JPH0381418A - Method for making steep slope of banking - Google Patents
Method for making steep slope of bankingInfo
- Publication number
- JPH0381418A JPH0381418A JP21745789A JP21745789A JPH0381418A JP H0381418 A JPH0381418 A JP H0381418A JP 21745789 A JP21745789 A JP 21745789A JP 21745789 A JP21745789 A JP 21745789A JP H0381418 A JPH0381418 A JP H0381418A
- Authority
- JP
- Japan
- Prior art keywords
- slope
- embankment
- reinforcing bars
- bag
- anchor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims description 12
- 239000000463 material Substances 0.000 claims abstract description 36
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 34
- 239000004570 mortar (masonry) Substances 0.000 claims abstract description 12
- 238000010276 construction Methods 0.000 claims abstract description 10
- 230000000149 penetrating effect Effects 0.000 claims abstract description 4
- 238000009434 installation Methods 0.000 claims description 4
- 239000004567 concrete Substances 0.000 description 13
- 238000005507 spraying Methods 0.000 description 8
- 238000009412 basement excavation Methods 0.000 description 7
- 238000010586 diagram Methods 0.000 description 6
- 239000011440 grout Substances 0.000 description 6
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 6
- 229910000831 Steel Inorganic materials 0.000 description 5
- 239000010959 steel Substances 0.000 description 5
- 230000000694 effects Effects 0.000 description 3
- 238000003780 insertion Methods 0.000 description 3
- 230000037431 insertion Effects 0.000 description 3
- 238000005056 compaction Methods 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 2
- 239000004744 fabric Substances 0.000 description 2
- 238000009415 formwork Methods 0.000 description 2
- 230000007257 malfunction Effects 0.000 description 2
- 239000002184 metal Substances 0.000 description 2
- 239000011378 shotcrete Substances 0.000 description 2
- 238000007598 dipping method Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 125000006850 spacer group Chemical group 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
Description
【発明の詳細な説明】
〈産業上の利用分野〉
本発明は鉄道や道路等の盛土法面を急勾配化する方法に
関するものである。DETAILED DESCRIPTION OF THE INVENTION <Industrial Application Field> The present invention relates to a method for steepening embankment slopes for railways, roads, etc.
〈従来の技術〉
近年、特に都市部においては土地の効率的利用、高度利
用が求められている。<Conventional Technology> In recent years, efficient and advanced use of land has been required, especially in urban areas.
しかし、鉄道や道路等の構造物としては、都市部におい
ても盛土形式のものが多く用いられており、大きな用地
を占めている。However, structures such as railways and roads are often in the form of embankments, even in urban areas, and occupy a large amount of land.
そこで、盛土の法面を急勾配化し、これにより生じる用
地の有効利用が図られている。Therefore, the slope of the embankment is made steeper in order to make effective use of the resulting land.
従来の急勾配化工法としては、盛土体の法面をより急勾
配に掘削し、掘削後の法面にコンクリートを吹き付は被
覆する方法や、コンクリート板や鋼矢板により法面を被
覆する方法が用いられている。Conventional steepening methods include excavating the slope of the embankment to a steeper slope and spraying or covering the slope with concrete after excavation, or covering the slope with concrete plates or steel sheet piles. is used.
〈本発明が解決しようとする問題点〉
前記した従来の急勾配化工法には、次のような問題点が
存在する。<Problems to be Solved by the Present Invention> The conventional steepening method described above has the following problems.
〈イ〉急勾配化工法においては、鉄道や道路等の営業を
停止した後、再び営業を開始するまでの短時間のうちに
、作業を完了させる必要がある。(a) In the steep slope construction method, the work must be completed within a short period of time after railways, roads, etc. are closed and before they are restarted.
しかし、従来の吹き付はコンクリートによる方法は、コ
ンクリートの強度発現に時間がががり、また、不測の事
故(吹き付は機の故障等)により作業ができなくなる場
合が考えられ、作業時間が多くかかるため、急勾配化工
法に用いる場合には適当でない。However, with the conventional spraying method using concrete, it takes time for the concrete to develop its strength, and the work may become impossible due to unforeseen accidents (spraying equipment malfunctions, etc.), which requires a lot of work time. Therefore, it is not suitable for use in steep slope construction methods.
