JPH04237764A - Construction method for high-rise buildings - Google Patents
Construction method for high-rise buildingsInfo
- Publication number
- JPH04237764A JPH04237764A JP451991A JP451991A JPH04237764A JP H04237764 A JPH04237764 A JP H04237764A JP 451991 A JP451991 A JP 451991A JP 451991 A JP451991 A JP 451991A JP H04237764 A JPH04237764 A JP H04237764A
- Authority
- JP
- Japan
- Prior art keywords
- frame
- floor
- construction
- building
- robot
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【0001】0001
【産業上の利用分野】本発明は高層建物の構築工法に係
るものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for high-rise buildings.
【0002】0002
【従来の技術】従来の高層建物の構築においては、移動
及び設置タイプのクレーンによって、部材及び資材を建
方及び仕上げ工事を行なう位置まで揚重したのち、人手
、あるいは床上を移動する塗装ロボツト等によって工事
を行なうものである。[Prior Art] In the construction of conventional high-rise buildings, after parts and materials are lifted to the position where erection and finishing work is carried out using mobile and installation type cranes, they are then moved manually or by painting robots that move on the floor. The construction work will be carried out by
【0003】0003
【発明が解決しようとする課題】移動及び設置タイプの
クレーンによって部材及び資材を建方及び仕上げ工事部
分に揚重、移送する従来の方法では、クレーン設置部分
が建物の内部に位置するため、クレーンの除去後におい
て設置部分の後工事が必要となることが多い。また、ク
レーンによる揚重方式では部材を吊上げるために、同部
材を据付け位置へ正確に移動することができず、更に揚
重した部材を回転させることができないため、据付、組
立工事の自動化が非常に困難となっている。[Problems to be Solved by the Invention] In the conventional method of lifting and transporting parts and materials to the construction and finishing work area using a mobile and installation type crane, the crane installation area is located inside the building. After removal, post-installation work is often required. In addition, with the lifting method using a crane, since the parts are lifted, it is not possible to move the parts accurately to the installation position, and furthermore, the lifted parts cannot be rotated, making it difficult to automate installation and assembly work. It has become extremely difficult.
【0004】近年建築工事の自動化、省力化は建設作業
員の不足、及び危険作業対策として、建設会社、建設機
械メーカー等を中心として急速に研究開発が進められて
いる。その結果コンクリート床仕上げ、鉄骨溶接、塗装
ロボツト等が現在までに開発されているが、いずれも移
動、センシング機能等が現場に対応しきれないため、十
分な省力化、無人化効果が得られていないのが現状であ
る。[0004] In recent years, research and development has been rapidly progressing on automation and labor saving in construction work, mainly by construction companies and construction machinery manufacturers, as a measure against the shortage of construction workers and dangerous work. As a result, concrete floor finishing, steel frame welding, painting robots, etc. have been developed to date, but all of these robots have not been able to achieve sufficient labor-saving and unmanned effects because their mobile, sensing functions, etc. cannot be used on-site. The current situation is that there is no such thing.
【0005】本発明は前記従来技術の有する問題点に鑑
みて提案されたもので、その目的とする処は、自動化施
工に適するように改良された高層建物の構築工法を提供
する点にある。The present invention has been proposed in view of the problems of the prior art, and its object is to provide a construction method for high-rise buildings that is improved to be suitable for automated construction.
【0006】[0006]
【課題を解決するための手段】前記の目的を達成するた
め、本発明に係る高層建物の構築工法によれば、建物最
上階部分のフレームを地上部で組立てるとともに、同フ
レーム外周部及び同フレームの天井部に配設されたロボ
ツト保持及び移動レールに、それぞれ柱組立ロボツト及
び据付け組立ロボツトを装架し、前記フレームを建物両
側に配設された柱を支えとしてリフトアツプし、前記据
付け組立ロボツトを施工階床部に保持し、同部の施工を
完了すると前記フレームをリフトアツプして順次上部施
工階床部分に移動せしめるとともに、前記フレームを支
承する柱を同フレームに装架された前記柱組立ロボツト
によって接合して順次上階を構築するものである。[Means for Solving the Problems] In order to achieve the above object, according to the construction method for a high-rise building according to the present invention, the frame of the top floor of the building is assembled on the ground, and the outer peripheral part of the frame and the frame A column assembly robot and an installation assembly robot are respectively mounted on the robot holding and moving rails arranged on the ceiling of the building, and the frame is lifted up using pillars installed on both sides of the building as support, and the installation assembly robot is mounted on the robot holding and moving rails arranged on the ceiling of the building. The frame is held in the construction floor section, and when the construction of that section is completed, the frame is lifted up and sequentially moved to the upper construction floor section, and the column supporting the frame is moved to the column assembly robot mounted on the frame. The upper floors will be built sequentially by joining them together.
