JPH0366463B2 - - Google Patents

Info

Publication number
JPH0366463B2
JPH0366463B2 JP57087125A JP8712582A JPH0366463B2 JP H0366463 B2 JPH0366463 B2 JP H0366463B2 JP 57087125 A JP57087125 A JP 57087125A JP 8712582 A JP8712582 A JP 8712582A JP H0366463 B2 JPH0366463 B2 JP H0366463B2
Authority
JP
Japan
Prior art keywords
formwork
concrete
girder
beams
floor slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP57087125A
Other languages
Japanese (ja)
Other versions
JPS58204244A (en
Inventor
Masami Kuromya
Shigeo Yaegashi
Katsufumi Sugai
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP8712582A priority Critical patent/JPS58204244A/en
Publication of JPS58204244A publication Critical patent/JPS58204244A/en
Publication of JPH0366463B2 publication Critical patent/JPH0366463B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【発明の詳細な説明】 本発明は、一定高さ以上の多層階建築物の構造
形式として最も多く施工実施されるところの鉄骨
鉄筋コンクリート造り建築物の構築方法に関す
る。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing a steel-framed reinforced concrete building, which is the most frequently constructed structural type of multi-story building of a certain height or more.

上記のような構造形式の建築物の一般階の躯体
は、柱、大梁、小梁、床版、壁、階段などから構
成され、そのうち、大梁、小梁、床版が躯体の大
部分を占める。この大部分を占める大梁、小梁、
床版をコンクリート打設により構築するに際し
て、従来では第6図で示すように、大梁作製用型
枠07、小梁作製用型枠08、床版作製用型枠0
6を各別に用い、これらを端太材013及び林立
させた多数本のパイプサポート09等で支保さ
せ、かつ、所要の鉄筋を組立てた上でコンクリー
トを打設することにより大梁01、小梁02、床
版03を構築していた。
The frame of a general floor of a building with the above structural type is composed of columns, girders, small beams, floor slabs, walls, stairs, etc. Of these, the girders, small beams, and floor slabs make up the majority of the frame. . Large beams, small beams, and
When constructing a floor slab by concrete pouring, conventionally, as shown in FIG.
6 are used separately, supported by thick timbers 013 and a large number of pipe supports 09 standing in a forest, etc., and by assembling the necessary reinforcing bars and pouring concrete, the large beam 01 and the small beam 02 are constructed. , was constructing floor slab 03.

しかし、このような従来方法によるときは、型
枠・支保工に使用する資材及び、それらを組立て
る労力が膨大なものであり、そのための費用及び
時間が全工事費及び全工事期間に占める割合が非
常に大きく、その結果、コンクリート打設後、所
定の養生期間(通常4週間位)が経過するまでは
型枠を解体することができないこと、型枠解体作
業完了後にその使用資材を搬出して工事場の片付
け、清掃を行なわれなければ後続の仕上工事等に
着手できないこと等も加わつて、全工事期間を一
段と延長化させるものであつた。加えて、膨大な
資材の搬入搬出が高所作業となるための危険率が
増大する問題もあつた。
However, when such conventional methods are used, the materials used for formwork and shoring and the labor to assemble them are enormous, and the cost and time for this is a large proportion of the total construction cost and construction period. As a result, the formwork cannot be dismantled until a specified curing period (usually around 4 weeks) has passed after concrete is poured, and the materials used must be removed after the formwork dismantling work is completed. This added to the fact that subsequent finishing work could not be started unless the construction site was cleared and cleaned, which further extended the overall construction period. In addition, there was also the problem of increasing the risk of carrying in and out of huge amounts of materials, which required working at heights.

本発明は、かかる実情に鑑み、躯体工事の大部
分を占める大梁、小梁、床版の構築に際しての使
用材料を合理化することで、大巾な工期短縮、施
工精度の向上が図れる鉄骨鉄筋コンクリート造り
構築物の構築方法を提案する点に目的がある。
In view of these circumstances, the present invention aims to significantly shorten the construction period and improve construction accuracy by streamlining the materials used when constructing the large beams, small beams, and deck slabs that make up the majority of the construction work. The purpose is to propose a method for constructing a structure.

