JPH0424330A - Earthquake-proof reinforcing structure of construction - Google Patents

Earthquake-proof reinforcing structure of construction

Info

Publication number
JPH0424330A
JPH0424330A JP12878190A JP12878190A JPH0424330A JP H0424330 A JPH0424330 A JP H0424330A JP 12878190 A JP12878190 A JP 12878190A JP 12878190 A JP12878190 A JP 12878190A JP H0424330 A JPH0424330 A JP H0424330A
Authority
JP
Japan
Prior art keywords
pipe
liquefaction
ground
filter
plug
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP12878190A
Other languages
Japanese (ja)
Other versions
JP2780438B2 (en
Inventor
Yukio Saimura
幸生 才村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Sumitomo Metal Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Metal Industries Ltd filed Critical Sumitomo Metal Industries Ltd
Priority to JP12878190A priority Critical patent/JP2780438B2/en
Publication of JPH0424330A publication Critical patent/JPH0424330A/en
Application granted granted Critical
Publication of JP2780438B2 publication Critical patent/JP2780438B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Foundations (AREA)

Abstract

PURPOSE:To prevent a liquefying of the ground by providing penetration holes in the axial direction to plugs installed to numerous holes engraved on the pipe wall, and using a liquefying preventive tube in which filters are arranged in the penetration holes as a part of holding pillars of the foundation of a construction. CONSTITUTION:To each small hole of the holes 2 of a liquefying preventive pipe 1, a plug 4 is installed. And the plug 4 is composed of a shaft 5, plug removal-preventive members 9 and 10, and a filter protective member 8, and a penetration hole 6 is formed in the axial direction. And the pipe 1 is used as a basic pile set on a ground liable to be liquefied, and the void water in the ground is exhausted into the hollow pipe 1 through the plugs 4 so as to escape the excessive void water generated in the liquefied ground in an earthquake. Consequently, a generation of liquefying can be prevented.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は地震時に液状化発生の可能性のある地盤(以下
、単に液状化地盤という)に設置される橋梁、建築物、
貯蔵タンクなどの構造物の杭基礎あるいは住宅の直接基
礎における耐震補強構造に関するものである。
[Detailed Description of the Invention] [Industrial Application Field] The present invention is applicable to bridges, buildings,
This relates to seismic reinforcement structures for pile foundations of structures such as storage tanks or direct foundations of houses.

〔従来の技術〕[Conventional technology]

従来、液状化対策として、地盤中に多数の孔あき管を離
散的に設け、地震時に生ずる過剰間隙水圧を抜孔あき管
内に逸散させて、液状化を防止する工法がある(特開昭
61−146910号公報、特開昭62−211416
号公報など参照)。
Conventionally, as a countermeasure against liquefaction, there is a construction method in which a large number of perforated pipes are installed discretely in the ground, and excess pore water pressure generated during an earthquake is dissipated into the perforated pipes to prevent liquefaction (Japanese Patent Laid-Open No. 61 -146910 Publication, JP-A-62-211416
(Refer to the publication number, etc.)

すなわち、第28図(a)〜(C)に示すような、長手
方向および周方向に多数の小孔62を穿設し、その孔部
に通水性のあるフィルター63を設けた孔あき管61を
、液状化の恐れのある砂質地盤の所定深さに立設するこ
とにより、地震時に砂質地盤に発生する過剰間隙水圧を
、その孔62を通して孔あき管61内に逸散させること
ができる。上記通水性のフィルター63は、砂が間隙水
とともに孔あき管61内部に侵入するのを阻止するため
に設けられている。
That is, as shown in FIGS. 28(a) to 28(C), a perforated pipe 61 is provided with a large number of small holes 62 in the longitudinal direction and the circumferential direction, and a water-permeable filter 63 is provided in each hole. By erecting the pipe at a predetermined depth in sandy ground that is at risk of liquefaction, excess pore water pressure generated in the sandy ground during an earthquake can be dissipated into the perforated pipe 61 through the hole 62. can. The water-permeable filter 63 is provided to prevent sand from entering the perforated tube 61 together with interstitial water.

また、このような液状化抑止機能を有する孔あき管を構
造物の基礎杭として用いた耐震補強構造が従来提案され
ている。
Furthermore, an earthquake-reinforced structure using such a perforated pipe having a liquefaction inhibiting function as a foundation pile of a structure has been proposed.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

上述の通水性のフィルターは、通常、テトロン、ナイロ
ンなどの合成繊維、合成樹脂、または金属製の薄い材料
からなり、土砂、施工機械などとの接触により損傷を受
けやすい。そして、損傷を受けた場合には孔部からの砂
の侵入を阻止する役割を十分果たせないことになる。し
たがって、孔あき管はその運搬、地盤への設置時などの
取り扱いに十分注意しなければならないという問題点が
あった。
The above-mentioned water-permeable filters are usually made of synthetic fibers such as Tetron and nylon, synthetic resins, or thin metal materials, and are easily damaged by contact with earth and sand, construction machinery, and the like. If the hole is damaged, it will not be able to sufficiently prevent sand from entering through the hole. Therefore, there is a problem in that the perforated pipe must be handled with great care when transporting it, installing it on the ground, etc.

また、上記フィルターは、土砂、施工機械などとの接触
による損傷の可能性を若干でも少なくするためには、通
常孔あき管の内側から取付けることが好ましいが、この
場合、孔あき管の内部の空間が狭いため、取付は作業が
非常に煩雑となる。
In addition, in order to reduce the possibility of damage due to contact with earth and sand, construction machinery, etc., it is usually preferable to install the above filter from the inside of the perforated pipe. Due to the narrow space, installation is very complicated.

さらに、上述のようにフィルターが損傷を受けやすいこ
とから、従来、例えばフィルターを管外周面全面に設け
た孔あき管を地盤に設置する場合、鋼管製のケーシング
パイプをオーガーにより回転正大して所定深さまで建込
んだ後、ケーシングパイプ内を通して孔あき管を所定深
さまで立設し、次にケーシングパイプ先端を開放してケ
ーシングパイプを地盤から抜き上げ、孔あき管を液状化
層に残置するなどの方法がとられている。しかし、この
方法では施工が大がかりとなるだけでなく、施工上、ケ
ーシングパイプの外径と孔あき管の外径との間に隙間が
でき、地盤への設置後の孔あき管の周囲近傍地盤はどう
しても緩んでしまうこととなり、そのままでは液状化の
危険を増すことにもなりかねない。
Furthermore, as mentioned above, filters are easily damaged, so conventionally, for example, when installing a perforated pipe with a filter on the entire outer circumferential surface of the pipe in the ground, the steel casing pipe was rotated with an auger to the desired depth. After the construction is complete, a perforated pipe is passed through the casing pipe and erected to a specified depth, then the tip of the casing pipe is opened, the casing pipe is pulled out of the ground, and the perforated pipe is left in the liquefaction layer. A method is being taken. However, this method not only requires large-scale construction, but also creates a gap between the outer diameter of the casing pipe and the outer diameter of the perforated pipe. will inevitably become loose, and if left as is, it may increase the risk of liquefaction.

したがって、上記のような孔あき管を構造物の基礎杭と
して用いることは実質的に困難であり、施工が難しいだ
けでなく、液状化抑止機能の面でも、また基礎杭として
の機能の面でも不十分であった。
Therefore, it is practically difficult to use the above-mentioned perforated pipes as foundation piles for structures, and not only is construction difficult, but also in terms of liquefaction prevention function and function as foundation piles. It was insufficient.

本発明は上述のような問題点の解決を図ったもので、運
搬、地盤への設置時などの取り扱いが容易で、確実な液
状化抑止機能を発揮する液状化対策管を用いた、抵抗力
の大きい安全な耐震補強構造を提供することを目的とし
ている。
The present invention is an attempt to solve the above-mentioned problems, and uses a liquefaction prevention pipe that is easy to handle during transportation and installation on the ground, and has a reliable liquefaction prevention function. The aim is to provide a large and safe seismic reinforced structure.

〔課題を解決するための手段〕[Means to solve the problem]

本発明の耐震補強構造に用いる液状化対策管は、管壁に
多数の孔を穿設し、その孔に通水性のあるフィルターが
内設された栓を取付けることにより、孔あき管の運搬や
地盤への設置の際のフィルターの損傷を防止するととも
に、フィルターの取付は作業を著しく容易にするもので
ある。すなわち、栓の軸部にはその軸方向に貫通孔を有
し、該貫通孔内にはフィルターが設けられている。
The liquefaction countermeasure pipe used in the seismic reinforced structure of the present invention has many holes in the pipe wall, and plugs equipped with water-permeable filters are attached to the holes, making it easy to transport the perforated pipe. In addition to preventing damage to the filter during installation in the ground, the installation of the filter greatly facilitates the work. That is, the shaft portion of the stopper has a through hole in the axial direction, and a filter is provided within the through hole.

栓の貫通孔には、フィルターとともに土砂によるフィル
ターの損傷防止用に通水性のあるフィルター防護部材を
設けることができる。また、管の運搬時や地盤への設置
時に、栓が管から離脱しないように、栓の一端または両
端に管の孔の径よりも大きい径を有する離脱防止部を設
けるこ止もできる。
In the through hole of the stopper, a water-permeable filter protection member can be provided together with the filter to prevent damage to the filter due to earth and sand. Further, in order to prevent the plug from separating from the pipe when the pipe is transported or installed on the ground, it is possible to provide a detachment prevention portion having a diameter larger than the diameter of the hole in the pipe at one or both ends of the plug.

液状化対策用管の製作方法としては、上述の栓を穿孔済
の管の番孔に嵌合することにより、フィルター付の孔あ
き管を容易に製作することができる。
As a method for manufacturing a liquefaction countermeasure pipe, a perforated pipe with a filter can be easily manufactured by fitting the above-mentioned plug into a hole in a perforated pipe.

また、本発明の耐震補強構造に用いる液状化対策管は、
フィルターを栓の貫通孔に内設し、必要に応じフィルタ
ー防護部材を設けであるため、ケーシングバイブなどを
用いて、フィルターを保護することなく、ディーゼルハ
ンマー、油圧ハンマ、バイブロハンマー、圧入機などに
より、直接、地盤に設置することができる。
In addition, the liquefaction countermeasure pipe used in the seismic reinforcement structure of the present invention is
The filter is installed inside the through-hole of the stopper, and a filter protection member is installed if necessary, so it can be easily removed using a diesel hammer, hydraulic hammer, vibro hammer, press-fit machine, etc. without using a casing vibrator to protect the filter. , can be installed directly into the ground.

本発明の構造物の耐震補強構造は、上述の液状化対策管
を、構造物、例えば建物、橋梁の橋脚、橋台、貯蔵タン
クなどの基礎の支持杭の少なくとも一部に用いたもので
、あるいはさらに液状化対策管を支持杭の周辺にも設置
して、地盤の液状化を防止するとともに、抵抗力の高い
安全な耐震補強構造を形成することができる。
The seismic reinforcement structure of the structure of the present invention uses the above-mentioned liquefaction prevention pipe for at least part of the support piles of the foundation of a structure, such as a building, a bridge pier, an abutment, or a storage tank, or Furthermore, by installing liquefaction prevention pipes around the support piles, it is possible to prevent liquefaction of the ground and form a safe seismic reinforcement structure with high resistance.

また、直接基礎を有する住宅建築においては、地震時に
地盤の液状化が懸念される地層に設置される住宅の直接
基礎の下部に上述の液状化対策管を設け、あるいはさら
に住宅の直接基礎間または周辺にも液状化対策管を設置
することにより、住宅建築に対する抵抗力の高い安全な
耐震補強構造を形成することができる。
In addition, in residential buildings with direct foundations, the above-mentioned liquefaction countermeasure pipes are installed below the direct foundations of houses installed in strata where there is a risk of ground liquefaction during an earthquake, or between the direct foundations of houses or By installing liquefaction countermeasure pipes around the area, it is possible to create a safe seismic reinforced structure with high resistance to residential construction.

〔作 用〕[For production]

液状化防止の原理は、液状化対策管を液状化の懸念され
る地盤に設置される基礎杭に用い、杭としての管に取付
けられた栓を通して地盤内の間隙水を中空の管内に排出
できるようにすることにより、地震時に液状化地盤に発
生する過剰間隙水圧を逸散させ、液状化の発生を防止す
るものである。
The principle of liquefaction prevention is that liquefaction prevention pipes are used for foundation piles installed in ground where liquefaction is a concern, and pore water in the ground can be drained into the hollow pipes through plugs attached to the pipes serving as piles. By doing so, the excess pore water pressure generated in the liquefied ground during an earthquake is dissipated and the occurrence of liquefaction is prevented.

第16図は液状化対策管の模型を液状化地盤を設置して
自由減衰波加振実験の結果を示したものである。液状化
対策管を設置した地盤では、過剰間隙水圧比が0.5以
下に優に収まっており、液状化防止効果があるのに対し
、設置しない地盤のみの場合は、過剰間隙水圧比が0.
6以上となりほぼ液状化した状態になる。
Figure 16 shows the results of a free damping wave excitation experiment using a model of a liquefaction countermeasure pipe installed in liquefaction ground. In the ground where liquefaction countermeasure pipes are installed, the excess pore water pressure ratio is well below 0.5, which has a liquefaction prevention effect, whereas in the case of only the ground where no liquefaction pipes are installed, the excess pore water pressure ratio is 0. ..
When it becomes 6 or more, it becomes almost liquefied.

