JPH04289330A - Open cut method - Google Patents
Open cut methodInfo
- Publication number
- JPH04289330A JPH04289330A JP3128918A JP12891891A JPH04289330A JP H04289330 A JPH04289330 A JP H04289330A JP 3128918 A JP3128918 A JP 3128918A JP 12891891 A JP12891891 A JP 12891891A JP H04289330 A JPH04289330 A JP H04289330A
- Authority
- JP
- Japan
- Prior art keywords
- primary
- trench
- excavation
- excavated
- concrete structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title abstract description 8
- 238000009412 basement excavation Methods 0.000 claims abstract description 23
- 238000010276 construction Methods 0.000 claims description 14
- 238000010586 diagram Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
【0001】0001
【産業上の利用分野】本発明は、広い面積を開削して地
下構造物を構築する場合に使用する開削工法に関するも
のである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an excavation method used when constructing an underground structure by excavating a large area.
【0002】0002
【従来の技術】広い面積を開削すれば周囲の土砂が崩壊
してしまう。したがって、開削予定範囲の周囲には開削
を行う前に事前に地中に垂直に土留壁を構築し、相対向
する位置の土留壁に切り梁を設置し、周囲の崩壊を阻止
しながら掘削を行うのが普通である。BACKGROUND OF THE INVENTION If a wide area is excavated, the surrounding earth and sand will collapse. Therefore, before excavation is carried out, a vertical earth retaining wall is constructed in the ground around the planned excavation area, and cut beams are installed on the earth retaining wall at opposite positions, so that excavation can be carried out while preventing the surrounding area from collapsing. It is common to do so.
【0003】0003
【発明が解決しようとする問題点】前記した従来の開削
工法にあっては、特に軟弱地盤で施工するような場合に
は地盤改良する必要が有る。したがって開削する面積が
広い場合には、改良すべき地盤の面積が広大となり、き
わめて不経済なものであった。[Problems to be Solved by the Invention] In the conventional cut-and-cover construction method described above, it is necessary to improve the ground, especially when construction is performed on soft ground. Therefore, when the area to be excavated is wide, the area of ground to be improved becomes vast, which is extremely uneconomical.
【0004】0004
【本発明の目的】本発明はこの様な問題を改善するため
になされたもので、広い範囲の開削を経済的に行うこと
のできる開削工法を提供することを目的とする。OBJECTS OF THE INVENTION The present invention has been made to solve these problems, and it is an object of the present invention to provide a cut-and-cut method that can economically perform cut-and-cut work over a wide range.
【0005】[0005]
【問題点を解決するための手段】本発明は、開削すべき
予定の地域の外周に一次開削溝を構築し、一方の一次開
削溝から相対向する位置の一次開削溝に向けて水平に支
持部材を押し込むことによって地中梁を形成し、次に一
次開削溝内部にコンクリート構造物を構築し、このコン
クリート構造物に包囲され、かつ地下に水平支持部材を
押し込んだ部分を二次開削して行う、開削工法である[Means for Solving the Problems] The present invention constructs a primary trench on the outer periphery of an area to be excavated, and supports horizontally from one primary trench to the opposite primary trench. An underground beam is formed by pushing the members in, then a concrete structure is constructed inside the primary excavation trench, and a secondary excavation is carried out in the area surrounded by this concrete structure and with horizontal support members pushed underground. This is a trenchless construction method.
【
0006】[
0006
【本発明の構成】以下図面を参照しながら本発明につい
て説明する。[Structure of the present invention] The present invention will be explained below with reference to the drawings.
