JPH0412328B2 - - Google Patents
Info
- Publication number
- JPH0412328B2 JPH0412328B2 JP12493684A JP12493684A JPH0412328B2 JP H0412328 B2 JPH0412328 B2 JP H0412328B2 JP 12493684 A JP12493684 A JP 12493684A JP 12493684 A JP12493684 A JP 12493684A JP H0412328 B2 JPH0412328 B2 JP H0412328B2
- Authority
- JP
- Japan
- Prior art keywords
- hole
- aggregate
- grout
- ground
- injected
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 239000011440 grout Substances 0.000 claims description 13
- 238000000034 method Methods 0.000 claims description 9
- 238000002347 injection Methods 0.000 description 12
- 239000007924 injection Substances 0.000 description 12
- 238000005553 drilling Methods 0.000 description 6
- 239000003795 chemical substances by application Substances 0.000 description 5
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 4
- 239000004568 cement Substances 0.000 description 3
- 239000008267 milk Substances 0.000 description 3
- 210000004080 milk Anatomy 0.000 description 3
- 235000013336 milk Nutrition 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 239000006227 byproduct Substances 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000013505 freshwater Substances 0.000 description 1
- 239000011800 void material Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Description
【発明の詳細な説明】 (産業上の利用分野) 本発明はグラウト工法に関する。[Detailed description of the invention] (Industrial application field) The present invention relates to a grouting method.
(従来技術)
脆弱な地盤のダム構築におけるダムサイトの地
盤補強として一般にグラウト工法が用いられてい
る。(Prior Art) A grouting method is generally used to reinforce the ground at a dam site when constructing a dam on weak ground.
すなわち、第7図はこの種の従来例を示すもの
で、先ずイ図に示すように、先端に削孔ビツト
4′を有するボーリングロツド5′を回転させつつ
水槽1′内の清水2′を矢印で示すように正循環さ
せながら脆弱な地盤Gを削孔し、この削孔が所定
の深さのグラウト全長lに達すると、ボーリング
ロツド5′を引き抜き、ロ図に示すように、今度
は削孔底部まで注入管10′を建て込むとともに、
削孔上部にパツカー11′を設置し、セメントミ
ルク等の注入剤14′をグラウトポンプ12′を介
し加圧注入し、地盤中の空隙g′に矢印で示す如く
注入剤14′を注入して地盤の補強または遮水を
している。 That is, FIG. 7 shows a conventional example of this type. First, as shown in FIG. A hole is drilled in the weak ground G while positively circulating as shown by the arrow, and when this hole reaches a predetermined depth and the total length l of the grout, the boring rod 5' is pulled out and as shown in the diagram, Next, install the injection pipe 10' to the bottom of the drilling hole,
A packer 11' is installed at the top of the excavation hole, and an injection agent 14' such as cement milk is injected under pressure through a grout pump 12', and the injection agent 14' is injected into the gap g' in the ground as shown by the arrow. The ground is reinforced or water-blocked.
しかしながら、この場合、削孔終了後、削孔か
らボーリングロツド5′を引き抜き、注入管1
0′を挿入し、セメントミルク注入するまでの間
の過程で脆弱な地盤においては削孔の孔壁が崩壊
してしまうことがあり、ダムサイトの空隙g′にグ
ラウト注入ができないという欠点が伴なつてい
た。 However, in this case, after the drilling is completed, the boring rod 5' is pulled out from the hole and the injection pipe 1 is
In the process between inserting grout 0' and injecting cement milk, the hole wall of the drilled hole may collapse in weak ground, and this has the disadvantage that grout cannot be injected into the gap g' at the dam site. I was getting used to it.
(発明の目的)
本発明は上記の点に鑑み提案されたもので、そ
の目的とするところは、ボーリングロツドを引き
抜いていく場合に削孔内にグラウト注入が可能な
骨剤を填充することにより、確実に孔壁の崩壊を
防止しつつ空隙部分にグラウト注入ができ、礫岩
などの脆弱な部分を補強ないしは遮水し得るグラ
ウト工法を提供することにある。(Object of the Invention) The present invention was proposed in view of the above points, and its purpose is to fill a drilled hole with an aggregate that can be injected with grout when a boring rod is pulled out. Therefore, it is an object of the present invention to provide a grouting method in which grout can be injected into a void part while reliably preventing the collapse of a hole wall, and which can reinforce or block water from a weak part such as conglomerate.
