JPH0428048B2 - - Google Patents
Info
- Publication number
- JPH0428048B2 JPH0428048B2 JP17526287A JP17526287A JPH0428048B2 JP H0428048 B2 JPH0428048 B2 JP H0428048B2 JP 17526287 A JP17526287 A JP 17526287A JP 17526287 A JP17526287 A JP 17526287A JP H0428048 B2 JPH0428048 B2 JP H0428048B2
- Authority
- JP
- Japan
- Prior art keywords
- shield machine
- construction method
- side wall
- enlarged diameter
- open
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000010276 construction Methods 0.000 claims description 24
- 238000009434 installation Methods 0.000 claims 1
- 238000009412 basement excavation Methods 0.000 description 7
- 238000000034 method Methods 0.000 description 4
- 239000002689 soil Substances 0.000 description 4
- 230000000694 effects Effects 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000003517 fume Substances 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 230000014759 maintenance of location Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000010865 sewage Substances 0.000 description 1
- 238000009751 slip forming Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は、地中構造物の施工法のうち、オープ
ンシールド工法に関する。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to an open shield construction method among construction methods for underground structures.
オープンシールド工法は、上下水道や電信、電
話の布設道その他の地下道を形成する地中構造物
の施工に関し、開削工法とシールド工法のそれぞ
れの長所を生かし、市街地や軟弱地盤でも安全に
かつ簡単に工事が行えるようにしたものである。
The open shield construction method takes advantage of the respective strengths of the open-cut construction method and the shield construction method when constructing underground structures that form water, sewage, telegraph, telephone, and other underground passages, safely and easily even in urban areas and on soft ground. It was designed to allow construction work to be carried out.
先にこのオープンシールド工法の一般例を第3
図〜第6図について各工程別に説明すると、まず
第3図に示すように上面が開口し、推進ジヤツキ
2を設けたU型シールド機1を発進坑3内に設置
し、発進坑3の前面の土留4を切断し、発進坑3
内に形成した反力壁5を反力に用いて推進ジヤツ
キ2を伸長し地山に掘進させる。その掘進の際の
土砂の排出は、バツクホー7等のシヨベルやオー
ガー等を用いて行う。 First, let's look at a general example of this open shield method in Part 3.
To explain each process with respect to FIGS. 3 to 6, first, as shown in FIG. The earth retaining hole 4 is cut and the starting shaft 3 is cut.
The propulsion jack 2 is extended by using the reaction wall 5 formed therein as a reaction force to make it dig into the ground. During the excavation, the earth and sand will be discharged using a shovel such as a excavator 7, an auger, etc.
次いで、U型シールド機1のテール部に地上か
らコンクリート函体6等を吊降ろし(第5図参
照)、該コンクリート函体6を反力にして更にU
型シールド機1を掘進させる。 Next, a concrete box 6, etc. is suspended from the ground to the tail of the U-type shield machine 1 (see Figure 5), and the concrete box 6 is used as a reaction force to further extend the U
Type shield machine 1 is made to dig.
このようにして複数個のコンクリート函体6を
縦列させたならば、その上面に埋戻し土8を施
し、また函体6の周囲をグランドポンプ9により
グラウトする。 After a plurality of concrete boxes 6 are arranged in tandem in this manner, backfilling soil 8 is applied to the upper surface thereof, and the area around the boxes 6 is grouted using a ground pump 9.
かかる工程を繰り返し、また必要に応じて路面
仮復旧工としてタイヤローラー10等で路面舗装
11も行い、U型シールド機1が到達坑17内へ
達したならばこれを撤去して工事を完了する。 This process is repeated, and if necessary, the road surface is paved 11 using tire rollers 10 etc. as a temporary road restoration work. When the U-shaped shield machine 1 reaches the reach hole 17, it is removed and the work is completed. .
ところで、例えば第7図に示すように比較的大
型の地中構造物としてのコンクリート函体6と、
小地中構造物としてのヒユーム管12などの複数
の地中構造物を同時に施工するには、それだけ大
きな矩形断面のU型シールド機1を用いて施工を
行つている。 By the way, for example, as shown in FIG. 7, a concrete box 6 as a relatively large underground structure,
In order to simultaneously construct a plurality of underground structures such as humid pipes 12 as small underground structures, a U-shaped shield machine 1 having a large rectangular cross section is used.
このように従来では、大型のU型シールド機1
を使用するため余掘り量が大となり、工期、工費
が増大する。そして、埋戻し土砂量も増大してし
まい、さらに工期、工費が大きくなる。
In this way, conventionally, a large U-shaped shield machine 1
The amount of excess excavation is large due to the use of a large amount of excavation, which increases the construction period and cost. The amount of backfilling soil also increases, further increasing the construction period and cost.
