JPH0366454B2 - - Google Patents

Info

Publication number
JPH0366454B2
JPH0366454B2 JP28063286A JP28063286A JPH0366454B2 JP H0366454 B2 JPH0366454 B2 JP H0366454B2 JP 28063286 A JP28063286 A JP 28063286A JP 28063286 A JP28063286 A JP 28063286A JP H0366454 B2 JPH0366454 B2 JP H0366454B2
Authority
JP
Japan
Prior art keywords
cofferdam
continuous wall
temporary
construction method
continuous
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP28063286A
Other languages
Japanese (ja)
Other versions
JPS63134713A (en
Inventor
Matsuhei Ogawa
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP28063286A priority Critical patent/JPS63134713A/en
Publication of JPS63134713A publication Critical patent/JPS63134713A/en
Publication of JPH0366454B2 publication Critical patent/JPH0366454B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 ≪産業上の利用分野≫ この発明は連続地中壁による仮締切工法に関
し、特に締切工の内部をドライアツプする際に適
用される仮締切工法の改良に関するものである。
DETAILED DESCRIPTION OF THE INVENTION <<Industrial Application Field>> The present invention relates to a temporary cofferdam construction method using a continuous underground wall, and particularly relates to an improvement in a temporary cofferdam construction method applied when drying up the inside of a cofferdam.

≪従来の技術≫ 周知のように、河川あるいは海中に橋脚フーチ
ングなどの構造物を構築する場合、水域内に仮締
切工を形成し、締切工内の水を排水してドライな
状態にし、陸上と同じ条件で工事を行なうことが
ある。
<<Prior art>> As is well known, when constructing a structure such as a bridge pier footing in a river or the sea, a temporary cofferdam is formed in the water body, the water inside the cofferdam is drained to make it dry, and then it is placed on land. Construction work may be carried out under the same conditions.

この種の仮締切工としては、鋼矢板を用いた工
法が広く採用されている。
As this type of temporary cofferdam, construction methods using steel sheet piles are widely adopted.

鋼矢板を用いる仮締切工法は、施工が容易で取
扱いが簡単ではあるが、深度が深くしかも大規模
な水域を締切るには外力に対する抵抗が十分に得
られなかつた。
Temporary cofferdam construction methods using steel sheet piles are easy to construct and handle, but they do not provide sufficient resistance to external forces for sealing off large and deep bodies of water.

そこで、鋼矢板で水域を締切り、締切工内に中
詰土砂を投入した状態で、締切工中に海底地盤中
から水面上まで達するコンクリート製の連続壁を
形成する仮締切工法が提案されている。
Therefore, a temporary cofferdam method has been proposed in which a water body is closed off with steel sheet piles, and filler soil is poured into the cofferdam, and a continuous wall made of concrete that reaches from the seabed ground to above the water surface is formed during the cofferdam construction. .

しかしながら、このような連続壁を用いた仮締
切工法には、特に、締切工内の水を排水してドラ
イアツプする場合に、以下に説明する問題があつ
た。
However, such a temporary cofferdam construction method using a continuous wall has the following problems, particularly when water in the cofferdam is drained and dried up.

≪発明が解決しようとする問題点≫ すなわち、仮締切工内をドライアツプすると、
仮締切工にはその周囲の土・水圧が作用するが、
これらの外力は連続壁を用いた仮締切工事が、前
述したように大深度且つ大規模な工事に適用され
るので、かなり大きなものとなる。従つて、ドラ
イアツプした時に仮締切工に加わる外力に抵抗す
るためには、必然的に連続壁の壁厚を大きくしな
ければならなかつた。
≪Problems to be solved by the invention≫ In other words, when dry-up inside the temporary cofferdam,
Temporary cofferdams are affected by surrounding soil and water pressure, but
These external forces are quite large because temporary cofferdam work using continuous walls is applied to deep and large-scale construction work as described above. Therefore, in order to resist the external force applied to the temporary cofferdam during dry-up, it was necessary to increase the wall thickness of the continuous wall.

ところで、この種の仮締切工は、通常工事目的
物を安全且つ迅速に施工するための仮設備であ
り、工事完了後には撤去が予定されており、安全
性などが確保されればできる限り経済的なものが
望ましく、いかに安価に安全な仮締切工を構築す
るかは極めて重要な技術的関心事である。
By the way, this type of temporary cofferdam is usually temporary equipment used to safely and quickly construct a construction object, and is scheduled to be removed after the construction is completed. It is desirable to have a temporary cofferdam that is safe, and how to construct a safe temporary cofferdam at low cost is an extremely important technical concern.

