JPH0377903B2 - - Google Patents
Info
- Publication number
- JPH0377903B2 JPH0377903B2 JP15249085A JP15249085A JPH0377903B2 JP H0377903 B2 JPH0377903 B2 JP H0377903B2 JP 15249085 A JP15249085 A JP 15249085A JP 15249085 A JP15249085 A JP 15249085A JP H0377903 B2 JPH0377903 B2 JP H0377903B2
- Authority
- JP
- Japan
- Prior art keywords
- main
- members
- small
- reinforcements
- beam member
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 230000002787 reinforcement Effects 0.000 claims description 41
- 239000004567 concrete Substances 0.000 claims description 22
- 238000010276 construction Methods 0.000 claims description 8
- 230000003014 reinforcing effect Effects 0.000 description 6
- 238000000034 method Methods 0.000 description 4
- 238000009434 installation Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
Landscapes
- Rod-Shaped Construction Members (AREA)
- Joining Of Building Structures In Genera (AREA)
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は交点を有するプレキヤスト鉄筋コンク
リート小梁(以下PC小梁と呼称する)の構築工
法に係るものである。DETAILED DESCRIPTION OF THE INVENTION (Industrial Application Field) The present invention relates to a construction method for precast reinforced concrete beams having intersection points (hereinafter referred to as PC beams).
(従来の技術)及び(発明が解決しようとする問
題点)
従来この種のPC小梁を施工しようとする場合、
揚重装置及び支保工等の仮設工事に難点があり、
未だ実施されるに至つていないのが現状である。(Prior art) and (problems to be solved by the invention) Conventionally, when attempting to construct this type of PC beam,
There were difficulties in temporary construction work such as lifting equipment and shoring.
The current situation is that it has not yet been implemented.
(問題点を解決するための手段)
本発明はこのような問題点を解決するために提
案されたもので、柱及び大梁を構築したのち、小
梁交叉部側面より梁主筋が突設されたPC小梁部
材を相対する大梁間に架渡し、次いで同PC小梁
部材より突設された前記梁主筋と同PC小梁部材
に交叉する他の小梁部材の梁主筋とを接合して、
梁主筋を接合したPC小梁部材同士間の〓間に後
打ちコンクリートを打設することを特徴とする
PC小梁構築工法に係るものである。(Means for Solving the Problems) The present invention was proposed to solve these problems, and after constructing the columns and girders, the main beam reinforcements were installed protruding from the side surfaces of the small beam intersections. A PC small beam member is spanned between opposing large beams, and then the main beam reinforcement protruding from the PC small beam member and the main beam reinforcement of another small beam member intersecting the same PC small beam member are connected,
The feature is that post-cast concrete is placed between the PC beam members with the main beam reinforcements connected.
This relates to the PC beam construction method.
(作用)
本発明においては前記したように、小梁交叉部
側面より梁主筋が突設されたPC小梁部材を予め
製作し、同PC小梁部材を相対する大梁間に架渡
し、同部材の小梁交叉部側面より突出する梁主筋
と、同部材と交叉する小梁部材の梁主筋とを接合
したのち、梁主筋を接合したPC梁部材同士間に
形成された〓間に後打ちコンクリートを打設する
ことによつて、前記PC小梁部材に他の小梁部材
を一体に交叉するように施工するものである。(Function) As described above, in the present invention, a PC small beam member having main beam reinforcements protruding from the side surface of the small beam intersection is manufactured in advance, and the PC small beam member is spanned between opposing girders. After joining the main beam reinforcement that protrudes from the side of the small beam intersection and the main beam reinforcement of the small beam member that intersects with the same member, post-cast concrete is placed between the gaps formed between the PC beam members to which the main beam reinforcements have been joined. By pouring, the PC beam member is constructed so as to integrally intersect with the other small beam member.
(発明の効果)
このように本発明によれば、小梁交叉部側面に
梁主筋が突設されたPC小梁部材を予め製作し、
同部材を柱、大梁の構築後搬入して相対する大梁
間に架渡し、前記梁主筋の突出部と、他の小梁部
材の梁主筋とを接合したのち、梁主筋を接合した
PC梁部材同士間に形成された〓間に後打ちコン
クリートを打設するようにしたので、支保工が大
幅に簡略化され、また柱、大梁の建込用揚重装置
をそのまま利用して前記PC小梁部材の据付が行
なわれ、施工が著しく簡略化される。(Effects of the Invention) According to the present invention, a PC beam member having main beam reinforcements protruding from the side surface of the cross section of the beam is manufactured in advance, and
After constructing the columns and girders, the same members were brought in and placed between the opposing girders, and the protruding parts of the main beam reinforcements were connected to the main beam reinforcements of other small beam members, and then the main beam reinforcements were connected.