第17図は液状化対策管および液状化対策をしない普通
の管を設置した地盤において、同一荷重を管に作用させ
た場合、加振しない常時の変位に対する加振時の管の変
位をそれぞれの管について示したものである。加振時の
管の変位は常時のそれに比べて無対策管の場合では3倍
近くになるのに対して、液状化対策管の場合には1.5
倍程度に収まる。このことから、液状化対策管を設置し
た地盤では、地震時においてもかなりの水平抵抗力が期
待できることがわかる。
Figure 17 shows the displacement of the pipe during vibration compared to the normal displacement without vibration when the same load is applied to the pipe in the ground where liquefaction countermeasures pipes and ordinary pipes without liquefaction countermeasures are installed. This shows the tube. The displacement of the pipe during vibration is nearly three times as much in the case of a pipe without countermeasures as compared to that under normal conditions, while in the case of a pipe with liquefaction countermeasures it is 1.5 times as much.
It fits about twice as much. This indicates that the ground where liquefaction prevention pipes have been installed can be expected to have considerable horizontal resistance even in the event of an earthquake.

第18図は液状化対策管または無対策管を打設した地盤
、および管を打設しない地盤に、載荷板により水平荷重
を加えてゆき、途中で地盤全体を加振した場合の水平荷
重Pと載荷板変位δの関係を示したものである。液状化
対策管を設置した場合には加振中でも水平抵抗が期待で
きるのに対し、無対策管を設置した場合には加振中はと
んど水平抵抗が期待できない。すなわち、液状化対策管
を設置した地盤では管周囲が液状化することなく、管が
水平抵抗力を発揮するのに対し、無対策管を設置した地
盤では管周囲も液状化して管は水平抵抗力がほとんどな
くなる。
Figure 18 shows the horizontal load P when a horizontal load is applied by a loading plate to the ground where a liquefaction countermeasure pipe or no countermeasure pipe is installed, and the ground where no pipe is installed, and the entire ground is vibrated in the middle. This figure shows the relationship between δ and loading plate displacement δ. If pipes with liquefaction countermeasures are installed, horizontal resistance can be expected even during excitation, whereas if pipes without countermeasures are installed, no horizontal resistance can be expected during excitation. In other words, in the ground where liquefaction countermeasures pipes are installed, the area around the pipe does not liquefy and the pipe exerts horizontal resistance, whereas in the ground where no countermeasures are installed, the area around the pipe also liquefies and the pipe exerts horizontal resistance. Almost no power left.

以上のように、液状化対策管を設置すると、地震時にお
ける地盤の液状化を防止し得るとともに、水平抵抗力を
期待することができる。
As described above, by installing liquefaction countermeasure pipes, it is possible to prevent liquefaction of the ground during an earthquake, and at the same time, it is possible to expect horizontal resistance.

したがって、このような液状化対策管を構造物の基礎杭
などに用いると、最も液状化の発生しやすい基礎杭近傍
の液状化を防止することができるので、安全性の高い基
礎杭を提供することができる。
Therefore, when such liquefaction prevention pipes are used for foundation piles of structures, it is possible to prevent liquefaction near the foundation piles where liquefaction is most likely to occur, thereby providing highly safe foundation piles. be able to.

そして、フィルターが内部に装着された栓を孔あき管の
孔部に取付けるという方法を用いることにより、孔あき
管の運搬や地盤への立設の際のフィルターの損傷を防止
できる。また、フィルター防護部材を設けることにより
、特に液状化対策管を地盤に設置する際に、栓の軸方向
に土砂が侵入してきてもフィルターの損傷を防ぐことが
できる。
By using a method of attaching a stopper with a filter inside to the hole of the perforated pipe, damage to the filter can be prevented when the perforated pipe is transported or erected on the ground. Further, by providing the filter protection member, it is possible to prevent damage to the filter even if dirt enters in the axial direction of the plug, especially when installing the liquefaction countermeasure pipe in the ground.

なお、栓の端部に離脱防止部を設けることにより、管の
地盤への設置時にも栓の離脱を確実に防止することがで
きる。
In addition, by providing a detachment prevention part at the end of the plug, it is possible to reliably prevent the plug from detaching even when the pipe is installed on the ground.

施工方法についても従来のようにケーシングパイプを地
盤に圧入して、またはケーシングオーガーを回転圧入さ
せ地盤に設置孔を設けた後、排水管を設置する方法を採
用する必要はなく、管を直接、地盤に圧入機により圧入
することができるし、バイブロハンマーやディーゼルハ
ンマーナトの機器により、直接、j?!!盤に打設する
ことができる。
Regarding the construction method, there is no need to adopt the conventional method of press-fitting a casing pipe into the ground, or rotating a casing auger to make an installation hole in the ground, and then installing a drainage pipe. It can be press-fitted into the ground with a press-fitting machine, and directly with a vibrohammer or diesel hammernato equipment. ! ! It can be placed on the board.

よって施工は従来に比べ極めて簡単となり、施工方法に
も幅をもたせることができる。
Therefore, construction is much easier than before, and there is a wide range of construction methods available.

さらに、液状化対策管の製作方法についても、穿孔した
管の孔部に、内部にフィルターの装着された栓を嵌合す
るだけなので、従来の孔あき管のフィルターの取付は作
業に比べ、はるかに容易なものとなる。
Furthermore, regarding the manufacturing method of the liquefaction countermeasure pipe, simply fitting a plug with a filter inside into the hole of a perforated pipe is much easier than installing a filter on a conventional perforated pipe. It becomes easy to use.

〔実施例〕〔Example〕

次に、本発明の実施例を添付した図面に基づいて説明す
る。
Next, embodiments of the present invention will be described based on the attached drawings.

第1図は本発明に係る液状化対策管1の概要を示したも
ので、管1の穿孔部2の各小孔には栓4が取付けられて
おり、その栓4の内部にはフィルターが内設されている
。
FIG. 1 shows an outline of a liquefaction countermeasure pipe 1 according to the present invention. A plug 4 is attached to each small hole in a perforated portion 2 of the pipe 1, and a filter is installed inside the plug 4. It is installed internally.

管の穿孔部2の長さは、対象となる液状化地盤の層厚に
対応する長さ以上とすればよい。
The length of the perforated portion 2 of the pipe may be greater than or equal to the layer thickness of the target liquefied ground.

第2図は栓4の断面の一例および孔あき管1への栓4の
装着方法の一例を示したものである。また、第3図(a
)は第2図の栓4の側面図で、第3図ら)J3よび第3
図(C)は正面図および背面図である。
FIG. 2 shows an example of a cross section of the plug 4 and an example of a method of attaching the plug 4 to the perforated pipe 1. Also, Figure 3 (a
) is a side view of the stopper 4 in FIG. 2, and FIG.
Figure (C) is a front view and a rear view.

この実施例においては、栓4は軸部5、栓離脱防止部9
,10、およびフィルター防護部材8から構成され、そ
の軸方向に貫通孔6を有している。
In this embodiment, the plug 4 includes a shaft portion 5, a plug detachment prevention portion 9
, 10, and a filter protection member 8, and has a through hole 6 in its axial direction.

そして、その貫通孔6内のフィルター防護部材8の管1
内面側に通水性のあるフィルター7が内設されている。
Then, the tube 1 of the filter protection member 8 in the through hole 6
A water-permeable filter 7 is provided on the inner surface.

栓軸部5の外径は、管1の孔3の直径とほぼ同寸法とな
っている。栓離脱防止部9゜10の径は管1の孔3の直
径より大きい。フィルター防護部材8は栓軸部5と一体
的に設けられているのが望ましく、この防護部材8には
通水性を確保するため、多くの小孔が設けられている。
The outer diameter of the plug shaft portion 5 is approximately the same as the diameter of the hole 3 of the tube 1. The diameter of the stopper separation preventing portion 9°10 is larger than the diameter of the hole 3 of the tube 1. The filter protection member 8 is preferably provided integrally with the stopper shaft 5, and this protection member 8 is provided with many small holes to ensure water permeability.

また、本発明に係る液状化対策管は、通常、管の孔に栓
が取付けられた状態で運搬され、さらに地盤中に立設さ
れ、地盤の液状化防止に供用されるものであるため、栓
はその過程で損傷をうけることのないよう十分な強度を
有する必要がある。
In addition, the liquefaction prevention pipe according to the present invention is usually transported with a plug attached to the hole of the pipe, and is further erected in the ground and used to prevent liquefaction of the ground. The stopper needs to be strong enough so that it is not damaged in the process.

また、栓を管の孔に挿設するためには、少なくとも栓離
脱防止部はある程度柔軟性のある材料とする必要がある
。また、フィルター防護部材は、ナイロンフィルター等
、比較的薄く、弱いフィルターを液状化対策管の運搬、
立設、供用時などに、その損傷から防護するものである
から、この目的を満足する強度を確保する必要がある。
Furthermore, in order to insert the stopper into the hole of the tube, at least the stopper separation prevention part needs to be made of a material with some degree of flexibility. In addition, the filter protection member is used to transport relatively thin and weak filters such as nylon filters in liquefaction prevention pipes.
Since it is intended to protect it from damage during erection and use, it is necessary to ensure the strength to satisfy this purpose.

また、この意味からもフィルター防護部材は栓と一体的
に製造するのが望ましいが、もちろん別体として後から
取付けることも可能である。栓の材料としては、上記の
条件を満足するものであれば特に限定されないが、栓の
孔への嵌合性実験、地盤中への液状化対策管の打設実験
などの結果からは、例えば塩化ビニール、ポリエチレン
、ナイロン、ポリプロピレンなどの合成樹脂、ゴムなど
が適当と考えられる。
Also, from this point of view, it is desirable to manufacture the filter protection member integrally with the stopper, but it is of course possible to attach it later as a separate body. The material for the plug is not particularly limited as long as it satisfies the above conditions, but based on the results of experiments on the fit of the plug into the hole and experiments on driving liquefaction prevention pipes into the ground, for example, Synthetic resins such as vinyl chloride, polyethylene, nylon, and polypropylene, rubber, etc. are considered suitable.

また、フィルター防護部材は通水性のための小孔が設け
られているが、小孔の形状は円形、角形など特に限定さ
れるものでない。フィルター防護部材の各小孔の径、メ
ツシュはほぼ同じ大きさであることが望ましい。また、
フィルターは防護部材がないと、液状化対策管の立設時
に粒径の比較的大きい砂(荒砂)との摩擦によって破損
するおそれがあるため、フィルター防護部材の小孔の径
、メツシュは対象とする荒砂の大きさより小さくしてお
けばよい。フィルター防護部材の材料は、例えば前述の
塩化ビニール、ポリエチレン、ナイロン、ポリプロピレ
ンなどの合成樹脂、ゴムなどでよく、防護部材の孔径ま
たはメツシュとピッチを調節することによって所要の強
度を確保すればよい。
Further, although the filter protection member is provided with small holes for water permeability, the shape of the small holes is not particularly limited, such as circular or square. It is desirable that the diameters and meshes of each small hole in the filter protection member are approximately the same size. Also,
If the filter does not have a protective member, there is a risk that it will be damaged by friction with relatively large sand (rough sand) when the liquefaction countermeasure pipe is erected. It should be smaller than the size of the rough sand. The material of the filter protection member may be, for example, the aforementioned vinyl chloride, synthetic resin such as polyethylene, nylon, or polypropylene, or rubber, and the required strength may be ensured by adjusting the pore diameter or mesh and pitch of the protection member.

第2図および第3図の実施例においては、フィルター防
護部材8が荒砂の管1内への流入を防止する1次のフィ
ルターの役割をも果たし、この防護部材8の管内側にあ
るフィルター7は、フィルター防護部材8を通過した比
較的細かい土粒子の管内への流入を防止する役割を果た
す。
In the embodiments shown in FIGS. 2 and 3, the filter protection member 8 also serves as a primary filter for preventing coarse sand from flowing into the pipe 1, and the filter 7 located inside the pipe of this protection member 8 serves to prevent relatively fine soil particles that have passed through the filter protection member 8 from flowing into the pipe.

フィルターとしては、ステンレス製のフィルターを用い
てもよく、合成繊維製のものや合成樹脂製のものを用い
てもよい。発錆の懸念があるときは、後者のフィルター
の方が好ましく、例えばナイロン製、ポリエチレンモノ
フィラメント製、ポリエステル製などの経編布や、ポリ
プロピレン製、ポリエステル繊維製などの不織布などを
用いることができる。また、合成繊維どうし、合成樹脂
どうし、あるいは合成繊維と合成樹脂を組合わせたり、
重ね合せたりして、フィルターとしてもよい。
As the filter, a stainless steel filter, a synthetic fiber filter, or a synthetic resin filter may be used. When there is a concern about rust, the latter filter is preferable, and for example, warp knitted fabrics such as nylon, polyethylene monofilament, or polyester, or nonwoven fabrics such as polypropylene or polyester fibers can be used. In addition, combining synthetic fibers, synthetic resins, or synthetic fibers and synthetic resins,
They can also be layered to form a filter.