しかるに、前述した工法では連続壁の壁厚を大
きくしなければならないので経済的な面で大きな
問題があつた。
However, the above-mentioned construction method required increasing the wall thickness of the continuous wall, which caused a big problem from an economic point of view.

ここで、連続壁の壁厚を薄くしておき、締切工
の内部をドライアツプする際に、連続壁の内側に
逆巻壁を形成することも考えられるが、この工法
では仮締切工の構築に時間がかかるという問題が
ある。
Here, it is also possible to reduce the wall thickness of the continuous wall and form a reverse wall on the inside of the continuous wall when dry-up the inside of the cofferdam, but this construction method is not suitable for constructing a temporary cofferdam. The problem is that it takes time.

この発明はこのような従来の問題点に鑑みてな
されたものであつて、その目的とするところは、
経済的にしかも短期間に構築できる連続壁による
仮締切工法を提供することにある。
This invention was made in view of these conventional problems, and its purpose is to:
The object of the present invention is to provide a temporary cofferdam construction method using continuous walls that can be constructed economically and in a short period of time.

≪問題点を解決するための手段≫ 上記の目的を達成するために、この発明は、水
域内に締切工を形成し、この締切工内に連続壁を
形成した後、前記連続壁で囲んだ内側をドライア
ツプする工法において、前記連続壁と前記締切工
との間に形成される内外間隙部のいずれか一方に
予め補強梁を設置することを特徴とする。
≪Means for Solving the Problems≫ In order to achieve the above object, the present invention forms a cofferdam in a water body, forms a continuous wall within the cofferdam, and then surrounds the cofferdam with the continuous wall. The method of dry-up the inside is characterized in that a reinforcing beam is installed in advance in either the inner or outer gap formed between the continuous wall and the cofferdam.

≪作用≫ 上記構成の仮締切工法によれば、連続壁の内・
外側のいずれか一方に補強梁が設けてあるので、
締切工の内部をドライアツプした時に、締切工に
加わる外力に対して連続壁と補強梁とが協働して
抵抗するので、連続壁の壁厚は大きくしなくて済
む。
≪Operation≫ According to the temporary cofferdam construction method with the above configuration, the inside of the continuous wall
There is a reinforcing beam on either side of the outside, so
When the inside of the cofferdam is dry-uped, the continuous walls and reinforcing beams work together to resist external forces applied to the cofferdam, so there is no need to increase the wall thickness of the continuous walls.

また、補強梁は締切工の構築時に予め設置する
ので、仮締切工の工期も長期化することはない。
Furthermore, since the reinforcing beams are installed in advance when constructing the cofferdam, the construction period for the temporary cofferdam will not be prolonged.

≪実施例≫ 以下、この発明の好適な実施例について添附図
面を参照にして詳細に説明する。
<<Example>> Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

第1図はこの発明に係る連続壁による仮締切工
法の一実施例を工程順に示す縦断面図である。
FIG. 1 is a vertical sectional view showing an embodiment of the temporary cofferdam construction method using continuous walls according to the present invention in the order of steps.

同図に示す工法では、まず、第1図aに示すよ
うに、鋼矢板、鋼管矢板などの締切材10が、海
底地盤Eの所定深度まで打設され、締切材10−
10間に中詰土砂12が投入される。
In the construction method shown in FIG. 1, first, as shown in FIG.
Filling soil 12 is put in between 10 and 10.

中詰土砂12が海底地盤E上に所定の厚みだけ
堆積すると、第1の補強梁14aが設置され、そ
の後再び中詰土砂12を投入して第2および第3
の補強梁14b,14cを設置する。
When the filling soil 12 is deposited to a predetermined thickness on the seabed ground E, the first reinforcing beam 14a is installed, and then the filling soil 12 is put in again and the second and third reinforcing beams 14a are installed.
reinforcing beams 14b and 14c are installed.

ここで、各補強梁14a,b,cは、それぞれ
締切材10−10間のほぼ中心位置に設けられる
連続壁16と締切工10との外側間隙部17にあ
つて、連続壁16の外側に位置しており、連続壁
16の外周形状に沿うようにして設置される。
Here, each of the reinforcing beams 14a, b, and c is located in an outer gap 17 between the continuous wall 16 and the cofferdam 10, which are provided at approximately the center position between the cofferdams 10-10, and on the outside of the continuous wall 16. The continuous wall 16 is located along the outer circumferential shape of the continuous wall 16.