さらに、U型シールド機1は前記のごとくコン
クリート函体6を反力として掘進するものであ
り、このコンクリート函体6はその断面がシール
ド機1よりも小さいので、函体6とシールド機1
間での推進ジヤツキの配置は上下左右のバランス
が悪いものとなる。その結果、掘進方向が狂いや
すい。 Furthermore, as mentioned above, the U-type shield machine 1 excavates using the concrete box 6 as a reaction force, and since the concrete box 6 has a smaller cross section than the shield machine 1, the box 6 and the shield machine 1
The arrangement of the propulsion jacks in between will result in an imbalance in the vertical and horizontal directions. As a result, the direction of excavation is likely to be deviated.
本発明の目的は前記従来例の不都合を解消し、
複数の地中構造物を同時施工する場合でも極力必
要な個所のみを掘削するようにしてシールド機掘
進時の余掘り量や埋戻し量の増加を防ぎ、工期、
工費を減少させることができ、また掘進時の方向
性も良好な地中構造物の施工法を提供することに
ある。 The purpose of the present invention is to eliminate the disadvantages of the conventional example,
Even when constructing multiple underground structures at the same time, by excavating only the necessary areas as much as possible, we can prevent an increase in the amount of excess excavation and backfilling when excavating with a shield machine, and reduce the construction period.
It is an object of the present invention to provide a construction method for an underground structure that can reduce construction costs and provide good directionality during excavation.
本発明は前記目的を達成するため、上面が開口
し、推進ジヤツキを備えたU型シールド機を順次
シールド機の後方に配設するコンクリート函体を
反力として掘進させるオープンシールド工法にお
いて、前記U型シールド機の側壁又は底板を部分
的に膨出させ、さらに側壁上部を張出させて拡径
部を形成し、該膨出部で脇溝を、及び拡径部で段
差部を、それぞれ同時に施工し、ここに小地中構
造物を配設することを要旨とするものである。
In order to achieve the above object, the present invention provides an open shield construction method in which a U-shaped shield machine with an open top surface and a propulsion jack is sequentially disposed behind the shield machine to excavate using a reaction force as a reaction force. The side wall or bottom plate of the mold shielding machine is partially bulged out, and the upper part of the side wall is bulged out to form an enlarged diameter part, and the bulged part forms a side groove and the enlarged diameter part forms a stepped part, respectively. The purpose is to construct a small underground structure and install a small underground structure there.
本発明によれば、大きなコンクリート函体とヒ
ユーム管等の小地中構造物を同時施工する場合、
該小地中構造物配設はU型シールド機の側壁上部
の拡径部及び側壁又は底板の膨出部を利用して行
うので、シールド機全体がそれ程大きくならない
ですむ。従つて、余掘り量及び埋戻し量もさほど
増大せず、コンクリート函体とシールド機も必要
以上に大きさが異ならず、両者間に配設される推
進ジヤツキの上下、左右のバランスもくずれな
い。
According to the present invention, when simultaneously constructing a large concrete box and a small underground structure such as a humid pipe,
Since the small underground structure is installed using the enlarged diameter part of the upper part of the side wall and the bulge part of the side wall or bottom plate of the U-shaped shield machine, the whole shield machine does not need to be so large. Therefore, the amount of over-excavation and backfilling does not increase significantly, the concrete box and shield machine do not differ in size more than necessary, and the vertical and horizontal balance of the propulsion jack installed between them does not collapse. .
以下、図面について本発明の実施例を詳細に説
明する。
Embodiments of the present invention will be described in detail below with reference to the drawings.
第1図は本発明の地中構造物の施工法の1実施
例を示す正面図で、図中1はオープンシールド工
法用として、上面が開口し、内部又は後端に推進
ジヤツキ(図示せず)を備えたU型シールド機1
を示す。 Figure 1 is a front view showing one embodiment of the underground structure construction method of the present invention, and 1 in the figure is for the open shield construction method, with the top surface open and a propulsion jack (not shown) installed inside or at the rear end. ) U-type shield machine 1
shows.
そして、本発明工法で使用するU型シールド機
1は、一方の側壁1aの一部(図示では底部近
く)を外側へ矩形に張出させ、長さ方向に連続す
る膨出部13を形成した。 The U-shaped shield machine 1 used in the construction method of the present invention has a part of one side wall 1a (near the bottom in the figure) extended outward in a rectangular shape to form a bulge 13 continuous in the length direction. .