〈口〉また、吹き付はコンクリートの場合は、湧水や雨
水等のために地山から浮いてしまう場合があり、確実に
法面を押さえることが困難となる。<Exposure> Also, if sprayed concrete is used, it may float off the ground due to spring water, rainwater, etc., making it difficult to securely hold down the slope.
〈ハ〉従来のコンクリート板や鋼矢板により法面を被覆
する方法は、コンクリート板等が大重量であるため、施
工性が悪く、作業時間が多くかかる。<C> The conventional method of covering slopes with concrete plates or steel sheet piles has poor workability and takes a lot of time because the concrete plates are heavy.
く本発明の目的〉
本発明は上記のような問題点を解決するためになされた
もので、短時間にかつ容易に盛土体の急勾配化作業がで
き、しかも湧水や雨水等の影響を受けることが少ない盛
土法面の急勾配化工法を提供することを目的とする。OBJECT OF THE INVENTION The present invention was made to solve the above-mentioned problems, and it is possible to easily steepen the embankment body in a short time, and to avoid the effects of spring water, rainwater, etc. The purpose of this invention is to provide a method for steepening embankment slopes that are less prone to damage.
〈本発明の構成〉
以下、図面を参照しながら本発明の一実施例について説
明する。<Configuration of the Present Invention> An embodiment of the present invention will be described below with reference to the drawings.
〈イ〉盛土体頭部の締め固め(第1.2図〉先ず第2図
に示すように、盛土体の頭部のなるべく法肩に近い場所
に、略水平方向に貫通孔を削孔する。<B> Compaction of the head of the embankment body (Figure 1.2) First, as shown in Figure 2, a through hole is drilled in the approximately horizontal direction in the head of the embankment body as close to the shoulder as possible. .
そして、この孔内に鉄筋1を挿入して貫通させ、その両
端部を孔外に露出させておく。Then, the reinforcing bar 1 is inserted into and passed through the hole, and both ends thereof are exposed outside the hole.
この鉄筋1の露出する両端部には、予めネジ部を形成し
ておく。Threaded portions are previously formed at both exposed ends of the reinforcing bar 1.
一方、盛土体の延長方向に沿って、両側の法面上端部に
腹起し材2を配置する。On the other hand, raising materials 2 are arranged at the upper end of the slope on both sides along the extension direction of the embankment body.
この腹起し材2には、例えば断面がコの字状の溝形鋼等
を使用し、溝部が外側に向くように配置する。This raised member 2 is made of, for example, channel steel having a U-shaped cross section, and is arranged so that the groove portion faces outward.
また、この腹起し材2の法面との接触面には、鉄筋1の
挿入孔を間隔をおいて複数開設し、この挿入孔に鉄筋1
の露出するネジ部を挿入して配置する。In addition, a plurality of insertion holes for the reinforcing bars 1 are opened at intervals on the surface of the raised material 2 that contacts the slope, and the reinforcing bars 1 are inserted into the insertion holes.
Insert and position the exposed screw part.
なお、腹起し材2は、手で持てる程度の長さのものを使
用すると作業が行い易い。It is to be noted that the work will be easier if the length of the raising material 2 is long enough to be held by hand.
そして、腹起し材2の挿入孔より貫通する鉄筋1の両端
ネジ部に、ナツト等を取り付けて締結する。Then, nuts or the like are attached to the threaded portions at both ends of the reinforcing bar 1 that pass through the insertion hole of the upright material 2 and fastened.
これによって、腹起し材2が支圧板として作用するため
、盛土体の頭部を両側の法面より締め固めることができ
る。As a result, the raised material 2 acts as a bearing plate, so that the head of the embankment can be compacted from the slopes on both sides.
〈口〉アンカー鉄筋の定着(第3図〉
次に第3図に示すように、上記腹起し材2のやや下方の
法面に、盛土体の中心に向けてやや下方に傾斜するよう
に、アンカー孔3を削孔する。<Opening> Anchor reinforcing bars (Fig. 3) Next, as shown in Fig. 3, on the slope slightly below the raised material 2, an anchor is placed on the slope slightly downward toward the center of the embankment. , the anchor hole 3 is drilled.
