JPH04140366A - Preceding erection method of prefabricated column bar and semi-pc girder in pc construction - Google Patents
Preceding erection method of prefabricated column bar and semi-pc girder in pc constructionInfo
- Publication number
- JPH04140366A JPH04140366A JP26203690A JP26203690A JPH04140366A JP H04140366 A JPH04140366 A JP H04140366A JP 26203690 A JP26203690 A JP 26203690A JP 26203690 A JP26203690 A JP 26203690A JP H04140366 A JPH04140366 A JP H04140366A
- Authority
- JP
- Japan
- Prior art keywords
- joint
- semi
- plates
- hardware
- joint plates
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims description 15
- 238000000034 method Methods 0.000 title description 6
- 230000002787 reinforcement Effects 0.000 claims description 13
- 230000003014 reinforcing effect Effects 0.000 claims description 8
- 239000002184 metal Substances 0.000 abstract description 2
- 229910001294 Reinforcing steel Inorganic materials 0.000 abstract 1
- 230000008878 coupling Effects 0.000 abstract 1
- 238000010168 coupling process Methods 0.000 abstract 1
- 238000005859 coupling reaction Methods 0.000 abstract 1
- 238000009415 formwork Methods 0.000 description 3
- 238000003466 welding Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000001934 delay Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009432 framing Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- Rod-Shaped Construction Members (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【発明の詳細な説明】
「産業上の利用分野」
この発明は、RC造におけるプレハブ鉄筋と半PC大梁
の先行建方工法に関するものである。DETAILED DESCRIPTION OF THE INVENTION "Field of Industrial Application" The present invention relates to a pre-construction method for prefabricated reinforcing bars and semi-PC girders in RC construction.
「従来の技術」
従来のRC造は、 (1)鉄筋、型枠を原意値で一階層
づつ組んでコンクリートを打設する工法、 (2)−R
層毎にプレキャスト部材とプレハブ鉄筋を組み合わせて
コンクリートを打設する工法、 (3)プレハブ化した
柱筋及び梁筋の用いて数階要分の鉄筋を先組みして、コ
ンクリートを打設する工法などが知られている。``Conventional technology'' Conventional RC construction consists of (1) a construction method in which reinforcing bars and formwork are assembled one level at a time according to the original values, and concrete is poured; (2) -R
A method in which concrete is poured by combining precast members and prefabricated reinforcing bars for each layer; (3) A method in which prefabricated column and beam reinforcements are used to assemble several floors of reinforcing bars before concrete is poured. etc. are known.
「発明が解決せんとする問題点」
上記(1)の工法では、現場において多数の作業員が必
要で、作業員の確保が困難な現状においては工期の遅れ
が避けられないという問題があり、 (2)の工法にお
いては、作業員は少なくて済むが、揚重設備が常時必要
であり、かつ各階層毎に割り付けであるため、部材数が
多いという問題があり、 (3)の工法においては。``Problems that the invention is not intended to solve'' The construction method described in (1) above requires a large number of workers on site, and in the current situation where it is difficult to secure workers, there is a problem that delays in the construction period are unavoidable. Method (2) requires fewer workers, but there is a problem in that the number of parts is large because lifting equipment is required at all times and is allocated for each floor. teeth.
揚重設備は鉄筋建方時にのみでよいが、型・枠について
は現場作業量が多いという問題があった。Lifting equipment only needs to be used when erecting reinforcing bars, but forming and framing requires a lot of on-site work.
[問題点を解決するための手段」
この発明は前記従来の課題を解決するために、鉛直な継
手板を水平直交方向に十字状に突設した継手金物を、プ
レハブ柱筋の各階層位置に固定し、半PC大梁の両端に
突設した鉛直の継手板を各継手金物の継手板に接合する
ようにしたRC造におけるプレハブ鉄筋と半PC大梁の
先行建方工法を提案するものである。[Means for Solving the Problems] In order to solve the above-mentioned conventional problems, the present invention provides joint hardware in which vertical joint plates are protruded in a cross shape in a horizontal orthogonal direction at each level of the prefabricated column reinforcement. This paper proposes an advance construction method for prefabricated reinforcing bars and semi-PC girders in RC construction, in which vertical joint plates protruding from both ends of the semi-PC girders are fixed and joined to the joint plates of each joint hardware.
「作用」
プレハブ柱筋とプレキャスト大梁または/JX梁が複数
階要分同時に建方でき、工程を短縮することが可能とな
る。``Operation'' Prefabricated column reinforcements and precast girders or /JX beams can be erected simultaneously for multiple floors, making it possible to shorten the process.
