JPH0425879Y2 - - Google Patents
Info
- Publication number
- JPH0425879Y2 JPH0425879Y2 JP1986061488U JP6148886U JPH0425879Y2 JP H0425879 Y2 JPH0425879 Y2 JP H0425879Y2 JP 1986061488 U JP1986061488 U JP 1986061488U JP 6148886 U JP6148886 U JP 6148886U JP H0425879 Y2 JPH0425879 Y2 JP H0425879Y2
- Authority
- JP
- Japan
- Prior art keywords
- hanging pipe
- pipe
- shaped steel
- threaded rod
- flange
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Movable Scaffolding (AREA)
Description
【考案の詳細な説明】
[産業上の利用分野]
本考案は、建築現場或は補修現場等において、
H型鋼、I型鋼等のフランジに足場を吊り下げ取
り付ける足場取り付け装置に関するものである。[Detailed explanation of the invention] [Industrial application field] This invention can be used at construction sites, repair sites, etc.
This invention relates to a scaffold attachment device for hanging and attaching a scaffold to a flange of H-type steel, I-type steel, etc.
[従来の技術と考案が解決しようとする課題]
従来より、建築現場、補修現場においてH型
鋼、或はI型鋼に吊り下げ取り付けられる足場取
り付け装置は種々用いられている。その一例とし
ては第4図に示すものが存する。この従来例は、
H型鋼31のフランジ32底面に取り付けピース
33を溶接にて取り付け、この取り付けピース3
3の一対の孔に一対のサスペンダパイプ35,3
5をボルト、ナツトにて締結し、このサスペンダ
パイプ35,35に桁パイプ36と手摺パイプ3
7,37とを組付けている。しかしながら、この
第4図に示す従来例では、H型鋼31のフランジ
32底面に所定間隔で取り付けピース33を予め
溶接にて取り付けておく必要があり、しかも足場
を撤去した後には溶接した取り付けピース33を
取り外し、この取り外し跡を平面に仕上げて塗装
する必要がある。[Problems to be solved by conventional techniques and ideas] Conventionally, various scaffolding installation devices that are suspended from H-beams or I-beams have been used at construction sites and repair sites. An example of this is shown in FIG. This conventional example is
The mounting piece 33 is attached to the bottom of the flange 32 of the H-shaped steel 31 by welding, and this mounting piece 3
A pair of suspender pipes 35, 3 in a pair of holes 3
5 with bolts and nuts, and connect the girder pipe 36 and handrail pipe 3 to the suspender pipes 35, 35.
7 and 37 are assembled. However, in the conventional example shown in FIG. 4, it is necessary to attach attachment pieces 33 to the bottom surface of the flange 32 of the H-shaped steel 31 at predetermined intervals by welding in advance. It is necessary to remove it, finish the removal mark flat and paint it.
又、第5図に示す従来例は、一対のサスペンダ
パイプ38,38をX字状に交叉し、この交叉部
を枢支支点とする一方、これら一対のサスペンダ
パイプ38,38の上端にH型鋼31のフランジ
32,32端面を挾持する挾持金具39とボルト
からなる押圧部40を設け、取り付けピースをH
型鋼に溶接することなくサスペンダパイプ38,
38をH型鋼31のフランジ32,32に吊り下
げることができるようになつている。しかしなが
ら、この第5図に示す従来例では、X字状に交叉
したサスペンダパイプ38,38下端に枢着され
た桁パイプ36の片方に重量が掛かつた場合、反
重量側の桁パイプ36を支えるサスペンダパイプ
38側が浮き上がつて挾持金具39部分が緩むと
いつた不都合がある。 Further, in the conventional example shown in FIG. 5, a pair of suspender pipes 38, 38 intersect in an X-shape, and this intersection is used as a pivot point, while an H-shaped steel is installed at the upper ends of these pair of suspender pipes 38, 38. A clamping fitting 39 that clamps the end faces of the flanges 32 and 32 of 31 and a pressing part 40 consisting of a bolt are provided, and the mounting piece is
Suspender pipe 38 without welding to shaped steel,
38 can be suspended from the flanges 32, 32 of the H-shaped steel 31. However, in the conventional example shown in FIG. 5, when weight is applied to one of the girder pipes 36 pivoted to the lower ends of the suspender pipes 38, 38 which intersect in an X-shape, the girder pipe 36 on the opposite side of the weight is There is an inconvenience that the supporting suspender pipe 38 side lifts up and the clamping fitting 39 portion loosens.