そして、このアンカー孔3内に、アンカー鉄筋31を乳
臭まで挿入する。Then, the anchor reinforcing bar 31 is inserted into the anchor hole 3 up to the milky part.
このアンカー鉄筋31には、法面の掘削予定線の孔奥部
にバッカー32が取り付けである。A backer 32 is attached to the anchor reinforcing bar 31 at the back of the hole on the planned excavation line on the slope.
また、アンカー鉄筋31は、法面の掘削予定線の孔外側
が撤去できるように、ジ冒インド金具33によって取り
外し可能に連結されている。Further, the anchor reinforcing bars 31 are removably connected by a dipping metal fitting 33 so that the outside of the hole on the planned excavation line on the slope can be removed.
但し、法面掘削後に、アンカー鉄筋31の孔外側の端部
が、法面よりやや突出するように、ジ日インド金具33
を法面の掘削予定線より孔外側にやや寄せて取り付けて
おく。However, after the slope is excavated, the steel fittings 33 are installed so that the ends of the anchor reinforcing bars 31 on the outside of the hole protrude slightly from the slope.
Install it a little closer to the outside of the hole than the planned excavation line on the slope.
また、法面掘削後に、アンカー鉄筋31の法面より突出
する部分には、予めネジ部を形成しておく。Further, after the slope surface is excavated, a threaded portion is previously formed in a portion of the anchor reinforcing bar 31 that protrudes from the slope surface.
そして、注入管等によってアンカー孔3内にグラウト材
34を充填し、グラウト材34の硬化を待って、アンカ
ー鉄筋31の孔外側の端部を、法面に配置した支圧板等
に定着する。Then, the anchor hole 3 is filled with grout material 34 using an injection pipe or the like, and after waiting for the grout material 34 to harden, the end of the anchor reinforcing bar 31 outside the hole is fixed to a bearing plate or the like disposed on the slope.
くハ〉法面の掘削(第4図) 法面の掘削作業の前に、線路又は道路等を閉鎖する。Excavation of Kuha slope (Fig. 4) Close railroad tracks or roads before excavating slopes.
そして、第4図に示すように、アンカー鉄筋31の周囲
の法面を、所定の角度をもって急勾配に掘削する。Then, as shown in FIG. 4, the slope around the anchor reinforcing bars 31 is excavated at a steep slope at a predetermined angle.
掘削と同時に、ジ目インド金具33を取り外し、アンカ
ー鉄筋31の孔外側部分を撤去する。Simultaneously with the excavation, the grooved metal fittings 33 are removed, and the outer part of the anchor reinforcing bars 31 is removed.
なお、バッカー32が取り付けであることによって、ア
ンカー孔3からグラウト材34の流出を防ぐことができ
る。Note that by attaching the backer 32, it is possible to prevent the grout material 34 from flowing out from the anchor hole 3.
〈二〉ドレーン材の設置(第し4,6図〉次に、第1.
4図に示すように、掘削後の法面に、間隔をおいてドレ
ーン材4を複数配置する。<2> Installation of drain material (Figures 4 and 6) Next, step 1.
As shown in FIG. 4, a plurality of drain materials 4 are placed at intervals on the slope after excavation.
またドレーン材4は、盛土体の上下方向に連続するよう
縦に設置する。Moreover, the drain material 4 is installed vertically so as to be continuous in the vertical direction of the embankment body.
このドレーン材4は、盛土体内の湧水や雨水を集めて、
排水を良好に行うためのものである。This drain material 4 collects spring water and rainwater inside the embankment,
This is to ensure good drainage.
例えば、第6図に示すように、透水シート41を筒状に
形成し、その内部に透水シート41の内部空間を確保す
るため、波形等のスペーサー42を装着したものが考え
られる。For example, as shown in FIG. 6, it is conceivable that the water-permeable sheet 41 is formed into a cylindrical shape, and a corrugated spacer 42 is attached therein in order to secure the internal space of the water-permeable sheet 41.