例えば、薄い経編布や不織布からなる合成繊維製のフィ
ルターの片面または両面に、この合成繊維製フィルター
より厚く、メツシュの大きい合成樹脂製のフィルター、
または合成繊維製フィルターより厚く、そのメツシュよ
り大きい小孔を多数有する合成樹脂製のネットを重ね合
せて補強したフィルターを用いることもできる。この場
合、メツシュの大きい合成樹脂製のフィルターやネット
が前述のフィルター防護部材の役割を果たすことになり
、その場合は別途フィルター防護部材を用いなくてもよ
い。
For example, on one or both sides of a synthetic fiber filter made of thin warp knitted fabric or non-woven fabric, a synthetic resin filter that is thicker and has a larger mesh than the synthetic fiber filter,
Alternatively, it is also possible to use a filter reinforced by overlapping synthetic resin nets that are thicker than synthetic fiber filters and have many small holes larger than the mesh. In this case, a synthetic resin filter or net with a large mesh will play the role of the above-mentioned filter protection member, and in that case, there is no need to use a separate filter protection member.

フィルターとしての経編布や不織布、またはステンレス
製フィルターなどのメツシュまたは間隙は、液状化防止
などの対象とする地盤(一般には砂地盤)の土の粒径分
布を勘案して、土砂によるフィルターの目詰まりを起こ
さないように設定するのがよい。このメツシュまたは間
隙は、液状化の可能性のある地盤で、土の粒径が特別大
きく、比較的均一に分布している地盤では1〜3mm程
度に大きく設定することも可能であるが、こうした地盤
は少なく、液状化の可能性のある一般的な地盤では1〜
3mm程度よりかなり小さく設定するのがよい。また、
フィルターは目詰まり防止のためには薄い方が望ましい
。フィルターのメツシュまたは間隙が1〜3肛程度に大
きく設定することが可能な場合には、上述したフィルタ
ー防護部材と同様な材質、強度を持たせ、孔径またはメ
ツシュを1〜3M程度に設定したフィルター防護部材の
みを、フィルターとして機能させることも可能である。
The mesh or gap of warp knitted fabric, non-woven fabric, or stainless steel filter as a filter is determined by considering the particle size distribution of the ground (generally sandy ground) that is targeted for liquefaction prevention. It is best to set it to prevent clogging. This mesh or gap can be set as large as 1 to 3 mm in ground where there is a possibility of liquefaction and where the soil particle size is particularly large and relatively uniformly distributed. There is little ground, and in general ground with the possibility of liquefaction, 1 to 1
It is best to set it considerably smaller than about 3 mm. Also,
The thinner the filter, the better to prevent clogging. If the mesh or gap of the filter can be set large to about 1 to 3 holes, the filter should be made of the same material and strength as the above-mentioned filter protection member, and the pore size or mesh should be set to about 1 to 3M. It is also possible for the protective member alone to function as a filter.

液状化対策におけるフィルターの透水係数は、液状化対
策管の設置地盤にもよるが、一般に10−2cm/ s
ec 〜10−’Cm/ sec程度以上のものが好ま
しい。また、フィルター防護部材の孔径またはメツシュ
は、一般にフィルターのメツシュまたは間隙より大きい
ので、フィルターの透水係数が所定のものなら、フィル
ター防護部材とフィルターを重ね合せたときの透水係数
も所定の仕様を確保することができる。
The permeability coefficient of a filter for liquefaction countermeasures depends on the ground where the liquefaction countermeasure pipe is installed, but it is generally 10-2 cm/s.
ec to about 10-'Cm/sec or more is preferable. In addition, the pore diameter or mesh of the filter protection member is generally larger than the mesh or gap of the filter, so if the filter has a specified water permeability coefficient, the water permeability coefficient when the filter protection member and filter are stacked will also ensure the specified specification. can do.

第2図の実施例におけるフィルター付き栓4の管1への
嵌設については、栓離脱防止部10側を管1の孔3に当
てがい、栓離脱防止部9側をハンマーなどで打撃するこ
とにより、容易に管壁の孔3に装着することができる。
In order to fit the plug 4 with a filter into the pipe 1 in the embodiment shown in FIG. 2, the side of the stopper separation prevention part 10 is applied to the hole 3 of the pipe 1, and the side of the stopper separation prevention part 9 is struck with a hammer or the like. Therefore, it can be easily attached to the hole 3 in the tube wall.

栓離脱防止部10の径は管壁の孔径より大きいので、装
着時は管壁の孔径まで縮小され、この孔部を栓離脱防止
部10が通過すると拡径し、装着は完了する。したがっ
て栓の材質は弾性あるいは可撓性を有することが必要で
ある。栓4の装着を容易にするために、第3図に示すよ
うに栓4の軸部5から栓離脱防止部10にわたりスリッ
ト11を設けてもよい。第3図の例ではスリット11を
4箇所設けているが、スリット11の幅、長さ、数は、
栓4の嵌設が容易であり、かつ嵌設後栓4が離脱しない
ように、栓4の材質、軸部5の長さに応じて適当に変え
ればよい。
Since the diameter of the stopper removal prevention part 10 is larger than the hole diameter of the tube wall, it is reduced to the hole diameter of the tube wall when it is installed, and when the stopper removal prevention part 10 passes through this hole, it expands and the installation is completed. Therefore, the material of the stopper needs to have elasticity or flexibility. In order to facilitate attachment of the stopper 4, a slit 11 may be provided extending from the shaft portion 5 of the stopper 4 to the stopper detachment prevention portion 10, as shown in FIG. In the example shown in Fig. 3, slits 11 are provided at four locations, but the width, length, and number of slits 11 are as follows:
The material may be appropriately changed depending on the material of the plug 4 and the length of the shaft portion 5 so that the plug 4 can be easily fitted and the plug 4 does not come off after fitting.

上述のようにして栓4を装着すれば、栓離脱防止部9,
10により、栓4が機械的に管1の孔3に固定されるこ
ととなり、液状化対策管の運搬、施工時などに離脱しな
くなる。
If the stopper 4 is attached as described above, the stopper separation prevention part 9,
10, the stopper 4 is mechanically fixed to the hole 3 of the pipe 1, and will not come off during transportation or construction of the liquefaction countermeasure pipe.

栓を装着する管本体は、鋼管、鋳鉄管、コンクリート管
、鋼・コンクリート複合管、塩化ビ、;ルやポリエチレ
ンなどの合成樹脂管など、いずれでもよく、液状化対策
の対象となる液状化地盤の層厚以上の管長にわたって穿
孔されている。
The main body of the pipe to which the stopper is attached may be any steel pipe, cast iron pipe, concrete pipe, steel/concrete composite pipe, PVC pipe, synthetic resin pipe such as polyethylene, etc., and is suitable for liquefied ground that is subject to liquefaction measures. The holes are perforated over a pipe length that is equal to or greater than the layer thickness.

地震時に地盤の過剰間隙水圧を逸散し、液状化を防止す
るためには、開孔部の全面積(個々の孔の面積の和)の
、穿孔部の全表面積に対する割合(開孔率と呼ぶ)で1
%以上の通水し得る面積を確保するのが望ましい。この
開孔部の面積は地盤の性質(土砂の粒径、密度など)、
地震の性質、管の性質(管径、管内中空部の大きさ、内
面の粗度など)などにより決定すればよい。例えば、開
孔率約1〜6%で径20〜1400mmの管を対象とし
た実験結果では、この液状化対策管は地盤に適切なピッ
チで配置すれば液状化が確実に防止することができる。
In order to dissipate excess pore water pressure in the ground and prevent liquefaction during an earthquake, it is necessary to increase the ratio of the total area of the hole (sum of the areas of individual holes) to the total surface area of the hole (open area ratio). call) 1
% or more is desirable. The area of this opening depends on the nature of the ground (grain size, density, etc. of the soil),
It may be determined based on the nature of the earthquake, the properties of the pipe (pipe diameter, size of the hollow part inside the pipe, roughness of the inner surface, etc.). For example, experimental results using pipes with a porosity of approximately 1 to 6% and a diameter of 20 to 1,400 mm show that liquefaction can be reliably prevented if these liquefaction prevention pipes are placed at an appropriate pitch on the ground. .

フィルター付き栓の別の実施例として、前述の栓の実施
例にフィルター防護部材8bを管1の内面側にさらに付
加したものを第4図、第5図に示す。この実施例は第2
図、第3図に示した実施例と栓4の部材は同じであり、
液状化対策管1の施工時に管1内面に土砂が入ってきた
場合のフィルター4の破損防止のために、フィルター防
護部材8bを付加したものである。フィルター防護部材
8bは栓4の軸部5などと一体成形することもできる。
As another embodiment of the plug with a filter, a filter protection member 8b is further added to the inner surface of the tube 1 in addition to the above-mentioned plug embodiment, as shown in FIGS. 4 and 5. This example is the second
The members of the plug 4 are the same as the embodiment shown in FIGS.
A filter protection member 8b is added to prevent damage to the filter 4 in the event that dirt enters the inner surface of the pipe 1 during construction of the liquefaction countermeasure pipe 1. The filter protection member 8b can also be integrally molded with the shaft portion 5 of the stopper 4 and the like.

また、フィルター防護部材8aを栓4の軸部5などと一
体成形した後、フィルター防護部材8bを栓4の軸部5
に接着接合して栓4を製造してもよい。
Further, after integrally molding the filter protection member 8a with the shaft portion 5 of the plug 4, etc., the filter protection member 8b is attached to the shaft portion 5 of the plug 4.
The stopper 4 may be manufactured by adhesively bonding the material to the material.

フィルター7を防護部材8a、8bで防護した形のこの
栓4は、例えば第1図に示すような管1において、管1
の先端が開放されており、施工時に管内に土砂が侵入し
てくる場合などにおいても、フィルター7の破損を防止
することができる。
This stopper 4, which has a filter 7 protected by protective members 8a and 8b, can be used, for example, in a pipe 1 as shown in FIG.
Since the tip of the filter 7 is open, damage to the filter 7 can be prevented even if dirt or sand enters the pipe during construction.

なお、地盤の液状化層にある液状化対策管の内部は、地
震時に地盤の間隙水を排出するために中空であることが
必要なので、土砂が施工時にこの部分に侵入する場合に
は、液状化対策管を地盤へ建込んだ後、管内侵入土砂を
グラブハンマーや、第6図に示すような土砂吸引排出機
31 (パイプ32に吸引力を与え、液状化対策管1内
に入れたバイブ32先端から管内の土砂33を吸引し、
地盤上へ排出する機械、例えば水中ポンプなどを利用す
ればよい)などにより液状化対策管の外へ排出すればよ
い。
The inside of the liquefaction prevention pipe located in the liquefaction layer of the ground needs to be hollow in order to drain pore water in the ground during an earthquake, so if earth and sand enters this part during construction, the liquefaction pipe should be hollow. After erecting the liquefaction countermeasure pipe into the ground, use a grab hammer or a sand suction/discharge machine 31 (a vibrator that applies suction force to the pipe 32 and placed inside the liquefaction countermeasure pipe 1) as shown in Fig. 6 to remove the sediment that has entered the pipe. 32 Suction of earth and sand 33 inside the pipe from the tip,
The water can be discharged out of the liquefaction prevention pipe using a machine that discharges it onto the ground, such as a submersible pump.

第7図、第8図および第9図、第10図にフィルター付
き栓4の別の実施例を示す。これらの例においては栓軸
部5が円錐台の外形を有している。
FIGS. 7, 8, 9, and 10 show other embodiments of the plug 4 with a filter. In these examples, the stopper shaft portion 5 has a truncated conical outer shape.

栓4の材質、フィルター7の特性は前述の例と同じであ
り、フィルター7の破損のおそれのある場合は、フィル
ター防護部材8を設けるのが望ましい。
The material of the plug 4 and the characteristics of the filter 7 are the same as in the above example, and if there is a risk of damage to the filter 7, it is desirable to provide a filter protection member 8.

第7図、第8図に示す実施例は第2図〜第5図に示した
実施例に比べ軸部5の形状が異なり、先端の栓離脱防止
部10を省略した構造となっている。第9図、第10図
の実施例は、第7図、第8図の実施例から、さらに離脱
防止部9を除いた例である。
The embodiment shown in FIGS. 7 and 8 differs in the shape of the shaft portion 5 from the embodiment shown in FIGS. 2 to 5, and has a structure in which the plug detachment prevention portion 10 at the tip is omitted. The embodiment shown in FIGS. 9 and 10 is an example in which the detachment prevention part 9 is further removed from the embodiment shown in FIGS. 7 and 8.

これらの実施例における栓4は管1の孔3の中に、その
軸部5を所要の押込み力により押込むことによって挿設
される。この際、円錐台の外形を有する軸部5は、その
直径方向に圧縮力を受け、基部においても先端部と略同
寸法の直径となる。
The plug 4 in these embodiments is inserted into the hole 3 of the tube 1 by pushing its shaft 5 with the required pushing force. At this time, the shaft portion 5 having the external shape of a truncated cone is subjected to a compressive force in its diametrical direction, so that the diameter of the base portion is approximately the same as that of the tip portion.

