発振器
9に送られる電流値を検知することにより締固め
の程度を検知することができる。更にこの1本の
突き棒8により締固めるコンクリートの量におい
ても、この量が多い場合には締固めに時間がかか
り、この量が少い場合には早く締固めが完了し、
この傾向は検知器12にて検知される電流値の時
間に対する増加の割合を検知することにより締固
めの途中においても締固め時間を計算することが
できる。ここで発振器9の電流値が突き棒8の挿
入程度および締固め程度より定められる最適締固
めの値に達したならば作業が完了し計算機構13
より電磁弁15を介してバイブレータジヤツキ1
0が作動し、突き棒8が抜き出され、締固め作業
の1‐サイクルが完了する。 When operating the device configured as described above, first press the vibrator's push rod 8.
is propelled by the vibrator jack 10 and inserted into the uncompacted part 4 of the poured concrete through the closing plate 6, and the oscillator 9 transmits vibrations to the thrust rod 8 to start compaction. In this case, the push rod is 8
The load current of the oscillator 9 is small in the process where the rod is not fully inserted into the concrete or the concrete is not sufficiently compacted, and then the ramming rod 8 is sufficiently inserted into the concrete and compaction progresses. At the same time, the load current of the oscillator 9 increases. Therefore, by detecting the current value sent to the oscillator 9 by the detector 12, the degree of compaction can be detected. Furthermore, regarding the amount of concrete to be compacted by this single ramming rod 8, if this amount is large, it will take time to compact, and if this amount is small, compaction will be completed quickly.
This tendency allows the compaction time to be calculated even during compaction by detecting the rate of increase in the current value detected by the detector 12 over time. When the current value of the oscillator 9 reaches the optimum compaction value determined from the insertion degree of the ramming rod 8 and the compaction degree, the work is completed and the calculation mechanism 13
Vibrator jack 1 via solenoid valve 15
0 is activated, the thrust rod 8 is extracted, and one cycle of compaction work is completed.
本発明に係るコンクリートの締固め装置は上記
の如き構成および作用を有するものであり、従つ
て従来コンクリートの締固めの定量的な把握は困
難で多分に経験的な勘に頼つていたものを定量的
に電流値にて把握することにより確実に締固めを
行いうるとともに無駄な締固めをおこなうことも
なく、またバイブレータがコンクリートの内部に
まで達するので表面のみならず、内部をも確実に
締固めをおこなうことができ、作業時間を短縮す
るとともに品質のよいコンクリート覆工ができる
ものである。 The concrete compaction device according to the present invention has the above-mentioned configuration and function, and therefore it has been found that conventionally it has been difficult to quantitatively understand the compaction of concrete and it has largely relied on empirical intuition. By quantitatively determining the current value, compaction can be performed reliably and unnecessary compaction will not be performed.Also, since the vibrator reaches the inside of the concrete, it is possible to compact not only the surface but also the inside. It can be compacted, shorten work time, and produce high-quality concrete lining.
第1図は本発明の装置の構成作用をあらわす略
断面および制御のブロツク図、第2図は第1図の
妻型枠の正面部分図、第3図は塞ぎ板の拡大正面
図である。
8…突き棒、9…発振器、10…ジヤツキ、1
1…電源、12…検知器、13…計算機構、14
…パワーユニツト、15…電磁弁。
FIG. 1 is a schematic cross-sectional view and control block diagram showing the structure and operation of the apparatus of the present invention, FIG. 2 is a partial front view of the gable form shown in FIG. 1, and FIG. 3 is an enlarged front view of the closing plate. 8... Thrust rod, 9... Oscillator, 10... Jacket, 1
1...Power supply, 12...Detector, 13...Calculation mechanism, 14
...Power unit, 15...Solenoid valve.