【0007】[0007]
【作用】本発明によれば前記したように、予め建物最上
階部分のフレームを地上部で組立てるとともに、同フレ
ームの天井部にロボツト保持移動レールを配設し、同レ
ールに据付け組立ロボツトを装架するとともに、前記フ
レームの外周部を移動用レールとして同部に柱組立ロボ
ツトを装架し、前記最上階部分のフレームを建物の両側
に配設された柱を支えとして所要の施工階床までリフト
アツプして、前記据付け組立ロボツトを前記施工階床部
に保持し、同ロボツトにより同階床部に所要の施工を施
したのち、前記最上階部分のフレームをリフトアツプし
て順次上部施工階床部分に移動せしめ、前記据付組立ロ
ボツトによって同各施工階床の施工を行なう。[Operation] According to the present invention, as described above, the frame for the top floor of the building is assembled in advance on the ground, and a robot holding and moving rail is provided on the ceiling of the frame, and the assembly robot is mounted on the rail. At the same time, a pillar assembly robot is mounted on the outer periphery of the frame as a moving rail, and the frame on the top floor is supported by pillars placed on both sides of the building to the required construction floor. After lifting up and holding the installation assembly robot on the construction floor, and performing the required construction on the floor using the same robot, the frame of the top floor is lifted up and the upper construction floor is sequentially installed. Then, the installation and assembly robot constructs each floor.
【0008】一方、前記最上階部分のフレームの外周部
に装架した柱組立ロボツトによって、前記フレームのリ
フトアツプに伴って同フレームを支承する柱を接合して
、順次上階を構築するものである。[0008] On the other hand, as the frame lifts up, pillars supporting the frame are joined together by a column assembly robot mounted on the outer periphery of the frame of the top floor, and the upper floors are successively constructed. .
【0009】[0009]
【実施例】以下、本発明を図示の実施例について説明す
る。1は地上部で組立てられた建物最上階部分のフレー
ムで、その天井面にロボツト保持及び移動レール2を前
記フレーム1の梁等を介して固定し、同レール2に部材
の据付組立ロボツト3を縦、横、高さ方向に移動自在に
装架する。また前記フレーム1の外周部をロボツト移動
レール4として、同レール4に柱組立ロボツト5を移動
自在に装架する。更に前記フレーム1は建物の両側に配
設された柱6を支えとして、リフトアツプ用ジヤツキ7
を介して上方に移動できるようになっている。図中8は
外壁である。DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to the illustrated embodiments. Reference numeral 1 denotes a frame for the top floor of the building assembled on the ground. A robot holding and moving rail 2 is fixed to the ceiling surface of the frame through the beams of the frame 1, and an assembly robot 3 is mounted on the rail 2. Mounted so that it can be moved vertically, horizontally, and heightwise. Further, the outer peripheral portion of the frame 1 is used as a robot movement rail 4, and a column assembly robot 5 is movably mounted on the rail 4. Further, the frame 1 is supported by pillars 6 disposed on both sides of the building, and is supported by lift-up jacks 7.
It is now possible to move upwards through. 8 in the figure is an outer wall.
【0010】而して前記フレーム1をリフトアツプ用ジ
ヤツキ7を使用して施工階9まで移動せしめる。一方、
部材10は自動リフト11によって建方実施中の施工階
9まで上げられ、部材ストツク棚12に一時保管される
。据付組立ロボツト3をロボツト保持及び移動レール2
に沿って移動せしめて、前記ストツク棚12から部材1
0を据付け場所まで搬送したのち、所定の位置にセツト
する。建方実施中の施工階9の工事が終了したのち、前
記フレーム1を上昇させて上階工事を行う。図中13は
建方完了階である。The frame 1 is then moved to the construction floor 9 using the lift-up jack 7. on the other hand,
The members 10 are lifted by an automatic lift 11 to the construction floor 9 where erection is in progress, and temporarily stored on a member stock shelf 12. Installing and assembling robot 3 onto robot holding and moving rail 2
The member 1 is moved from the stock shelf 12 along the
After transporting the 0 to the installation location, set it in the predetermined position. After the construction on the construction floor 9, which is currently being erected, is completed, the frame 1 is raised and construction on the upper floors is carried out. 13 in the figure is the completed floor.