したがって、軸部5周面と孔3の内周面との間には摩擦
力が生じ、この摩擦力によって栓4が孔3に固定される
こととなる。よって、本発明に係る液状化対策管1を地
盤中に立設する場合、周辺の地盤から抵抗力をうけても
、栓4は脱落することなく、孔3に固定されたままとな
る。
Therefore, a frictional force is generated between the circumferential surface of the shaft portion 5 and the inner circumferential surface of the hole 3, and the plug 4 is fixed to the hole 3 by this frictional force. Therefore, when the liquefaction prevention pipe 1 according to the present invention is installed in the ground, the plug 4 remains fixed in the hole 3 without falling off even if it receives resistance from the surrounding ground.

さらにより確実に栓4を管1の孔3に固定するためには
、栓4の軸部5周面に接着剤を塗布した後、栓4を管1
の孔3に嵌設してもよい。
Furthermore, in order to securely fix the plug 4 to the hole 3 of the tube 1, after applying adhesive to the circumferential surface of the shaft portion 5 of the plug 4, the plug 4 is attached to the tube 1.
It may be fitted into the hole 3 of.

第7図、第8図に示した栓4の場合、管1の表面側に栓
離脱防止部9を有しており、液状化対策管1の施工時に
、土砂と管1外面が接触する場合でも、土砂が貫通孔6
に侵入するのを防ぐので、フィルター7の破損を防止す
ることができる。
In the case of the plug 4 shown in FIGS. 7 and 8, there is a plug detachment prevention part 9 on the surface side of the pipe 1, and when the outer surface of the pipe 1 comes into contact with earth and sand during construction of the liquefaction countermeasure pipe 1. However, the dirt is in the through hole 6.
This prevents the filter 7 from being damaged.

第9図、第10図に示した例は栓離脱防止部9゜10が
ないので、液状化対策管lの施工時に土砂の侵入圧力が
対策管1の管径方向にかかる場合や、液状化対策管1の
供用時に、管が水平方向に振動して土砂の圧力が管径方
向にかかる場合などについて、栓4の軸部5外周面と管
1の孔2内周面の摩擦力で、上記侵入圧力に抵抗できる
か検討すべきである。実験によると、栓細部外径を管の
孔に対し適当に調節すると所要の抵抗力をもたせること
がわかった。さらに、確実に栓を管の孔部に固定するた
めには前述したように接着剤を利用してもよい。なお、
第9図、第10図に示した例は栓4に栓離脱防止部9,
10がないので栓材料が少なくてすむという利点がある
。
The example shown in Figs. 9 and 10 does not have the stopper detachment prevention parts 9 and 10, so if the intrusion pressure of earth and sand is applied in the radial direction of the countermeasure pipe 1 during construction of the liquefaction countermeasure pipe 1, or if the liquefaction countermeasure pipe 1 is Measures When the pipe 1 is in service, when the pipe vibrates horizontally and the pressure of earth and sand is applied in the pipe radial direction, the friction force between the outer circumferential surface of the shaft portion 5 of the plug 4 and the inner circumferential surface of the hole 2 of the pipe 1, You should consider whether you can resist the above intrusion pressure. Experiments have shown that appropriate adjustment of the outer diameter of the stopper part relative to the bore of the tube provides the required resistance. Additionally, an adhesive may be used as described above to securely fix the stopper to the tube hole. In addition,
In the example shown in FIGS. 9 and 10, the stopper 4 has a stopper separation prevention part 9,
Since there is no 10, there is an advantage that less plugging material is required.

第2図、第3図、および第4図、第5図に挙げた栓離脱
防止部9.10をもつ構造の栓では、栓離脱防止部10
は栓4の軸部5とあらかじめ一体的に成形されている。
In the plugs having the structure shown in FIGS. 2, 3, 4, and 5, the plug separation prevention portion 10 is
is formed integrally with the shaft portion 5 of the stopper 4 in advance.

一方、以下に述べる栓は栓離脱防止部10を管1の孔3
へ挿設した後、拡大するものである。この栓は管の孔部
への嵌合をより容易にし、嵌合後は栓の離脱を防止しよ
うとするものである。
On the other hand, in the plug described below, the plug detachment prevention part 10 is connected to the hole 3 of the pipe 1.
It is expanded after being inserted into. The purpose of this plug is to make it easier to fit the pipe into the hole, and to prevent the plug from coming off once it has been fitted.

第11図はこの実施例において栓4を孔3に取付けた状
態を示し、第12図ら)はその状態における栓4の側面
図、第12図(C)は同じく断面図である。この例にお
いては、次のような方法により孔3に取付ける。すなわ
ち、第12図(a)のように栓4は、孔3への取付は前
は栓離脱防止部10が拡大されていない状態となってい
る。ただし、孔3へ挿設の後、硬化材の注入によって栓
離脱防止部10を拡大できるよう、軸部5の内部に予め
注入管12を設けておき、栓離脱防止部10は硬化材を
収納し得る袋にしておく。栓4を孔3へ挿設した後に、
硬化材を注入管12の中に注入することによって、栓離
脱防止部10の袋の中に硬化材が充填され、軸部5先端
において拡大され、第11図、第12図(b)、 (C
)に示されるように、栓離脱防止部10が拡大する。そ
の結果、栓4は孔3に係止され固定される。フィルター
7およびフィルター防護部材8の内設される位置は、前
述の実施例の場合と同様である。
FIG. 11 shows a state in which the plug 4 is attached to the hole 3 in this embodiment, FIGS. 12 and 12) are side views of the plug 4 in this state, and FIG. 12(C) is a sectional view of the same. In this example, it is attached to the hole 3 by the following method. That is, as shown in FIG. 12(a), before the stopper 4 is attached to the hole 3, the stopper separation preventing portion 10 is not enlarged. However, an injection pipe 12 is provided inside the shaft part 5 in advance so that the plug detachment prevention section 10 can be expanded by injecting the hardening material after insertion into the hole 3, and the plug detachment prevention section 10 accommodates the hardening material. Keep it in a bag that can be used. After inserting the plug 4 into the hole 3,
By injecting the hardening material into the injection tube 12, the hardening material is filled into the bag of the stopper detachment prevention part 10 and expanded at the tip of the shaft part 5, as shown in FIGS. 11 and 12(b). C
), the stopper detachment prevention portion 10 expands. As a result, the plug 4 is locked and fixed in the hole 3. The positions where the filter 7 and the filter protection member 8 are installed are the same as in the previous embodiment.

なお、硬化材とは経時により硬化する特性のある材料で
、例えばセメントモルタル、ポリマーモルタル、合成樹
脂などを用いることができる。
Note that the hardening material is a material that hardens over time, such as cement mortar, polymer mortar, synthetic resin, and the like.

以上に述べた5タイプの栓は液状化対策管の運搬、施工
、供用条件によって選択すればよい。
The five types of plugs described above may be selected depending on the transportation, construction, and service conditions of the liquefaction prevention pipe.

般には、孔あき管への嵌設が簡単で、孔への係止、固定
が確実である、第2図〜第5図に示した栓離脱防止部9
.10を有する栓を用いれば十分所定性能、条件を満足
する液状化対策管を得ることができる。
In general, the stopper detachment prevention part 9 shown in FIGS. 2 to 5 is easy to fit into a perforated pipe and securely locks and fixes in the hole.
.. By using a stopper having a diameter of 10, it is possible to obtain a liquefaction prevention pipe that satisfies the specified performance and conditions.

液状化対策管の栓を嵌設している部分(穿孔部)は管を
液状化地盤へ立設した後、地盤の液状化防止に供用する
段階においては、管内が地盤の間隙水の排出経路となる
ため中空である必要がある。
The part of the liquefaction prevention pipe where the stopper is fitted (the perforated part) is used as a drainage route for pore water in the ground after the pipe is installed in the liquefaction ground and is used for preventing liquefaction of the ground. Therefore, it must be hollow.

第1図に示した液状化対策管で管先端が開放されている
ものは、この管の地盤への立設時に穿孔部2の管内に土
砂が侵入してくるおそれがある。穿孔部管内に土砂が侵
入した場合には、前述したようにグラブハンマー、土砂
吸引排出機などで土砂を管外へ排出し、穿孔部管内を中
空にすればよいが、他の方法としては第1図に示した液
状化対策管1の穿孔部2の管内下端から液状化対策管の
先端部の間に土砂侵入防止手段を講じればよい。
In the case of the liquefaction countermeasure pipe shown in FIG. 1 whose tip is open, there is a risk that earth and sand may enter the pipe in the perforated section 2 when the pipe is erected on the ground. If earth and sand enters the perforated pipe, the earth and sand can be ejected out of the pipe using a grab hammer, a sand suction ejector, etc., as described above, to make the inside of the perforated pipe hollow. A means for preventing the intrusion of earth and sand may be provided between the lower end of the perforated portion 2 of the liquefaction prevention pipe 1 shown in FIG. 1 and the tip of the liquefaction prevention pipe.

第13図(a)、 (b)はその−例として、液状化対
策管1の下端に土砂侵入防止のためのキャップ13を設
けたもの(第13図ら))および液状化対策管1の穿孔
部2の下端に土砂侵入防止蓋14を設けた例(第13図
う))を示したものである。この例では蓋14をリブ1
5で補強し、蓋14には管1の立設を容易にするため、
小さい空気抜き孔16を設けている。この蓋14は、例
えば管径が500〜600祁程度以上の鋼管なら、溶接
により容易に取付けることができる。また、管径が40
〜200皿程度の鋼管なら、リブまた空気抜き孔をなく
した蓋またはキャップを溶接により管先端部に取付けて
もよい。さらに、管径が40〜200回程度の樹脂管な
ら、リブまたは空気抜き孔をなくして樹脂溶接により管
先端部に取付けてもよいし、管先端部にキャップを同様
により取付けてもよい。
FIGS. 13(a) and 13(b) show, as an example, a cap 13 provided at the lower end of the liquefaction countermeasure pipe 1 to prevent soil intrusion (FIG. 13 et al.)) and a perforation of the liquefaction countermeasure pipe 1. This shows an example in which a dirt intrusion prevention lid 14 is provided at the lower end of the part 2 (Fig. 13B). In this example, the lid 14 is
5, and to facilitate the installation of the tube 1 on the lid 14,
A small air vent hole 16 is provided. This lid 14 can be easily attached by welding, for example, to a steel pipe having a diameter of about 500 to 600 mm or more. Also, the pipe diameter is 40
For steel pipes of up to 200 plates, a lid or cap without ribs or air vents may be attached to the tip of the pipe by welding. Furthermore, in the case of a resin pipe having a diameter of about 40 to 200 times, the rib or air vent hole may be eliminated and the resin pipe may be attached to the tip of the tube by resin welding, or a cap may be similarly attached to the tip of the tube.

一方、管先端の構造を前述のものとは別にした例を第1
4図、第15図に示す。
On the other hand, the first example shows an example in which the structure of the tube tip is different from the one described above.
It is shown in Fig. 4 and Fig. 15.

第14図(a)は円形断面の管を穿孔し、フィルター封
栓4を嵌設した液状化対策管1の例である。
FIG. 14(a) is an example of a liquefaction prevention pipe 1 in which a pipe with a circular cross section is bored and a filter sealing plug 4 is fitted therein.

管先端部には平板からなる土砂浸入防止蓋24を設けて
いる。径の大きい管であっても、管設置地盤の強度が小
さければ、このような蓋24で十分実用的である。また
、細径管であっても、同様にこのような蓋24で十分実
用的である。管1の上端部は蓋19で閉じている。この
場合、地盤の間隙水は液状化対策管1の上部から管外へ
排出され、液状化地盤の過剰間隙水圧が逸散されること
となる。管径が40〜200mm程度の管なら一般に第
14図(a)に示す構造の液状化対策管1を用いればよ
い。
An earth and sand infiltration prevention lid 24 made of a flat plate is provided at the tip of the pipe. Even if the pipe has a large diameter, such a lid 24 is sufficiently practical as long as the strength of the ground on which the pipe is installed is small. Further, even if the tube has a small diameter, such a lid 24 is sufficiently practical. The upper end of the tube 1 is closed with a lid 19. In this case, the pore water in the ground is discharged from the upper part of the liquefaction countermeasure pipe 1 to the outside of the pipe, and the excess pore water pressure in the liquefaction ground is dissipated. If the pipe diameter is about 40 to 200 mm, the liquefaction countermeasure pipe 1 having the structure shown in FIG. 14(a) may generally be used.

また、必要に応じて管1上部の孔数は他の部分に比べて
増やしてもよい。
Further, if necessary, the number of holes in the upper part of the tube 1 may be increased compared to other parts.

第14図ら)は円形断面を有する、第14図(a)に示
したものと別の構造を持つ液状化対策管10例である。
FIGS. 14(a) and 14(b) show ten examples of liquefaction countermeasure pipes having a circular cross section and a structure different from that shown in FIG. 14(a).

