JPH0432169B2 - - Google Patents

Info

Publication number
JPH0432169B2
JPH0432169B2 JP11655787A JP11655787A JPH0432169B2 JP H0432169 B2 JPH0432169 B2 JP H0432169B2 JP 11655787 A JP11655787 A JP 11655787A JP 11655787 A JP11655787 A JP 11655787A JP H0432169 B2 JPH0432169 B2 JP H0432169B2
Authority
JP
Japan
Prior art keywords
groove
stabilizing liquid
guide hole
concrete
excavated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP11655787A
Other languages
Japanese (ja)
Other versions
JPS63284316A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP11655787A priority Critical patent/JPS63284316A/en
Publication of JPS63284316A publication Critical patent/JPS63284316A/en
Publication of JPH0432169B2 publication Critical patent/JPH0432169B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、上層部が崩壊しやすい地層で、下
層部がクラツク等を有し安定液を使用できない地
層を二段階に掘削して連続地中壁を構築する際
の、連続地中壁のジヨイント部の施工方法に関す
る。
[Detailed Description of the Invention] [Field of Industrial Application] This invention aims to excavate in two stages a stratum in which the upper layer is prone to collapse and the lower layer has cracks, etc., making it impossible to use a stabilizing liquid. This invention relates to a construction method for a joint part of a continuous underground wall when constructing an inner wall.

〔従来の技術〕[Conventional technology]

地中に止水壁、土留壁あるいは構造壁として鉄
筋または鉄骨を挿入したコンクリート等の連続壁
を泥水工法によつて施工することは、打込み式の
矢板壁などの代わりに公害が少ない工法として建
設工事において一般に多く行われている。
Constructing continuous walls such as concrete with reinforcing bars or steel frames inserted into the ground as water-stop walls, earth retaining walls, or structural walls using the muddy water construction method is a construction method that causes less pollution as an alternative to driving-in sheet pile walls. This is commonly done in construction.

これは、泥水を掘削孔内に満たして掘削壁面の
崩落を防ぎながら地盤を例えば断面小判形に所要
深さに掘削し、しかる後に泥水を置換するように
コンクリートや鉄筋コンクリートもしくはアスフ
アルトや粘土などの塑性材料を打設して単位壁体
(エレメント)を築造し、さらにこの工法を繰返
すことによつてエレメントの連続した連続地中壁
を構築するものである。
This is done by filling the excavation hole with muddy water to prevent the excavated wall from collapsing while excavating the ground to the required depth, for example, into an oval cross-section. By pouring materials to construct unit walls (elements) and repeating this construction method, a continuous underground wall with continuous elements is constructed.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

しかしながら、このような従来の連続地中壁の
構築方法にあつては、構築しようとする地盤が単
に崩壊しやすい地層等である場合は適用できる
が、この地層に続く下層部がクラツク等を有する
ために投入した安定液が急激に地中に流出する逸
水現象が生じるような地層である場合には、従来
の方法を適用するのは困難であるという問題点が
あつた。
However, such conventional methods for constructing continuous underground walls can be applied when the ground to be constructed is simply a stratum that easily collapses, but if the lower layer following this stratum has cracks, etc. There was a problem in that it was difficult to apply conventional methods in geological formations where a water loss phenomenon occurs in which the stabilizing solution poured into the ground suddenly flows out into the ground.

この発明はこのような従来の問題点にかんがみ
てなされたものであつて、安定液を使用できない
下層部の溝をドライで掘削してコンクリートを打
設した後に、インタロツキングパイプ引抜き後の
ガイドホールを止水部材で閉塞する施工法とする
ことにより、上記問題点を解決することを目的と
している。
This invention was made in view of the problems of the conventional art, and it is possible to install a guide after pulling out an interlocking pipe after dry excavating a groove in the lower layer where stabilizing liquid cannot be used and pouring concrete. The purpose is to solve the above problems by using a construction method that closes the hole with a water-stopping member.