(発明の構成)
第1図ないし第6図は本発明の一実施例にかか
るグラウト工法の工程を順次示すもので、以下、
その工法を説明する。(Structure of the Invention) Figures 1 to 6 sequentially show the steps of the grouting method according to an embodiment of the present invention.
The construction method will be explained.
先ず、水槽1内の清水2を正循環させつつ削
孔ビツト4が設けられたボーリングロツド5を
介し礫岩などの脆弱な地盤Gに第1段階l1の削
孔を行う(第1図参照)。なお、図中6は周知
構成のターンテーブル、7は注入管8に設けら
れたポンプである。 First, a first step of drilling is performed in fragile ground G such as conglomerate through a boring rod 5 equipped with a drilling bit 4 while circulating fresh water 2 in a water tank 1 (Fig. 1). reference). In addition, in the figure, 6 is a turntable of a known configuration, and 7 is a pump provided in the injection pipe 8.
第1段階l1の削孔終了後、ボーリングロツド
5を引き抜きながら、予め地上側に用意された
骨材9を水と混合してボーリングロツド5の中
空部を介し削孔内に送り込み、骨材9を孔底か
ら孔頭まで詰め込んでいく(第2図参照)。こ
の骨材9としてはグラウト注入ができるよう骨
材9相互間に空隙が生じ、かつ軽量で容易に破
砕し易いものであると好ましく、人工軽量骨
材、天然軽量骨材、副産軽量骨材などのうち最
適なものが適宜選択して用いられる。 After the completion of drilling in the first stage l1 , while pulling out the boring rod 5, the aggregate 9 prepared in advance on the ground side is mixed with water and fed into the hole through the hollow part of the boring rod 5. Fill the aggregate 9 from the bottom of the hole to the hole head (see Figure 2). The aggregate 9 is preferably one that has voids between the aggregates 9 so that grout can be injected, is lightweight and easily crushed, and may be an artificial lightweight aggregate, a natural lightweight aggregate, or a by-product lightweight aggregate. The most suitable one is selected and used as appropriate.
ボーリングロツド5を完全に引き抜いた後は
注入管10を削孔上部に差し込むとともにパツ
カー11を取付け、グラウトポンプ12を介し
水槽13内のセメントミルクの如き注入剤14
を削孔内に加圧注入する。この場合、削孔内に
は骨材9が填充され、孔壁は骨材9によつて支
持されているため崩壊することはない。また、
注入剤14は各骨材9の間を通り、矢印で示す
ように、地盤の空隙gに注入されていく(第3
図参照)。なお、図中15はバツチヤーである。 After the boring rod 5 is completely pulled out, the injection pipe 10 is inserted into the upper part of the drilled hole, the packer 11 is attached, and the injection agent 14 such as cement milk in the water tank 13 is pumped through the grout pump 12.
is injected into the drilled hole under pressure. In this case, the hole is filled with aggregate 9 and the hole wall is supported by the aggregate 9, so it will not collapse. Also,
The injection agent 14 passes between each aggregate 9 and is injected into the ground gap g as shown by the arrow (third
(see figure). Note that 15 in the figure is a batcher.
第1段階の注入が終了後は骨材9が入つてい
る第1段階l1の削孔をリボーリングし、続いて
地盤に対し第2段階l2のボーリングを行う(第
4図参照)。なお、図中G1は既に注入が終了し
た箇所である。 After the first stage injection is completed, the hole in the first stage l1 containing the aggregate 9 is rebored, and then the ground is bored in the second stage l2 (see Fig. 4). Note that G1 in the figure is a location where the injection has already been completed.
第2段階l2の削孔が終了した後は、この部分
の削孔に前記で説明したように骨材9を詰め
込んでいく(第5図参照)。 After the hole drilling in the second stage l2 is completed, aggregate 9 is packed into the hole in this portion as explained above (see FIG. 5).
しかして、第2段階l2の削孔に骨材9が填充
された後は、前記で説明したように、第1段
階l1の削孔を通して第2段階l2の削孔上部に注
入管10を入れるとともにパツカー11を取付
け、かつグラウトポンプ12を介し地盤の空隙
gに注入剤を注入する(第6図参照)。 After the aggregate 9 is filled into the hole in the second stage l2 , as explained above, an injection pipe is inserted into the upper part of the hole in the second stage l2 through the hole in the first stage l1. At the same time, a grout car 11 is installed, and a grouting agent is injected into the ground gap g via the grout pump 12 (see Fig. 6).
