JPH0380210B2 - - Google Patents

Info

Publication number
JPH0380210B2
JPH0380210B2 JP26042887A JP26042887A JPH0380210B2 JP H0380210 B2 JPH0380210 B2 JP H0380210B2 JP 26042887 A JP26042887 A JP 26042887A JP 26042887 A JP26042887 A JP 26042887A JP H0380210 B2 JPH0380210 B2 JP H0380210B2
Authority
JP
Japan
Prior art keywords
flange
slab
insert
precast concrete
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP26042887A
Other languages
Japanese (ja)
Other versions
JPH01102105A (en
Inventor
Zenzaburo Takuma
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ORIENTAL KENSETSU KK
Original Assignee
ORIENTAL KENSETSU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ORIENTAL KENSETSU KK filed Critical ORIENTAL KENSETSU KK
Priority to JP26042887A priority Critical patent/JPH01102105A/en
Publication of JPH01102105A publication Critical patent/JPH01102105A/en
Publication of JPH0380210B2 publication Critical patent/JPH0380210B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】 産業上の利用分野 この発明は鋼桁橋の損傷を受けたコンクリート
床板の打替の際に用いられるプレキヤストコンク
リート床版と鋼桁との固定方法に関するものであ
る。
DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application This invention relates to a method for fixing a precast concrete deck slab and a steel girder, which is used when replacing a damaged concrete deck slab of a steel girder bridge.

従来の技術 従来、この種の固定方法に用いる装置として実
開昭61−198310号公報記載の考案が知られてい
る。同考案は概略ほぼ第7図及び第8図に示すよ
うに形成されている。第7図は鋼桁橋の一例の断
面を示し、aはプレキヤストコンクリート床版
(以下単に床版と言う)、bは鋼桁、cは橋脚、d
は歩道である。
BACKGROUND ART Conventionally, a device described in Japanese Utility Model Application Publication No. 198310/1983 has been known as a device used in this type of fixing method. The device is generally constructed as shown in FIGS. 7 and 8. Figure 7 shows a cross section of an example of a steel girder bridge, where a is a precast concrete deck slab (hereinafter simply referred to as the deck slab), b is a steel girder, c is a bridge pier, and d
is a sidewalk.

そして床版aの新旧交換の際、新床版aを鋼桁
bに固定する場合、ほぼ第8図に示すようにして
行われる。即ち、同図において、まず鋼桁bのフ
ランジeにボルト穴fをあけ、又フランジeの端
縁に山形鋼による型枠gを溶接する。そしてこの
型枠g上に床版aをのせ、次に型枠g内にモルタ
ルhを注入する。なおこの床版aにも凹部kに通
じるボルト穴lが形成されている。次に前記ボル
ト穴l、同i、同fを貫通してボルトmを設け、
ナツトnにより固定する。なおpはパツキン、q
はパイプを示す。
When the new deck slab a is replaced with a new one, fixing the new deck slab a to the steel girder b is carried out approximately as shown in FIG. 8. That is, in the figure, bolt holes f are first drilled in the flange e of the steel girder b, and a formwork g made of angle iron is welded to the edge of the flange e. Then, a floor slab a is placed on this form g, and then mortar h is poured into the form g. Note that bolt holes l communicating with the recesses k are also formed in this floor slab a. Next, bolts m are provided passing through the bolt holes l, i, and f,
Secure with nut n. In addition, p is Patsukin, q
indicates a pipe.

発明が解決しようとする問題点 しかし上記従来の方法は次のような難点を有し
ている。それは鋼桁bのフランジeにボルト穴f
をあけなければならず、又山形鋼gを溶接しなけ
ればならず面倒である。しかもこれらは多数個所
で、かつかなり長い長さに亘つて行わなければな
らず、これらの作業を夜間等の交通のない時間内
に行うことは困難である。
Problems to be Solved by the Invention However, the above conventional method has the following difficulties. It is the bolt hole f in the flange e of the steel girder b.
It is troublesome because the angle iron g has to be welded. Moreover, these operations must be performed at multiple locations and over a considerable length of time, and it is difficult to perform these operations during times when there is no traffic, such as at night.

この発明はこのような問題を解決するためにな
されたもので、その目的は上記のような面倒な現
場での作業を省略でき、床版の打替え工事をきわ
めて短時間に、かつ従来のものより容易にできる
プレキヤストコンクリート床版と鋼桁との固定方
法を提供することである。
This invention was made in order to solve these problems, and its purpose is to eliminate the troublesome on-site work mentioned above, to make the floor slab replacement work extremely short, and to replace the conventional work. An object of the present invention is to provide an easier method of fixing a precast concrete deck slab and a steel girder.