Post-cast concrete is placed between the gaps between the PC beam members, which greatly simplifies the shoring work, and the lifting equipment used for pillar and girder erection can be used as is. PC beam members are installed, which greatly simplifies construction.
更に前記PC小梁部材と他の小梁部材との交叉
部において、同小梁部材の梁主筋と前記PC小梁
部材における梁主筋の突出部とを接合して、梁主
筋を接合したPC梁部材同士間に形成された〓間
にコンクリートを打設するようにしたので、前記
PC小梁部材と他の小梁部材とが交叉部において
一体的に接合され、構造的に信頼性の高い、交点
を有するPC小梁が構築される。 Furthermore, at the intersection of the PC small beam member and another small beam member, the main beam reinforcement of the same small beam member and the protruding part of the main beam reinforcement of the PC small beam member are joined to form a PC beam in which the main beam reinforcements are joined. Since concrete was placed between the gaps formed between the members, the above-mentioned
The PC beam member and other beam members are integrally joined at the intersection, and a structurally reliable PC beam having an intersection is constructed.
(実施例) 以下本発明を図示の実施例について説明する。(Example) The present invention will be described below with reference to the illustrated embodiments.
AはPC小梁部材で、長尺の縦部材1の一側面
より一双の短尺の横部材2が一体に岐出され、他
側面からは前記横部材2の延長位置において梁主
筋3が突設されている。更に前記縦横両部材1,
2の自由端には大梁載架用の切欠段部1a,2a
が欠截されている。(第3図参照)
A′は前記PC小梁部材Aと交叉すべきPC小梁部
材で、その両端面より梁主筋4が突設されてい
る。(第3照参照)
而してPC柱B、PC大梁Cを構築して構造物の
構格を構成したのち、(第4図参照)一双のPC小
梁部材Aの各縦部材1の両端切欠段部1aを相対
する大梁Cに設けた小梁受け用切欠段部5に載架
するとともに、各横部材2の切欠段部2aを前記
相対する大梁C間に配設された大梁Cの切欠段部
5に載架する。 A is a PC beam member, in which a pair of short horizontal members 2 are integrally branched out from one side of a long vertical member 1, and a main beam reinforcement 3 is protruded from the other side at an extended position of the horizontal member 2. has been done. Furthermore, the vertical and horizontal members 1,
At the free ends of 2, there are cutout steps 1a and 2a for girder mounting.
is missing. (See Figure 3) A' is a PC beam member that is to intersect with the PC beam member A, and main beam reinforcements 4 are provided protruding from both end faces thereof. (See Figure 3) After constructing the frame of the structure by constructing PC columns B and PC girders C, (see Figure 4) both ends of each vertical member 1 of a pair of PC beam members A are constructed. The cutout steps 1a are placed on the cutout steps 5 for supporting small beams provided on the opposing girders C, and the cutout steps 2a of each horizontal member 2 are mounted on the cutout steps 5 of the girder C provided between the opposing girders C. It is mounted on the cutout stepped portion 5.
次いで相隣るPC小梁部材A,A間にPC小梁部
材A′を配設し、同PC小梁部材A′の突出梁主筋4
と、前記PC小梁部材Aの突出梁主筋3とをカプ
ラー6で継接して、後打ちコンクリート7を打設
し、(第2図参照)前記両部材A,A′を一体に結
合し、格子状のPC小梁を構築する。(第1図参
照)
なお前記各部材A,A′は第5図に示すように
上下主筋3,4及びスターラツプ8とが内蔵され
る場合と、第6図に示すように下端主筋3,4と
スターラツプ8の一部とだけが内蔵され、上端主
筋がPC小梁上のスラブ施工時に配筋される場合
とがある。 Next, a PC small beam member A' is arranged between adjacent PC small beam members A, A, and the protruding beam main reinforcement 4 of the PC small beam member A' is
and the protruding beam main reinforcement 3 of the PC beam member A are connected with a coupler 6, post-cast concrete 7 is poured (see Figure 2), and the two members A and A' are joined together, Build a grid of PC beams. (See Fig. 1) Each member A, A' has two cases in which the upper and lower main reinforcements 3 and 4 and a stirrup 8 are built in as shown in Fig. 5, and a case in which the lower end main reinforcements 3 and 4 are built in as shown in Fig. 6. In some cases, only part of the stirrup 8 is built-in, and the upper main reinforcement is placed during slab construction on the PC beam.
