JPH0367166B2 - - Google Patents
Info
- Publication number
- JPH0367166B2 JPH0367166B2 JP60228442A JP22844285A JPH0367166B2 JP H0367166 B2 JPH0367166 B2 JP H0367166B2 JP 60228442 A JP60228442 A JP 60228442A JP 22844285 A JP22844285 A JP 22844285A JP H0367166 B2 JPH0367166 B2 JP H0367166B2
- Authority
- JP
- Japan
- Prior art keywords
- reinforcement
- mesh
- concrete
- core
- cross
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Foundations (AREA)
Description
【発明の詳細な説明】
〔産業上の利用分野〕
この発明は現場における配筋作業を簡略化した
地中梁の施工方法に関するものである。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for constructing underground beams that simplifies reinforcement work on site.
地中梁の施工においては肋筋、主筋等の鉄筋は
現場で組み立てられるのが一般的であるが、この
配筋作業では工程数が多い等現場作業の能率の低
下を招いていた。これに対し、肋筋等を工場でメ
ツシユ状に組み立てたものを現場で継ぐ方法が提
案されているが、コンクリート打設前に配筋工事
のみを先行させて行なう方法のために継手が多く
なり、またメツシユ筋を保持する手段を必要とす
る。
In the construction of underground beams, reinforcing bars such as crossbars and main bars are generally assembled on site, but this reinforcement work requires a large number of steps, which reduces the efficiency of on-site work. In contrast, a method has been proposed in which reinforcing bars, etc. are assembled in a mesh shape in a factory and then joined on site, but this method requires only reinforcement work to be carried out before pouring concrete, resulting in a large number of joints. , also requires a means to hold the meshwork muscles.
この発明は鉄筋を確実に固定しながら簡単に地
中梁を施工する目的からなされたもので、メツシ
ユ筋の継手毎にコンクリートを打設していくこと
により鉄筋の組み立てを確実に、容易に行なおう
とするものである。 This invention was made for the purpose of easily constructing underground beams while reliably fixing reinforcing bars.By pouring concrete at each joint of mesh bars, reinforcing bars can be assembled reliably and easily. This is what we are trying to do.
本発明では施工手順を梁鉄筋の組み立て部分に
従つて三段階に分け、その段階毎に鉄筋の組み立
て、コンクリートの打設を行ない、基礎スラブを
含めて地中梁を形成する。
In the present invention, the construction procedure is divided into three stages according to the parts where the beam reinforcing bars are assembled, and in each stage, the reinforcing bars are assembled and concrete is placed to form the underground beam including the foundation slab.
梁鉄筋の肋筋、中子筋は予めメツシユ状に組ま
れたものであり、これを所定の位置に設置してコ
ンクリートを打設した後にそれらを鉛直に相互に
継ぐ。 The ribs and core bars of the beam reinforcing bars are assembled in advance in the form of a mesh, and after they are installed at predetermined positions and concrete is poured, they are vertically connected to each other.
一段階では下筋及び中子筋、肋筋を組み立て、
設置するとともに基礎スラブの配筋をし、コンク
リートを打設して基礎スラブを形成する。 In the first step, assemble the lower muscles, trumpet muscles, and costal muscles,
At the same time, the foundation slab will be reinforced and concrete will be poured to form the foundation slab.
二段階では一段階でコンクリートに定着された
中子筋、肋筋に継いで更に中子筋、肋筋を建込む
とともにコンクリートを打設し、三段階で上筋、
かぶせ筋、更にスラブ筋を配筋してコンクリート
を打設し、床スラブまで形成する。 In the second stage, the core reinforcement and rib reinforcement that were fixed in the concrete in the first stage are followed by further core reinforcement and rib reinforcement, and concrete is poured, and in the third stage, the upper reinforcement,
Covering reinforcements and slab reinforcements are placed and concrete is placed to form the floor slab.
以下本発明を一実施例を示す図面とともに説明
する。
The present invention will be described below with reference to drawings showing one embodiment.