問題点を解決するための手段 この発明について述べると、それはプレキヤス
トコンクリート床版に予め近接させて主インサー
ト及び副インサートを設け、該プレキヤストコン
クリート床版を主桁のフランジ上に乗せ、前記主
インサートにより、高さ調整ボルトを用いて該プ
レキヤストコンクリート床版の前記フランジから
の高さを調整し、前記副インサートに、押え金具
を有する鉛直ボルトを螺合し、該押え金具により
前記フランジの端部に型枠を固定し、該型枠内に
モルタルを打設し、該モルタルの硬化後前記高さ
調整ボルト及び型枠を取り去り、前記鉛直ボルト
により押え金具を用いて、前記プレキヤストコン
クリート床版とフランジとを固定することを特徴
とするプレキヤストコンクリート床版と鋼桁との
固定方法である。
Means for Solving the Problems This invention is described by providing a main insert and a sub-insert in advance in close proximity to a precast concrete slab, placing the precast concrete slab on a flange of a main girder, and inserting the main insert into the main girder. The height of the precast concrete slab from the flange is adjusted by the insert using a height adjustment bolt, and a vertical bolt with a holding fitting is screwed into the sub-insert, and the holding fitting is used to adjust the height of the precast concrete slab from the flange. A formwork is fixed at the end, mortar is poured into the formwork, and after the mortar has hardened, the height adjustment bolts and the formwork are removed, and the precast concrete is fixed with the vertical bolts using a holding fitting. This is a method of fixing a precast concrete floor slab and a steel girder, which is characterized by fixing the floor slab and a flange.

作 用 フランジの上にのせた床版の主インサートに、
高さ調整ボルトを螺合し、これを螺進させてフラ
ンジを押し、又は後退させて高さを調整し、これ
により床版を既設床版と同じ高さに調整する。次
に副フランジに鉛直ボルトを螺合し、その押え金
具で、フランジに型枠を固定し、この型枠内にモ
ルタルを注入する。このモルタルの硬化後高さ調
整ボルトを抜き取る。又型枠を外し、前記のよう
にフランジと床版を固定するものである。
Function The main insert of the deck placed on the flange is
Screw the height adjustment bolts together and screw them forward to push or retreat the flange to adjust the height, thereby adjusting the floor slab to the same height as the existing floor slab. Next, a vertical bolt is screwed onto the secondary flange, a formwork is fixed to the flange using the holding metal fittings, and mortar is poured into the formwork. After this mortar hardens, remove the height adjustment bolt. Also, the formwork is removed and the flanges and floor slabs are fixed as described above.

実施例 第1図において、1は床版であり、2は鋼桁、
3は舗装、4はフランジを示す。又、第2図にお
いて5は主インサートであり、6は副インサート
を示す。7は高さ調整ボルト、8は鉛直ボルトで
ある。そして該鉛直ボルト8に押え金具9が設け
られており、同金具9は第5図に示すように複数
のボルト10が基体11に螺合して、これにより
型枠12をフランジ4に押しつけて固定するよう
になつている。13はばね、14はワツシヤ、1
5はボルト頭部を示す。又前記基体11は押え部
16を有している。次に第3図において17は主
インサートの設けられている穴、18は副インサ
ート6の設けられている穴を示す。
Example In Fig. 1, 1 is a deck slab, 2 is a steel girder,
3 indicates the pavement, and 4 indicates the flange. Further, in FIG. 2, 5 is a main insert, and 6 is a sub insert. 7 is a height adjustment bolt, and 8 is a vertical bolt. A holding fitting 9 is provided on the vertical bolt 8, and the holding fitting 9 has a plurality of bolts 10 screwed into the base body 11 as shown in FIG. 5, thereby pressing the formwork 12 against the flange 4. It is supposed to be fixed. 13 is a spring, 14 is a washer, 1
5 indicates the bolt head. Further, the base body 11 has a holding portion 16. Next, in FIG. 3, reference numeral 17 indicates a hole in which the main insert is provided, and 18 indicates a hole in which the sub-insert 6 is provided.

又、前記押え金具9は第4図に示すように形成
されてもよい。即ちばね13により押え部16を
兼ねさせても差支えはない。
Further, the presser metal fitting 9 may be formed as shown in FIG. 4. That is, there is no problem even if the spring 13 also serves as the presser part 16.