管1の先端には管の地盤への立設を容易とし、管1内へ
の土砂侵入防止のだ約尖端部17を有している。管1上
端部には、図に示すようにフィルター18を設け、液状
化対策管1を地盤に立設後、液状化抑止のために供用し
た場合、管上部から管内に土砂が流入しないようしてい
る。このフィルター18は栓4に付けるフィルター7と
同じ材質のものでもよいが、フィルターは破損しやすい
ため、通水性のある樹脂ネットまたは溶接金網などで防
護することが望ましい。
The tip of the pipe 1 has a bellows tip 17 that facilitates the installation of the pipe on the ground and prevents dirt from entering the pipe 1. A filter 18 is provided at the upper end of the pipe 1, as shown in the figure, to prevent earth and sand from flowing into the pipe from the upper part of the pipe when the pipe 1 for liquefaction prevention is installed in the ground and used to prevent liquefaction. ing. This filter 18 may be made of the same material as the filter 7 attached to the stopper 4, but since the filter is easily damaged, it is desirable to protect it with a water-permeable resin net or welded wire mesh.

あるいは、例えば第14図(C)に示すように液状化対
策管1の上端部は完全に蓋19で閉じてもよい。この場
合、地盤の間隙水は液状化対策管1の上部から管外へ排
出されるので、液状化対策管1の上部に、間隙水の排出
を円滑にするために必要な孔面積を確保すればよい。一
般には、管1の上端部を蓋19で閉じても、管1の上部
の孔径、孔数は管1の下部とほぼ同じでよい。対策管上
部の構造の他の一例として、図に示したように、管1上
部の孔を他の部分に比べ大きくし、ここに前述した構造
のフィルター封栓20を嵌設してもよい。
Alternatively, the upper end of the liquefaction countermeasure tube 1 may be completely closed with a lid 19 as shown in FIG. 14(C), for example. In this case, the pore water in the ground will be discharged from the top of the liquefaction countermeasure pipe 1 to the outside of the pipe, so it is necessary to secure the necessary hole area at the top of the liquefaction countermeasure pipe 1 to ensure smooth discharge of the pore water. Bye. Generally, even if the upper end of the tube 1 is closed with the lid 19, the pore diameter and number of holes in the upper portion of the tube 1 may be approximately the same as in the lower portion of the tube 1. As another example of the structure of the upper part of the countermeasure tube, as shown in the figure, the hole in the upper part of the tube 1 may be made larger than other parts, and the filter sealing plug 20 having the above-described structure may be fitted therein.

この場合、間隙水はこの栓20またはこの栓20の下方
の栓4を通じて外部へ排出される。また、第14図(社
)中、21は液状化対策管1をバイブロハンマーで打設
する場合に使用するチャック把持用治具の一例を示した
ものであり、蓋19部分に固定されている。
In this case, the interstitial water is discharged to the outside through the plug 20 or the plug 4 below the plug 20. In addition, in Fig. 14 (company), reference numeral 21 indicates an example of a chuck gripping jig used when driving the liquefaction countermeasure pipe 1 with a vibrohammer, and it is fixed to the lid 19 part. .

第14図(d)に示した液状化対策管1は、第14図(
a)に示したものと同様な管1の下部に螺旋状ひれ(オ
ーガー)23を取り付けた例である。この場合、管1は
液状化地盤に管1を回転圧入して設置すれば、施工が容
易となる。また、管lを回転圧入して設置する場合、管
1と地盤の摩擦を切り施工を容易とするために、管1の
下部は第13図(a)に示した構造とするか、管1下部
外周面に帯状に平板22を取付けた構造(第14図(C
)参照)としてもよい。
The liquefaction countermeasure pipe 1 shown in FIG. 14(d) is
This is an example in which a spiral fin (auger) 23 is attached to the lower part of the tube 1 similar to that shown in a). In this case, the pipe 1 can be easily constructed by rotating and press-fitting the pipe 1 into the liquefied ground. In addition, when installing the pipe 1 by rotary press-fitting, in order to reduce friction between the pipe 1 and the ground and make installation easier, the lower part of the pipe 1 should have the structure shown in Figure 13 (a), or the pipe 1 A structure in which a flat plate 22 is attached in a band shape to the outer peripheral surface of the lower part (Fig. 14 (C)
) may also be used.

また、液状化対策管1の管断面は必ずしも円形でなくて
よく、第15図(a)、ら)、 (C)のように角形で
あってもよい。さらに、多角形または任意の断面を持つ
管であってもよいが、要は管内が地盤の間隙水の排出経
路となるため、円滑な排出のための中空部断面積が確保
されていればよい。
Further, the cross section of the liquefaction countermeasure pipe 1 does not necessarily have to be circular, but may be square as shown in FIGS. 15(a), 15(a) and 15(c). Furthermore, the pipe may be polygonal or have any cross section, but since the inside of the pipe serves as a drainage route for pore water in the ground, it is sufficient that the cross-sectional area of the hollow part is ensured for smooth drainage. .

また、液状化対策管を液状化層下方の非液状化層まで立
設する場合は、管が非液状層に入る部分は第14図(a
)、 (C)、第15図(a)、 (C)などに示すよ
うに穿孔しなくてよい。
In addition, if the liquefaction countermeasure pipe is installed upright to the non-liquefaction layer below the liquefaction layer, the part where the pipe enters the non-liquefaction layer is shown in Figure 14 (a).
), (C), and there is no need to drill holes as shown in FIGS. 15(a) and (C).

液状化対策管を地盤の液状化防止に供用するため、液状
化地盤41に設置した状況を第19図(a)。
FIG. 19(a) shows a situation in which a liquefaction prevention pipe is installed in liquefaction ground 41 in order to prevent liquefaction of the ground.

ら)に示す。et al.).

液状化対策管は地盤の液状化防止に必要な間隔で設置す
る。比較的細い径の管IBを用いる場合には管の内径は
一般に40〜200闘程度、またはそれ以上でよく、管
の配置間隔は一般に200〜3000肛程度、またはそ
れ以上でよい。液状化対策管IB本体として鋼管、鋼・
コンクリート複合管(例えばいわゆるSC杭)、コンク
リート杭などのような剛性と強度の高いものを用いた液
状化対策管IBを液状化地盤41下方の締った地盤42
まで貫入すると、対策管IBは液状化地盤41の液状化
を防止するだけでなく、液状化地盤41を拘束し、安定
化させる効果がある。特に、地表面または液状化層下面
が傾斜している場合、地盤は液状化によりすべりをおこ
し、大災害となるおそれがあることが現在確認されてお
り、液状化対策管1Bはこの場合、大いに効果を発揮す
ることとなる。
Liquefaction prevention pipes will be installed at necessary intervals to prevent ground liquefaction. When relatively small diameter tubes IB are used, the inner diameter of the tubes may generally be on the order of 40 to 200 mm or more, and the spacing between the tubes may generally be on the order of 200 to 3000 mm or more. As the main body of the liquefaction countermeasure pipe IB, steel pipes,
A liquefaction countermeasure pipe IB using something with high rigidity and strength such as a concrete composite pipe (for example, a so-called SC pile) or a concrete pile is installed in the compacted ground 42 below the liquefied ground 41.
When penetrated to this point, the countermeasure pipe IB not only prevents the liquefied ground 41 from liquefying, but also has the effect of restraining and stabilizing the liquefied ground 41. In particular, it has been confirmed that when the ground surface or the lower surface of the liquefaction layer is sloped, the ground may slip due to liquefaction, leading to a major disaster. It will be effective.

例えば、第20図(a)、 (b)に示すように、液状
化地盤41上に鉄道道路、堤防などの盛土43が構築さ
れている場合、または盛土43を新設する場合、盛土4
3下方の液状化地盤41、または盛土のり尻近辺の液状
化地盤に液状化対策管IBを設置すれば、液状化地盤4
1や液状化する可能性のある盛土43の液状化を防止で
きるだけでなく、液状化地盤41や盛土43の強度を増
し、盛土のすべり崩壊を防ぐことができる。図中、44
は液状化対策管IB上端から排出される間隙水を排水す
るだめの砕石層である。
For example, as shown in FIGS. 20(a) and 20(b), when an embankment 43 such as a railway road or embankment is constructed on liquefied ground 41, or when a new embankment 43 is constructed, the embankment 43
3. If the liquefaction countermeasure pipe IB is installed in the liquefied ground 41 below or in the liquefied ground near the toe of the embankment, the liquefied ground 4
This not only prevents the liquefaction of the liquefied ground 41 and the embankment 43 that may liquefy, but also increases the strength of the liquefied ground 41 and the embankment 43, and prevents the embankment from sliding and collapsing. In the figure, 44
is a crushed stone layer that drains the pore water discharged from the upper end of the liquefaction countermeasure pipe IB.

液状化対策管IBの地盤拘束効果をより確かなものとす
るためには、第21 図(a)、 (b)に示すようう
に対策管IBを締った非液状化地盤42まで建込み、対
策管18頭部を結合材45(例えば棒鋼、形鋼など)で
結べばよい。図は2方向に結んだ例であるが、いずれか
1方向だけ管頭部を結んでもよい。この場合、対策管I
Bの上下端で変位が拘東され、従って、液状化地盤41
も拘束されるので液状化防止効果はより大きく、地盤の
安定化も確実に図れる。こうした対策管IBの設置方法
は地表面や液状化層下面が傾斜している場合に適用すれ
ば最も大きな効果が期待できる。
In order to ensure the ground restraint effect of the liquefaction countermeasure pipe IB, the countermeasure pipe IB should be built up to the tight non-liquefaction ground 42 as shown in Figures 21 (a) and (b). The head of the countermeasure pipe 18 may be tied with a binding material 45 (for example, steel bar, shaped steel, etc.). Although the figure shows an example where the tube is tied in two directions, the tube head may be tied in only one direction. In this case, countermeasure pipe I
The displacement is restricted at the upper and lower ends of B, and therefore the liquefied ground 41
Since the soil is also restrained, the liquefaction prevention effect is even greater, and the stabilization of the ground can be ensured. This method of installing countermeasure pipes IB can be expected to have the greatest effect if applied when the ground surface or the lower surface of the liquefaction layer is sloped.

本発明に係る液状化対策管は、バイブロ/’%ンマ、油
圧ハンマー、ディーゼルハンマー、圧入機などにより地
盤に直接打込み、設置でき、施工が極めて簡単である。
The liquefaction prevention pipe according to the present invention can be installed by directly driving it into the ground using a vibro/'% pump, a hydraulic hammer, a diesel hammer, a press-fitting machine, etc., and is extremely easy to install.

前述したように、従来は、小孔を多数有し、管周囲に破
断しやすい薄いフィルターを巻付けた樹脂管を地盤に設
置するため、鋼管製のケーシングパイプをオーガーによ
り回転正大して所定深さまで建込んだ後、ケーシングパ
イプの中を通して前記樹脂管を所定深さまで立設し、次
にケーシングパイプ先端を開放してケーシングパイプを
地盤から抜き上げ、前記樹脂管を液状化層の残置するな
どの方法がとられていた(この方法は、従来の砕石ドレ
ーン工法における砕石の液状化層へ残置させ地盤内に砕
石杭を設ける方法と同様である)。しかし、従来の方法
では、ケーシングパイプの外径(通常は100〜125
mm程度)と樹脂管の外径(通常は50〜100鵬程度
)の間に、施工上、差ができてしまい、地盤への設置後
の樹脂管の周囲近傍地盤はどうしても緩んでしまうこと
となる。
As mentioned above, conventionally, in order to install a resin pipe with many small holes and a thin filter wrapped around the pipe that is easy to break, the steel casing pipe is rotated and enlarged with an auger until it reaches a specified depth. After construction, the resin pipe is passed through the casing pipe and erected to a predetermined depth, then the tip of the casing pipe is opened, the casing pipe is pulled out of the ground, and the resin pipe is left with a liquefied layer. (This method is similar to the method used in the conventional crushed stone drain method, in which crushed stone is left in the liquefaction layer and crushed stone piles are installed in the ground.) However, in the conventional method, the outer diameter of the casing pipe (usually 100 to 125
During construction, there is a difference between the outside diameter of the resin pipe (usually about 50 to 100 mm), and the ground around the resin pipe inevitably becomes loose after it is installed in the ground. Become.

液状化層を排水管(孔あき樹脂管など)の設置前より緩
めることは、本来、緩い状態にあり液状化の危険がある
地盤を、さらに緩めることであり、同じ大きさの地震に
おいて、地盤の過剰間隙水圧が短時間により高まりやす
くなる。すなわち、液状化の危険をより大きくすること
になる。
Loosening the liquefaction layer before installing drainage pipes (perforated resin pipes, etc.) means further loosening the ground, which is already loose and at risk of liquefaction. Excess pore water pressure tends to increase in a short period of time. In other words, the risk of liquefaction becomes greater.

したがって、設置される排水管の開孔率はより大きく、
またその配置間隔はより密にしないと地盤の過剰間隙水
圧を短時間に逸散することができなくなる。
Therefore, the porosity of the installed drainage pipe is larger,
In addition, unless the arrangement intervals are made closer, excess pore water pressure in the ground cannot be dissipated in a short time.