〔問題点を解決するための手段〕[Means for solving problems]

この発明は、崩壊しやすい上層部とクラツク等
を有し安定液が使用できない下層部を有する地層
中に連続地中壁を構築するにあたつて、該地中壁
構築予定位置の前記上層部に安定液を使用して壁
面の崩落を防止しつつガイドホール掘削及び中抜
き掘削を行つて上部溝を形成し、次いで該上部溝
下方の下層部に安定液を使用することなくガイド
ホール掘削及び中抜き掘削を行つて下部溝を形成
し、この溝と前記上部溝とよりなる深溝の側端に
インタロツキングパイプを設置して該溝内にコン
クリートを打設し、このコンクリートの硬化後、
該インタロツキングパイプを引抜き、さらに引抜
いた跡であるガイドホールのコンクリート天端付
近に下層部への安定液の流入を阻止するための止
水部材を設置し、しかる後に該止水部材の上方の
ガイドホール部に安定液を満たして次のエレメン
ト用の上部溝を掘削する連続地中壁のジヨイント
部の施工方法を提供するものである。
When constructing a continuous underground wall in a stratum that has an upper layer that is easy to collapse and a lower layer that has cracks or the like and cannot be used with a stabilizing liquid, the above-mentioned upper layer at the planned construction location of the underground wall is A stabilizing liquid is used to prevent the wall from collapsing while a guide hole is excavated and a hollow is excavated to form an upper groove, and then a guide hole is excavated and hollowed out in the lower layer below the upper groove without using a stabilizing liquid. A hollow excavation is performed to form a lower groove, an interlocking pipe is installed at the side end of a deep groove formed by this groove and the upper groove, concrete is poured into the groove, and after this concrete hardens,
After pulling out the interlocking pipe, a water stop member is installed near the concrete top of the guide hole where the interlocking pipe was pulled out to prevent the stabilizing liquid from flowing into the lower layer, and then above the water stop member. The present invention provides a construction method for a joint part of a continuous underground wall, in which the guide hole part is filled with stabilizing liquid and an upper groove for the next element is excavated.

〔作用〕[Effect]

崩壊しやすい上層部には安定液を使用して壁面
の崩壊を防止しつつガイドホール掘削及び中抜き
掘削を行つて上部溝を形成し、この溝内の安定液
を除去する。次にこの溝の下方の下層部には安定
液を使用しないドライ状態ガイドホール掘削及び
中抜き掘削を行うと、前記上部溝に上下に連続し
て下部溝が形成される。そしてこの上下連続した
深溝の側端にインタロツキングパイプを設置した
後、下部溝内にコンクリートを打設し、コンクリ
ート硬化後、コンクリート上の上部溝に砂を埋戻
して先行エレメントが築造される。しかる後に前
記インタロツキングパイプを引抜き、引抜いた跡
に生じるガイドホールのコンクリート天端付近に
下層部への安定液の流入を阻止するための止水部
材を設置する。次いで、この止水部材上方のガイ
ドホール部に安定液を満たすと、このガイドホー
ル部は次のエレメント用上部溝を形成するための
ガイドホールとして準備されたジヨイント部とな
る。
A stabilizing liquid is used in the upper layer, which is likely to collapse, to prevent the wall from collapsing, and a guide hole is excavated and a hollow is excavated to form an upper groove, and the stabilizing liquid in this groove is removed. Next, by performing dry guide hole drilling and hollow drilling without using a stabilizing liquid in the lower layer below this groove, a lower groove is formed vertically continuous with the upper groove. After installing interlocking pipes at the side ends of this continuous deep groove, concrete is placed in the lower groove, and after the concrete hardens, the upper groove above the concrete is backfilled with sand to construct the preceding element. . Thereafter, the interlocking pipe is pulled out, and a water-stopping member is installed near the concrete top of the guide hole created at the site where the interlocking pipe was pulled out to prevent the stabilizing liquid from flowing into the lower layer. Next, when the guide hole portion above the water stopper member is filled with a stabilizing liquid, this guide hole portion becomes a joint portion prepared as a guide hole for forming the next upper groove for the element.

〔実施例〕〔Example〕

以下、この発明を図面に基づいて説明する。第
1〜16図は本発明の一実施例を工程順に示した
図で、同図aは上面図、同図bは縦断面図であ
る。第17図は地中壁を構築する地山の断面図、
第18,19図は第14〜16図bにおける止水
部材の詳細図である。
The present invention will be explained below based on the drawings. 1 to 16 are diagrams showing an embodiment of the present invention in the order of steps, in which figure a is a top view and figure b is a longitudinal cross-sectional view. Figure 17 is a cross-sectional view of the ground on which the underground wall will be constructed.
18 and 19 are detailed views of the water stop member in FIGS. 14 to 16b.