上記目的を達成すべく創意工夫された本発明に
よる鉄骨鉄筋コンクリート造り建築物の構築方法
の要旨は、鉄骨鉄筋コンクリート造り建物の主要
構造である大梁、小梁、床版を構築するに、小梁
としてプレキヤストコンクリート小梁を使用し、
このプレキヤストコンクリート小梁と大梁の側型
枠とに亘つて架設の仮受梁群の上に波形捨型枠を
敷設することにより床版型枠を組立構成し、この
床版型枠及び大梁型枠内にコンクリートを打設し
て床版及び大梁を構築することにある。
The gist of the method for constructing a steel-framed reinforced concrete building according to the present invention, which has been ingeniously devised to achieve the above object, is that when constructing the main structures of a steel-framed reinforced concrete building, such as the main beams, small beams, and floor slabs, Using cast concrete beams,
The floor slab formwork is constructed by laying corrugated concrete formwork on top of the temporary support beam group that spans the precast concrete small beams and the side formwork of the girder, and the floor slab formwork and the girder The purpose is to construct the floor slabs and girders by pouring concrete into the formwork.

即ち、プレキヤストコンクリート小梁を使用
し、これを鉄骨建方と同時併行的に揚重し大梁取
合部に取付けることにより、小梁構築に際しての
型枠及び支保工の使用を不要にできる。しかも、
このプレキヤストコンクリート小梁の本設として
の十分に大なる耐力を利用して、このプレキヤス
トコンクリート小梁を床版型枠の仮受梁の支点と
して仮受梁をプレキヤストコンクリート小梁と大
梁の側型枠とに亘つて架設し、その仮受梁群上に
キーストンプレートやデツキプレート等の波形捨
型枠を敷設することで床版型枠を組立構成するか
ら床版型枠に対するパイプサポート等の支保工も
不要にできる。
That is, by using precast concrete beams, lifting them simultaneously with the erection of the steel frame, and attaching them to the joints of the girders, it is possible to eliminate the need for formwork and shoring when constructing the beams. Moreover,
Utilizing the sufficiently large bearing capacity of this precast concrete small beam as a permanent installation, this precast concrete small beam is used as a fulcrum for the temporary support beam of the floor slab formwork, and the temporary support beam is connected to the precast concrete small beam and the main beam. The pipe support for the floor slab formwork is constructed by constructing the floor slab formwork by constructing it across the side formwork and laying corrugated abandoned formwork such as keystone plates and deck plates on the temporary support beam group. This also eliminates the need for shoring.

その上、小梁のみをプレキヤスト化し、大梁
は、床版とともに現場打ちとしてあるから、例え
ば大梁も小梁と同様にプレキヤスト化し、床版作
製のコンクリート打設により、打設したコンクリ
ートと大梁から突出させた鉄筋や鉄骨とを結合さ
せて大梁と床版とを一体化する場合に比較して、
大梁と床版とのコンクリートを一連化してコンク
リート同士の結合をおこなわせ、大梁と床版との
結合強度を大なるものにできる。
In addition, only the small beams are precast, and the girders are cast in-situ together with the floor slabs, so for example, the girders are also made of precast like the small beams, and when the concrete is poured for the floor slabs, they protrude from the cast concrete and the girders. Compared to the case where the girder and floor slab are integrated by combining them with reinforced reinforcing bars and steel frames,
By connecting the concrete between the girder and the floor slab in a series, the concrete can be bonded to each other, and the strength of the bond between the girder and the floor slab can be increased.

以上のように、大梁、小梁、床版といつた主要
構造の構築に際しての材料の合理的使用により、
省力化、省資材化を図り、従来に比し施工能率の
著しい向上をもつて大巾な工期短縮を達成できる
とともに、現場施工で煩雑な作業となり易い小梁
のプレキヤスト化に伴い全体施工をシンプルなも
のとし、施工精度の向上が達成できる。また、使
用資材が少ないので、揚重、組立、解体等作業時
の危険率も少なくなる。その上、そのような施工
能率及び施工精度の向上を図りながらも、大梁と
床版との結合を強力に行なえて躯体を丈夫なもの
にできる。
As mentioned above, through the rational use of materials when constructing the main structures such as girders, beams, and deck slabs,
By saving labor and materials, it is possible to significantly shorten the construction period by significantly improving construction efficiency compared to conventional methods, and simplifying the overall construction by precasting small beams, which tend to be complicated work in on-site construction. This makes it possible to improve construction accuracy. In addition, since fewer materials are used, the risk of danger during lifting, assembly, and disassembly work is also reduced. Furthermore, while improving the construction efficiency and accuracy, the girder and the floor slab can be strongly connected and the frame can be made durable.