一方、排水管の開孔率を大きくすると、管の剛性、強度
が低下するし、孔数が増えることにもなるのでより高価
となる。また、排水管の配置間隔をより密にすると、液
状化対策費が嵩み、地盤が排水管設置により緩む割合が
さらに大きくなる。
On the other hand, if the porosity of the drain pipe is increased, the rigidity and strength of the pipe will decrease, and the number of holes will increase, making it more expensive. Furthermore, if the spacing between drain pipes is made closer, the cost of countermeasures against liquefaction will increase, and the rate of loosening of the ground due to the installation of drain pipes will further increase.

以上のように、排水管設置時に液状化地盤をより緩め、
軟弱化する従来の施工方法は大きな欠点を有し、液状化
対策効果は低いと言える。また、実際に、剛性の低い排
水管を緩い地盤に設置して振動台実験を行ったが、排水
管をかなり密に配置しても地盤の液状化防止効果は少な
いことが判明した。
As mentioned above, when installing drainage pipes, the liquefied ground can be loosened,
The conventional construction method, which causes softening, has a major drawback and can be said to be less effective as a countermeasure against liquefaction. In addition, we actually conducted a shaking table experiment by installing drainage pipes with low rigidity on loose ground, and found that even if the drainage pipes were arranged very closely together, they had little effect on preventing ground liquefaction.

従来の排水管は管内への土砂侵入防止用フィルターが管
周囲に取付けられており、この薄いフィルターが地盤と
の摩擦により破断するので、排水管を地盤にそのまま打
ち込むことができなかった。
Conventional drainage pipes have a filter attached around the pipe to prevent dirt from entering the pipe, and this thin filter breaks due to friction with the ground, making it impossible to drive the pipe directly into the ground.

ところが、本発明に係る栓を付けた排水管(液状化対策
管)はそのまま地盤に打込んでもフィルターは破れない
構造となっており、大きな特長を有している。
However, the drain pipe with a stopper (liquefaction countermeasure pipe) according to the present invention has a structure in which the filter does not break even if it is directly driven into the ground, and has a great feature.

実際、粒径分布範囲0.05〜2.0画、平均粒径I)
s。
In fact, the particle size distribution range is 0.05 to 2.0 degrees, average particle size I)
s.

= 0.48mm、標準貫入試験のN値が35以内の地
盤に、栓を多数付けた液状化対策管をハンマーにより打
込んだ後、この液状化対策管を引き抜き、枠部のフィル
ターの損傷を確認する実験を行ったところ、フィルター
は全く損傷していなかった。液状化対策を施す対象地盤
は通常N値15以内であり、本発明に係る液状化対策管
は直接の打ち込みに耐えられ、十分な実用性を有してい
る。
= 0.48mm, after driving a liquefaction countermeasure pipe with multiple plugs into the ground with a standard penetration test N value of 35 or less using a hammer, pull out the liquefaction countermeasure pipe and check for damage to the filter in the frame. When we conducted an experiment to confirm, the filter was not damaged at all. The ground to which liquefaction countermeasures are applied usually has an N value of 15 or less, and the liquefaction countermeasure pipe according to the present invention can withstand direct driving and has sufficient practicality.

よって、本発明に係る液状化対策管は従来のようなケー
シングパイプを使うことなく、直接液状化地盤にバイブ
ロハンマー、油圧ハンマー、ディーゼルハンマー、圧入
機などにより立設することができ、地盤を緩めることは
ない。
Therefore, the liquefaction countermeasure pipe according to the present invention can be installed directly on liquefied ground using a vibro hammer, hydraulic hammer, diesel hammer, press-fit machine, etc. without using a conventional casing pipe, and loosens the ground. Never.

むしろ、管の立設により地盤は締固まることとなる。Rather, the erection of the pipe will compact the ground.

すなわち、管を地盤へ立設するとき、 ■ 管は地盤を側方に移動せしめ、締固める。In other words, when installing the pipe into the ground, ■ The pipe moves the ground laterally and compacts it.

■ 管周辺地盤では、局部液状化がおこり、間隙水が管
内に流入することにより、砂の骨格の再編成が生じ、す
なわち、砂と砂の間隙が小さくなり、管周辺地盤が締固
まることとなる。特にこの現象はバイブロハンマーを用
いたときに顕著である。
■ Local liquefaction occurs in the ground around the pipe, and pore water flows into the pipe, causing a reorganization of the sand skeleton.In other words, the gaps between sand become smaller, and the ground around the pipe becomes compacted. Become. This phenomenon is particularly noticeable when using a vibrohammer.

また、地盤への打込み作業は過剰間隙水圧を逸散させる
効果により、同じ大きさの通常の管を打込む場合より容
易となる利点もある。
Another advantage is that driving into the ground is easier than driving a regular pipe of the same size due to the effect of dissipating excess pore water pressure.

液状化対策管の施工例を第22図に示す。この例では、
液状化対策管1として第14図に示したような構造をも
つものを用い、それを油圧ショベル22に装着したバイ
ブロハンマー23により、液状化地盤41に立設してい
る。この場合、液状化対策管1の立設以前の液状化地盤
はN値10以下とかなり緩かったが、対策管1の立設後
はN値が増加したこと、および液状化対策管1の立設作
業は順調に行え、フィルターが破断することもなかった
ことが確認できた。
An example of construction of liquefaction prevention pipes is shown in Figure 22. In this example,
A liquefaction countermeasure pipe 1 having a structure as shown in FIG. 14 is used, and is erected on the liquefaction ground 41 by a vibrohammer 23 attached to a hydraulic excavator 22. In this case, the liquefaction ground was quite loose with an N value of 10 or less before the liquefaction countermeasure pipe 1 was erected, but after the liquefaction countermeasure pipe 1 was erected, the N value increased and It was confirmed that the installation work went smoothly and the filter did not break.

よって、地盤の強度がより高まっていること、および地
盤内の過剰間隙水圧が高まろうとしても、間隙水が中空
の対策管内を通って上部へスムーズに排出されるので、
過剰間隙水圧の上昇が避けられることにより、地震時の
地盤の液状化防止が効果的に行えることとなる。
Therefore, even if the strength of the ground is increased and excessive pore water pressure in the ground increases, the pore water can be smoothly discharged upward through the hollow countermeasure pipe.
By avoiding an increase in excess pore water pressure, liquefaction of the ground during an earthquake can be effectively prevented.

上述した液状化対策管を用いた本発明の耐震補強構造を
杭基礎に適用した場合の例を第23図に示す。この場合
、液状化対策管IAの液状化地盤42にある部分にのみ
液状化対策部を設ければよい。建物490基礎杭として
は、保有耐力の大きい鋼管などが望ましく、鋼管であれ
ば管径は一般に400〜800画程度である。
FIG. 23 shows an example in which the seismic reinforcement structure of the present invention using the above-mentioned liquefaction prevention pipe is applied to a pile foundation. In this case, it is sufficient to provide the liquefaction countermeasure section only in the portion of the liquefaction countermeasure pipe IA that is located in the liquefaction ground 42. As the building 490 foundation pile, it is desirable to use steel pipes that have a large bearing capacity, and the diameter of steel pipes is generally about 400 to 800 squares.

第23図に示した本発明による杭基礎は、液状化対策管
IA周辺の液状化が防止でき、水平地盤反力が地震時で
も取れるので、液状化対策を施してない通常の杭を用い
た場合よりも相当安全な基礎となる。
The pile foundation according to the present invention shown in Fig. 23 can prevent liquefaction around the liquefaction countermeasure pipe IA and can take horizontal ground reaction force even during an earthquake, so ordinary piles without liquefaction countermeasures can be used. It is a much safer foundation than the case.

さらに、安全にしようとすれば、第24図に示すように
、建物49の周辺地盤にも液状化対策管IBを設置すれ
ばよい。この場合も建物49の基礎杭としての液状化対
策管IAには、栓を用いて液状化対策を施した鋼管杭な
どを用いることが望ましい。また、液状化対策管IBの
本体材料は、地盤の拘束効果を期待できる点からは鋼管
などの剛性・強度をもつ材料が望ましいが、単に液状化
防止を意図するだけならこの材料は合成樹脂管であって
もよい。ただし、液状化対策管IBも液状化対策管IA
と同様にディーゼル/’%ンマー、油圧ハンマー、バイ
ブロハンマー、圧入機などにより液状化地盤に設置する
ので、対策管IB本体の材料が合成樹脂管であっても、
設置に耐えられるだけの強度、剛性を有することが必要
である。
Furthermore, if you want to make it safer, liquefaction countermeasure pipes IB can also be installed in the ground around the building 49, as shown in FIG. In this case as well, it is preferable to use a steel pipe pile or the like that is provided with a plug to prevent liquefaction as the liquefaction prevention pipe IA as the foundation pile of the building 49. In addition, the main body material of the liquefaction countermeasure pipe IB is preferably a material with rigidity and strength such as steel pipe from the viewpoint of being able to restrain the ground, but if the purpose is simply to prevent liquefaction, this material should be a synthetic resin pipe. It may be. However, liquefaction countermeasure pipe IB is also liquefaction countermeasure pipe IA.
Similarly, since it is installed on liquefied ground using a diesel/'% hammer, hydraulic hammer, vibrohammer, press-in machine, etc., even if the material of the countermeasure pipe IB body is a synthetic resin pipe,
It is necessary to have sufficient strength and rigidity to withstand installation.

周辺地盤に設置される液状化対策管IBの管径は、建物
の基礎の検討から定まる対策管IAの管径よりも一般に
小さくてよく、前述したように40〜200mm程度、
またはそれ以上でよい。
The pipe diameter of the liquefaction countermeasure pipe IB installed in the surrounding ground may generally be smaller than the pipe diameter of the countermeasure pipe IA determined from the study of the foundation of the building, and as mentioned above, it is about 40 to 200 mm,
Or more is fine.

第25図(a)、 (b)は本発明の耐震補強構造とし
て、液状化対策管IBを地震時に地盤の液状化が懸念さ
れる地層に設置される住宅46の直接基礎47の下部に
設けた場合の実施例を示したものである。
FIGS. 25(a) and 25(b) show, as an earthquake-reinforced structure of the present invention, a liquefaction countermeasure pipe IB is installed at the bottom of the direct foundation 47 of a house 46 installed in a stratum where there is a risk of ground liquefaction during an earthquake. This is an example of a case in which

液状化地盤42に建築される個人住宅46の直接基礎4
7(布基礎)の沈下防止、補強として、液状化対策管を
用いるときは管径40〜200mm程度の鋼管を液状化
対策管IBの本体として用いればよい。このとき、液状
化対策管IBの先端は支持力が必要なだけ取れる地盤4
2まで貫入すればよい。このようにして液状化対策管I
Bを用いれば、地震に対し安全な住宅の基礎となる。
Direct foundation 4 of a private residence 46 built on liquefied ground 42
When a liquefaction countermeasure pipe is used to prevent subsidence and reinforce 7 (cloth foundation), a steel pipe with a diameter of about 40 to 200 mm may be used as the main body of the liquefaction countermeasure pipe IB. At this time, the tip of the liquefaction countermeasure pipe IB should be placed on the ground 4, which can provide as much support as necessary.
It is enough to penetrate up to 2. In this way, the liquefaction countermeasure pipe I
If B is used, it will become the foundation of a house that is safe against earthquakes.

図中、48は砕石部であり、地震時に液状化対策管IB
の上部より排出される間隙水を側溝48aに導いて排水
する。
In the figure, 48 is the crushed stone section, and the liquefaction countermeasure pipe IB in the event of an earthquake
The interstitial water discharged from the upper part of the pipe is led to the side gutter 48a and drained.

なお、住宅用の耐震補強構造においても、地盤の液状化
に対し、さらに安全性を図るため、同様の液状化対策管
を住宅の直接基礎間や住宅の周辺の液状化地盤にも設置
することが考えられる。この場合の直接基礎間や住宅の
周辺の液状化地盤に設置される液状化対策管の本体は鋼
管に限らず、単に液状化防止を意図するだけなら、合成
樹脂管であってもよい。
In addition, in order to further improve safety against ground liquefaction in seismic reinforcement structures for residential buildings, similar liquefaction prevention pipes should be installed directly between the foundations of the house and in the liquefied ground around the house. is possible. In this case, the main body of the liquefaction prevention pipe installed directly between the foundations or on the liquefied ground around the house is not limited to a steel pipe, but may be a synthetic resin pipe if the purpose is simply to prevent liquefaction.

次に、本発明の耐震補強構造を橋梁の橋脚50または橋
台部分の基礎杭に適用した場合の実施例を第26図に示
す。この場合も液状化対策管IAの本体の材料は鋼管な
どが望ましく、液状化対策部は液状化地盤41に相当す
る基礎杭の一部分だけでよい。この例では杭の施工誤差
も考慮し、安全をみて非液状地盤42層に入る杭の一部
にも本発明の栓4を取付けている。
Next, FIG. 26 shows an embodiment in which the seismic reinforcement structure of the present invention is applied to a bridge pier 50 or a foundation pile of an abutment portion of a bridge. In this case as well, the material of the main body of the liquefaction countermeasure pipe IA is preferably a steel pipe, and the liquefaction countermeasure part only needs to be a part of the foundation pile corresponding to the liquefaction ground 41. In this example, the plug 4 of the present invention is also attached to a part of the pile that enters the 42nd layer of non-liquid ground for safety reasons, taking into account the construction error of the pile.

