JPH0412348B2 - - Google Patents

Info

Publication number
JPH0412348B2
JPH0412348B2 JP59128969A JP12896984A JPH0412348B2 JP H0412348 B2 JPH0412348 B2 JP H0412348B2 JP 59128969 A JP59128969 A JP 59128969A JP 12896984 A JP12896984 A JP 12896984A JP H0412348 B2 JPH0412348 B2 JP H0412348B2
Authority
JP
Japan
Prior art keywords
reinforcing bars
steel
frame
assembled
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP59128969A
Other languages
Japanese (ja)
Other versions
JPS6110682A (en
Inventor
Takeshi Kojima
Ichiro Abe
Kenzo Mizuhara
Noboru Fujii
Keiji Himi
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP12896984A priority Critical patent/JPS6110682A/en
Publication of JPS6110682A publication Critical patent/JPS6110682A/en
Publication of JPH0412348B2 publication Critical patent/JPH0412348B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 この発明は鉄骨鉄筋コンクリート構造物の施工
法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing a steel reinforced concrete structure.

従来鉄骨鉄筋コンクリート構造物の場合、鉄骨
は先組しても鉄筋は建込んだ鉄骨周縁に現場配筋
しており、省力化、工期短縮等から改善が要望さ
れていた。この要望にこたえるため、出願人は先
に鉄骨と鉄筋とを可能な限りプレハブ化した施工
法を開発したが、この発明は柱、梁のいずれもが
鉄骨、鉄筋からなる構造物に関するものであつ
た。しかしながら近時鉄骨量をできるだけ削減す
る考慮がなされており、その施工に際して省力
化、工期短縮が期待できる施工法の開発が要望さ
れていた。
Conventionally, in the case of steel-framed reinforced concrete structures, even though the steel frames were pre-assembled, the reinforcing bars were placed on site around the periphery of the erected steel frames, and improvements were needed to save labor and shorten the construction period. In order to meet this demand, the applicant has previously developed a construction method in which steel frames and reinforcing bars are prefabricated as much as possible. Ta. However, in recent years, consideration has been given to reducing the amount of steel frames as much as possible, and there has been a demand for the development of a construction method that can be expected to save labor and shorten the construction period.

この発明は前記事情に鑑み開発されたもので、
柱は鉄骨鉄筋コンクリート構造からなり、梁は鉄
筋コンクリート構造からなる建築物において、組
立て作業がきわめて簡単、かつ短期間でおこなう
ことができるとともに、作業の安全性がきわめて
高い鉄骨鉄筋コンクリート建築物の施工法を提供
することを目的とする。
This invention was developed in view of the above circumstances,
Provides a construction method for steel-framed reinforced concrete buildings where the columns are made of a steel-framed reinforced concrete structure and the beams are made of a reinforced concrete structure, and the assembly work can be done extremely easily and in a short period of time, and the work is extremely safe. The purpose is to

以下、図示した実施例に基いて説明すると、ま
ず構築現場の地組ヤードで構築される鉄骨鉄筋コ
ンクリート構造物の鉄骨と鉄筋とからなる軸組を
その構造物の複数階分、および複数スパン分ずつ
組立てて軸組ユニツト1とする。組立てられる軸
組ユニツト1の型には第3図乃至第10図に示す
ようなものがあり、いずれも柱部分2と梁部分3
とを一体的に構成する。
The following is an explanation based on the illustrated example. First, the frame consisting of the steel frame and reinforcing bars of a steel-framed reinforced concrete structure to be constructed in the assembling yard of the construction site is constructed for multiple floors and multiple spans of the structure. Assemble it to form the frame unit 1. There are types of the frame unit 1 that can be assembled as shown in Figures 3 to 10, and each type has a column part 2 and a beam part 3.
and integrally constitute.