また、他方の側壁1aの上部を外側に張出さ
せ、長さ方向に連続する拡径部14を形成する。 Moreover, the upper part of the other side wall 1a is made to project outward to form an enlarged diameter part 14 that continues in the length direction.
なお、このような膨出部13や拡径部14の形
成個所や個数は特に限定されず、例えば両側壁1
aに拡径部14を形成し、その下方に膨出部13
を形成してもよい。 Note that the location and number of such bulging portions 13 and enlarged diameter portions 14 are not particularly limited; for example, on both side walls 1.
An enlarged diameter portion 14 is formed at a, and a bulged portion 13 is formed below the enlarged diameter portion 14.
may be formed.
また、他の実施例として、第2図に示すように
底板1bに膨出部13を形成することもできる。 Furthermore, as another embodiment, a bulge 13 may be formed on the bottom plate 1b as shown in FIG.
次に、このようなU型シールド機1を用いて行
う本発明工法を説明する。 Next, the construction method of the present invention using such a U-shaped shield machine 1 will be explained.
オープンシールド工法全体については前記第3
図〜第6図で説明した通りであり、U型シールド
機1の後方に、順次コンクリート函体6を配設
し、これを反力としてシールド機1を前進させる
点は同一なので詳細説明は省略する。 Regarding the entire open shield construction method, please refer to Section 3 above.
This is as explained in Figures to Figure 6, and the concrete box 6 is sequentially arranged behind the U-type shield machine 1, and the shield machine 1 is moved forward using this as a reaction force, so the detailed explanation is omitted. do.
該U型シールド機1での掘進は当然拡径部は拡
径部14についても行われ、この膨出部13で脇
溝15も連続的に形成され、拡径部14で棚状の
段差部16が形成される。 Naturally, the U-shaped shield machine 1 excavates the enlarged diameter portion 14 as well, and the side grooves 15 are also continuously formed in the enlarged portion 13, and a shelf-like stepped portion is formed in the enlarged diameter portion 14. 16 is formed.
従つて、該脇溝15内や、段差部16上にコン
クリートヒユーム管12や鋼管等を配設し、これ
を順次連結していけばよい。 Therefore, it is sufficient to arrange the concrete fume pipes 12, steel pipes, etc. in the side groove 15 or on the stepped portion 16, and connect them one after another.
このようにして、コンクリート函体6とヒユー
ム管12を同時に配設して、適宜埋戻し土を施し
ていくことができる。 In this way, the concrete box 6 and the humid pipe 12 can be placed at the same time, and backfilling can be done as appropriate.
以上述べたように本発明の地中構造物の施工
は、上面が開口し、推進ジヤツキを備えたU型シ
ールド機を該シールド機の後方に順次配設するコ
ンクリート函体を反力として掘進させるオープン
シールド工法において、コンクリート函体とヒユ
ーム管等の小地中構造物を同時施工する場合に、
全体が均一に大きいシールド機を使用しないの
で、余掘り部分が少なくてすみ、また埋戻し土の
量も少なくてよい。その結果、工期を大巾に短縮
し、またコストダウンを実現できるものである。
As described above, in the construction of the underground structure of the present invention, a U-shaped shield machine with an open top and a propulsion jack is sequentially disposed behind the shield machine, and the concrete box is used as a reaction force to excavate. In the open shield construction method, when constructing a concrete box and a small underground structure such as a humid pipe at the same time,
Since a shield machine that is uniformly large throughout is not used, there is less need for over-digging, and the amount of backfilling soil can also be reduced. As a result, the construction period can be significantly shortened and costs can be reduced.
さらに、シールド機とコンクリート函体との断
面の大きさの差もそれ程大きくならないので、両
者間での推進ジヤツキの配置個所も上下、左右で
アンバランスにならず、コンクリート函体を反力
として推進ジヤツキを伸長しながらシールド機を
押出す際に方向が狂うおそれが少なく、信頼性の
高いものとなる。 Furthermore, since the difference in cross-sectional size between the shield machine and the concrete box is not that large, the placement of the propulsion jacks between them will not be unbalanced vertically or horizontally, and the concrete box will be used as a reaction force to propel the vehicle. When pushing out the shield machine while extending the jack, there is less risk of the direction going out of order, making it highly reliable.