地震時、地盤の間隙水は栓4を通じて、支持杭としての
機能も果たす液状化対策管IAの内部に流入し、対策管
IAの上部から砕石部51を通じて地盤上方へ排出され
、地盤の液状化を防止する。
During an earthquake, pore water in the ground flows through the plug 4 into the liquefaction countermeasure pipe IA, which also functions as a support pile, and is discharged from the upper part of the countermeasure pipe IA to the upper ground through the crushed stone section 51, causing liquefaction of the ground. prevent.

よって、杭の水平地盤反力が地盤時に確実に取れ、安全
な基礎を提供することができる。
Therefore, the horizontal ground reaction force of the pile can be reliably taken when the pile is in the ground, and a safe foundation can be provided.

基礎杭から離れた所まで地盤の液状化を確実に防止すれ
ば杭基礎の安全性はさらに高まる。このため、第27図
に示すように液状化対策管IBを基礎杭としての液状化
対策管IAの周辺に打設することができる。
The safety of pile foundations will further increase if liquefaction of the ground is reliably prevented far from the foundation piles. Therefore, as shown in FIG. 27, the liquefaction prevention pipe IB can be driven around the liquefaction prevention pipe IA as a foundation pile.

液状化対策管IAの管径は基礎杭の機能の検討から決定
され、対策管IAの管本体材料が鋼管の場合、通常50
0〜1400mm程度が多く使用される。
The pipe diameter of the liquefaction countermeasure pipe IA is determined by considering the function of the foundation pile, and if the pipe body material of the countermeasure pipe IA is steel pipe, it is usually 50
A length of about 0 to 1400 mm is often used.

液状化対策管IBは第25図の実施例の場合と同様、管
径は40〜200皿程度、管本体材料は鋼管が望ましい
が、所定の剛性、強度を備えていれば合成樹脂管であっ
てもよい。
As with the embodiment shown in Figure 25, the liquefaction countermeasure pipe IB should have a diameter of about 40 to 200 plates, and the main material of the pipe should preferably be steel, but a synthetic resin pipe can be used as long as it has the specified rigidity and strength. You can.

液状化対策管IAを通して地震時の地盤の間隙水を地盤
外へ排出する方法は、第26図の場合と同様であっても
よいが、第27図に示すように液状化対策管IAの上部
に、地盤の間隙水の円滑な排出に必要な中空断面積を持
つ排水管52を取付け、この排水管52を橋脚5oのフ
ーチング内に配管し、液状化地盤の間隙水を地盤外へ排
出させてもよい。
The method for discharging pore water in the ground during an earthquake to the outside of the ground through the liquefaction countermeasure pipe IA may be the same as that shown in Fig. 26, but as shown in Fig. 27, A drain pipe 52 having a hollow cross-sectional area necessary for smooth discharge of pore water in the ground is installed, and this drain pipe 52 is installed inside the footing of the pier 5o to drain the pore water in the liquefied ground to the outside of the ground. You can.

以上のように本発明の耐震補強構造は、地盤の液状化を
確実に防止でき、地震に対して安全な杭基礎としても機
能することができる。
As described above, the seismic reinforcement structure of the present invention can reliably prevent liquefaction of the ground and can also function as a safe pile foundation against earthquakes.

〔発明の効果〕〔Effect of the invention〕

■ 本発明の杭基礎における耐震補強構造は、基礎杭周
辺の地盤の液状化を防止するので、地震時においても杭
の水平地盤反力がとれ、杭の肉厚、外径などから決まる
断面、または杭本数を、液状化対策を施さない普通の杭
を用いた場合より大幅に減少させることができる。
■ The seismic reinforcement structure of the pile foundation of the present invention prevents liquefaction of the ground around the foundation pile, so even in the event of an earthquake, the horizontal ground reaction force of the pile is removed, and the cross-section determined by the pile thickness, outer diameter, etc. Alternatively, the number of piles can be significantly reduced compared to when ordinary piles without liquefaction measures are used.

よって、地震に対し抵抗力のある、安全で経済的な杭基
礎を提供できる。
Therefore, it is possible to provide a safe and economical pile foundation that is resistant to earthquakes.

■ 液状化地盤の上に建つ住宅の直接基礎(布基礎)の
支持部材として、本体が細径の鋼管からなる液状化対策
管を用いれば、液状化地盤の締固めなどの従来の改良方
法を用いることなく、地震時においても液状化や沈下を
防止できる、安全で経済的な直接基礎(布基礎)を提供
でき、工期も短かくて済む。
■ If liquefaction countermeasure pipes made of small-diameter steel pipes are used as supporting members for direct foundations (fabric foundations) of houses built on liquefied soil, conventional improvement methods such as compaction of liquefied soil can be avoided. It is possible to provide a safe and economical direct foundation (fabric foundation) that can prevent liquefaction and subsidence even in the event of an earthquake without using it, and the construction period can be shortened.

■ また、液状化対策管を用いた基礎杭の群周辺の液状
化地盤にも、基礎杭の群を取り囲むように、液状化対策
管を適当な配置間隔で立設すれば、該群周辺地盤の液状
化をも防止することができ、地震に対し、さらに抵抗力
の大きい安全な杭基礎を提供できる。
■ In addition, if liquefaction prevention pipes are erected at appropriate intervals so as to surround the group of foundation piles, the ground around the group can be It is also possible to prevent liquefaction of water and provide a safe pile foundation with greater resistance to earthquakes.

■ 本発明の液状化対策管を用いた耐震補強構造では液
状化抑止機能を付与した杭を所定間隔で立設することに
より、確実に液状化が防止でき、杭の孔部のフィルター
は地盤の土砂により目づまりすることがないので、繰り
返し地震が来ても液状化防止効果が持続される。
■ In the seismic reinforcement structure using the liquefaction prevention pipe of the present invention, liquefaction can be reliably prevented by erecting piles with a liquefaction prevention function at specified intervals, and the filters in the holes of the piles are Since it is not clogged with earth and sand, the liquefaction prevention effect is maintained even after repeated earthquakes.

■ 本発明に係る液状化対策管は、地盤に立設すること
により液状化を防止できるだけでなく、地盤の動きを止
め、拘束する効果も有し、地震に対し抵抗の大きい地盤
に改良することができる。特に、液状化層が傾斜してい
る場合や、盛土の補強、ケーソン前鉦マウンドのり尻部
の補強などにおいて、より有効な地盤拘束効果が期待で
きる。
■ The liquefaction prevention pipe according to the present invention not only prevents liquefaction by being installed in the ground, but also has the effect of stopping and restraining the movement of the ground, and improves the ground to have greater resistance to earthquakes. I can do it. In particular, a more effective ground restraint effect can be expected when the liquefaction layer is sloped, when reinforcing embankments, and when reinforcing the butt of a caisson front mound.

■ 本発明に係る液状化対策管は、運搬、地盤への設置
時などにフィルターが損傷することがなく、取り扱いが
極めて容易である。
(2) The liquefaction prevention pipe according to the present invention does not damage the filter during transportation or installation on the ground, and is extremely easy to handle.

■ 本発明に係る液状化対策管を用いた杭は、フィルタ
ーを保護するためのケーシングパイプなどを用いること
なく、バイブロハンマー、油圧ハンマー、ディーゼルハ
ンマー、圧入機などの通常の施工機械を用いて直接地盤
に打ち込め、打ち込み時に地盤の間隙水を液状化対策管
を用いた杭部分から抜くことができるので、施工が極め
て容易である。また、施工時に地盤を緩めることもない
。
■ Piles using the liquefaction prevention pipe according to the present invention can be constructed directly using ordinary construction machinery such as a vibro hammer, hydraulic hammer, diesel hammer, or press-in machine, without using a casing pipe to protect the filter. It is extremely easy to install because it can be driven into the ground, and pore water in the ground can be extracted from the pile using liquefaction prevention pipes during driving. Also, the ground will not be loosened during construction.

■ 本発明に係る液状化対策管は、孔を穿設した管の孔
部に、貫通孔内にフィルターを設けた栓を、高価な機械
を使うことなく極めて簡単に、嵌合し固定できるので製
作が容易である。
■ The liquefaction countermeasure pipe according to the present invention allows a stopper with a filter provided in the through hole to be fitted and fixed into the hole of the pipe with a hole in it very easily without using expensive machinery. Easy to manufacture.

また、−度固定されると、運搬、施工、供用時の衝撃、
摩擦などで管の孔部から離脱することもないので、品質
も保証される。
In addition, if it is fixed at a - degree, it will be affected by shocks during transportation, construction, and use.
Since it does not come off from the hole in the pipe due to friction, quality is also guaranteed.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明に係る液状化対策管の概要を示す斜視図
、第2図は孔あき管への栓の装着状態の一例を示す鉛直
断面図、第3図(a)〜(C)はそれぞれ第2図の栓の
側面図、正面図および背面図、第4図は栓の他の実施例
における装着状態を示す鉛直断面図、第5図(a)〜(
C)はそれぞれ第4図の栓の側面図、正面図および背面
図、第6図は管内土砂吸引排出システムの概要を示す鉛
直断面図、第7図は栓のさらに他の実施例における装着
状態を示す鉛直断面図、第8図(a)〜(C)はそれぞ
れ第7図の栓の正面図、側面図および断面図、第9図は
栓のさらに他の実施例における装着状態を示す鉛直断面
図、第10図(a)、(社)はそれぞれ第9図の栓の側
面図および断面図、第11図は栓のさらに他の実施例に
おける装着状態を示す鉛直断面図、第12図(a)〜(
C)はそれぞれ第10図の栓の離脱防止部拡大前の側面
図、拡大後の側面図および拡大後の断面図、第13図(
a)、ら)はそれぞれ先端に土砂侵入防止キャップまた
は蓋を設けた液状化対策管の例を示す斜視図、第14図
(a)〜(d)および第15図(a)〜(C)はそれぞ
れ本発明に係る液状化対策管の異なる実施態様における
斜視図、第16図は自由減衰波加振実験による過剰間隙
水圧比の経時変化を示すグラフ、第17図は液状化対策
管の実験における加速度と管の変位比(5本配置)を示
すグラフ、第18図は液状化対策管の実験における水平
抵抗と載荷板変位関係を示すグラフ、第19図(a)、
 (b)は液状化対策管の地盤への設置状況を示す平面
図および鉛直断面図、第20図(a)、ら)はそれぞれ
液状化地盤上に盛土がある場合の適用例を示す鉛直断面
図、第21図は液状化対策管の頭部を結合した場合の配
置例を示す平面図および鉛直断面図、第22図は液状化
対策管の地盤への打込み施工状況を示す鉛直断面図、第
23図は本発明の耐震補強構造の建物基礎への適用例を
示す鉛直断面図、第24図は建物基礎および周辺地盤へ
の適用を示す鉛直断面図、第25図(a)、ら)はそれ
ぞれ本発明の耐震補強構造の住宅の直接基礎への適用例
を示す鉛直断面図および基礎部の水平断面図、第26図
は本発明の耐震補強構造の橋脚基礎への適用を示す鉛直
断面図、第27図は本発明の耐震補強構造の橋脚基礎お
よび周辺地盤への適用を示す鉛直断面図、第28図(a
)〜(C)は従来の液状化対策管の一例を示す斜視図、
正面図(一部所面図)および水平断面図である。 1・・・液状化対策管、2・・・穿孔部、3・・・孔、
4・・・栓、5・・・軸部、6・・・貫通孔、7・・・
フィルター、8・・・フィルター防護部材、9.10・
・・栓離脱防止部、11・・・スリット、12・・・注
入管、13・・・キャップ、14・・・土砂侵入防止蓋
、15・・・リブ、16・・・空気抜き孔、17・・・
尖端部、18・・・フィルター 19・・・蓋、20・
・・フィルター封栓、21・・・チャック把持用治具、
22・・・帯状平板、23・・・螺旋状ひれ、24・・
・土砂侵入防止蓋、25・・・油圧ショベル、26・・
・バイブロハンマー、31・・・土砂吸引排出機、32
・・・パイプ、33・・・土砂、41・・・液状化地盤
、42・・・非液状化地盤、43・・・盛土、44・・
・砕石層、45・・・結合材、46・・・住宅、47・
・・直接基礎、48・・・砕石部、48a・・・側溝、
49・・・建物、50・・・橋脚、51・・・砕石部、
52・・・排水管第 ] 図 (a) 第 図 第 図 (b) (C) 第 図 第 図 第 図 第 図 (a) 第 図 (b) 第13 図 (a) (b) (C) 第 ]4 図 (a) 第 (b) 図 (C) 第 図 第 図 第 図 液状化対策管 載何仮父直δ(mm) 第 図
Fig. 1 is a perspective view showing an outline of the liquefaction countermeasure pipe according to the present invention, Fig. 2 is a vertical sectional view showing an example of how a plug is attached to a perforated pipe, and Figs. 3 (a) to (C). 2 are a side view, a front view, and a rear view of the stopper shown in FIG. 2, FIG. 4 is a vertical cross-sectional view showing the state in which the stopper is installed in another embodiment, and FIGS.
C) is a side view, front view, and rear view of the plug in FIG. 4, FIG. 6 is a vertical cross-sectional view showing an overview of the intrapipe sediment suction and discharge system, and FIG. 7 is a state in which the plug is installed in yet another embodiment. 8(a) to (C) are respectively a front view, a side view, and a sectional view of the stopper in FIG. 10(a) and 10(a) are respectively a side view and a sectional view of the stopper in FIG. 9, FIG. 11 is a vertical sectional view showing the state of attachment of the stopper in yet another embodiment, and FIG. 12 (a)~(
C) is a side view before enlargement, a side view after enlargement, and a sectional view after enlargement of the detachment prevention part of the stopper shown in Fig. 10, and Fig. 13 (
Figures 14 (a) to (d) and 15 (a) to (C) are perspective views showing examples of liquefaction prevention pipes each having a cap or lid for preventing soil intrusion at the tip; are perspective views of different embodiments of the liquefaction countermeasure pipe according to the present invention, FIG. 16 is a graph showing the change in excess pore water pressure ratio over time in a free damping wave excitation experiment, and FIG. 17 is an experiment of the liquefaction countermeasure pipe. Figure 18 is a graph showing the relationship between horizontal resistance and loading plate displacement in the liquefaction countermeasure pipe experiment, Figure 19 (a),
(b) is a plan view and a vertical cross-sectional view showing how the liquefaction countermeasure pipe is installed on the ground, and Figure 20 (a) and (a) are vertical cross-sectional views showing an example of application when there is embankment on liquefaction ground. Figure 21 is a plan view and vertical sectional view showing an example of the arrangement when the heads of liquefaction prevention pipes are combined, and Figure 22 is a vertical sectional view showing the state of driving the liquefaction prevention pipe into the ground. Fig. 23 is a vertical sectional view showing an example of application of the seismic reinforcement structure of the present invention to a building foundation, Fig. 24 is a vertical sectional view showing application to a building foundation and surrounding ground, and Fig. 25 (a), et al. 26 is a vertical cross-sectional view and a horizontal cross-sectional view of the foundation, respectively, showing an example of application of the seismic reinforcement structure of the present invention to a direct foundation of a house, and FIG. Figure 27 is a vertical sectional view showing the application of the seismic reinforcement structure of the present invention to the pier foundation and surrounding ground, and Figure 28 (a
) to (C) are perspective views showing examples of conventional liquefaction prevention pipes,
They are a front view (partial view) and a horizontal sectional view. 1... Liquefaction countermeasure pipe, 2... Perforated part, 3... Hole,
4... Plug, 5... Shaft, 6... Through hole, 7...
Filter, 8... Filter protection member, 9.10.
... Stopper separation prevention part, 11 ... Slit, 12 ... Injection pipe, 13 ... Cap, 14 ... Earth and sand intrusion prevention lid, 15 ... Rib, 16 ... Air vent hole, 17 ...・・・
Pointed end, 18... Filter 19... Lid, 20.
... Filter sealing plug, 21 ... Chuck gripping jig,
22... Band-shaped flat plate, 23... Spiral fin, 24...
・Earth and sand intrusion prevention lid, 25...Hydraulic excavator, 26...
・Vibrohammer, 31... Sediment suction discharge machine, 32
... Pipe, 33... Earth and sand, 41... Liquefied ground, 42... Non-liquefied ground, 43... Embankment, 44...
- Crushed stone layer, 45... Binding material, 46... Housing, 47.
... Direct foundation, 48... Crushed stone section, 48a... Side ditch,
49... Building, 50... Pier, 51... Stone crushing section,
52... Drain pipe] Figure (a) Figure (b) (C) Figure (a) Figure (b) Figure 13 (a) (b) (C) ] 4 Figure (a) Figure (b) Figure (C) Figure Figure Figure Figure Liquefaction Countermeasures Pipe Installation Temporary Direction δ (mm) Figure