図において、E1は崩壊しやすい上層部の地層、
E2はクラツク等を有する下層部の地層、E3は不
透水層を示す。1は地山を鉛直方向に掘削してガ
イドホールを形成するアースオーガ、2は隣り合
うガイドホール間の土を掘削するいわゆる中抜き
掘削を行うためのクラブバケツトであつて、これ
らの掘削機は安定液を使用できない下層部E2
溝掘削にも使用できる機種である。
In the figure, E 1 is the upper stratum that is prone to collapse;
E 2 indicates the lower stratum with cracks, etc., and E 3 indicates the impermeable layer. 1 is an earth auger that excavates the ground vertically to form guide holes; 2 is a club bucket for excavating the soil between adjacent guide holes, so-called hollow excavation; these excavators This is a model that can be used for trench excavation in the lower part E2 where stabilizing liquid cannot be used.

本実施例では上層部E1の溝M1の深さh1≒10m、
下層部E2の溝深さh2≒30m程度の場合の施工例に
つき説明するが、これに限定するものではない。
In this embodiment, the depth h 1 of the groove M 1 in the upper layer E 1 is approximately 10 m,
A construction example will be described in which the groove depth h 2 of the lower layer E 2 is approximately 30 m, but the present invention is not limited thereto.

先ず、地層E1にアースオーガ1を用いて深さh1
にガイドホール3,4を、安定液Qを供給しつつ
掘削する(第1,2図)。安定液Qは通常、ベン
トナイトやアタパルジヤイト等の粘土鉱物や
CMC等の安定剤を水や海水等に撹拌して溶解し
た泥水状のものであつて、掘削中に壁面の崩落を
防止するために使用されるものである。
First, use earth auger 1 to dig into stratum E 1 to a depth of h 1.
Guide holes 3 and 4 are drilled while supplying stabilizing liquid Q (Figs. 1 and 2). Stabilizer Q usually contains clay minerals such as bentonite and attapulgite.
It is a slurry made by stirring and dissolving stabilizers such as CMC in water or seawater, and is used to prevent walls from collapsing during excavation.

ガイドホール3,4の掘削が完了すると、この
両ガイドホール間の部分E11を安定液Qを満たし
た状態で、クラブバケツト2により中抜き掘削
(第3図)して上部溝M1を完成する(第4図)。
そして、この溝M1が完成したらこの溝M1の楕円
形断面とほぼ同形の断面を有するケーシング5を
この溝5内に建込み(第5図)、ポンプ6により
溝M1すなわちケーシング5内の泥水(安定液)
を揚水して除去する(第6図)。なおケーシング
5の外周と地山との間の隙間には泥水を挿入して
固化させるか、低強度モルタル、砂等を充填し、
後工程においてケーシング5を撤去した際に溝壁
面が崩落するのを防止する。
When the guide holes 3 and 4 have been excavated, the part E11 between the two guide holes is filled with the stabilizing liquid Q, and the upper groove M1 is hollowed out using the club bucket 2 (Fig. 3). Complete (Figure 4).
When this groove M 1 is completed, a casing 5 having a cross section that is almost the same as the oval cross section of this groove M 1 is built into this groove 5 (Fig. 5), and a pump 6 is used to fill the inside of groove M 1 , that is, the casing 5. muddy water (stabilizing liquid)
water is pumped up and removed (Figure 6). Note that the gap between the outer periphery of the casing 5 and the ground is filled with muddy water and solidified, or with low-strength mortar, sand, etc.
To prevent the groove wall surface from collapsing when the casing 5 is removed in a post-process.