くホ〉袋体の設置く第4.5図〉
次に、14.5図に示すように、ドレーン材4に重ねて
、掘削後の法面全体に布製等の袋体5を設置する。Figure 4.5: Installation of bag Next, as shown in Figure 14.5, a bag 5 made of cloth or the like is installed over the entire excavated slope, overlapping the drain material 4.
このとき、アンカー鉄筋31の露出端部35は、袋体5
の中央部に貫通させる。At this time, the exposed end portion 35 of the anchor reinforcing bar 31
Penetrate through the center of the
袋体5のアンカー鉄筋31の貫通部分は、内部に注入す
るモルタル51が流出しないように、穴あけ加工が施し
である。The penetrating portion of the anchor reinforcing bar 31 of the bag body 5 is perforated to prevent the mortar 51 injected into the bag from flowing out.
次に、袋体5内に早強性等のモルタル51を注入する。Next, mortar 51 such as early strength mortar is injected into the bag body 5.
そして、モルタル51に所定の強度が発・現した後、支
圧板、ナツト等を露出端部35に取り付けて締結する。After the mortar 51 has developed a predetermined strength, a bearing plate, nuts, etc. are attached to the exposed end portion 35 and fastened.
以上のようにして一段目を施工した後、同じ要領で二段
目、三段目というように、下方に施工を進めていく。After constructing the first stage as described above, proceed downwards to construct the second, third, and so on in the same manner.
最後まで施工が終了した後、線路又は道路等の閉鎖を解
除する。After the construction is completed, the closure of the railway or road will be lifted.
〈その他の実施例1)
その他の実施例として、第7.8図に示すように、アン
カー鉄筋31の代わりに引張材6を用いて、プレストレ
スを導入する場合も考えられる。<Other Examples 1> As another example, as shown in FIG. 7.8, it is also possible to introduce prestress by using tensile material 6 instead of anchor reinforcing bars 31.
この場合は、先ず初めに法面を所定の角度で急勾配に掘
削し、法面に削孔した孔内に引張材6を挿入して、引張
材の孔奥部を急結材61等を充填して定着する。In this case, first, the slope is steeply excavated at a predetermined angle, the tensile material 6 is inserted into the hole drilled in the slope, and the quick-setting material 61 or the like is applied to the deep part of the tensile material hole. Fill and fix.
次に引張材6の露出端部を貫通させて、法面に袋体5を
取り付け、この袋体5の内部にモルタル51を注入する
。Next, the exposed end of the tensile material 6 is penetrated, the bag 5 is attached to the slope, and the mortar 51 is injected into the inside of the bag 5.
モルタル51に所定の強度が発現した後、引張材6を緊
張して、引張材6の露出端部を袋体51:定着させる。After the mortar 51 develops a predetermined strength, the tensile material 6 is tensioned to fix the exposed end of the tensile material 6 to the bag body 51.
最後に、アンカー孔内にグラウト材62を充填して作業
を終了する。Finally, the anchor hole is filled with grout 62 to complete the work.
〈その他の実施例2〉
また、上記実施例では、いずれも盛土体の頭部に、鉄筋
lを略水平方向に貫通させて設置した場合であるが、第
9図に示すように、盛土の片側が切土面等の場合は、ア
ンカー鉄筋7を用いて盛土体の頭部の締め固めを行うこ
とが考えられる。<Other Embodiment 2> In the above embodiments, the reinforcing bars I are installed at the head of the embankment in a substantially horizontal direction, but as shown in FIG. If one side is a cut surface, it is conceivable to use anchor reinforcing bars 7 to compact the head of the embankment body.
この場合は、盛土体の頭部に、法面から略水平方向にア
ンカー孔を削孔し、このアンカー孔内にアンカー鉄筋7
を挿入し、グラウト材71によって定着する方法である
。In this case, an anchor hole is drilled in the head of the embankment in a substantially horizontal direction from the slope, and the anchor reinforcing bar 7 is inserted into the anchor hole.
This is a method in which the grout material 71 is inserted and fixed with grout material 71.
〈本発明の効果〉
本発明は以上説明したようになるので、次のような効果
を期待することができる。<Effects of the Present Invention> Since the present invention has been described above, the following effects can be expected.