Claims (5)

【特許請求の範囲】[Claims] (1)管壁に多数の孔を穿設してなる管の前記各孔に栓
が取付けられており、該栓はその軸方向に貫通孔を有し
、該貫通孔内にフィルターを設けてなる液状化対策管を
、地震時に地盤の液状化が懸念される地層に設置される
構造物基礎の支持杭の少なくとも一部に用いたことを特
徴とする構造物の耐震補強構造。
(1) A plug is attached to each hole of a pipe formed by drilling a large number of holes in the pipe wall, the plug has a through hole in the axial direction, and a filter is provided in the through hole. 1. An earthquake-resistant reinforcement structure for a structure, characterized in that a liquefaction countermeasure pipe made of liquefaction prevention pipe is used for at least a part of a support pile of a structure foundation installed in a stratum where there is a concern about ground liquefaction during an earthquake.
(2)前記液状化対策管を前記構造物基礎の支持杭の周
辺の、地震時に地盤の液状化が懸念される地層にも設置
したことを特徴とする構造物の耐震補強構造。
(2) An earthquake-resistant reinforcement structure for a structure, characterized in that the liquefaction countermeasure pipe is also installed in a stratum around the support pile of the structure foundation, where there is a concern that the ground may liquefy during an earthquake.
(3)前記栓の貫通孔には、前記フィルターとともにフ
ィルターの損傷防止用の通水性のあるフィルター防護部
材を設けたことを特徴とする請求項1または2記載の構
造物の耐震補強構造。
(3) The seismic reinforcement structure for a structure according to claim 1 or 2, wherein the through hole of the plug is provided with a water-permeable filter protection member for preventing damage to the filter together with the filter.
(4)管壁に多数の孔を穿設してなる鋼管の前記各孔に
栓が取付けられており、該栓はその軸方向に貫通孔を有
し、該貫通孔内にフィルターを設けてなる液状化対策管
を、地震時に地盤の液状化が懸念される地層に設置され
る住宅の直接基礎の下部に設けたことを特徴とする住宅
の耐震補強構造。
(4) A plug is attached to each hole of a steel pipe formed by drilling a large number of holes in the pipe wall, the plug has a through hole in the axial direction, and a filter is provided in the through hole. 1. A seismic reinforcement structure for a house, characterized in that a liquefaction countermeasure pipe is installed directly below the foundation of the house, which is installed in a stratum where there is a risk of ground liquefaction during an earthquake.
(5)前記液状化対策管を前記住宅の直接基礎間または
前記住宅の周辺の、地震時に地盤の液状化が懸念される
地層にも設置したことを特徴とする住宅の耐震補強構造
。
(5) An earthquake-resistant reinforcement structure for a house, characterized in that the liquefaction prevention pipe is installed directly between the foundations of the house or in the strata around the house, where there is a concern that the ground will liquefy in the event of an earthquake.
JP12878190A 1990-05-18 1990-05-18 Seismic reinforcement structure of structures Expired - Fee Related JP2780438B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12878190A JP2780438B2 (en) 1990-05-18 1990-05-18 Seismic reinforcement structure of structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12878190A JP2780438B2 (en) 1990-05-18 1990-05-18 Seismic reinforcement structure of structures

Publications (2)

Publication Number Publication Date
JPH0424330A true JPH0424330A (en) 1992-01-28
JP2780438B2 JP2780438B2 (en) 1998-07-30

Family

ID=14993306

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12878190A Expired - Fee Related JP2780438B2 (en) 1990-05-18 1990-05-18 Seismic reinforcement structure of structures

Country Status (1)

Country Link
JP (1) JP2780438B2 (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5148001B1 (en) * 2012-03-27 2013-02-20 美喜男 梅岡 Steel pipe piles for preventing levitation of underground objects, and methods for preventing levitation of underground objects using the same
JP2013108253A (en) * 2011-11-18 2013-06-06 Maeda Corp Liquefaction countermeasure device
JP2013185399A (en) * 2012-03-09 2013-09-19 Shimizu Corp Foundation structure of structure
JP2014001562A (en) * 2012-06-19 2014-01-09 Tadatoshi Nakajima Liquefaction prevention method
JP2014051867A (en) * 2012-09-10 2014-03-20 Nippon Steel & Sumitomo Metal Steel material with drainage function
JP2014051866A (en) * 2012-09-10 2014-03-20 Nippon Steel & Sumitomo Metal Steel material with drainage function
JP2015057534A (en) * 2013-08-12 2015-03-26 城東テクノ株式会社 Drain material
JP2018165444A (en) * 2017-03-28 2018-10-25 日鐵住金建材株式会社 Flange structure of fitting member
JP2019108677A (en) * 2017-12-15 2019-07-04 東京電力ホールディングス株式会社 Drain pile and liquefaction countermeasures method
JP2020070658A (en) * 2018-11-01 2020-05-07 中村物産有限会社 Sheet pile wall embedding structure
JP2020180458A (en) * 2019-04-24 2020-11-05 株式会社竹中工務店 Ground liquefaction suppression structure
JP2020180459A (en) * 2019-04-24 2020-11-05 株式会社竹中工務店 Ground unevenness suppression structure
JP2020180457A (en) * 2019-04-24 2020-11-05 株式会社竹中工務店 Ground liquefaction suppression structure
JP2020180456A (en) * 2019-04-24 2020-11-05 株式会社竹中工務店 Ground liquefaction suppression structure

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3789127B1 (en) * 2004-08-06 2006-06-21 有限会社太田ジオリサーチ Seismic structure

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013108253A (en) * 2011-11-18 2013-06-06 Maeda Corp Liquefaction countermeasure device
JP2013185399A (en) * 2012-03-09 2013-09-19 Shimizu Corp Foundation structure of structure
JP5148001B1 (en) * 2012-03-27 2013-02-20 美喜男 梅岡 Steel pipe piles for preventing levitation of underground objects, and methods for preventing levitation of underground objects using the same
JP2014001562A (en) * 2012-06-19 2014-01-09 Tadatoshi Nakajima Liquefaction prevention method
JP2014051867A (en) * 2012-09-10 2014-03-20 Nippon Steel & Sumitomo Metal Steel material with drainage function
JP2014051866A (en) * 2012-09-10 2014-03-20 Nippon Steel & Sumitomo Metal Steel material with drainage function
JP2015057534A (en) * 2013-08-12 2015-03-26 城東テクノ株式会社 Drain material
JP2018165444A (en) * 2017-03-28 2018-10-25 日鐵住金建材株式会社 Flange structure of fitting member
JP2019108677A (en) * 2017-12-15 2019-07-04 東京電力ホールディングス株式会社 Drain pile and liquefaction countermeasures method
JP2020070658A (en) * 2018-11-01 2020-05-07 中村物産有限会社 Sheet pile wall embedding structure
JP2020180458A (en) * 2019-04-24 2020-11-05 株式会社竹中工務店 Ground liquefaction suppression structure
JP2020180459A (en) * 2019-04-24 2020-11-05 株式会社竹中工務店 Ground unevenness suppression structure
JP2020180457A (en) * 2019-04-24 2020-11-05 株式会社竹中工務店 Ground liquefaction suppression structure
JP2020180456A (en) * 2019-04-24 2020-11-05 株式会社竹中工務店 Ground liquefaction suppression structure

Also Published As

Publication number Publication date
JP2780438B2 (en) 1998-07-30

Similar Documents

Publication Publication Date Title
JP2780438B2 (en) Seismic reinforcement structure of structures
JP2006225926A (en) Banking construction method utilizing backfilling material such as fluidized soil, pit sand, local soil and crushed stone
JP2890869B2 (en) Sheet pile with drainage function, method of manufacturing the same, and plug
JP2789803B2 (en) Liquefaction control piles and plugs for liquefaction control piles
JP6832101B2 (en) Reinforcement structure of embankment and reinforcement method of embankment
JP2789783B2 (en) Liquefaction control pipe, method of manufacturing the same, and plug for liquefaction control pipe
JP3385876B2 (en) Cast-in-place pile construction method just below the existing foundation
JP3789127B1 (en) Seismic structure
JPH02183006A (en) Manufacturing method, its ground drainage member and anti-liquefaction method therewith
JPH09316874A (en) Liquefaction countermeasure support pile
JP4316940B2 (en) Masonry wall reinforcement method
JPH0552366B2 (en)
JP2001207437A (en) Reinforcement method of ground below existing structure
KR101020217B1 (en) Rock construction using anchor and construction method
JPS58127822A (en) Liquefaction preventive structure of foundation ground
JPH08302661A (en) Sand protection mat construction method
JP2006299605A (en) Equipment for countermeasure against liquefaction of ground immediately below underground structure, and equipment and construction method for countermeasure against liquefaction of ground immediately below fill
JPH0765315B2 (en) Embankment structure
JP2008031754A (en) Foundation ground reinforcing structure and foundation ground reinforcing method
JPH0348962B2 (en)
JPS60250122A (en) Foundation pile structure for preventing liquefaction of ground
JP3519375B2 (en) Cast-in-place pile construction method just below the existing foundation
JPH0617414A (en) Drainage reinforcement pile
JP2976390B2 (en) Method for preventing liquefaction of the foundation directly under the existing structure
JPH01125413A (en) Steel sheet pile for preventing liquefaction

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090515

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100515

Year of fee payment: 12

LAPS Cancellation because of no payment of annual fees