図中9は幅止め筋、10は補強筋である。 In the figure, 9 is a stop bar, and 10 is a reinforcing bar.
図示の実施例は前記したように小梁交叉部側面
に梁主筋3が突設された縦部材1と、同部材1よ
り岐出された横部材2とよりなるPC小梁部材A
を予め製作し、同部材Aを柱B、大梁Cの構築後
搬入して前記縦横部材1,2の各端部切欠段部1
a,2aを大梁Cの切欠段5に載架することによ
つて同大梁C間の支保工なしで前記PC小梁部材
Aを支持し、同部材Aにおける梁主筋3の突出部
とPC小梁部材A′の梁主筋4の突出部とを接合し
て後打ちコンクリート7を打設し、前記両部材
A,A′が一体的に結合された格子状のPC小梁を
構築するようにしたものであり、図示の実施例に
よれば支保工が大幅に簡略化され、また柱B、大
梁Cの建込用揚重装置がそのまま前記各部材A,
A′の据付用に利用され、施工が著しく容易にな
る。 As described above, the illustrated embodiment is a PC beam member A consisting of a vertical member 1 having a main beam reinforcement 3 protruding from the side surface of the cross section of the beam, and a horizontal member 2 branching out from the member 1.
is manufactured in advance, and the same member A is carried in after constructing the pillars B and girders C, and the cutout steps 1 at each end of the vertical and horizontal members 1 and 2 are made.
a, 2a are mounted on the cutout step 5 of the girder C, the PC beam member A is supported without shoring between the girder C, and the protrusion of the beam main reinforcement 3 in the member A and the PC small beam member A are supported. The beam member A' is joined to the protruding part of the beam main reinforcement 4, and post-cast concrete 7 is poured to construct a lattice-shaped PC beam in which both the members A and A' are integrally connected. According to the illustrated embodiment, the shoring is greatly simplified, and the lifting equipment for erection of the pillars B and girders C can be used as is for the above-mentioned members A,
It is used for the installation of A′, and the construction becomes significantly easier.
更に前記両部材A,A′は夫々の梁主筋3,4
の突出端部がカプラー6で接合され、後打ちコン
クリート7が打設されるので、前記両部材A,
A′は一体的に結合され、構造的に信頼性の高い
格子状PC小梁が構築される。 Furthermore, both members A and A' are connected to the beam main reinforcements 3 and 4, respectively.
The protruding ends of the members A,
A′ is integrally connected to construct a structurally reliable lattice-shaped PC beam.
第7図は本発明の他の実施例を示し、PC小梁
部材Aが部材1と同部材1より岐出された1本の
横部材2とより構成されている他は、前記実施例
と同じである。 FIG. 7 shows another embodiment of the present invention, which is the same as the embodiment described above except that the PC beam member A is composed of a member 1 and one horizontal member 2 branched out from the member 1. It's the same.
図中前記実施例と均等部分には同一符号が附さ
れている。 In the figure, parts equivalent to those of the above embodiment are given the same reference numerals.
またPC小梁部材A′は前記PC小梁部材Aに対向
する一端部より梁主筋4が突設され、他端部が直
接大梁Cの切欠段部5に載架され、前記両部材
A,A′の相対する梁主筋突設部を接合して、同
部に後打ちコンクリート7を打設するものであ
る。 Also, the PC beam member A' has a main beam reinforcement 4 protruding from one end opposite to the PC beam member A, and the other end is directly mounted on the cutout step 5 of the girder C. The opposing beam main reinforcement protrusions of A' are joined and post-cast concrete 7 is placed in the same area.
第8図は本発明の他の実施例を示し、第1図の
実施例においてPC小梁部材A′の代りに現場打ち
コンクリートによる小梁部材A″を適用したもの
で、相対するPC小梁部材Aの縦部材1,1の各
側面に突設された梁主筋3,3と継手用主筋11
の両端とを重ね継ぎし、現場打ちコンクリート1
2を打設して前記両PC小梁部材Aと一体化され
た現場打ちコンクリート製の小梁部材A″を構成
する。(第9図参照)
なお図中前記実施例と均等部分には同一符号が
附されている。 FIG. 8 shows another embodiment of the present invention, in which a small beam member A'' made of cast-in-place concrete is applied instead of the PC small beam member A' in the embodiment of FIG. Beam main reinforcements 3, 3 and joint main reinforcements 11 protruding from each side of the vertical members 1, 1 of member A
Layer and splice both ends of the cast-in-place concrete 1.
2 to construct a cast-in-place concrete beam member A″ that is integrated with both PC beam members A. (See Figure 9) In the figure, the same parts as in the above example are the same. A code is attached.