第1図は本発明の地中構造物の施工法の第1実
施例を示す正面図、第2図は同上第2実施例を示
す正面図、第3図〜第6図はオープンシールド工
法の一般例の各工程を示す説明図、第7図は従来
例を示す正面図である。
1……U型シールド機、1a……側壁、1b…
…底板、2……推進ジヤツキ、3……発進坑、4
……土留、5……反力壁、6……コンクリート函
体、7……バツクホー、8……埋戻し土、9……
グラウトポンプ、10……タイヤローラー、11
……路面舗装、12……ヒユーム管、13……膨
出部、14……拡径部、15……脇溝、16……
段差部、17……到達坑。
Fig. 1 is a front view showing the first embodiment of the construction method for underground structures of the present invention, Fig. 2 is a front view showing the second embodiment of the same as above, and Figs. 3 to 6 are the open shield construction method. An explanatory diagram showing each process of a general example, and FIG. 7 is a front view showing a conventional example. 1...U-type shield machine, 1a...side wall, 1b...
...Bottom plate, 2...Propulsion jack, 3...Starting shaft, 4
... Earth retention, 5 ... Reaction wall, 6 ... Concrete box, 7 ... Backfill, 8 ... Backfill soil, 9 ...
Grout pump, 10... Tire roller, 11
... Road surface pavement, 12 ... Hium tube, 13 ... Bulging part, 14 ... Expanded diameter part, 15 ... Side groove, 16 ...
Step part, 17...reaching pit.
Claims (1)
ールド機を、該シールド機の後方に順次配設する
コンクリート函体を反力として掘進させるオープ
ンシールド工法において、前記U型シールド機の
側壁又は底板を部分的に膨出させ、さらに側壁上
部を張出させて拡径部を形成し、該膨出部で脇溝
を、及び拡径部で段差部を、それぞれ同時に施工
し、ここに小地中構造物を配設することを特徴と
した地中構造物の施工法。1. In the open shield construction method in which a U-shaped shield machine with an open top and a propulsion jack is used as a reaction force to excavate concrete boxes sequentially arranged behind the shield machine, the side wall or bottom plate of the U-shaped shield machine The upper part of the side wall is made to partially bulge out, and the upper part of the side wall is made to bulge out to form an enlarged diameter section.The bulge section is used to construct a side groove, and the enlarged diameter section is used to construct a stepped section at the same time. A construction method for underground structures characterized by the installation of medium-sized structures.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP17526287A JPS6417996A (en) | 1987-07-13 | 1987-07-13 | Method of executing underground structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP17526287A JPS6417996A (en) | 1987-07-13 | 1987-07-13 | Method of executing underground structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6417996A JPS6417996A (en) | 1989-01-20 |
| JPH0428048B2 true JPH0428048B2 (en) | 1992-05-13 |
Family
ID=15993082
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP17526287A Granted JPS6417996A (en) | 1987-07-13 | 1987-07-13 | Method of executing underground structure |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6417996A (en) |
-
1987
- 1987-07-13 JP JP17526287A patent/JPS6417996A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6417996A (en) | 1989-01-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH0574677B2 (en) | ||
| KR970007379B1 (en) | Open shield method and open shield machine used therein | |
| JPH06306853A (en) | Construction of underground structure | |
| JPH0428048B2 (en) | ||
| JPH0762436B2 (en) | Open shield method | |
| JPH0428044B2 (en) | ||
| JPH0428047B2 (en) | ||
| JPS6117696A (en) | Construction of underground head | |
| JP2554507B2 (en) | Underground space construction method | |
| JPH0249896A (en) | Open shield method and machine thereof | |
| JP2004316126A (en) | Construction method of large section tunnel and shield section excavator with irregular section | |
| JP2657731B2 (en) | Open shield method and open shield machine | |
| JPH0654016B2 (en) | Underground space construction method | |
| CN215948218U (en) | A construction support frame for narrow and small space | |
| JP3302661B2 (en) | Open shield machine and construction method of underground structure using it | |
| KR970007378B1 (en) | Open shield machine | |
| JP2004316125A (en) | Construction method of large section tunnel and shield section excavator with irregular section | |
| JPH02248521A (en) | Open shield method | |
| JPH07269289A (en) | Construction method of underground structure and launching hole to be used for the method | |
| JP2963802B2 (en) | How to build an underground parking | |
| JP3333770B2 (en) | Construction method for underground structures | |
| JP2657733B2 (en) | Open shield method and open shield machine | |
| JPH0416622A (en) | Protective structure of underground structure made of concrete and construction method thereof | |
| JPH054491B2 (en) | ||
| JP2541845Y2 (en) | Concrete box for underground structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| LAPS | Cancellation because of no payment of annual fees |