建方と同時にデツキプレートと半PC床板を敷き込むこ
とにより、作業足場の確保が容易で安全性の向上を図る
ことができる。By installing deck plates and semi-PC floorboards at the same time as construction, it is easy to secure work scaffolding and improve safety.
予め工場加工したプレハブ柱、とプレキャスト大梁また
は小梁、軽量な十字状継手金物を組み込むので、必要最
小限の作業員と揚重機で施工することができる。It incorporates factory-fabricated prefabricated columns, precast girders or small beams, and lightweight cross-shaped joint hardware, so it can be constructed with a minimum number of workers and lifting equipment.
「実施例」
以下この発明を図面に示す実施例について説明すると、
複数階要分のプレハブ柱筋1を建方し、その各階層位置
に鋼板を十字状に組んだ継手金物2を設置する。"Embodiments" Below, embodiments of the present invention shown in the drawings will be described.
Prefabricated column reinforcements 1 for multiple floors are erected, and joint metal fittings 2 made of cross-shaped steel plates are installed at each floor position.
継手金物2は、鉛直な継手板28〜2dを水平直交方向
に十字状に突設し、隣接する継手板相互間に方杖状の連
結材3により補強してなり、継手板28〜2dの上端部
及び下端部にはカンザシ筋4が水平に固定されている。The joint hardware 2 is made up of vertical joint plates 28 to 2d protruding in a cross shape in the horizontal orthogonal direction, and reinforced by a cane-shaped connecting member 3 between adjacent joint plates. Kantashi muscle 4 is horizontally fixed to the upper and lower ends.
そして、プレハブ柱筋1の各階層位置において、上下の
カンザシ筋4を四周の各柱筋1に締結金具5等によりレ
ベル出しして固定する。Then, at each hierarchical position of the prefabricated columnar reinforcement 1, the upper and lower Kanzashi reinforcements 4 are leveled and fixed to each of the four circumferential columnar reinforcements 1 using fastening fittings 5 or the like.
なお、カンザシ筋4は、継手板28〜2dの上端部及び
下端部に設けた切欠溝に嵌合して溶接により固定するか
、場合によっては溶接することなく嵌合させた状態で柱
Blに締結固定する。In addition, the Kanzashi reinforcement 4 may be fitted into notched grooves provided at the upper and lower ends of the joint plates 28 to 2d and fixed by welding, or in some cases, may be fitted to the column Bl without welding. Fasten and fix.
このようにして固定された各階層の継手金物2の各継手
板2a〜2dに、端部間をコンクリートで成形してなる
半プレキヤスト化された半PC大梁6の両端に突設した
鉛直の継手板7をボルト締め等により接合する。Vertical joints protruding from both ends of semi-precast semi-PC girders 6 formed by molding concrete between the ends are attached to each of the joint plates 2a to 2d of the joint hardware 2 of each floor fixed in this way. The plates 7 are joined by bolting or the like.
次いで同様に小梁、デツキプレート、半PC床板などを
取付だ後、各柱・梁接合部及び梁上部に所要の鉄筋を配
筋し、それぞれの周囲及び柱筋1の周囲に型枠8を設置
し、現場打ちコンクリートを打設して柱・梁を一体化す
る。Next, after attaching small beams, deck plates, semi-PC floor plates, etc. in the same way, the required reinforcing bars are arranged at each column-beam joint and the top of the beam, and formwork 8 is placed around each and around the column reinforcement 1. The columns and beams are then integrated by pouring cast-in-place concrete.
r発明の効果J
以上の通りこの発明によれば、プレハブ柱筋とプレキャ
スト大梁または小梁が複数階要分同時に簡単な作業で建
方でき、工程を短縮することが可能となる(特に、定置
式揚重機が設置できない狭い敷地の場合に有効)。Effects of the Invention J As described above, according to the present invention, prefabricated column reinforcements and precast large beams or small beams can be erected for multiple floors at the same time with simple work, and the process can be shortened (in particular, it is possible to (Effective when the site is narrow where a type lifting machine cannot be installed).
建方と同時にデツキプレートと半PC床板を敷き込むこ
とにより、作業足場の確保が容易で安全性の向上を図る
ことができる。By installing deck plates and semi-PC floorboards at the same time as construction, it is easy to secure work scaffolding and improve safety.
予め工場加工したプレハブ柱、とプレキャスト大梁また
は小梁、軽量な十字状継手金物を組み込むので、必要最
小限の作業員と揚重機で施工することができる。It incorporates factory-fabricated prefabricated columns, precast girders or small beams, and lightweight cross-shaped joint hardware, so it can be constructed with a minimum number of workers and lifting equipment.