Claims (1)
ルの覆工コンクリートの締固めに用いられる装置
であって、バイブレータの入力電流を検知する検
知器と、バイブレータジヤツキの挿入、引抜き制
御をおこなうパワーユニツトおよび電磁弁と、上
記検知器よりの信号にもとづきバイブレータの作
動時間の算出およびバイブレータジヤツキによる
挿入、引抜きを制御する制御機構とから構成せら
れたコンクリートの締固め装置。1. A device used for compaction of cast-in-place concrete lining concrete for shield tunnels, which includes a detector that detects the input current of a vibrator, a power unit and a solenoid valve that controls the insertion and withdrawal of the vibrator jack, A concrete compaction device comprising a control mechanism that calculates the operating time of a vibrator based on the signal from the detector and controls the insertion and withdrawal of the vibrator jack.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP58217298A JPS60109499A (en) | 1983-11-18 | 1983-11-18 | Concrete solidifying apparatus |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP58217298A JPS60109499A (en) | 1983-11-18 | 1983-11-18 | Concrete solidifying apparatus |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS60109499A JPS60109499A (en) | 1985-06-14 |
| JPH0363640B2 true JPH0363640B2 (en) | 1991-10-01 |
Family
ID=16701941
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP58217298A Granted JPS60109499A (en) | 1983-11-18 | 1983-11-18 | Concrete solidifying apparatus |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS60109499A (en) |
Families Citing this family (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS63103199A (en) * | 1986-10-16 | 1988-05-07 | 三井建設株式会社 | shield excavator |
| JPS63141294U (en) * | 1987-03-10 | 1988-09-16 | ||
| JPH07558Y2 (en) * | 1988-05-13 | 1995-01-11 | 三井建設株式会社 | Concrete exciter for shield machine |
| JPH0381498A (en) * | 1989-08-22 | 1991-04-05 | Komatsu Ltd | Direct-placing concrete lining construction method of shield drilling machine |
| JPH03233096A (en) * | 1990-02-08 | 1991-10-17 | Taisei Corp | Tail void filling equipment |
| JP6265787B2 (en) * | 2014-03-07 | 2018-01-24 | 前田建設工業株式会社 | Device for calculating compaction characteristics of fresh concrete |
| JP6265786B2 (en) * | 2014-03-07 | 2018-01-24 | 前田建設工業株式会社 | Judgment method of compaction characteristics of fresh concrete |
| JP6588319B2 (en) * | 2015-11-27 | 2019-10-09 | 鹿島建設株式会社 | Concrete placement method and concrete placement structure |
| DE102022118542A1 (en) * | 2022-07-25 | 2024-01-25 | Wacker Neuson Produktion GmbH & Co. KG | Concrete compaction device with measurement of the compaction progress |
-
1983
- 1983-11-18 JP JP58217298A patent/JPS60109499A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS60109499A (en) | 1985-06-14 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH0363640B2 (en) | ||
| JP3625892B2 (en) | Construction method of underground structure using precast concrete column | |
| JPH08177395A (en) | Lining concrete compaction device for tunnel construction method | |
| JPH0325600B2 (en) | ||
| JP2019073853A (en) | Compacting method of construction joint in tunnel lining | |
| JPS60105800A (en) | Construction of shield tunnel | |
| GB650083A (en) | Improvements relating to methods of casting concrete piles and apparatus therefor | |
| JPH0828190A (en) | Cast-in-place lining shield construction method and shield excavating machine | |
| JPH01247698A (en) | Cast-in-place shield construction | |
| JPS5924099A (en) | Method of shield construction | |
| JP2534898B2 (en) | In-situ concrete concrete tunneling method | |
| JPH0578636B2 (en) | ||
| JPH0381498A (en) | Direct-placing concrete lining construction method of shield drilling machine | |
| JP2526312B2 (en) | Shield machine and in-situ lining type shield construction method using the machine | |
| JPH04176998A (en) | Quality control method for tunnel lining by cast-in-place concrete | |
| JPH0631553B2 (en) | Shield excavation method and shield excavator for implementing this method | |
| JPH05295994A (en) | Direct placing shield lining method | |
| JPH02132295A (en) | Constructing method for tunnel lining work | |
| JPS60109498A (en) | Concrete casting method | |
| JP2758716B2 (en) | Shield machine | |
| JP2546000B2 (en) | Shield machine | |
| JPH0796836B2 (en) | Concrete pouring equipment | |
| JPS63161299A (en) | shield excavator | |
| JPH0351499A (en) | Cast-in-place lining shield excavator | |
| JPH05118194A (en) | Sealing method of lining in cast-in-place lining shield method |