本発明は地中梁Aを三段階に分けて施工するも
ので、その段階毎に鉄筋の設置、組み立て、続い
てコンクリートの打設を行なつて地中梁Aを構成
するものである。 In the present invention, the underground beam A is constructed in three stages, and in each stage, reinforcing bars are installed and assembled, and then concrete is poured to construct the underground beam A.
まず第一の発明を第1図及び第2図に基づいて
説明する。 First, the first invention will be explained based on FIGS. 1 and 2.
この発明は外周の地中梁Aの施工方法であり、
一段階で下筋1及び肋筋メツシユ2−1、中子筋
メツシユ3−1を配筋、配置してコンクリート4
−1を打設し、二段階で更に肋筋メツシユ2−2、
中子筋メツシユ3−2を建込んでコンクリート4
−2を打設し、三段階で上筋5及びかぶせ筋6、
スラブ筋を配筋してコンクリート4−3を打設す
るという工程からなる。 This invention is a method of constructing an underground underground beam A on the outer periphery,
In one step, lower reinforcement 1, cost reinforcement mesh 2-1 , and core reinforcement mesh 3-1 are laid out and placed to form concrete 4.
- 1 , and in the second step further rib mesh 2-2 ,
Concrete 4 by erecting core mesh 3-2
− 2 , and in three stages the upper reinforcement 5 and the cover reinforcement 6,
The process consists of arranging slab reinforcement and pouring concrete 4-3 .
以下施工手順を段階毎に順を追つて第1図によ
り詳細に説明する。 The construction procedure will be explained step by step in detail with reference to FIG. 1 below.
一段階()ではまず杭7頭部の両脇に鉄筋ス
ペーサー8を配置し、この鉄筋スペーサー8上に
予めメツシユ状に組まれ、L字状に折り曲げられ
た肋筋メツシユ2−1を杭7の上方に伸びた杭筋
9の両外側に梁方向に載置する。次に下筋1の下
端筋1−1を肋筋メツシユ2−1の水平部上に配
筋・圧接し、肋筋メツシユ2−1と同じくメツシ
ユ状に組まれたL字状の中子筋メツシユ3−1を
肋筋メツシユ2−1の内側に、これに平行に配置
する。続いて交差筋10−1を下端筋1−1上に、
これに垂直に配筋し、その上に下筋1の上端筋1
−2を配筋・圧接した後、基礎スラブBの配筋を
し、コンクリート4−1を基礎スラブBの部分に
打設する。このとき肋筋メツシユ2−1、中子筋
メツシユ3−1の上部は基礎スラブBから突出す
る。 In the first step (), first, reinforcing bar spacers 8 are placed on both sides of the head of the pile 7, and the rib mesh 2-1 , which has been assembled in a mesh shape in advance on the reinforcing bar spacers 8 and bent into an L shape, is attached to the pile 7. It is placed in the direction of the beam on both sides of the pile reinforcements 9 that extend upward. Next, the lower end reinforcement 1-1 of the lower reinforcement 1 is placed and pressed onto the horizontal part of the rib mesh 2-1 , creating an L-shaped core reinforcement that is arranged in a mesh shape like the rib mesh 2-1 . The mesh 3-1 is placed inside and parallel to the rib mesh 2-1 . Next, place the cross reinforcement 10-1 on the lower end reinforcement 1-1 ,
Arrange reinforcement perpendicularly to this, and place upper end reinforcement 1 of lower reinforcement 1 on top of it.
- After reinforcing and pressing 2 , place reinforcement for foundation slab B, and pour concrete 4-1 onto foundation slab B. At this time, the upper portions of the rib mesh 2-1 and the core mesh 3-1 protrude from the base slab B.