さらにこの種足場取り付け装置としては、実開
昭50−151529号公報に記載のものが知られてい
る。この従来例はフランジを挾持する押圧部を有
する一対のプレートをスライド可能にし、押圧部
の間隔を可能にしているが、その固定にボルト、
ナツトを用いており締め付け作用が煩雑である。 Furthermore, as this type of scaffolding attachment device, one described in Japanese Utility Model Application Publication No. 151529/1983 is known. In this conventional example, a pair of plates with pressing parts that hold the flange are made slidable, and the interval between the pressing parts is made possible, but bolts and bolts are used to fix them.
Since nuts are used, the tightening action is complicated.
本考案は、これらの事情に鑑みてなされたもの
で、取り付けピースを溶接することなく着脱が容
易であり、しかも装着時には緩みが生じることな
く確実に取り付けることができて安全性が確保さ
れ、しかも簡単に押圧部材間の間隔を調整できる
足場取り付け装置を提供することを目的としてい
る。 The present invention was developed in consideration of these circumstances, and it is easy to attach and detach without welding the attachment piece, and it can be securely attached without loosening when attached, ensuring safety. It is an object of the present invention to provide a scaffold attachment device that can easily adjust the interval between pressing members.
[課題を解決するための手段及びその作用]
前記目的を達成するため本考案による足場取り
付け装置は、桁パイプを下端に設けたサスペンダ
を取り付ける取り付けピースを下向きに固定して
H型鋼或はI型鋼のフランジ底面に直交状態で保
持される吊りパイプと、前記取付けピースを中心
にした吊りパイプの上部に相対峙して配置されて
前記H型鋼或はI型鋼のフランジに対峙する一
方、前記吊りパイプの軸方向に互いに接近方向及
び離間方向へ移動して間隔を設定自在にした一対
の顎部材と、前記吊りパイプに貫通すると共に、
該吊りパイプ内に内設した軸受部材に回動自在に
支承され、略中央部を境に一方が右ねじに他方が
左ねじに形成されたねじ棒と、前記ねじ棒の右ね
じ部と左捩子部に各々螺合されたナツトと、前記
顎部材が移動する範囲の吊りパイプに軸方向に形
成したスリツトと、前記ナツトを前記スリツトを
介して顎部材に連結する連結部材と、前記吊りパ
イプの両端に突出したねじ棒に螺合されてねじ棒
の回動を規制するロツクナツトと、前記吊りパイ
プの両端に突出したねじ棒の端部に固定されたハ
ンドルと、前記一対の顎部材に上下動自在に設け
られて前記H型鋼或はI型鋼のフランジ底面に直
交状態で保持される吊りパイプと相俟つて前記フ
ランジを押圧挾持する押圧部材を備えている。[Means for Solving the Problems and Their Effects] In order to achieve the above object, the scaffolding installation device according to the present invention fixes downwardly the mounting piece to which the suspenders having the girder pipes are attached at the lower end, and attaches the suspension to the H-shaped steel or I-shaped steel. a hanging pipe held perpendicularly to the bottom surface of the flange of the hanging pipe; and a hanging pipe that is arranged opposite to each other at the upper part of the hanging pipe with the mounting piece in the center and facing the flange of the H-beam or I-beam; a pair of jaw members that can freely set the spacing by moving toward and away from each other in the axial direction;
A threaded rod is rotatably supported by a bearing member installed inside the hanging pipe, and has a right-hand thread on one side and a left-hand thread on the other side with approximately the center as a boundary; a nut screwed onto each threaded portion, a slit formed in the axial direction in the suspension pipe in a range in which the jaw member moves, a connecting member connecting the nut to the jaw member via the slit, and the suspension pipe. A lock nut that is screwed onto the threaded rods protruding from both ends of the pipe to restrict rotation of the threaded rods, a handle fixed to the ends of the threaded rods protruding from both ends of the hanging pipe, and the pair of jaw members. A pressing member is provided which presses and clamps the flange in conjunction with a hanging pipe that is vertically movable and held perpendicular to the bottom surface of the flange of the H-shaped steel or I-shaped steel.