【0011】一方、建物最上階部分のフレーム1を支持
する柱6は、前記フレーム1の外周部材をロボツト移動
レール4として移動する柱組立ロボツト5によって順次
上方に継接されていき、かくして高層建物の構築施工を
自動化するものである。この際、前記建物最上階部分の
フレーム1に雨よけ屋根14及び建方実施階を掩蔽する
防音壁15を設置することによって、天候に左右されず
建設公害を軽減するものである。On the other hand, the columns 6 supporting the frame 1 on the top floor of the building are successively joined upward by a column assembly robot 5 that moves using the outer circumferential member of the frame 1 as a robot moving rail 4, and thus the high-rise building This is to automate the construction and construction of. At this time, construction pollution is reduced regardless of the weather by installing a rainproof roof 14 and a soundproof wall 15 that covers the construction floor on the frame 1 on the top floor of the building.
【0012】0012
【発明の効果】本発明によれば、建物最上階部分のフレ
ームを地上階で組立て、同フレームを建物両側の柱を支
えとして順次施工階床にリフトアツプし、前記フレーム
の天井部に配設されたロボツト保持及び移動レールに装
架された部材の据付け組立ロボツト、及びロボツト移動
レールを構成する前記フレームの外周部に装架された柱
組立ロボツトによって順次各階床部の建方及び前記フレ
ームの支柱の継接作業を行ない、かくして高層建層物の
自動化施工を可能ならしめたものである。[Effects of the Invention] According to the present invention, a frame for the top floor of a building is assembled on the ground floor, and the frame is sequentially lifted up to the construction floor using pillars on both sides of the building as support, and then installed on the ceiling of the frame. The assembled robot holds the robot and installs the members mounted on the moving rail, and the pillar assembly robot mounted on the outer periphery of the frame that constitutes the robot moving rail sequentially erects each floor and supports the frame. This joint work made it possible to automate the construction of high-rise buildings.
【0013】請求項2の発明は、前記建物最上階部分の
フレームに雨よけ屋根、及び建方実施階を掩蔽する防音
壁を装架したことによって、天候に作用されることなく
施工が行なわれ、建設公害の発生が抑制されるようにし
たものである。[0013] According to the second aspect of the invention, the construction can be carried out without being affected by the weather by installing a rainproof roof and a soundproof wall that covers the floor where construction is performed on the frame of the top floor of the building. This is intended to suppress construction pollution.
【図1】本発明に係る高層建物の構築工法の一実施例の
実施状況を示す縦断面図である。FIG. 1 is a longitudinal sectional view showing the implementation status of an embodiment of the construction method for a high-rise building according to the present invention.
【図2】本発明の方法の実施状況を示す平面図である。FIG. 2 is a plan view showing the implementation situation of the method of the invention.
1 建物最上階部分のフレーム
2 ロボツト保持及び移動レール3 部材
の据付組立ロボツト
4 ロボツト移動レール
5 柱組立ロボツト
6 柱
7 リフトアツプ用ジヤツキ
9 施工階
14 雨よけ屋根
15 防音壁1 Frame of the top floor of the building 2 Robot holding and moving rail 3 Part installation assembly robot 4 Robot moving rail 5 Pillar assembly robot 6 Column 7 Lift-up jack 9 Construction floor 14 Rain roof 15 Soundproof wall
Claims (2)
組立てるとともに、同フレーム外周部及び同フレームの
天井部に配設されたロボツト保持及び移動レールに、そ
れぞれ柱組立ロボツト及び据付け組立ロボツトを装架し
、前記フレームを建物両側に配設された柱を支えとして
リフトアツプし、前記据付け組立ロボツトを施工階床部
に保持し、同部の施工を完了すると前記フレームをリフ
トアツプして順次上部施工階床部分に移動せしめるとと
もに、前記フレームを支承する柱を同フレームに装架さ
れた前記柱組立ロボツトによって接合して順次上階を構
築することを特徴とする高層建物の構築工法。Claim 1: A frame for the top floor of a building is assembled on the ground, and a column assembly robot and an installation assembly robot are installed on the robot holding and moving rails provided on the outer periphery of the frame and on the ceiling of the frame, respectively. The above-mentioned frame is then lifted up using pillars installed on both sides of the building as support, and the installation assembly robot is held on the construction floor. When the construction of the same section is completed, the frame is lifted up and sequentially moved to the upper construction floor. A construction method for a high-rise building, characterized in that the upper floors are sequentially constructed by moving the columns to the floor area and joining the columns supporting the frame by the column assembly robot mounted on the frame.