また、各補強梁14a,b,cは、例えば締切
工内に構築する目的物が円形断面であれば、適当
な幅と厚みを有する鋼材をリング状に結合したも
のが最も実際的であるが、補強梁14a,b,c
の設置位置に対応した割合の中詰土砂12を、水
中での分離を抑制するための特殊添加剤を加えた
固化剤で固結して補強梁14a,b,cとしても
よい。
Furthermore, if the object to be constructed within the cofferdam has a circular cross section, the most practical way for each of the reinforcing beams 14a, b, and c is to combine steel members having an appropriate width and thickness into a ring shape. , reinforcement beams 14a, b, c
The reinforcing beams 14a, b, and c may be formed by solidifying the filling soil 12 in a proportion corresponding to the installation position with a solidifying agent containing special additives to suppress separation in water.

補強梁14a,b,cが段状に設置されると、
第1図bに示すように、締切材10−10間のほ
ぼ中心に連続壁16が構築される。
When the reinforcing beams 14a, b, c are installed in steps,
As shown in FIG. 1b, a continuous wall 16 is constructed approximately centrally between the cofferdams 10-10.

連続壁16は、中詰土砂12および海底地盤E
を泥水を満たしながら掘削し、掘削孔内に鉄筋を
建込んだ後、コンクリートを打設することによつ
て形成される。
The continuous wall 16 is made up of the filling earth and sand 12 and the seabed ground E.
It is formed by excavating a hole while filling it with muddy water, placing reinforcing bars in the hole, and then pouring concrete.

連続壁16の構築が終了すると仮締切工が完了
するので、第1図cに示すように、補強梁14
a,b,cが設置されていない方、つまり仮締切
工で仕切つた内側の水を排水してドライアツプ
し、仮締切工中に目的物を構築する。
When the construction of the continuous wall 16 is completed, the temporary cofferdam is completed, so as shown in Fig. 1c, the reinforcing beam 14 is
Drain the water from the side where a, b, and c are not installed, that is, the inside partitioned by the temporary cofferdam, and dry it up, and construct the target object during the temporary cofferdam.

さて、以上の如き方法で仮締切工を構築すれ
ば、第1図cに示した、仮締切工中をドライアツ
プした時に、これに作用する外力に対しては、補
強梁14a,b,cと連続壁16とが協働して対
抗することになるので、補強梁14a,b,cで
分担する分だけ、連続壁16の壁厚を薄くするこ
とができる。
Now, if the temporary cofferdam is constructed using the method described above, the reinforcing beams 14a, b, and c will be able to withstand the external force that acts on the temporary cofferdam when it is dry-up, as shown in Figure 1c. Since the continuous walls 16 cooperate with each other to oppose each other, the wall thickness of the continuous walls 16 can be made thinner by the amount shared by the reinforcing beams 14a, b, and c.

また、仮締切工中に内巻コンクリートを構築す
る場合にも、下方から上方に向けてコンクリート
を打設する順巻工法が採用できるので、工期の短
縮も可能となる。
Furthermore, when constructing inner-rolling concrete during temporary cofferdam construction, a sequential-rolling method in which concrete is poured from the bottom to the top can be adopted, making it possible to shorten the construction period.

第2図はこの発明に係る連続壁による仮締切工
法の他の実施例を示しており、その特徴点につい
てのみ以下に説明する。
FIG. 2 shows another embodiment of the temporary cofferdam construction method using a continuous wall according to the present invention, and only its characteristic points will be described below.

この実施例では補強梁14a〜14cを、連続
壁16と締切工10との間に形成される内側間隙
部18に予め埋設しておく。
In this embodiment, reinforcing beams 14a to 14c are embedded in advance in an inner gap 18 formed between a continuous wall 16 and a cofferdam 10.

そして、締切工10−10間の内部をドライア
ツプする時に、上段側から順次補強梁14a〜1
4cが露出すると、補強梁14a〜14cと連続
壁16との間にコンクリートなどの連結材20を
充填して、第2図bに示すように、補強梁14a
〜14cと連続壁16とを一体化させる。
When drying up the inside of the cofferdam 10-10, the reinforcing beams 14a to 1 are sequentially removed from the upper stage side.
4c is exposed, a connecting material 20 such as concrete is filled between the reinforcing beams 14a to 14c and the continuous wall 16, and as shown in FIG. 2b, the reinforcing beam 14a is
~14c and the continuous wall 16 are integrated.