この構成で、前記吊りパイプをH型鋼或はI型
鋼のフランジ底面に当てがい、一対の顎部材をそ
の間隔が前記両フランジを挾持できる間隔に調整
し、その後これら顎部材の押圧部材を下動させて
フランジ上面に押圧させ、前記フランジ下面に位
置する吊り杆とこの一対の押圧部材とで両フラン
ジを挾持して吊り杆をH型鋼或はI型鋼のフラン
ジに取り付けるものである。 In this configuration, the hanging pipe is applied to the bottom surface of the flange of the H-type steel or I-type steel, the distance between the pair of jaw members is adjusted to a distance that allows the two flanges to be clamped, and then the pressing members of these jaw members are moved downward. The suspension rod is then pressed against the upper surface of the flange, and both flanges are held between the suspension rod located on the lower surface of the flange and the pair of pressing members, and the suspension rod is attached to the flange of H-type steel or I-type steel.
[実施例]
以下、図面を参照して本考案の実施例を具体的
に説明する。[Example] Hereinafter, an example of the present invention will be specifically described with reference to the drawings.
第1図ないし第3図は本考案装置の一実施例に
係り、第1図は一部切欠正面図、第2図はH型鋼
への取り付け状態を示す正面図、第3図は第2図
の斜視図である。 Figures 1 to 3 relate to an embodiment of the device of the present invention, in which Figure 1 is a partially cutaway front view, Figure 2 is a front view showing how it is attached to the H-shaped steel, and Figure 3 is Figure 2. FIG.
これらの図において、符号1は足場取り付け装
置で、取り付けピース2を下向きにして中央に溶
接固定しH型鋼(又はI型鋼、以下同じ)3のフ
ランジ3a,3bの底面に直交状態で当てがわれ
る吊りパイプ4と、前記取り付けピース2を中心
とした吊りパイプ4の上部に相対峙して配置さ
れ、該吊りパイプ4の軸方向に互いに逆方向へ移
動して間隔を設定自在とした一対の顎部材5,5
と、これら一対の顎部材5,5に上下動自在に設
けられて前記H型鋼3のフランジ3a,3b底面
に直交状態で当てがわれる前記吊りパイプ4とで
フランジ3a,3bを押圧挾持する押圧部材6と
から構成されている。 In these figures, reference numeral 1 denotes a scaffold attachment device, which is welded and fixed in the center with the attachment piece 2 facing downward, and is applied perpendicularly to the bottom surfaces of flanges 3a and 3b of H-beam steel (or I-beam steel, hereinafter the same) 3. A pair of jaws which are arranged facing each other on the upper part of the hanging pipe 4 and the hanging pipe 4 centered on the mounting piece 2, and whose spacing can be freely set by moving in opposite directions in the axial direction of the hanging pipe 4. Parts 5, 5
and a pressing force that presses and clamps the flanges 3a, 3b with the hanging pipe 4, which is provided on the pair of jaw members 5, 5 so as to be movable up and down, and applied orthogonally to the bottom surfaces of the flanges 3a, 3b of the H-shaped steel 3. It is composed of a member 6.