そして、注入終了後は、前記で説明したよ
うに、第2段階l2の削孔のリボーリングを行
い、以上上記工程を繰り返すことにより所定の
深さまで削孔する。 After the injection is completed, as explained above, the hole is rebored in the second stage l2 , and the above steps are repeated to drill the hole to a predetermined depth.
(発明の効果)
以上の通り本発明によれば、グラウト工法にお
いて、削孔を行つたボーリングロツドを引き抜く
場合に削孔内に骨材を填充し、グラウト注入をす
るように構成したから、脆弱な地盤であつても孔
壁の崩壊を確実に防止しながらダムサイトの空隙
にグラウト注入を行つていくことができる利点が
ある。(Effects of the Invention) As described above, according to the present invention, in the grouting method, when the boring rod that has drilled the hole is pulled out, the drilled hole is filled with aggregate and grout is injected. This method has the advantage of being able to inject grout into the voids at the dam site while reliably preventing collapse of the hole walls even in weak ground.
第1図ないし第6図は本発明の工程手順を示す
説明図、第7図イ,ロは従来例である。
1 to 6 are explanatory diagrams showing the process steps of the present invention, and FIGS. 7A and 7B are conventional examples.
Claims (1)
ングロツドを引き抜く場合に削孔内に骨材を填充
し、グラウト注入をすることを特徴としたグラウ
ト工法。1. A grouting method characterized by filling the hole with aggregate and injecting grout when pulling out the boring rod that has drilled the hole.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12493684A JPS615113A (en) | 1984-06-18 | 1984-06-18 | Grouting work |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12493684A JPS615113A (en) | 1984-06-18 | 1984-06-18 | Grouting work |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS615113A JPS615113A (en) | 1986-01-10 |
| JPH0412328B2 true JPH0412328B2 (en) | 1992-03-04 |
Family
ID=14897834
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP12493684A Granted JPS615113A (en) | 1984-06-18 | 1984-06-18 | Grouting work |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS615113A (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112983344A (en) * | 2019-12-17 | 2021-06-18 | 北京大地高科地质勘查有限公司 | Novel grouting drill rod and using method thereof |
-
1984
- 1984-06-18 JP JP12493684A patent/JPS615113A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS615113A (en) | 1986-01-10 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110331992A (en) | A kind of hole daguanpeng construction method | |
| US3507121A (en) | Tie rod anchoring method and apparatus | |
| JPH0774498B2 (en) | Method of forming cast-in-place concrete pile | |
| JPH0673893A (en) | Building method of precast structure and precast concrete member therefor | |
| CN105350988A (en) | Tunnel base reinforcing method | |
| US3191390A (en) | Method of preparing subsurface and forming concrete column therein | |
| JP3481508B2 (en) | Stone masonry retaining wall reinforcement method | |
| JPS59126821A (en) | Erection work of foundation pile | |
| JP4197377B2 (en) | Ground strengthening method | |
| JPH0841870A (en) | Method of connecting piles of ready-made concrete piles | |
| CN108952765B (en) | Construction method of advanced support of super large tube shed in water-rich sand layer | |
| RU2089706C1 (en) | Pile frozen into permafrost and method of erection of pile frozen into permafrost | |
| JPS615113A (en) | Grouting work | |
| JP3200240B2 (en) | Filling method of self-hardening material in ground reinforcement method | |
| JP2874906B2 (en) | Shaft construction method | |
| JP2617267B2 (en) | Rock anchoring method for steel pipe piles | |
| JPS6013118A (en) | Pile erection work and excavation head for forming consolidated perforated wall therefor | |
| JPS621048B2 (en) | ||
| KR200325653Y1 (en) | Earth anchor including a duplex grouting pipe | |
| JPH11256572A (en) | Composite ground reinforcement method | |
| JPS649413B2 (en) | ||
| JPH0525828A (en) | Floating prevention structure for grounded floor | |
| JP2566522B2 (en) | Ground improvement method for tunnel excavation and its surroundings | |
| GB2048999A (en) | Improvements relating to the construction of in situ piles | |
| JPS59145822A (en) | Construction work of underground continuous wall |