以下本発明方法の実施例を図面に基づいて詳述
すると、鉄骨鉄筋コンクリート造り建築物の主要
構造である鉄骨鉄筋入りコンクリート製大梁1、
鉄筋入りコンクリート製小梁2、及び鉄筋入りコ
ンクリート製床版3を構築するにあたつて、前記
小梁2としてプレキヤストコンクリート小梁を使
用し、これを第1図乃至第3図で示したように鉄
筋建方と同時併行的に揚重し、かつ大梁取合部に
取付ける。
Hereinafter, embodiments of the method of the present invention will be described in detail based on the drawings.The main structure of a steel-framed reinforced concrete building is a steel-framed reinforced concrete girder 1;
In constructing the reinforced concrete beam 2 and the reinforced concrete deck slab 3, a precast concrete beam was used as the reinforced concrete beam 2, as shown in Figures 1 to 3. Lift the reinforcing bars at the same time as erecting them, and attach them to the joints of the girders.

而して、前記プレキヤストコンクリート小梁2
と、パイプサポート9により支保させる状態で組
立られた大梁1作製用型枠7のうちの側型枠7A
の上端部とに亘つて、軽量組立トラスや軽量矩形
角パイプからなる仮受梁4の複数個を小梁長手方
向適当間隔置きに架設し、これら仮受梁4群上で
三辺の大梁側型枠7Aと一辺のプレキヤストコン
クリート小梁2とで囲まれる所にキーストンプレ
ートやデツキプレート等の波形捨(永久)型枠5
を敷設することにより床版型枠6を組立構成す
る。次いで大梁用の鉄筋10a、床版用鉄筋10
bを配設した上で、各型枠6及び7内にコンクリ
ート11を打設することにより、第5図で示すよ
うに床版3及び大梁1、並びにプレキヤスト小梁
2といつた階躯体の主要構造を構築するのであ
る。
Therefore, the precast concrete beam 2
and the side formwork 7A of the formwork 7 for making the girder 1 assembled in a state where it is supported by the pipe support 9.
A plurality of temporary support beams 4 made of lightweight prefabricated trusses or lightweight rectangular pipes are erected at appropriate intervals in the longitudinal direction of the small beams over the upper end of the temporary support beams. A corrugated (permanent) formwork 5 such as a keystone plate or deck plate is placed in the area surrounded by the formwork 7A and the precast concrete beam 2 on one side.
By laying the floor slab formwork 6, the floor slab formwork 6 is assembled and configured. Next, reinforcing bars 10a for the girder and reinforcing bars 10 for the floor slab
By placing concrete 11 in each formwork 6 and 7 after arranging b, the floor slab 3, girder 1, and precast girder 2 are assembled into a floor structure as shown in Fig. 5. Build the main structure.

前記プレキヤストコンクリート小梁2は、第4
図にも示すように、肋筋の上端位置より下方で大
梁1に取り付けたときにちようど床構築用型枠で
ある波形捨型枠5が設設される位置に相当する位
置まで、予めコンクリート打設が施されたもので
あつて、コンクリートよりも上方に露出する肋筋
10は、床版作製のために打設されたコンクリー
ト11内に埋込まれ、床版3との結合材として作
用する。
The precast concrete beam 2 has a fourth
As shown in the figure, the height of the corrugated waste formwork 5, which is the formwork for constructing the floor, will be installed in advance below the top end of the ribs to a position corresponding to the position where the corrugated waste formwork 5, which is the formwork for constructing the floor, will be installed when it is attached to the girder 1. The reinforcing bars 10 that are exposed above the concrete are embedded in the concrete 11 that has been cast for making the slab, and are used as a bonding material with the slab 3. act.

尚、前記仮受梁4は解体撤去後、反復使用が可
能である。また、大梁型枠7に関し、大梁鉄骨1
2からの吊り型枠とすれば、パイプサポート等の
支保工が不要で全体として一層経済的、効果的な
構築が行なえる。
Note that the temporary support beam 4 can be used repeatedly after being dismantled and removed. Regarding girder formwork 7, girder steel frame 1
If the formwork is suspended from 2, there is no need for shoring such as pipe supports, making the construction more economical and effective overall.

【図面の簡単な説明】[Brief explanation of drawings]

図面は本発明に係る鉄骨鉄筋コンクリート造り
建築物の構築方法の実施例を示し、第1図は一階
躯体の構築要領を示す要部の平面図、第2図、第
3図は第1図−線、−線での拡大縦断面
図、第4図はプレキヤストコンクリート小梁の斜
視図、第5図は構築後の要部拡大縦断面図、第6
図は従来方法を示す要部の拡大縦断面図である。 1……大梁、2……プレキヤスト小梁、3……
床版、4……仮受梁、5……波形捨型枠、6……
床版型枠、7……大梁型枠、7A……側型枠。
The drawings show an embodiment of the method for constructing a steel-framed reinforced concrete building according to the present invention, and FIG. 1 is a plan view of the main parts showing the procedure for constructing a one-story frame, and FIGS. 2 and 3 are similar to FIGS. Fig. 4 is a perspective view of the precast concrete beam, Fig. 5 is an enlarged longitudinal sectional view of the main part after construction, Fig. 6
The figure is an enlarged vertical sectional view of the main parts showing the conventional method. 1...Large beam, 2...Precast small beam, 3...
Floor slab, 4... Temporary support beam, 5... Corrugated waste formwork, 6...
Floor slab formwork, 7... girder formwork, 7A... side formwork.