前記吊りパイプ4の中空内にはねじ棒7が貫通
配置され、そのねじ棒7の中央は軸受部材8に回
動自在に支承されていると共に、ねじ棒7の両端
は吊りパイプ4の両端から外部に突出し、この突
出部に各々ロツクナツト9,9を介してハンドル
10,10が固着されている。前記ねじ棒7は中
央の軸受部材8を境に一方が右ねじ7aに、他方
が左ねじ7bに形成されている。そして、この右
ねじ7a及び左ねじ7bの各々にナツト11,1
1が螺合され、この各ナツト11,11は前記顎
部材5,5に連結部材を介して連結されている。
又、吊りパイプ4の前記顎部材が移動する範囲に
は軸方向のスリツト12,12が形成されてお
り、このスリツト12,12を経て吊りパイプ4
内のナツト11,11と外部の顎部材5,5とが
連結されている。さらに、前記顎部材5,5は吊
りパイプ4の外周を抱持して上部側へ立ち上がり
形成されている。さらに又、前記吊りパイプ4の
両端にはねじ棒7を貫通し突出するねじ孔を有す
るカバー13,13が被着されている。 A threaded rod 7 is inserted through the hollow of the hanging pipe 4, and the center of the threaded rod 7 is rotatably supported by a bearing member 8, and both ends of the threaded rod 7 extend from both ends of the hanging pipe 4. It protrudes to the outside, and handles 10, 10 are fixed to this protrusion via lock nuts 9, 9, respectively. The threaded rod 7 is formed with a right-hand thread 7a on one side and a left-hand thread 7b on the other side with the central bearing member 8 as a boundary. Then, nuts 11 and 1 are attached to each of the right-hand thread 7a and left-hand thread 7b.
1 are screwed together, and each nut 11, 11 is connected to the jaw members 5, 5 via a connecting member.
Further, axial slits 12, 12 are formed in the range in which the jaw members of the hanging pipe 4 move, and the hanging pipe 4 passes through these slits 12, 12.
The inner nuts 11, 11 and the outer jaw members 5, 5 are connected. Further, the jaw members 5, 5 are formed to hold the outer periphery of the hanging pipe 4 and rise upwardly. Furthermore, covers 13, 13 having screw holes projecting through the threaded rod 7 are attached to both ends of the hanging pipe 4.
一方、前記押圧部材6は、顎部材5の内側に固
定したナツト14と、このナツト14に螺合され
上下方向に貫通配置したねじ体15と、このねじ
体15の上端に固着したハンドル16と、このね
じ体15の下端に固着した接圧体17とからな
り、前記ハンドル16と顎部材5上面との間のね
じ体15にはロツクナツト18を螺合している。 On the other hand, the pressing member 6 includes a nut 14 fixed to the inside of the jaw member 5, a screw body 15 screwed onto the nut 14 and arranged to penetrate in the vertical direction, and a handle 16 fixed to the upper end of the screw body 15. , and a pressure contact body 17 fixed to the lower end of this screw body 15, and a lock nut 18 is screwed into the screw body 15 between the handle 16 and the upper surface of the jaw member 5.
尚、図中符号19,19は取り付けピース2に
ボルト、ナツト等にて固定したサスペンダパイ
プ、20はこのサスペンダパイプ19,19の下
端を固定した桁パイプ、21,21は桁パイプ2
0の側端に立設固定した手摺パイプである。 In the figure, reference numerals 19 and 19 are suspender pipes fixed to the mounting piece 2 with bolts, nuts, etc., 20 is a girder pipe to which the lower ends of the suspender pipes 19 and 19 are fixed, and 21 and 21 are girder pipes 2.
This is a handrail pipe that is erected and fixed at the side end of 0.
このような構成では、吊りパイプ4をH型鋼3
のフランジ3a,3b底面に該H型鋼3の長さ方
向に直交するよう当てがうと共に、ねじ棒7のハ
ンドル10,10を回動させて顎部材5,5が各
フランジ3a,3bに載る位置まで該顎部材5,
5を移動させ、この顎部材5,5の移動完了後
は、ロツクナツト9,9をカバー13,13側に
締結してねじ棒7の回動をロツクし、顎部材5,
5の移動を阻止する。その後、各顎部材5,5の
ハンドル16,16を回動させてねじ体15,1
5及び接圧体17,17を下動させ、該接圧体1
7,17をH型鋼3の各フランジ3a,3bに押
圧させ、且つロツクナツト18,18を顎部材
5,5の上面に締結してねじ体15の緩みを防止
し、前記吊りパイプ4とこれら押圧部材6,6の
接圧体17,17とでフランジ3a,3bを押圧
挾持して吊りパイプ4をH型鋼3に確実に取り付
けるものである。 In such a configuration, the hanging pipe 4 is connected to the H-shaped steel 3.