〈イ〉急勾配化工法においては、鉄道や道路等の営業を
停止した後、再び営業を開始するまでの短時間のうちに
、作業を完了させる必要がある。(a) In the steep slope construction method, the work must be completed within a short period of time after railways, roads, etc. are closed and before they are restarted.
しかし、従来の吹き付はコンクリートによる方法は、コ
ンクリートの強度発現が充分でなければアンカーの締付
ができず、時間がかかる。However, in the conventional spraying method using concrete, the anchor cannot be tightened unless the concrete has sufficient strength, and it takes time.
また、不測の事故(吹き付は機の故障等〉により作業が
できなくなる場合が考えられ、作業時間が多くかかるた
め、急勾配化工法に用いる場合には適当でない。In addition, it is not suitable for use in steep slope construction methods because the work may become impossible due to unforeseen accidents (spraying equipment malfunctions, etc.), and the work takes a lot of time.
それに対して本発明は、吹き付はコンクリートと比較し
て、袋状の型枠が存在するため、ある程度コンクリート
の強度が小さくても、アンカーの締付が可能である。In contrast, in the present invention, since a bag-shaped formwork is present in spraying compared to concrete, anchors can be tightened even if the strength of concrete is low to some extent.
従って、短時間に施工を完了させることができ、盛土体
の急勾配化工法に遺した方法であると言える。Therefore, construction can be completed in a short period of time, and it can be said that this method is a legacy of the steep slope construction method for embankments.
また、吹き付は機等の装置を必要としないため、不測の
事故(吹き付は機の故障等)により作業が中断すること
がない。Furthermore, since spraying does not require equipment such as a machine, the work will not be interrupted due to unexpected accidents (spraying machine failure, etc.).
〈口〉従来の吹き付はコンクリートの場合は、湧水や雨
水等のために地山から浮いてしまう場合があり、確実に
法面を押さえることが困難となる。<Exposure> In the case of conventional sprayed concrete, it may float off the ground due to spring water, rainwater, etc., making it difficult to securely hold down the slope.
それに対して本発明は、布製等の袋体をコンクリートの
型枠として使用するため、地山との密着性が良い。In contrast, the present invention uses a bag made of cloth or the like as a formwork for concrete, so it has good adhesion to the ground.
またドレーン材を袋体と法面との間に配置することによ
って、湧水や雨水等を良好に排水することができる。Furthermore, by arranging the drain material between the bag and the slope, spring water, rainwater, etc. can be drained well.
そのため、湧水や雨水等の影響を受けることがほとんど
なく、確実に法面を押さえることができる。Therefore, it is hardly affected by spring water or rainwater, and can reliably hold down the slope.
〈ハ〉従来のコンクリート板や鋼矢板により法面を被覆
する方法は、コンクリート板等が大重量であるため、施
工性が悪く、作業時間が多くかかる。<C> The conventional method of covering slopes with concrete plates or steel sheet piles has poor workability and takes a lot of time because the concrete plates are heavy.
しかし本発明は、軽量な袋体を使用するため、取り付は
作業が容易かつ短時間に行うことができ、施工性が向上
する。However, in the present invention, since a lightweight bag is used, installation can be performed easily and in a short time, and workability is improved.
〈二〉本発明は、施工が短時間に行えるため、特に、営
業路線の停止時間内の作業に遺している。(2) Since the present invention can be constructed in a short period of time, it is particularly suitable for work during the suspension time of commercial lines.
〈ホ〉盛土体の頭部を、法面を傷めることなく、鉄筋等
によって早期に締め固めることにより、法面の掘削時に
発生する側方への盛土体の変形を抑えることができる。<E> By compacting the head of the embankment with reinforcing bars or the like at an early stage without damaging the slope, it is possible to suppress the lateral deformation of the embankment that occurs when excavating the slope.
そのため、盛土体上面の路盤や路床の沈下、水平変位を
、極力少なくすることができ、安全性が高くなる。Therefore, the subsidence and horizontal displacement of the roadbed and roadbed on the upper surface of the embankment body can be minimized, and safety is increased.
くへ〉盛土体の頭部の締め固め作業は、盛土頭部に鉄筋
等を略水平方向に設置するだけでよいため、すべての作
業を側方から行うことができる。To compact the head of the embankment, all you need to do is install reinforcing bars and the like in a substantially horizontal direction at the head of the embankment, so all work can be done from the side.