Claims (1)

【特許請求の範囲】[Claims] 1 鉄骨鉄筋コンクリート造り建築物の主要構造
である大梁1、小梁2、及び床版3を構築する
に、小梁2としてプレキヤストコンクリート小梁
を使用し、このプレキヤストコンクリート小梁2
と大梁1の側型枠7Aとに亘つて架設の仮受梁4
群の上に波形捨型枠5を敷設することにより床版
型枠6を組立構成し、この床版型枠6及び大梁型
枠7内にコンクリートを打設して床版3及び大梁
1を構築することを特徴とする鉄骨鉄筋コンクリ
ート造り建築物の構築方法。
1. To construct the main beams 1, 2 small beams, and floor slab 3, which are the main structures of a steel-framed reinforced concrete building, precast concrete small beams are used as the small beams 2, and these precast concrete small beams 2
and the side formwork 7A of the girder 1.
A corrugated waste form 5 is laid on top of the group to assemble the floor slab form 6, and concrete is poured into the floor slab form 6 and girder form 7 to form the deck slab 3 and girder 1. A method of constructing a steel-framed reinforced concrete building.
JP8712582A 1982-05-21 1982-05-21 Construction of reinforced concrete building Granted JPS58204244A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8712582A JPS58204244A (en) 1982-05-21 1982-05-21 Construction of reinforced concrete building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8712582A JPS58204244A (en) 1982-05-21 1982-05-21 Construction of reinforced concrete building

Publications (2)

Publication Number Publication Date
JPS58204244A JPS58204244A (en) 1983-11-28
JPH0366463B2 true JPH0366463B2 (en) 1991-10-17

Family

ID=13906231

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8712582A Granted JPS58204244A (en) 1982-05-21 1982-05-21 Construction of reinforced concrete building

Country Status (1)

Country Link
JP (1) JPS58204244A (en)

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5227225Y2 (en) * 1971-10-26 1977-06-21
JPS4943387U (en) * 1972-07-13 1974-04-16
JPS4970726U (en) * 1972-09-30 1974-06-19
JPS57119017U (en) * 1981-01-16 1982-07-23
JPS57146856A (en) * 1981-03-09 1982-09-10 Hasegawa Komuten Kk Pc beam

Also Published As

Publication number Publication date
JPS58204244A (en) 1983-11-28

Similar Documents

Publication Publication Date Title
US9388561B2 (en) Modular construction mold apparatus and method for constructing concrete buildings and structures
JPH02243845A (en) Stereo skelton structure and constituting method thereof
HK1232269A1 (en) Prefabricated frame and construction method using the same
US20120297701A1 (en) Folded cardboard concrete form system
CN207686092U (en) A kind of assembled overlapped hollow floor system
JP2915897B1 (en) Building construction method
US4294052A (en) Prefabricated load bearing structure
JP2977798B1 (en) Construction method of steel frame / RC composite structure building and formwork thereof
CN107989247A (en) A kind of assembled overlapped hollow floor system and its construction method
SU1544901A1 (en) Ferroconcrete skeleton of building or structure
JPH0366463B2 (en)
JP2817591B2 (en) Construction method of steel reinforced concrete building
US3349539A (en) Construction of two-way composite building system
KR102679042B1 (en) PC half-slab construction method for quick construction of precast concrete apartment house
RU2836225C1 (en) Method of erection of monolithic and prefabricated monolithic frames
JPH0447737B2 (en)
JPS6226481Y2 (en)
JPS642742B2 (en)
RU2285771C1 (en) Method for building and building structure erection, renewal and reconstruction
JPS5925931Y2 (en) Composite girder using π-shaped steel
JPH044091Y2 (en)
EA006820B1 (en) Prefabricard monolithic reinforced concrete frame of mult-storey building
JP2518568Y2 (en) Connection structure of steel beams to concrete columns
JPH04149365A (en) Construction method of beam
JP2504658B2 (en) Foundation structure in middle-high-rise buildings