The jaw members 5, 5 rest on the respective flanges 3a, 3b by applying them to the bottom surfaces of the flanges 3a, 3b so as to be perpendicular to the length direction of the H-shaped steel 3, and rotating the handles 10, 10 of the threaded rod 7. the jaw member 5 to the position;
After moving the jaw members 5, 5, the lock nuts 9, 9 are fastened to the covers 13, 13 side to lock the rotation of the threaded rod 7, and the jaw members 5, 5 are moved.
Prevent the movement of 5. Thereafter, by rotating the handles 16, 16 of each jaw member 5, 5, the screw body 15, 1
5 and the pressure contact bodies 17, 17 are moved downward, and the pressure contact body 1
7 and 17 are pressed against the respective flanges 3a and 3b of the H-shaped steel 3, and lock nuts 18 and 18 are fastened to the upper surfaces of the jaw members 5 and 5 to prevent the screw body 15 from loosening, and the hanging pipe 4 and these pressing The flanges 3a, 3b are pressed and clamped by the contact members 17, 17 of the members 6, 6, and the hanging pipe 4 is securely attached to the H-shaped steel 3.
本考案において、顎部材5,5の移動、及び押
圧部材6,6の緩みを防止するため、実施例では
ロツクナツトを用いているが、これの代わりに、
或はこれらを併用してピンを固定側と回動側間に
係入する等、必要に応じて対策される。 In the present invention, in order to prevent the jaw members 5, 5 from moving and the pressing members 6, 6 from loosening, a lock nut is used in the embodiment, but instead of this, a lock nut is used.
Alternatively, countermeasures may be taken as necessary, such as using these together to engage the pin between the fixed side and the rotating side.
尚、本考案において、吊りパイプの取り付けピ
ースに吊り下げられる足場装置は図示例に限るこ
となく、例えばチエーン方式等種々用いられる。 In the present invention, the scaffolding device suspended from the attachment piece of the hanging pipe is not limited to the illustrated example, and various types of scaffolding devices, such as a chain type, can be used.
[考案の効果]
以上説明したように本考案によれば、取り付け
ピースを溶接することなく着脱が容易であり、し
かも装着時には緩みが生じることなく確実に取り
付けることができて安全性を確保でき、しかも間
隔調整を容易にできる効果がある。[Effects of the invention] As explained above, according to the invention, the attachment piece can be easily attached and detached without welding, and it can be securely attached without loosening when attached, ensuring safety. Moreover, there is an effect that the interval can be easily adjusted.
第1図ないし第3図は本考案装置の一実施例に
係り、第1図は一部切欠正面図、第2図はH型鋼
への取り付け状態を示す正面図、第3図は第2図
の斜視図、第4図及び第5図は従来の足場取り付
け装置を示す説明図である。
1……足場取り付け装置、2……取り付けピー
ス、3……H型鋼、3a,3b……フランジ、4
……吊りパイプ、5……顎部材、6……押圧部
材。
Figures 1 to 3 relate to an embodiment of the device of the present invention, in which Figure 1 is a partially cutaway front view, Figure 2 is a front view showing how it is attached to the H-shaped steel, and Figure 3 is Figure 2. The perspective view, FIGS. 4 and 5 are explanatory diagrams showing a conventional scaffold attachment device. 1...Scaffold attachment device, 2...Mounting piece, 3...H-shaped steel, 3a, 3b...flange, 4
... Hanging pipe, 5 ... Jaw member, 6 ... Pressing member.