以上のようにして仮締切工を造成しても、上記
実施例と同等な作用効果を得ることができる。
Even if the temporary cofferdam is created as described above, the same effects as those of the above embodiment can be obtained.

≪発明の効果≫ 以上、説明したように、この発明に係る連続壁
による仮締切工法によれば、この種の工法で最も
重要な経済的な面で有利な条件下で、大深度且つ
大規模な仮締切工が構築できる。
≪Effects of the Invention≫ As explained above, according to the temporary cofferdam construction method using continuous walls according to the present invention, construction can be carried out at great depths and on a large scale under economically advantageous conditions, which is the most important aspect of this type of construction method. A temporary cofferdam can be constructed.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明工法の工程を順に示す縦断面
図、第2図は同工法の他の実施例を工程順に示す
縦断面図である。 10……締切材、12……中詰土砂、14a,
b,c……補強梁、16……連続壁。
FIG. 1 is a longitudinal sectional view showing the steps of the construction method of the present invention in order, and FIG. 2 is a longitudinal sectional view showing another embodiment of the same method in order of steps. 10... cofferdam, 12... filling earth and sand, 14a,
b, c...Reinforcement beam, 16...Continuous wall.

Claims (1)

【特許請求の範囲】 1 水域内に締切工を形成し、この締切工内に連
続壁を形成した後、前記連続壁で囲んだ内側をド
ライアツプする工法において、前記連続壁と前記
締切工との間に形成される内外間隙部のいずれか
一方に予め補強梁を設置することを特徴とする連
続壁による仮締切工法。 2 上記補強梁は上記連続壁に沿つて深度方向に
所定の間隔を置いて多段状に埋設することを特徴
とする連続壁による仮締切工法。
[Scope of Claims] 1. A construction method in which a cofferdam is formed in a body of water, a continuous wall is formed within the cofferdam, and then the inside surrounded by the continuous wall is dry-upped, wherein the connection between the continuous wall and the cofferdam is A temporary cofferdam construction method using a continuous wall characterized by installing a reinforcing beam in advance on either the inner or outer gap formed between the inner and outer gaps. 2. A temporary cofferdam construction method using a continuous wall, characterized in that the reinforcing beams are buried in multiple stages at predetermined intervals in the depth direction along the continuous wall.
JP28063286A 1986-11-27 1986-11-27 Temporary coffering construction with continuous wall Granted JPS63134713A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP28063286A JPS63134713A (en) 1986-11-27 1986-11-27 Temporary coffering construction with continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP28063286A JPS63134713A (en) 1986-11-27 1986-11-27 Temporary coffering construction with continuous wall

Publications (2)

Publication Number Publication Date
JPS63134713A JPS63134713A (en) 1988-06-07
JPH0366454B2 true JPH0366454B2 (en) 1991-10-17

Family

ID=17627755

Family Applications (1)

Application Number Title Priority Date Filing Date
JP28063286A Granted JPS63134713A (en) 1986-11-27 1986-11-27 Temporary coffering construction with continuous wall

Country Status (1)

Country Link
JP (1) JPS63134713A (en)

Also Published As

Publication number Publication date
JPS63134713A (en) 1988-06-07

Similar Documents

Publication Publication Date Title
JP2000290936A (en) Construction method of pier footing and caisson for pier footing construction
JPS5936058B2 (en) How to construct a structure using underground continuous walls
JPH0366454B2 (en)
CN215211065U (en) Supporting structure
JPH07197473A (en) Open caisson structure
JPH0437205B2 (en)
KR20190019530A (en) Retaining wall method by using the precast house(PC house) of bridge building
JP2784314B2 (en) How to set up an open caisson
JP4146250B2 (en) Open caisson bottom plate construction method
JPH07216903A (en) How to construct a revetment caisson and revetment
JP2556380B2 (en) Construction method of revetment structure
JPS5949974B2 (en) Construction methods for foundations such as abutments and piers
JPH0572481B2 (en)
JP2581602B2 (en) Waste treatment method
CN113123349A (en) Supporting structure
JPS6215300Y2 (en)
JPH0510084A (en) Construction method of deep human hole
JPH0329922B2 (en)
JPH052774B2 (en)
JPH0469252B2 (en)
JP2022108444A (en) Reinforcement method for existing bank
JPH0439535B2 (en)
JPH09273165A (en) Execution method of undergroud structure
JPH0376922A (en) Construction of continuous underground wall and steel panel therefor
JPH07180127A (en) Construction method of retaining wall for water-storage dam, checkdam, etc.