次に、第6図に示すように押え金具9に支持部
材17を設けてもよい。同支持部材17は一例と
して基体11に設けたボルトであり、これにより
押え金具9を両持ちとさせ、一層安定性を増さし
めている。なお同図において19は既設床版、2
0は合板、21は桟木、22はモルタル、23は
コンクリート釘を示す。
Next, as shown in FIG. 6, a support member 17 may be provided on the presser fitting 9. The support member 17 is, for example, a bolt provided on the base body 11, which allows the presser metal fitting 9 to be supported on both sides, further increasing stability. In the same figure, 19 is the existing floor slab, 2
0 indicates plywood, 21 indicates crosspieces, 22 indicates mortar, and 23 indicates concrete nails.

なお前記モルタル22は超早強セメントを用い
るが、これに限るものではなく、早強セメント、
普通のセメントを用いてもよい。又同モルタル2
2は無収縮モルタルが用いられた。又前記型枠1
2は木製である。前記高さ調整ボルト7は前述の
通りモルタル22が硬化して強度が生じた際に抜
き取る。又前記ばね13は床版1にかかる繰り返
荷重により鉛直ボルト8のゆるむのを防止してい
る。なお床版1に形成された穴17,18等はモ
ルタル等により埋められる。
Note that the mortar 22 uses ultra-early strength cement, but is not limited to this, and may include early-strength cement,
Ordinary cement may also be used. Also the same mortar 2
In No. 2, non-shrinking mortar was used. Also, the formwork 1
2 is made of wood. The height adjustment bolt 7 is removed when the mortar 22 hardens and gains strength as described above. The springs 13 also prevent the vertical bolts 8 from loosening due to repeated loads applied to the floor slab 1. Note that the holes 17, 18, etc. formed in the floor slab 1 are filled with mortar or the like.

発明の効果 この発明は前記のように構成され、床版に主イ
ンサートを形成し、高さ調整ボルトを用いて床版
を既設床版の高さに調整するため作業が容易で短
時間で行うことができる。又、前記従来のものと
異り型枠をフランジに溶接せず、仮に固定すれば
よいので、短時間に、かつ容易に作業をすること
ができる。
Effects of the Invention This invention is constructed as described above, and the main insert is formed in the deck slab, and the height adjustment bolt is used to adjust the deck slab to the height of the existing deck slab, making the work easy and quick. be able to. Further, unlike the conventional method, the formwork is not welded to the flange, but only needs to be temporarily fixed, so the work can be done easily and in a short time.

【図面の簡単な説明】[Brief explanation of drawings]

第1図〜第3図はこの発明の実施例を示し、第
1図は鋼桁橋の断面図、第2図は第1図の部分の
拡大詳細図、第3図は第1図に示す桁橋の部分の
平面図、第4図はこの発明の第2の実施例を示す
第2図に相当する図、第5図は第2図の部分の拡
大平面断面図、第6図はこの発明の第3の実施例
を示す第2図に相当する図、第7図は従来の同種
方法の一例を示し、第1図に相当する図、第8図
は第1図の部分の拡大詳細図である。 1……プレキヤストコンクリート床版、2……
鋼桁、4……フランジ、5……主インサート、6
……副インサート、7……高さ調整ボルト、8…
…鉛直ボルト、9……押え金具、12……型枠、
22……モルタル。
Figures 1 to 3 show embodiments of the present invention, Figure 1 is a cross-sectional view of a steel girder bridge, Figure 2 is an enlarged detailed view of the portion shown in Figure 1, and Figure 3 is shown in Figure 1. 4 is a plan view of the girder bridge portion, FIG. 4 is a view corresponding to FIG. 2 showing the second embodiment of the invention, FIG. 5 is an enlarged plan sectional view of the portion shown in FIG. A diagram corresponding to FIG. 2 showing the third embodiment of the invention, FIG. 7 showing an example of a conventional similar method, a diagram corresponding to FIG. 1, and FIG. 8 showing enlarged details of the part in FIG. 1. It is a diagram. 1... Precast concrete floor slab, 2...
Steel girder, 4...Flange, 5...Main insert, 6
...Sub-insert, 7...Height adjustment bolt, 8...
...Vertical bolt, 9... Holding metal fitting, 12... Formwork,
22...Mortar.