4、4,
第1図はこの発明による建方状態を示す正面図、第2図
はこの発明による柱梁接合部の施工状態を示す平面図、
第3図は同縦断正面図である。
1・・プレハブ柱筋、2・・継手金物、28〜2d・・
継手板、3・・連結材、カ
ンザシ筋、
締結金具、
半PC大梁、
継手板、
型枠。
第
図
jI211gJ
第
図FIG. 1 is a front view showing the construction state according to the present invention, FIG. 2 is a plan view showing the construction state of the column-beam joint according to the present invention,
FIG. 3 is a longitudinal sectional front view of the same. 1. Prefabricated column reinforcement, 2. Joint hardware, 28~2d...
Joint plate, 3... Connecting material, Kanzashi reinforcement, fastening fittings, semi-PC girder, joint plate, formwork. Figure jI211gJ Figure
Claims (1)
手金物を、プレハブ柱筋の各階層位置に固定し、半PC
大梁の両端に突設した鉛直の継手板を前記各継手金物の
継手板に接合することを特徴とするRC造におけるプレ
ハブ鉄筋と半PC大梁の先行建方工法。1) Fix the joint hardware, which is a vertical joint plate protruding cross-shaped in the horizontal orthogonal direction, at each level of the prefabricated column reinforcement, and
An advance construction method for prefabricated reinforcing bars and semi-PC girders in RC construction, characterized in that vertical joint plates protruding from both ends of the girder are joined to the joint plates of the respective joint hardware.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP26203690A JPH04140366A (en) | 1990-09-29 | 1990-09-29 | Preceding erection method of prefabricated column bar and semi-pc girder in pc construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP26203690A JPH04140366A (en) | 1990-09-29 | 1990-09-29 | Preceding erection method of prefabricated column bar and semi-pc girder in pc construction |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH04140366A true JPH04140366A (en) | 1992-05-14 |
Family
ID=17370140
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP26203690A Pending JPH04140366A (en) | 1990-09-29 | 1990-09-29 | Preceding erection method of prefabricated column bar and semi-pc girder in pc construction |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH04140366A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101812898A (en) * | 2010-05-25 | 2010-08-25 | 西安建筑科技大学 | 45-degree arranged cross section steel SRC column with flanges |
| CN102720371A (en) * | 2012-07-04 | 2012-10-10 | 中国机械工业建设集团有限公司 | Butt joint method for multiple upright posts of steel structure module and temporary butt joint fixing device |
-
1990
- 1990-09-29 JP JP26203690A patent/JPH04140366A/en active Pending
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101812898A (en) * | 2010-05-25 | 2010-08-25 | 西安建筑科技大学 | 45-degree arranged cross section steel SRC column with flanges |
| CN102720371A (en) * | 2012-07-04 | 2012-10-10 | 中国机械工业建设集团有限公司 | Butt joint method for multiple upright posts of steel structure module and temporary butt joint fixing device |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH09209451A (en) | Joint construction of up and down columns with beam and joint method | |
| JP3752999B2 (en) | Upper and lower integrated bridge and its construction method | |
| JPS6314937A (en) | Reinforced steel composite column | |
| JPH04140366A (en) | Preceding erection method of prefabricated column bar and semi-pc girder in pc construction | |
| JPH0447737B2 (en) | ||
| JP2817591B2 (en) | Construction method of steel reinforced concrete building | |
| JPH02167937A (en) | Connecting work of steel plate-concrete structure | |
| JP2797023B2 (en) | Construction method of beam | |
| JP3830062B2 (en) | Seismic reinforcement method for reinforced concrete buildings | |
| JPH0261238A (en) | Steel plate concrete method | |
| JPS62178634A (en) | Frame construction method for structures | |
| JPS6195136A (en) | Construction of multistoried building skeletal by precast reinforced concrete unit | |
| JPH03275839A (en) | Connection construction of reinforced concrete column and steel beam | |
| JPH0366878A (en) | Construction method of precast columns and beams and precast shear walls | |
| JP2026003816A (en) | Column and beam frame construction method | |
| JPH0522777B2 (en) | ||
| JPS6141857Y2 (en) | ||
| JPH0833021B2 (en) | How to build a skyscraper | |
| JPH0781315B2 (en) | Construction method of composite structure with precast reinforced concrete columns and steel beams | |
| JPH0715177B2 (en) | How to build a reinforced concrete structure | |
| JPS62182329A (en) | Construction of concrete structure | |
| JPS6134549B2 (en) | ||
| JPH0782817A (en) | Building wall structure and construction method | |
| JPH0972001A (en) | Mixed frame | |
| JPH0711171B2 (en) | Reinforced steel composite column |