第1図および第2図は柱部分2を示したもの
で、H形鋼等からなる柱鉄骨4の周囲には主鉄筋
5およびフープ筋6を籠状をなすように先組して
ある。その際、鉄骨4を支持材とし、鉄骨4の周
囲に保持杆7を井桁状に組み、この保持杆7に主
鉄筋5を結束して取付ける。そしてこの主鉄筋5
にフープ筋6を巻付けて籠状をなすように先組す
る。梁部分3にあつては複数の主鉄筋8を配筋
し、その周囲にスターラツプ筋9を配筋する。
1 and 2 show a column portion 2, in which main reinforcing bars 5 and hoop bars 6 are pre-assembled in a cage shape around a column steel frame 4 made of H-beam steel or the like. At that time, the steel frame 4 is used as a supporting material, and retaining rods 7 are assembled around the steel frame 4 in a parallel cross-shape, and the main reinforcing bars 5 are bundled and attached to the retaining rods 7. And this main reinforcing bar 5
The hoop muscle 6 is wrapped around the hoop and assembled in a cage-like manner. In the beam portion 3, a plurality of main reinforcing bars 8 are arranged, and stirrup reinforcements 9 are arranged around them.

第3図に示す軸組ユニツト1は構築される構造
物軸組の一階分とし、梁3は一方向に組立てられ
たものであり、第4図に示す軸組ユニツト1は構
築される構造物軸組の一階分とし、梁3は二方向
に組立てられたものであり、第5図に示す軸組ユ
ニツト1は構築される構造物軸組の二階分とし、
梁3は一方向に組立てられたものであり、第6図
に示す軸組ユニツト1は構築される構築物軸組の
一階分、梁3は一方向とし、二スパン分組立てら
れたものであり、第7図に示す軸組ユニツト1は
構築される構造物軸組の二階分、梁3は二方向と
して組立てられたものであり、第8図に示す軸組
ユニツト1は構築される構造物軸組の一階分、梁
3は二方向とし、二スパン分組立てられたもので
あり、第9図に示す軸組ユニツト1は構築される
構造物軸組の二階分、梁3は一方向とし、二スパ
ン分組立てられたものであり、第10図に示す軸
組ユニツト1は構築される構造物軸組の二階分、
梁3は二方向とし、二スパン分組立てられたもの
である。なお、軸組ユニツト1の型および大きさ
は構築される構造物の規模やクレーンの稼動能力
等種々の施工条件を考えて決める。
The frame unit 1 shown in Fig. 3 corresponds to one floor of the frame of the structure to be constructed, and the beams 3 are assembled in one direction, and the frame unit 1 shown in Fig. 4 corresponds to the structure to be constructed. The beam 3 is assembled in two directions, and the frame unit 1 shown in FIG. 5 is the second floor of the structure frame to be constructed.
The beam 3 is assembled in one direction, and the frame unit 1 shown in Fig. 6 is for one floor of the frame of the structure to be constructed.The beam 3 is assembled in one direction and is assembled for two spans. , the frame unit 1 shown in FIG. 7 is assembled for two floors of the frame of the structure to be constructed, and the beams 3 are assembled in two directions, and the frame unit 1 shown in FIG. 8 is the frame of the structure to be constructed. The frame unit 1 is assembled for one floor of the frame, the beams 3 are in two directions, and two spans are assembled, and the frame unit 1 shown in Fig. 9 is the frame unit for the second floor of the structure to be constructed, and the beams 3 are in one direction. The frame unit 1 shown in FIG. 10 is assembled for two spans, and the frame unit 1 shown in FIG.
The beam 3 has two directions and is assembled for two spans. The type and size of the frame unit 1 are determined by considering various construction conditions such as the scale of the structure to be constructed and the operating capacity of the crane.