け屋根、及び施工階床部を掩蔽する防音壁を設置した請
求項1記載の高層建物の構築工法。2. The method for constructing a high-rise building according to claim 1, wherein a rainproof roof and a soundproof wall for covering the construction floor are installed on the frame of the top floor of the building.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP451991A JPH04237764A (en) | 1991-01-18 | 1991-01-18 | Construction method for high-rise buildings |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP451991A JPH04237764A (en) | 1991-01-18 | 1991-01-18 | Construction method for high-rise buildings |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH04237764A true JPH04237764A (en) | 1992-08-26 |
Family
ID=11586301
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP451991A Pending JPH04237764A (en) | 1991-01-18 | 1991-01-18 | Construction method for high-rise buildings |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH04237764A (en) |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE4409829A1 (en) * | 1994-03-22 | 1995-09-28 | Manfred Kobler | Method and device for producing walls and walls, in particular for buildings |
| KR20190098088A (en) | 2019-07-22 | 2019-08-21 | 임춘만 | Building or Varation Building |
| KR20190132302A (en) | 2019-11-05 | 2019-11-27 | 임춘만 | Building or Varation Building |
| KR20190132301A (en) | 2019-11-05 | 2019-11-27 | 임춘만 | Building or Varation Building |
| KR20200007761A (en) | 2019-12-10 | 2020-01-22 | 임춘만 | Building or Varation Building |
| KR20200141964A (en) | 2020-11-30 | 2020-12-21 | 임춘만 | Building or Varation Building |
| KR20200141962A (en) | 2020-11-30 | 2020-12-21 | 임춘만 | Building or Varation Building |
| KR20210070956A (en) | 2020-06-01 | 2021-06-15 | 임춘만 | Building or Varation Building |
-
1991
- 1991-01-18 JP JP451991A patent/JPH04237764A/en active Pending
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE4409829A1 (en) * | 1994-03-22 | 1995-09-28 | Manfred Kobler | Method and device for producing walls and walls, in particular for buildings |
| KR20190098088A (en) | 2019-07-22 | 2019-08-21 | 임춘만 | Building or Varation Building |
| KR20190132302A (en) | 2019-11-05 | 2019-11-27 | 임춘만 | Building or Varation Building |
| KR20190132301A (en) | 2019-11-05 | 2019-11-27 | 임춘만 | Building or Varation Building |
| KR20200007761A (en) | 2019-12-10 | 2020-01-22 | 임춘만 | Building or Varation Building |
| KR20210070956A (en) | 2020-06-01 | 2021-06-15 | 임춘만 | Building or Varation Building |
| KR20200141964A (en) | 2020-11-30 | 2020-12-21 | 임춘만 | Building or Varation Building |
| KR20200141962A (en) | 2020-11-30 | 2020-12-21 | 임춘만 | Building or Varation Building |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US5088263A (en) | Construction apparatus and construction method | |
| JPH04237764A (en) | Construction method for high-rise buildings | |
| KR100980806B1 (en) | Automated Construction System and Automated Construction Method Using the Same | |
| JP2957328B2 (en) | Peripheral holding self-elevating construction method | |
| JPH04306364A (en) | How to install external wall PC components | |
| JP2624020B2 (en) | How to build a building | |
| KR200200364Y1 (en) | High building construction apparatus | |
| JP2000257266A (en) | Construction method of building frame | |
| JP2957323B2 (en) | Lift-up construction method | |
| JPH0447072A (en) | Construction method for multistory building and its device | |
| JPH04237769A (en) | Climb-up method and device for constructing building | |
| JP3177726B2 (en) | Dismantling method of temporary shed for building structures | |
| JP2627705B2 (en) | Automatic frame assembly method | |
| JP2834589B2 (en) | Jack-up type building construction apparatus and its construction method | |
| JPH04231530A (en) | Method for constructing main frames of high-rise building | |
| JPH04238966A (en) | Self-running rise type building construction device and construction method thereof | |
| JPS62244942A (en) | Push-up method and apparatus | |
| JPH0586651A (en) | Method and apparatus for constructing column and beam | |
| JPH0833030B2 (en) | Construction method | |
| JPH04146372A (en) | Constructing method for frame | |
| JPH04330170A (en) | Method for constructing building | |
| JPH074050A (en) | Welding method and equipment for automatic rebuilding of extension column | |
| JPH0713405B2 (en) | How to build a structure | |
| JPH04254664A (en) | Screw-up type building construction device and its constructing method | |
| JPH05340001A (en) | Building construction method and device |