二段階()では初めて下部が基礎スラブBに
埋設された肋筋メツシユ2−1、中子筋メツシユ
3−1に継手を取つて地中梁A上部までの高さを
有する肋筋メツシユ2−2、中子筋メツシユ3−2
を建込む。この際メツシユ筋控え11により肋筋
メツシユ2−2及び中子筋メツシユ3−2を保持す
る。次に梁型枠12、床型枠13を組み立て、肋
筋メツシユ2−2、中子筋メツシユ3−2の先端部
の手前までコンクリート4−2を打設する。 In the second stage (), the lower part of the rib mesh 2-1 is buried in the foundation slab B for the first time, and the rib mesh 2-1, which has a height up to the upper part of the underground beam A by attaching joints to the core mesh 3-1 , is constructed. 2 , Core muscle mesh 3-2
Build. At this time, the rib muscle mesh 2-2 and the core muscle mesh 3-2 are held by the mesh muscle retainer 11. Next, the beam formwork 12 and the floor formwork 13 are assembled, and concrete 4-2 is poured up to the tips of the rib meshes 2-2 and core meshes 3-2 .
三段階()ではまず上筋受14、交差筋10
−3を肋筋メツシユ2−2、中子筋メツシユ3−2
先端部の横筋上に、梁垂直方向に二段に溶接し、
この各上筋受14、交差筋10−3上にそれぞれ
上筋5の下端筋5−1、上端筋5−2を配筋・圧接
する。次にかぶせ筋6を上筋5の上端筋5−2上
に、梁垂直方向に載せて取り付け、床スラブの配
筋後、コンクリートを打設する。 In the third stage (), first the upper muscle uke 14 and the cross muscle 10
−3 to costal muscle mesh 2-2 , core muscle mesh 3-2
Weld two steps vertically to the beam on the horizontal bar at the tip.
The lower end reinforcement 5-1 and the upper end reinforcement 5-2 of the upper reinforcement 5 are arranged and pressed onto each of the upper reinforcement supports 14 and the cross reinforcement 10-3 , respectively. Next, the covering reinforcing bars 6 are mounted on the top reinforcing bars 5-2 of the upper reinforcing bars 5 in a direction perpendicular to the beam, and after the reinforcement of the floor slab is arranged, concrete is poured.
第2図は各種鉄筋の配筋状態を示したものであ
る。 Figure 2 shows the arrangement of various reinforcing bars.
以上の工程により地中梁Aの施工作業は終了す
る。 The construction work of underground beam A is completed through the above steps.
次に第二の発明を第3図、第4図に基づいて説
明する。 Next, the second invention will be explained based on FIGS. 3 and 4.
この発明は内部の地中梁Aの施工方法であり、
施工手順は第一の発明と同様三段階からなる。 This invention is a method of constructing an internal underground beam A,
The construction procedure consists of three steps similar to the first invention.
第3図により施工手順を説明する。 The construction procedure will be explained with reference to FIG.
一段階()では最初に杭7頭部上に鉄筋スペ
ーサー8を設置し、この上に状に形成された肋
筋メツシユ2−1を梁方向に載置する。次に下筋
1の下端筋1−1を肋筋メツシユ2−1上に配筋・
圧接し、肋筋メツシユ2−1の内側にI字状の中
子筋メツシユ3−1を梁方向に配置する。続いて
交差筋10−1を下端筋1−1上に、これに垂直に
配筋し、その上に下筋1の上端筋1−2を配筋・
圧接した後、基礎スラブBの配筋をし、コンクリ
ート4−1を打設して基礎スラブBを形成する。
このときにも肋筋メツシユ2−1、中子筋メツシ
ユ3−1の上部は基礎スラブBから突出する。 In the first step (), first, a reinforcing bar spacer 8 is installed on the head of the pile 7, and a rib mesh 2-1 formed in the shape of a bar is placed thereon in the direction of the beam. Next, place the lower end reinforcement 1-1 of the lower reinforcement 1 on top of the rib mesh 2-1 .
The I-shaped core mesh 3-1 is placed inside the rib mesh 2-1 in the direction of the beam. Next, cross reinforcement 10-1 is placed perpendicular to bottom reinforcement 1-1 , and upper reinforcement 1-2 of bottom reinforcement 1 is placed on top of it.