次にこのように組立てられた軸組ユニツト1を
一本、一本クレーン10で吊上げ、構築される構
造物の上階方向およびスパン方向に連結しつつ組
立てる。軸組ユニツト1,1間の連結は、まず柱
部分2においては柱鉄骨4,4の端部双方に連結
プレート11を添接し、この連結プレート11を
介して、ボルト孔12に貫通するボルト、ナツト
13により締着し柱鉄骨3,3を連結自立させた
後、主鉄筋5,5同士を圧接、溶接あるいはスク
イズジヨイント、グリツプジヨイントなど機械的
継手によつて連結する。さらに梁部分3において
主鉄筋8,8同士を圧接、溶接あるいはスクイズ
ジヨイントなどによつて連結する。
Next, the frame units 1 assembled in this manner are lifted one by one by the crane 10 and assembled while being connected in the upper story direction and the span direction of the structure to be constructed. The connection between the frame units 1 and 1 is achieved by attaching connection plates 11 to both ends of the column steel frames 4 and 4 in the column portion 2, and then using bolts that pass through the bolt holes 12 through the connection plates 11. After tightening with nuts 13 to make the column steel frames 3, 3 connected and independent, the main reinforcing bars 5, 5 are connected to each other by pressure welding, welding, or mechanical joints such as squeeze joints and grip joints. Further, main reinforcing bars 8, 8 are connected to each other in the beam portion 3 by pressure welding, welding, squeeze joints, or the like.

次いで柱部分2の継手部分にフープ筋6を補足
して配筋し、梁部分3の継手部分にはスターラツ
プ筋9を補足して配筋し組立作業を完了する。
Next, hoop reinforcements 6 are supplemented and placed at the joints of the column parts 2, stirrup reinforcements 9 are added and placed at the joints of the beam parts 3, and the assembly work is completed.

以上、この発明に係る鉄骨鉄筋コンクリート構
造物、とくに柱は鉄骨鉄筋からなり、梁は鉄筋の
みからなる建築物の施工に際して柱鉄骨を支持材
とし、井桁状の保持枠に主鉄筋を取付け、その主
鉄筋にフープ筋を籠状をなすように配置するので
柱鉄骨と柱鉄筋の先組が可能となる。また上下鉄
骨を接続することにより軸組の組立作業をきわめ
て簡単かつ短期間でおこなうことができ、位置決
めされた梁鉄筋の接続も容易となり、現場作業に
おけるコストダウンが図れる。また作業の安全性
を大幅に高めることができる。
As described above, when constructing a steel-framed reinforced concrete structure according to the present invention, particularly a building in which the columns are made of steel reinforcing bars and the beams are made only of reinforcing bars, the steel columns are used as supporting materials, the main reinforcing bars are attached to the cross-shaped holding frame, and the main reinforcing bars are Since the hoop reinforcements are arranged in a cage-like manner on the reinforcing bars, it is possible to pre-assemble the column steel frame and the column reinforcing bars. Furthermore, by connecting the upper and lower steel frames, the assembly work of the frame can be done extremely easily and in a short period of time, and it is also easier to connect the positioned beam reinforcing bars, reducing the cost of on-site work. Furthermore, work safety can be greatly improved.

【図面の簡単な説明】[Brief explanation of drawings]

第1図、第2図は柱部分の平面図と立面図、第
3図〜第10図は軸組ユニツトの斜視図、第11
図は鉄骨鉄筋コンクリート構造物の軸組の組立方
法を示す構造物の軸組図、第12図は柱部分の連
結状態を示す斜視図である。 1……軸組ユニツト、2……柱、3……梁、4
……柱鉄骨、5……主鉄筋、6……フープ筋、7
……保持杆、8……主鉄筋、9……スターラツプ
筋、10……クレーン、11……連結プレート、
12……ボルト孔、3……ボルト、ナツト。
Figures 1 and 2 are a plan view and an elevation view of the column, Figures 3 to 10 are perspective views of the frame unit, and Figures 11 and 11 are perspective views of the frame unit.
The figure is a framework diagram of a structure showing a method of assembling the framework of a steel-framed reinforced concrete structure, and FIG. 12 is a perspective view showing a state in which column parts are connected. 1... Frame unit, 2... Column, 3... Beam, 4
...Column steel frame, 5...Main reinforcing bar, 6...Hoop bar, 7
...Holding rod, 8... Main reinforcing bar, 9... Stirrup bar, 10... Crane, 11... Connection plate,
12...Bolt hole, 3...Bolt, nut.