第10図に示す実施例は第7図の実施例におい
て中央部のPC小梁部材A′の部分を現場打ちコン
クリート製の小梁部材A″として構成した場合を
示す。 The embodiment shown in FIG. 10 shows a case where the central PC beam member A' in the embodiment shown in FIG. 7 is constructed as a small beam member A'' made of cast-in-place concrete.
図中前記各実施例と均等部分には同一符号が附
されている。 In the drawings, parts equivalent to those of the above embodiments are given the same reference numerals.
第11図に示す実施例では前記第8図乃至第1
0図に示す実施例において、相対するPC小梁部
材A,Aにおける縦部材1,1から突出された梁
主筋3,3に夫々カプラー13,13を介して継
手用主筋14,14を継接するとともに、同両継
手用主筋14,14を重ね継ぎし、現場打ちコン
クリート15を打設して、現場打ちコンクリート
による小梁部材A″を構成するものである。 In the embodiment shown in FIG.
In the embodiment shown in Figure 0, joint main reinforcements 14, 14 are connected to the beam main reinforcements 3, 3 protruding from the vertical members 1, 1 in the opposing PC beam members A, A through couplers 13, 13, respectively. At the same time, the main reinforcing bars 14, 14 for both joints are overlapped and cast-in-place concrete 15 is poured to form a small beam member A'' made of cast-in-place concrete.
図中前記各実施例と均等部分には同一符号が附
されている。 In the drawings, parts equivalent to those of the above embodiments are given the same reference numerals.
第12図に示す実施例は相対するPC小梁部材
A,A間に現場打ちコンクリートによる小梁部材
A″を施工するのに当り、相対するPC小梁部材
A,Aの側面に、梁主筋3の端部に継接されたス
リーブ16,16を埋設し、同各スリーブ16,
16には夫々継手用主筋17,17を継接し、相
対する継手用主筋17,17を重ね継ぎし、後打
ちコンクリート18を打設して現場打ちコンクリ
ートによる小梁部材A″を構成するものである。 The example shown in Fig. 12 is a small beam member made of cast-in-place concrete between the opposing PC small beam members A and A.
A'', the sleeves 16, 16 connected to the ends of the beam main reinforcements 3 are buried in the sides of the opposing PC beam members A, A, and the sleeves 16, 16 are
The main reinforcing bars 17, 17 for joints are respectively connected to 16, the opposing main reinforcing bars 17, 17 are overlapped, and post-cast concrete 18 is poured to form a small beam member A'' made of cast-in-place concrete. be.
なお前記スリーブ16には梁主筋3及び継手用
主筋17を継接したのち、グラウト材が注入され
るものである。 Incidentally, after the main beam reinforcing bars 3 and the main reinforcing bars 17 for joint are joined to the sleeve 16, grout material is injected into the sleeve 16.
図中前記各実施例と均等部分には同一符号が附
されている。 In the drawings, parts equivalent to those of the above embodiments are given the same reference numerals.
以上本発明を実施例について説明したが、本発
明は勿論このような実施例にだけ局限されるもの
ではなく、本発明の精神を逸脱しない範囲内で
種々の設計の改変を施しうるものである。 Although the present invention has been described above with reference to embodiments, the present invention is, of course, not limited to such embodiments, and can be modified in various ways without departing from the spirit of the present invention. .
第1図は本発明の方法によつてPC小梁及び柱、
大梁よりなる架構の一実施例を示す平面図、第2
図はその部分横断平面図、第3図は大梁間に架設
されるPC小梁部材及び同部材に交叉して接合さ
れるPC小梁部材の斜視図、第4図は小梁架設前
の架構を示す平面図、第5図及び第6図は夫々前
記大梁間に架設されるPC小梁部材及び同部材に
交叉して接合されるPC小梁部材の断面図、第7
図及び第8図は夫々本発明の方法によつて構成さ
れた架構の他の実施例を示す平面図、第8図は本
発明の方法によつて構成された架構の更に他の実
施例を示す平面図、第9図はその部分横断平面
図、第10図は本発明の方法によつて構成された
架構の他の実施例を示す平面図、第11図及び第
12図はその現場打ち小梁部材部分を示す横断平
面図である。
A…PC小梁部材、A′…PC小梁部材、A″…現
場打ちコンクリート小梁部材、、B…柱、C…大
梁、1…縦部材、2…横部材、3,4…梁主筋、
6…カプラー、7…後打ちコンクリート、11…
継手用主筋、12…現場打ちコンクリート、13
…カプラー、14…継手用主筋、15…現場打ち
コンクリート、16…スリーブ、17…継手用主
筋、18…現場打ちコンクリート。
FIG. 1 shows PC beams and columns formed by the method of the present invention.