Claims (1)
る取り付けピースを下向きに固定してH型鋼或は
I型鋼のフランジ底面に直交状態で保持される吊
りパイプと、前記取付けピースを中心にした吊り
パイプの上部に相対峙して配置されて前記H型鋼
或はI型鋼のフランジに対峙する一方、前記吊り
パイプの軸方向に互いに接近方向及び離間方向へ
移動して間隔を設定自在にした一対の顎部材と、
前記吊りパイプに貫通すると共に、該吊りパイプ
内に内設した軸受部材に回動自在に支承され、略
中央部を境に一方が右ねじに他方が左ねじに形成
されたねじ棒と、前記ねじ棒の右ねじ部と左ねじ
部に各々螺合されたナツトと、前記顎部材が移動
する範囲の吊りパイプに軸方向に形成したスリツ
トと、前記ナツトを前記スリツトを介して顎部材
に連結する連結部材と、前記吊りパイプの両端に
突出したねじ棒に螺合されてねじ棒の回動を規制
するロツクナツトと、前記吊りパイプの両端に突
出したねじ棒の端部に固定されたハンドルと、前
記一対の顎部材に上下動自在に設けられて前記H
型鋼或はI型鋼のフランジ底面に直交状態で保持
される吊りパイプと相俟つて前記フランジを押圧
挾持する押圧部材とを具備したことを特徴とする
足場取り付け装置。 A hanging pipe that is fixed downward to which a suspender with a girder pipe attached at the lower end is held perpendicular to the bottom of the flange of an H-shaped steel or I-shaped steel, and a hanging pipe that is attached to the upper part of the hanging pipe with the mounting piece in the center. a pair of jaw members that are arranged to face each other and face the flanges of the H-shaped steel or I-shaped steel, and that move toward and away from each other in the axial direction of the hanging pipe to freely set the interval;
a threaded rod that penetrates the hanging pipe, is rotatably supported by a bearing member installed inside the hanging pipe, and has one side having a right-handed thread and the other side having a left-handed thread with a substantially central portion as a boundary; A nut screwed onto a right-hand threaded portion and a left-hand threaded portion of a threaded rod, a slit formed in an axial direction in a hanging pipe within a range in which the jaw member moves, and the nut connected to the jaw member via the slit. a locking nut that is screwed onto a threaded rod protruding from both ends of the hanging pipe to restrict rotation of the threaded rod, and a handle fixed to an end of the threaded rod protruding from both ends of the hanging pipe. , the H is provided on the pair of jaw members so as to be movable up and down.
1. A scaffolding attachment device comprising a hanging pipe held perpendicular to the bottom surface of a flange of a type steel or I-type steel, and a pressing member that presses and clamps the flange.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1986061488U JPH0425879Y2 (en) | 1986-04-22 | 1986-04-22 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1986061488U JPH0425879Y2 (en) | 1986-04-22 | 1986-04-22 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS62173443U JPS62173443U (en) | 1987-11-04 |
| JPH0425879Y2 true JPH0425879Y2 (en) | 1992-06-22 |
Family
ID=30894873
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP1986061488U Expired JPH0425879Y2 (en) | 1986-04-22 | 1986-04-22 |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0425879Y2 (en) |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5212334Y2 (en) * | 1974-05-31 | 1977-03-18 |
-
1986
- 1986-04-22 JP JP1986061488U patent/JPH0425879Y2/ja not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS62173443U (en) | 1987-11-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US5918843A (en) | Scaffold bracket | |
| JPH0473373A (en) | Method for securing scaffold pipe stanchion | |
| JPS5924764Y2 (en) | Handrail support on temporary pedestal | |
| JPH069238Y2 (en) | Structure of light steel ceiling | |
| JPS5910271Y2 (en) | Scaffold board support bar with fastening means | |
| CN222633987U (en) | A pipe hanger for use on an I-beam | |
| JPH08431Y2 (en) | Fixing bracket for steel frame scaffolding | |
| JP2535460Y2 (en) | Coupling device | |
| JP2526237Y2 (en) | Hanging frame scaffold | |
| JPH0115795Y2 (en) | ||
| JPS6350343Y2 (en) | ||
| JPH0536041Y2 (en) | ||
| JPH086881Y2 (en) | Joiner for large and small beams | |
| JP2584962Y2 (en) | Wife stop fixing bracing with clamp | |
| JPS6222607Y2 (en) | ||
| JPH071426Y2 (en) | Hollow scaffolding support hardware | |
| JP2523167Y2 (en) | Stage equipment | |
| JPH08326211A (en) | Column steel frame, jig used for connecting the columns, and steel frame connecting method | |
| JPH0746674Y2 (en) | Parent rope | |
| JPH0448275Y2 (en) | ||
| JPS587851Y2 (en) | Joint structure of columns and horizontal members | |
| JPH0211548Y2 (en) | ||
| JPH0227079Y2 (en) | ||
| JP2538446Y2 (en) | Connecting fixture for fixing scaffolding pipe supports to the rim | |
| CN118933256A (en) | Steel beam bottom hanger fixing device |