【0007】<イ>一次開削
開削予定の用地の周囲をまず一次開削溝1で包囲する。
この一次開削溝1の崩壊を防止するために、その周囲に
は開削前に土留壁2を構築しておく。この土留壁の構築
方法は、従来公知の各種の地下壁の施工方法を採用する
ことができる。次に一次開削溝1の底部を地盤改良6す
る。この地盤改良6面積は、全開削予定面積と比較すれ
ば少ない面積で十分である。その後に土留壁2で両側を
防護した状態でその内部の掘削を行い、開削溝1を構築
する。<A> Primary excavation First, a primary excavation groove 1 is encircled around the site where the area is to be excavated. In order to prevent the collapse of this primary excavated groove 1, an earth retaining wall 2 is constructed around it before excavation. As a method for constructing this earth retaining wall, various conventionally known construction methods for underground walls can be employed. Next, the bottom of the primary trench 1 is ground improved 6. This 6 area of ground improvement is sufficient if it is small compared to the planned area of full excavation. Thereafter, with both sides protected by earth retaining walls 2, excavation is performed inside the retaining wall 2, and an open cut trench 1 is constructed.
【0008】<ロ>地中梁の押し込み
開削すべき予定の地域の外周に一次開削溝1の構築が完
成したら、一方の一次開削溝1から、相対向する位置の
一次開削溝1に向けて水平に支持部材3を押し込むこと
によって地中梁を形成する。この水平支持部材3は、例
えば長いコンクリートのブロック、鋼材、など各種のも
のを採用できる。このブロック等を多数本用意し、順次
連結しながらジャッキ7等を使用して地中に押し込んで
行く。この押し込み作業は、推進工法など公知の各種の
工法を利用することができる。この水平支持部材3の先
端が、相対向する位置の一次開削溝に到達すれば地中梁
が完成する。この地中梁を多数本構築すれば、一次開削
溝1に包囲された区域の地中は強固に補強されたことに
なる。<B> When the construction of the primary trench 1 is completed on the outer periphery of the area where the underground beam is to be pushed and cut, from one primary trench 1 to the primary trench 1 at the opposite position. An underground beam is formed by pushing the support member 3 horizontally. This horizontal support member 3 can be made of various materials, such as a long concrete block or steel. A large number of these blocks are prepared and pushed into the ground using a jack 7 or the like while sequentially connecting them. This pushing operation can be performed using various known methods such as a thrusting method. The underground beam is completed when the tip of the horizontal support member 3 reaches the primary cut groove at the opposing position. By constructing a large number of these underground beams, the underground area surrounded by the primary trench 1 will be firmly reinforced.
【0009】<ハ>コンクリート構造物の構築次に一次
開削溝内部にコンクリート構造物4を構築する。このコ
ンクリート構造物4は、両側を土留壁2に接触する状態
で構築する。そのために一次掘削溝1は強固な構造物に
よって置き換えられることになる。<C> Construction of concrete structure Next, a concrete structure 4 is constructed inside the primary trench. This concrete structure 4 is constructed with both sides in contact with the retaining wall 2. For this purpose, the primary excavation trench 1 will be replaced by a strong structure.
【00010】<ニ>二次掘削
こうして強固なコンクリート構造物4に包囲された包囲
用地5部分を二次開削して行う。この包囲用地5の掘削
には際しては、すでに先行地中梁8が完成しているから
内部の地盤改良を行う必要がない。なお両側のコンクリ
ート構造物4の面の間に切り梁9を設けて行えばより安
全である。こうして開削した包囲用地5の内部に所定の
構造物を構築する。<D> Secondary excavation The enclosing site 5 surrounded by the strong concrete structure 4 is then excavated for a second time. When excavating this enclosing site 5, there is no need to perform internal ground improvement because the preceding underground beam 8 has already been completed. Note that it is safer if a cut beam 9 is provided between the surfaces of the concrete structures 4 on both sides. A predetermined structure is constructed inside the enclosing site 5 excavated in this way.
【00011】00011
【発明の効果】本発明は以上説明したようになるから次
のような効果を得ることができる。
<イ>推進工法などを利用して、開削に先行して地中に
切り梁を構築しておく工法である。したがって地盤改良
の面積を大幅に減らすことができ、きわめて経済的であ
る。
<ロ>一次開削の溝内に本体構造物の一部を先行して構
築してしまう工法である。そのために開削部分の周囲を
強固なコンクリート構造物で包囲することになり安全性
の高い施工を行うことができる。[Effects of the Invention] Since the present invention is as explained above, the following effects can be obtained. <A> This is a construction method in which cut beams are constructed underground prior to excavation by using the propulsion method. Therefore, the area for ground improvement can be significantly reduced, making it extremely economical. <B> This is a construction method in which a part of the main structure is constructed in advance in the trench of the primary excavation. For this reason, the excavated area is surrounded by a strong concrete structure, allowing for highly safe construction.