次に、アースオーガ1よりやや直径の小さい、
ケーシング5内へ挿通できるアースオーガ11に
より、上部溝M1の底面からクラツク等を有する
下層部E2内にガイドホール31,41を安定液
Qを使用せずに掘削する。このときのガイドホー
ルの深さは地層E2を貫通し、不透水層E3内に達
する深さh3である(第7,8図)。次いでガイド
ホール31,41間の部分E21をクラブバケツト
2により中抜き掘削して(第9図)、下部溝M2
完成する(第10図)。その結果、上部溝M1と下
部溝M2とは上下方向に連続した一つの深溝M3
形成する。
Next, the diameter is slightly smaller than Earth Auger 1,
Guide holes 31, 41 are excavated from the bottom of the upper groove M1 into the lower layer E2 having cracks, etc., without using the stabilizing liquid Q, by means of an earth auger 11 that can be inserted into the casing 5. The depth of the guide hole at this time is a depth h3 that penetrates the stratum E2 and reaches the impermeable layer E3 (Figs. 7 and 8). Next, the portion E21 between the guide holes 31 and 41 is hollowed out using the club bucket 2 (FIG. 9) to complete the lower groove M2 (FIG. 10). As a result, the upper groove M 1 and the lower groove M 2 form one deep groove M 3 that is continuous in the vertical direction.

次に、この深溝M3の側端に、溝底を達する長
さのインタロツキングパイプ7とこのパイプ7に
近接し且つ溝M1を縦方向ち仕切る深さh1の仕切
板8とを設置し(第11図)、次いでトレミー管
9等を使用して溝M2内へコンクリートCを流込
み(第12図)、h2の深さまで充填して打設する
(第13図)。従つて仕切板8の下端はコンクリー
トCに達している。
Next, at the side ends of this deep groove M3 , an interlocking pipe 7 with a length reaching the groove bottom and a partition plate 8 with a depth h1 that is close to this pipe 7 and partitions the groove M1 in the vertical direction are installed. (Fig. 11), and then pour concrete C into the groove M2 using a tremie pipe 9 (Fig. 12), filling it to a depth of h2 and pouring it (Fig. 13). Therefore, the lower end of the partition plate 8 reaches the concrete C.

次に、コンクリートCが硬化したらインタロツ
キングパイプ7を引抜き、その跡に画成される孔
42のコンクリートC天端付近に止水部材10を
設置して孔42を閉塞し、泥水がこの孔42内へ
流入しないようにする(第14図)。止水部材1
0は第18図に示すように、ゴム等の弾性を有す
る閉塞袋101とこれを取付けた円板102及び
この円板中央に開口する注入管103より成り、
この閉塞袋101内へは水又は空気等を圧入する
ことにより孔42の内壁に圧接して円板102上
方からの泥水の流入を防止するようになつてい
る。またより厳密に止水を行う場合は、円板10
2上部に若干の泥水Qを入れてこれを固化させ、
しかる後に孔42の円板102上空間へ安定液Q
を満たすとともに、コンクリートC上部の溝M11
内へ砂Sを埋戻す。
Next, when the concrete C has hardened, the interlocking pipe 7 is pulled out, and the water stop member 10 is installed near the top of the concrete C of the hole 42 defined in its place to block the hole 42, and the muddy water flows through the hole. 42 (Fig. 14). Water stop member 1
0, as shown in FIG. 18, consists of a closure bag 101 made of elasticity such as rubber, a disc 102 to which it is attached, and an injection tube 103 opening at the center of the disc.
Water, air, or the like is pressurized into the closed bag 101 so that it comes into pressure contact with the inner wall of the hole 42 to prevent muddy water from flowing in from above the disk 102. In addition, when water is to be stopped more strictly, the disc 10
2 Add some muddy water Q to the top and solidify it.
After that, the stabilizing liquid Q is poured into the space above the disk 102 in the hole 42.
and groove M 11 on top of concrete C.
Backfill with sand S.

かくして、先行エレメント(単位地中壁)が完
成するとともに、孔42の上方部分42aは次の
エレメント築造用上部溝のガイドホールとして準
備されたことになる。すなわち、第16図に示す
ように、次のガイドホール43を掘削し、E12
を中抜き掘削することにより次のエレメント用上
部溝が形成され、ガイドホール42,42aは先
行エレメントと次のエレメントとのジヨイント部
となる。
In this way, the preceding element (unit underground wall) is completed, and the upper portion 42a of the hole 42 is prepared as a guide hole for the upper groove for constructing the next element. That is, as shown in FIG. 16, the next guide hole 43 is drilled and the E12 section is hollowed out to form the upper groove for the next element, and the guide holes 42, 42a are formed between the preceding element and the next element. It becomes the joint part with the element.

なお、第19図は他の止水部材を示したもの
で、胴部にはテーパねじが設けられていて、この
胴部を孔42内へ螺入することにより止水を行う
ようになつている。
In addition, FIG. 19 shows another water-stopping member, in which a tapered screw is provided on the body, and water is stopped by screwing this body into the hole 42. There is.