Claims (1)

【特許請求の範囲】[Claims] 1 柱が鉄骨鉄筋コンクリート構造で梁が鉄筋コ
ンクリート構造である建築物において柱鉄骨の周
囲にその鉄骨を支持材として、鉄骨の周辺に保持
枠を井桁状に組みこの保持枠に主鉄筋を取付け、
主鉄筋にフープ筋を籠状をなすように先組し、一
方向または二方向の主鉄筋とスタラツプ筋からな
る梁鉄筋を柱鉄骨、鉄筋と一体に先組し、次いで
先組した前記鉄骨、鉄筋を同時に吊上げ、先ず上
下柱鉄骨をボルト締めして連結自立させた後、上
下柱鉄筋を接続し、かつ梁鉄筋を接続することを
特徴とする鉄骨鉄筋コンクリート構造物の施工
法。
1. In a building where the columns are of a steel-framed reinforced concrete structure and the beams are of a reinforced concrete structure, a holding frame is built around the column steel frame in the form of a grid using the steel frame as a supporting material, and the main reinforcing bars are attached to this holding frame.
Hoop reinforcement is pre-assembled to the main reinforcing bars so as to form a cage shape, beam reinforcing bars consisting of main reinforcing bars and starp bars in one or two directions are pre-assembled together with column steel frames and reinforcing bars, and then the above-mentioned steel frames are pre-assembled; A construction method for a steel-framed reinforced concrete structure, which is characterized in that the reinforcing bars are lifted at the same time, the upper and lower column steel frames are first tightened with bolts to connect and stand on their own, and then the upper and lower column reinforcing bars are connected, and then the beam reinforcing bars are connected.
JP12896984A 1984-06-22 1984-06-22 Construction of reinforced concrete building Granted JPS6110682A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12896984A JPS6110682A (en) 1984-06-22 1984-06-22 Construction of reinforced concrete building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12896984A JPS6110682A (en) 1984-06-22 1984-06-22 Construction of reinforced concrete building

Publications (2)

Publication Number Publication Date
JPS6110682A JPS6110682A (en) 1986-01-18
JPH0412348B2 true JPH0412348B2 (en) 1992-03-04

Family

ID=14997883

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12896984A Granted JPS6110682A (en) 1984-06-22 1984-06-22 Construction of reinforced concrete building

Country Status (1)

Country Link
JP (1) JPS6110682A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009097247A (en) * 2007-10-17 2009-05-07 Ohbayashi Corp Column steel frame erection method, steel frame reinforcement unit for column, and steel framed reinforced concrete column

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59102037A (en) * 1982-12-03 1984-06-12 株式会社 長谷川工務店 Construction of reinforced concrete structure using large diameter main iron skeletal to beam

Also Published As

Publication number Publication date
JPS6110682A (en) 1986-01-18

Similar Documents

Publication Publication Date Title
JP2000073448A (en) Connection method and structure for precast concrete beam and column
JPH0412348B2 (en)
JP2566176B2 (en) Building construction method
JP3317057B2 (en) Construction method of earthquake-resistant tube frame and frame structure of high-rise office building
JPS603844Y2 (en) reinforced concrete structure
JPS6020541B2 (en) Reinforcement assembly method for reinforced concrete frame structures
JPH0699963B2 (en) Prestressed RPC method and prestressed PC columns with beams
JPS645134B2 (en)
JP2554535B2 (en) Steel beam / reinforced concrete column composite construction method
JPH067074Y2 (en) Steel column base structure
JP2620118B2 (en) Net formwork method for walls and floors
CN220768392U (en) Assembled beam column structural unit
JPS645133B2 (en)
JPS6321773B2 (en)
JP2614000B2 (en) Basics of steel frame
JPS6141857Y2 (en)
JP2003161041A (en) Seismic reinforcement structure of existing building and its construction method
JPH0694700B2 (en) Reinforced steel composite column
JP3830627B2 (en) Joint structure of reinforced concrete columns and beams
JP2000265548A (en) Construction method of column / beam joint structure and frame
JPH0742805B2 (en) Steel bar truss built-in rebar concrete column
JPH0213694B2 (en)
CN115726516A (en) Construction method for embedded steel truss and reinforced concrete combined prefabricated superposed beam
JPH0410954B2 (en)
JP2673235B2 (en) Parallel string reinforcement truss frame structure of building