【図1】施工状態の説明図[Figure 1] Explanatory diagram of construction status
【図2】施工状態の説明図[Figure 2] Explanatory diagram of construction status
【図3】施工状態の説明図[Figure 3] Explanatory diagram of construction status
【図4】施工状態の説明図[Figure 4] Explanatory diagram of construction status
Claims (1)
を構築し、一方の一次開削溝から相対向する位置の一次
開削溝に向けて水平に支持部材を押し込むことによって
地中梁を形成し、次に一次開削溝内部にコンクリート構
造物を構築し、このコンクリート構造物に包囲され、か
つ地下に水平支持部材を押し込んだ部分を二次開削して
行う、開削工法Claim 1: An underground beam is constructed by constructing a primary excavation groove around the outer periphery of the area where excavation is planned, and pushing a support member horizontally from one primary excavation groove toward the primary excavation groove at the opposite position. This is an open-cut construction method in which a concrete structure is built inside the primary trench, and a secondary excavation is performed in the area surrounded by the concrete structure and with horizontal support members pushed underground.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP3128918A JP2858277B2 (en) | 1991-03-18 | 1991-03-18 | Digging method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP3128918A JP2858277B2 (en) | 1991-03-18 | 1991-03-18 | Digging method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH04289330A true JPH04289330A (en) | 1992-10-14 |
| JP2858277B2 JP2858277B2 (en) | 1999-02-17 |
Family
ID=14996596
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP3128918A Expired - Lifetime JP2858277B2 (en) | 1991-03-18 | 1991-03-18 | Digging method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2858277B2 (en) |
-
1991
- 1991-03-18 JP JP3128918A patent/JP2858277B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JP2858277B2 (en) | 1999-02-17 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103939105A (en) | Construction method and structure for laying construction shaft above underground engineering | |
| JP2000352296A (en) | Method o constructing passage just under underground structure | |
| JPH04213695A (en) | Segment for shield tunnel | |
| JP3125171B2 (en) | How to build underground structures | |
| JP3135188B2 (en) | Construction method of underground cavity | |
| ES2039324T1 (en) | GUIDING PROCEDURE FOR THE EXCAVATION TOOL USED FOR THE CONSTRUCTION OF A MOLDED WALL INSIDE THE FLOOR, AND EXCAVATION TOOL FOR THE CONDUCT OF THIS PROCEDURE. | |
| JP2858277B2 (en) | Digging method | |
| JP2942874B2 (en) | How to join tunnels | |
| CN117432433A (en) | Urban rail transit engineering, entrance and exit structure thereof and construction method | |
| KR100322845B1 (en) | tubular roof tunnel construction method | |
| JP2656892B2 (en) | Underground structure construction method and continuous underground wall construction method | |
| JPH02300422A (en) | Construction of underground structure | |
| JPH0396600A (en) | Constructing method for building large space in large-depth underground section | |
| KR101671806B1 (en) | Construction method for tunneling | |
| JPS62220616A (en) | Construction work for underground space | |
| JP3865468B2 (en) | How to build a tunnel | |
| CN114657998B (en) | Subway station deep foundation pit retaining structure and construction method thereof | |
| JP3027685B2 (en) | Earth retaining wall and construction method | |
| JP2846248B2 (en) | Earth retaining wall and construction method | |
| JPH0381500A (en) | Method for constructing big space for building in great depth underground | |
| JPS60226917A (en) | Underground excavation method | |
| KR900007883B1 (en) | Underground tunnel construction method | |
| JPH09328987A (en) | Tunnel and construction method | |
| JPS60133117A (en) | How to construct a joint part of a continuous underground wall | |
| CN115075829A (en) | Novel ultra-shallow buried underground excavation construction method for primary support and semi-closed support in complex environment |