After welding, reinforcement is placed for foundation slab B, and concrete 4-1 is poured to form foundation slab B.
At this time as well, the upper portions of the rib mesh 2-1 and the core mesh 3-1 protrude from the base slab B.
二段階()ではまず基礎スラブBに定着され
た肋筋メツシユ2−1、中子筋メツシユ3−1に継
いで肋筋メツシユ2−2、中子筋メツシユ3−2を
メツシユ控え11により保持しながら建込む。次
に梁型枠12、床型枠13を組み立て、肋筋メツ
シユ2−2、中子筋メツシユ3−2先端部の手前ま
でコンクリート4−2を打設する。 In the second stage (), first, the rib mesh 2-1 , the core muscle mesh 3-1, which are fixed on the foundation slab B, and the rib mesh 2-2 and the core muscle mesh 3-2 are held by the mesh retainer 11. While building. Next, the beam formwork 12 and the floor formwork 13 are assembled, and concrete 4-2 is poured up to the tips of the rib meshes 2-2 and core meshes 3-2 .
三段階()では初めに上筋受14、交差筋1
0−3を肋筋メツシユ2−2、中子筋メツシユ3−
2先端部の横筋上に、梁垂直方向に二段に取り付
け、各上筋受14、交差筋10−3上にそれぞれ
上筋5の下端筋5−1、上端筋5−2を配筋・圧接
する。続いて上端筋5−2上にかぶせ筋6を梁垂
直方向に取り付け、スラブ筋の組み立て後コンク
リートを打設し、床スラブまで形成して作業は終
了する。 In the third stage (), first the upper muscle holder 14, the cross muscle 1
0-3 to costal muscle mesh 2-2 , takata muscle mesh 3-
On the horizontal reinforcement at the tip of 2 , the lower end reinforcement 5-1 and the upper end reinforcement 5-2 of the upper reinforcement 5 are placed on each upper reinforcement holder 14 and the cross reinforcement 10-3, respectively. Pressure contact. Next, the cover reinforcement 6 is installed on the upper end reinforcement 5-2 in the vertical direction of the beam, and after assembling the slab reinforcement, concrete is poured to form the floor slab, and the work is completed.
第4図は鉄筋の配筋状態を示す。 Figure 4 shows the arrangement of reinforcing bars.
この発明は以上の通り、メツシユの継手毎にコ
ンクリートを打設していくものであるので、鉄筋
の組み立てを確実に、容易に行なうことができ、
この結果簡単に地中梁を形成することができる。
As described above, in this invention, concrete is poured for each mesh joint, so reinforcing bars can be assembled reliably and easily.
As a result, underground beams can be easily formed.
第1図、第2図は第一の発明の実施例を示した
もので、第1図は施工手順を、第2図は配筋状態
をそれぞれ示した断面図である。第3図、第4図
は第二の発明の実施例を示したもので、同じく第
3図は施工手順を、第4図は配筋状態を示した断
面図である。
A……地中梁、B……基礎スラブ、1……下
筋、1−1……下端筋、1−2……上端筋、2−1,
2−2……肋筋メツシユ、3−1,3−2……中子
筋メツシユ、4−1,4−2……コンクリート、5
……上筋、5−1……下端筋、5−2……上端筋、
6……かぶせ筋、7……杭、8……鉄筋スペーサ
ー、9……杭筋、10−1,10−3……交差筋、
11……メツシユ筋控え、12……梁型枠、13
……床型枠、14……上筋受。
FIGS. 1 and 2 show an embodiment of the first invention, with FIG. 1 being a sectional view showing the construction procedure, and FIG. 2 being a sectional view showing the reinforcement arrangement state. FIG. 3 and FIG. 4 show an embodiment of the second invention, and FIG. 3 is a sectional view showing the construction procedure, and FIG. 4 is a sectional view showing the reinforcement state. A...Underground beam, B...Foundation slab, 1...Bottom reinforcement, 1-1 ...Bottom reinforcement, 1-2 ...Top reinforcement, 2-1 ,
2-2 ... Rib mesh, 3-1 , 3-2 ... Core mesh, 4-1 , 4-2 ... Concrete, 5
... Upper reinforcement, 5-1 ... Lower end reinforcement, 5- 2 ... Upper end reinforcement,
6... Cover bar, 7... Pile, 8... Rebar spacer, 9... Pile bar, 10-1 , 10-3 ... Cross bar,
11...Mesh reinforcement, 12...Beam formwork, 13
...Floor formwork, 14...Upper reinforcement support.