Claims (1)

【特許請求の範囲】[Claims] 1 プレキヤストコンクリート床版に予め近接さ
せて主インサート及び副インサートを設け、該プ
レキヤストコンクリート床版を主桁のフランジ上
に乗せ、前記主インサートにより、高さ調整ボル
トを用いて該プレキヤストコンクリート床版の前
記フランジからの高さを調整し、前記副インサー
トに、押え金具を有する鉛直ボルトを螺合し、該
押え金具により前記フランジの端部に型枠を固定
し、該型枠内にモルタルを打設し、該モルタルの
硬化後前記高さ調整ボルト及び型枠を取り去り、
前記鉛直ボルトにより押え金具を用いて、前記プ
レキヤストコンクリート床版とフランジとを固定
することを特徴とするプレキヤストコンクリート
床版と鋼桁との固定方法。
1. A main insert and a sub-insert are provided in advance in close proximity to the precast concrete slab, the precast concrete slab is placed on the flange of the main girder, and the main insert is used to insert the precast concrete using height adjustment bolts. Adjust the height of the floor slab from the flange, screw a vertical bolt with a holding fitting into the sub-insert, fix the formwork to the end of the flange with the holding fitting, and place it inside the formwork. Placing mortar and removing the height adjustment bolts and formwork after the mortar hardens;
A method for fixing a precast concrete deck slab and a steel girder, comprising fixing the precast concrete deck slab and a flange with the vertical bolts using a holding fitting.
JP26042887A 1987-10-15 1987-10-15 Method for fixing precast concrete floor panel and steel beam Granted JPH01102105A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26042887A JPH01102105A (en) 1987-10-15 1987-10-15 Method for fixing precast concrete floor panel and steel beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26042887A JPH01102105A (en) 1987-10-15 1987-10-15 Method for fixing precast concrete floor panel and steel beam

Publications (2)

Publication Number Publication Date
JPH01102105A JPH01102105A (en) 1989-04-19
JPH0380210B2 true JPH0380210B2 (en) 1991-12-24

Family

ID=17347796

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26042887A Granted JPH01102105A (en) 1987-10-15 1987-10-15 Method for fixing precast concrete floor panel and steel beam

Country Status (1)

Country Link
JP (1) JPH01102105A (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100467046B1 (en) * 2002-05-27 2005-01-24 동양종합건업 주식회사 Prestressed concrete bridge using thereof and method for connecting prestressed concrete beam using connecting plates
KR100544304B1 (en) * 2002-06-18 2006-01-23 (주) 선암기술연구소 Building blocks for bridge deck
JP5857379B2 (en) * 2011-11-07 2016-02-10 東急建設株式会社 Platform and platform construction method
US9874036B2 (en) 2015-05-08 2018-01-23 Cannon Design Products Group, Llc Prefabricated, deconstructable, multistory building construction
JP6785739B2 (en) * 2017-10-12 2020-11-18 川田建設株式会社 Steel girder fixing method for precast floor slabs
JP7003008B2 (en) * 2018-07-09 2022-01-20 株式会社横河ブリッジ Layered panel floor slab bridge construction method
JP7024130B1 (en) * 2021-06-14 2022-02-22 オリエンタル白石株式会社 Filling formwork under the PCa deck

Also Published As

Publication number Publication date
JPH01102105A (en) 1989-04-19

Similar Documents

Publication Publication Date Title
US6393781B1 (en) Pocketformer apparatus for a post-tension anchor system and method of using same
US5802652A (en) Bridge deck panel installation system and method
JP2994222B2 (en) Construction method of cast-in-place slab of precast concrete girder and its formwork
JPH01102105A (en) Method for fixing precast concrete floor panel and steel beam
JPH08105115A (en) Connection method of column and beam
JP3404637B2 (en) Drainage gutter installation method and grating support
JPH07247557A (en) Foundation, column mold, and underground beam made of precast reinforced concrete
JPH10311045A (en) Surface plate construction method and apparatus for erection of pillars
JPH0435441Y2 (en)
JPH053527Y2 (en)
JPH08105114A (en) Connection method of column and beam
JPH0352803Y2 (en)
CN224173750U (en) Reinforcing steel bar positioning device for concrete upright post
JP2560598B2 (en) RC reverse construction method
JP2713085B2 (en) Wall formwork mounting structure
JPH0547343Y2 (en)
JPH01198908A (en) Construction method for composite girder using precast concrete floorplate and fixture thereof
JPH0765297B2 (en) How to erection a cane ramen bridge
JPS6133793Y2 (en)
JPH0345479Y2 (en)
JP2002275913A (en) Foundation structure and building
JPH0529203Y2 (en)
JPH0430277Y2 (en)
JPH06257218A (en) Frame mounting structure of post/beam joint
JPH035442B2 (en)

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term