そのため、路線の閉鎖をする必要がなく、徐行運転程度
で作業を行うことができる。Therefore, there is no need to close the route, and the work can be carried out by driving slowly.
従って、路線閉鎖後の作業に時間的余裕ができる。Therefore, more time will be available for work after the route is closed.
第1図:本発明の一実施例の説明図
第2図:盛土体の頭部の締め固め説明図第3〜5図:施
工方法の説明図
第6図ニドレーン材の説明図
第7.8図:その他の実施例1の説明図第9図:その他
の実施例2の説明図Fig. 1: An explanatory diagram of one embodiment of the present invention Fig. 2: An explanatory diagram of compaction of the head of the embankment body Figs. 3 to 5: An explanatory diagram of the construction method Fig. 6 An explanatory diagram of Nidrene material Fig. 7.8 Figure: Explanatory diagram of other embodiment 1 Figure 9: Explanatory diagram of other embodiment 2
Claims (3)
て、 盛土体の頭部に略水平方向に鉄筋を貫通させ、この鉄筋
の両端部を、盛土体の延長方向に沿って法面の上端部に
配置した腹起し材に定着し、この腹起し材の下方の法面
に、盛土体の中心に向けて下方にやや傾斜するようアン
カー鉄筋を定着し、 次にこれらのアンカー鉄筋の周囲の法面をより急勾配に
掘削し、 アンカー鉄筋の露出端部を貫通させて、法面に袋体を取
り付け、 この袋体の内部にモルタルを注入し、 モルタルに所定の強度が発現した後、アンカー鉄筋の露
出端部を袋体に定着させたことを特徴とする、 盛土法面の急勾配化工法。(1) In the method of excavating the slope of an embankment to make it steeper, reinforcing bars are passed through the head of the embankment in a substantially horizontal direction, and both ends of the reinforcing bars are extended along the extension direction of the embankment. Anchor reinforcing bars are anchored to the raised material placed at the upper end of the surface, and anchor reinforcing bars are anchored to the slope below the raised material so as to be slightly inclined downward toward the center of the embankment. The slope around the anchor rebar is excavated at a steeper slope, the exposed end of the anchor rebar is penetrated, a bag is attached to the slope, mortar is injected into the inside of the bag, and the mortar has a specified strength. A method for steepening embankment slopes, which is characterized by fixing the exposed ends of anchor reinforcing bars to the bag body after the occurrence of this problem.
て、 盛土体の頭部に水平方向に鉄筋を貫通させ、この鉄筋の
両端部を、盛土体の延長方向に沿って法面の上端部に配
置した腹起し材に定着し、 次にこの腹起し材の下方の法面をより急勾配に掘削し、 この急勾配に掘削した法面に、盛土体の中心に向けて下
方にやや傾斜するよう削孔し、 この孔内に引張材を挿入して、引張材の孔奥部を定着し
、 次に引張材の露出端を貫通させて、法面に袋体を取り付
け、 この袋体の内部にモルタルを注入し、 モルタルに所定の強度が発現した後、引張材を緊張して
、引張材の露出端部を袋体に定着させたことを特徴とす
る、 盛土法面の急勾配化工法。(2) In the method of excavating the slope of the embankment to make it steeper, reinforcing bars are passed horizontally through the head of the embankment, and both ends of the reinforcing bars are attached to the slope along the extension direction of the embankment. It settles on the raised material placed at the upper end, and then the slope below this raised material is excavated at a steeper slope. A hole is drilled with a slight downward slope, and a tensile material is inserted into this hole to secure the deep part of the hole in the tensile material.Then, the exposed end of the tension material is penetrated and the bag is placed on the slope. Installation: Mortar is injected into the inside of the bag, and after the mortar develops a predetermined strength, the tensile material is tensioned to fix the exposed end of the tensile material to the bag. Method for making slopes steeper.