Claims (1)
筋スペーサー上に肋筋メツシユを杭上方に伸びた
杭筋の両外側に、梁方向に載置し、肋筋メツシユ
上に下筋の下端筋を配筋・圧接するとともに、肋
筋メツシユの内側に中子筋メツシユを梁方向に配
置して交差筋を下端筋上に、これに垂直に配筋
し、下筋の上端筋を交差筋上に配筋・圧接した
後、基礎スラブの配筋をするとともに、コンクリ
ートを打設して基礎スラブを形成し、 続いて肋筋メツシユ及び中子筋メツシユを既に
取り付けられた前記肋筋メツシユ、中子筋メツシ
ユに継いで建込み、梁型枠及び床型枠を組んで各
メツシユの先端手前までコンクリートを打設し、 更に上筋受及び交差筋を各メツシユに梁垂直方
向に取り付けてこれら上筋受及び交差筋上にそれ
ぞれ上筋の下端筋及び上端筋を配筋・圧接すると
ともに、かぶせ筋を上筋上に梁垂直方向に取り付
けて床スラブの配筋をし、コンクリートを打設し
て地中梁を形成する地中梁の施工方法。 2 杭頭上に鉄筋スペーサーを設置してこの鉄筋
スペーサー上に肋筋メツシユを梁方向に載置し、
肋筋メツシユ上に下筋の下端筋を配筋・圧接する
とともに、肋筋メツシユの内側に中子筋メツシユ
を梁方向に配置して交差筋を下端筋上に、これに
垂直に配筋し、下筋の上端筋を交差筋上に配筋・
圧接した後、基礎スラブの配筋をするとともに、
コンクリートを打設して基礎スラブを形成し、 続いて肋筋メツシユ及び中子筋メツシユを既に
取り付けられた前記肋筋メツシユ、中子筋メツシ
ユに継いで建込み、梁型枠及び床型枠を組んで各
メツシユの先端手前までコンクリートを打設し、 更に上筋受及び交差筋を各メツシユに梁垂直方
向に取り付けてこれら上筋受及び交差筋上にそれ
ぞれ上筋の下端筋及び上端筋を配筋・圧接すると
ともに、かぶせ筋を上筋上に梁垂直方向に取り付
けて床スラブの配筋をし、コンクリートを打設し
て地中梁を形成する地中梁の施工方法。[Scope of Claims] 1. Reinforcing bar spacers are placed on both sides of the pile head, and on the reinforcing bar spacers, cost bar meshes are placed on both sides of the pile bars extending above the pile in the direction of the beam, and on the cost bar meshes. At the same time, the lower end reinforcement of the lower end reinforcement is arranged and pressed, and the core reinforcement mesh is placed in the beam direction inside the cost reinforcement mesh, and the cross reinforcement is placed on the lower end reinforcement and perpendicular to it. After arranging and pressing the upper end reinforcement onto the cross reinforcement, we placed reinforcement for the foundation slab and poured concrete to form the foundation slab, and then the rib mesh and core reinforcement mesh were already installed. Erection is carried out in succession to the rib mesh and core mesh, the beam formwork and floor formwork are assembled, and concrete is poured to the front of the tip of each mesh.Furthermore, upper reinforcement supports and cross reinforcements are placed perpendicular to the beam on each mesh. At the same time, the lower end reinforcement and upper end reinforcement of the upper reinforcement are arranged and pressed onto the upper reinforcement and cross reinforcement, respectively, and the cover reinforcement is installed on the upper reinforcement in the vertical direction of the beam to arrange the floor slab reinforcement. , An underground beam construction method that involves pouring concrete to form an underground beam. 2 Install a reinforcing bar spacer above the pile head, place the rib mesh on this reinforcing bar spacer in the direction of the beam,
At the same time, arrange and press the lower end reinforcement of the lower end reinforcement on the rib mesh, place the core reinforcement mesh inside the costar mesh in the beam direction, and arrange the cross reinforcement on the lower end reinforcement perpendicular to it. , place the upper end reinforcement of the lower reinforcement on the cross reinforcement.