A plan view showing an example of a frame made of girders, 2nd
The figure is a partial cross-sectional plan view, Figure 3 is a perspective view of the PC beam member installed between the girders and the PC beam member connected to the same member, and Figure 4 is the frame before the installation of the beam. 5 and 6 are cross-sectional views of the PC beam members installed between the girders and the PC beam members intersecting and joined to the same members, respectively.
8 and 8 are plan views respectively showing other embodiments of the frame constructed by the method of the present invention, and FIG. 8 shows still another embodiment of the frame constructed by the method of the present invention. 9 is a partial cross-sectional plan view thereof, FIG. 10 is a plan view showing another embodiment of the structure constructed by the method of the present invention, and FIGS. 11 and 12 are its on-site construction. It is a cross-sectional plan view which shows a small beam member part. A...PC small beam member, A'...PC small beam member, A''...cast-in-place concrete small beam member, B...column, C...large beam, 1...vertical member, 2...horizontal member, 3, 4...beam main reinforcement ,
6...Coupler, 7...Post-cast concrete, 11...
Main reinforcement for joint, 12...Cast-in-place concrete, 13
...Coupler, 14...Main reinforcement for joint, 15...Cast-in-place concrete, 16...Sleeve, 17...Main reinforcement for joint, 18...Cast-in-place concrete.
Claims (1)
より梁主筋が突設されたPC小梁部材を相対する
大梁間に架渡し、次いで同PC小梁部材より突設
された前記梁主筋と同PC小梁部材に交叉する他
の小梁部材の梁主筋とを接合して、梁主筋を接合
したPC小梁部材同士間の〓間に後打ちコンクリ
ートを打設することを特徴とするPC小梁構築工
法。1 After constructing the columns and girders, the PC beam members with main beam reinforcements protruding from the side surfaces of the small beam intersections are placed between the opposing girders, and then the main beam reinforcements protruding from the PC beam members are A PC characterized in that the main beam reinforcement of another small beam member intersecting the same PC small beam member is joined, and post-cast concrete is poured between the PC small beam members to which the main beam reinforcements are connected. Small beam construction method.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP15249085A JPS6213628A (en) | 1985-07-12 | 1985-07-12 | PC beam construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP15249085A JPS6213628A (en) | 1985-07-12 | 1985-07-12 | PC beam construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6213628A JPS6213628A (en) | 1987-01-22 |
| JPH0377903B2 true JPH0377903B2 (en) | 1991-12-12 |
Family
ID=15541610
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP15249085A Granted JPS6213628A (en) | 1985-07-12 | 1985-07-12 | PC beam construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6213628A (en) |
-
1985
- 1985-07-12 JP JP15249085A patent/JPS6213628A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6213628A (en) | 1987-01-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3752999B2 (en) | Upper and lower integrated bridge and its construction method | |
| JP2535722B2 (en) | Reinforcement concrete column and steel beam connection structure and building construction method | |
| JP2622013B2 (en) | Reinforced concrete shear wall structure | |
| JPH0480444A (en) | Connection unit of reinforced concrete pole and steel framed beam | |
| JPH0377903B2 (en) | ||
| JP2758208B2 (en) | Joint method between column and steel reinforced concrete beam | |
| JPH1150538A (en) | Building and its construction method | |
| JP2516808B2 (en) | Construction method of ramen type precast concrete structure | |
| JPH0375704B2 (en) | ||
| JPS6312987B2 (en) | ||
| JPH0123614B2 (en) | ||
| JP2893406B2 (en) | Precast concrete beam-column joining method | |
| JPH02236328A (en) | Construction method for super-highrice building | |
| JPH06306931A (en) | Construction of steel frame reinforced concrete structure | |
| JPH0366878A (en) | Construction method of precast columns and beams and precast shear walls | |
| JPH0781315B2 (en) | Construction method of composite structure with precast reinforced concrete columns and steel beams | |
| JP2729132B2 (en) | How to join columns and precast concrete beams | |
| JPS6213629A (en) | Construction of pc small beam | |
| JPH04237735A (en) | Constructing method for pillar and beam of building | |
| JPH0350846B2 (en) | ||
| JPH0531630B2 (en) | ||
| JPH0443131B2 (en) | ||
| JPH04238927A (en) | Jointing method for precast src beam | |
| JP2001207528A (en) | U-shaped precast concrete beam member and column and beam joining structure | |
| JPH02292429A (en) | PC column and beam joining method |