の急勾配化工法において、 前記盛土体の頭部に略水平方向に貫通させた鉄筋の代わ
りに、 盛土体の頭部に略水平方向にアンカー体を定着した盛土
法面の急勾配化工法。(3) In the method for steepening the slope of an embankment according to claims 1 and 2, instead of reinforcing bars penetrating the head of the embankment body in a substantially horizontal direction, the head of the embankment body A construction method for steepening embankment slopes in which anchor bodies are anchored in a nearly horizontal direction.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP21745789A JPH0762350B2 (en) | 1989-08-25 | 1989-08-25 | Method of making steep slope on embankment slope |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP21745789A JPH0762350B2 (en) | 1989-08-25 | 1989-08-25 | Method of making steep slope on embankment slope |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0381418A true JPH0381418A (en) | 1991-04-05 |
| JPH0762350B2 JPH0762350B2 (en) | 1995-07-05 |
Family
ID=16704530
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP21745789A Expired - Fee Related JPH0762350B2 (en) | 1989-08-25 | 1989-08-25 | Method of making steep slope on embankment slope |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0762350B2 (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR100409196B1 (en) * | 2001-09-20 | 2003-12-18 | 주식회사 포스코 | Rod construction method for assembly steel frame |
| JP2010133155A (en) * | 2008-12-04 | 2010-06-17 | Mecc Miyazaki:Kk | Construction method of installing slope face stabilization pseudo-pressure receiving body, and pseudo-pressure receiving body used in construction method |
| JP2011094443A (en) * | 2009-11-02 | 2011-05-12 | Railway Technical Res Inst | Method for constructing wall surface work by using bag body |
-
1989
- 1989-08-25 JP JP21745789A patent/JPH0762350B2/en not_active Expired - Fee Related
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR100409196B1 (en) * | 2001-09-20 | 2003-12-18 | 주식회사 포스코 | Rod construction method for assembly steel frame |
| JP2010133155A (en) * | 2008-12-04 | 2010-06-17 | Mecc Miyazaki:Kk | Construction method of installing slope face stabilization pseudo-pressure receiving body, and pseudo-pressure receiving body used in construction method |
| JP2011094443A (en) * | 2009-11-02 | 2011-05-12 | Railway Technical Res Inst | Method for constructing wall surface work by using bag body |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0762350B2 (en) | 1995-07-05 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105002927B (en) | A construction method of anti-filtering layer for retaining wall of excavated slope | |
| JPS63277301A (en) | Road expanding method and apparatus | |
| CN109763518A (en) | A kind of construction method of basement post-pouring zone | |
| CN105604090A (en) | Open section tunnel structure with cast-in-place and prefabricating assembling combined | |
| CN105862912B (en) | A kind of agent on crack resistance of concrete sliding pile panelling construction method | |
| JPH10183624A (en) | Reinforced embankment wall construction method using retaining wall blocks | |
| JP3486602B2 (en) | Pier foundation method and pier foundation structure | |
| JPH0381418A (en) | Method for making steep slope of banking | |
| KR100433653B1 (en) | Constructing method for the filling out abutement of bridge | |
| KR20050017815A (en) | Construction and design method about center wall of two arch tunnel excavation method | |
| US5871307A (en) | Pre-cast concrete panel wall | |
| JP2730705B2 (en) | Improvement method for soft ground | |
| CN205399479U (en) | Cast -in -place and prefabricated unlimited section tunnel structure of assembling combination | |
| JPH0384117A (en) | Steep sloping method of banking slope | |
| JPH0384116A (en) | Steep sloping method of banking slope | |
| KR200194458Y1 (en) | The structure improved outer layer of tender base for improveing constrution of the dredged soil tender base | |
| JP3168197B2 (en) | Caisson anchor structure and construction method | |
| JP2668922B2 (en) | Seismic structure of excavated road | |
| JP3806069B2 (en) | Seismic isolation method from the ground of existing buildings | |
| CN113502851A (en) | Construction method of open cut tunnel extension foam concrete backfill structure | |
| JPH0381417A (en) | Method for making steep slope of banking | |
| JPH0477764B2 (en) | ||
| JP3295768B2 (en) | Precast concrete road gutter | |
| CN110318372B (en) | Anchor rod butt joint method | |
| JPH0243848B2 (en) |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080705 Year of fee payment: 13 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090705 Year of fee payment: 14 |
|
| LAPS | Cancellation because of no payment of annual fees |