After welding, we placed reinforcement for the foundation slab and
Concrete is poured to form a foundation slab, and then the cost reinforcement mesh and core reinforcement mesh are connected to the cost reinforcement mesh and core reinforcement mesh that have already been installed for erection, and the beam formwork and floor formwork are installed. Concrete is placed in front of the tip of each mesh, and upper reinforcement supports and cross reinforcements are attached to each mesh in the vertical direction of the beam, and the lower and upper reinforcements of the upper reinforcement are placed on these upper reinforcement supports and cross reinforcements, respectively. A construction method for underground beams in which reinforcement is placed and pressure welded, and cover reinforcements are installed perpendicularly to the beam on top of the upper reinforcement to arrange floor slab reinforcement, and concrete is poured to form an underground beam.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP22844285A JPS6286230A (en) | 1985-10-14 | 1985-10-14 | Construction of underground beam |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP22844285A JPS6286230A (en) | 1985-10-14 | 1985-10-14 | Construction of underground beam |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6286230A JPS6286230A (en) | 1987-04-20 |
| JPH0367166B2 true JPH0367166B2 (en) | 1991-10-22 |
Family
ID=16876557
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP22844285A Granted JPS6286230A (en) | 1985-10-14 | 1985-10-14 | Construction of underground beam |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6286230A (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0639790B2 (en) * | 1986-08-30 | 1994-05-25 | 鹿島建設株式会社 | Underground beam construction method |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS59161522A (en) * | 1983-02-22 | 1984-09-12 | Hiroshi Suwa | Fabrication work of underground beam of high height |
-
1985
- 1985-10-14 JP JP22844285A patent/JPS6286230A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6286230A (en) | 1987-04-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2897663B2 (en) | How to build underground structures | |
| JPH0959933A (en) | Filled coated steel tube concrete structure and construction method | |
| JPH10311041A (en) | Column base foundation of precast concrete column | |
| JPS6286230A (en) | Construction of underground beam | |
| JPH08319695A (en) | Reinforcing bar assembly for underground beams and method of constructing underground beams | |
| JP2790959B2 (en) | Underground beam construction method | |
| JP2003013493A (en) | Beam-column joint and beam-joint method | |
| JP2592224Y2 (en) | Structure of joint between RC beam and steel structure | |
| JPH0519383Y2 (en) | ||
| JPH03279533A (en) | Constructing method for rigid-frame type rc super-high building | |
| JPH02167937A (en) | Connecting work of steel plate-concrete structure | |
| JPH044091Y2 (en) | ||
| JPH01137032A (en) | Method of lap joint construction of main reinforcement in post and beam joining section | |
| JPH0571747B2 (en) | ||
| JP2001200594A (en) | Method for constructing structure consisting of column with large section and beam | |
| JPH0448136B2 (en) | ||
| JP2003013495A (en) | Concrete construction design and construction ordering system | |
| JP2651506B2 (en) | How to apply underground beams | |
| JPH02229337A (en) | Concrete pillar construction method | |
| JPH058303B2 (en) | ||
| JPH093914A (en) | Structure of underground beam and construction method of underground beam | |
| JPH0460183B2 (en) | ||
| JPH04309630A (en) | Skeleton construction method using pc member | |
| JPH04237731A (en) | Construction method of RC column with core reinforcement | |
| JPH0588331B2 (en) |