〔発明の効果〕〔Effect of the invention〕

以上説明したように、本発明によれば、先行エ
レメント用のガイドホールのコンクリート天端付
近に、下層部に安定液が流れ込まないための止水
部材に設置したジヨイント部の施工方法としたた
め、上層部の崩壊しやすい地層は安定液を用いて
掘削し、クラツク等を有し逸水現象を生じる地層
には安定液を使用せずに施工できるという効果が
得られる。
As explained above, according to the present invention, the joint part is installed near the concrete top of the guide hole for the preceding element as a water-stopping member to prevent the stabilizing liquid from flowing into the lower layer. The advantage of this method is that a stabilizing liquid can be used to excavate strata that are prone to collapse, while excavation can be carried out without using a stabilizing liquid for strata that have cracks or the like and can cause water loss.

【図面の簡単な説明】[Brief explanation of drawings]

第1〜16図は本発明に係る実施例を工程順に
示した説明図で、同図aは上面図、同図bは縦断
面図、第17図は地中壁を構築する地山の断面
図、第18,19図は第14〜16図bにおける
止水部材の詳細図である。 3,4,31,41,42,42a,43……
ガイドホール、5……ケーシング、7……インタ
ロツキングパイプ、10……止水部材。E1,E11
……上層部の地層、E2,E21……下層部の地層、
M1,M11……上部溝、M2……下部溝、M3……深
溝、Q……安定液、C……コンクリート。
Figures 1 to 16 are explanatory diagrams showing the embodiment of the present invention in the order of steps, in which figure a is a top view, figure b is a vertical cross-sectional view, and figure 17 is a cross-section of the ground for constructing an underground wall. Figures 18 and 19 are detailed views of the water stop member in Figures 14 to 16b. 3, 4, 31, 41, 42, 42a, 43...
Guide hole, 5...Casing, 7...Interlocking pipe, 10...Water stop member. E1 , E11
... Upper strata, E 2 , E 21 ... Lower strata,
M1 , M11 ...Top groove, M2 ...Bottom groove, M3 ...Deep groove, Q...Stabilizing liquid, C...Concrete.

Claims (1)

【特許請求の範囲】[Claims] 1 崩壊しやすい上層部のクラツク等を有し安定
液の使用できない下層部を有する地層中に連続地
中壁を構築するにあたつて、該地中壁構築予定位
置の前記上層部に安定液を使用して壁面の崩落を
防止しつつガイドホール掘削及び中抜き掘削を行
つて上部溝を形成し、この溝の完成後、該溝内に
ケーシングを建込んで安定液を揚水し、次いで該
上部溝下方の下層部に安定液を使用することなく
ガイドホール掘削及び中抜き掘削を行つて下部溝
を形成し、この溝と前記上部溝とよりなる深溝の
側端にインタロツキングパイプを設置した後、該
溝内にコンクリートを打設し、このコンクリート
の硬化後、該インタロツキングパイプを引抜き、
さらに引抜いた跡であるガイドホールのコンクリ
ート天端付近に下層部への安定液の流入を阻止す
るための止水部材を設置し、しかる後に該止水部
材の上方のガイドホール部に安定液を満たして次
のエレメント用の上部溝を掘削することを特徴と
する連続地中壁のジヨイント部の施工方法。
1. When constructing a continuous underground wall in a stratum that has a lower layer that cannot be used with a stabilizing liquid due to cracks in the upper layer that are prone to collapse, a stabilizing liquid is applied to the upper layer of the planned construction site of the underground wall. While preventing the wall from collapsing, a guide hole is excavated and a hollow is excavated to form the upper groove. After this groove is completed, a casing is built in the groove to pump up the stabilizing liquid. A lower groove is formed by drilling a guide hole and hollowing out the lower part of the lower part of the upper groove without using a stabilizing liquid, and an interlocking pipe is installed at the side end of the deep groove formed by this groove and the upper groove. After that, concrete is poured into the groove, and after the concrete has hardened, the interlocking pipe is pulled out.
Furthermore, a water stop member was installed near the concrete top of the guide hole where it was pulled out to prevent the stabilizing liquid from flowing into the lower layer, and then the stabilizing liquid was installed in the guide hole above the water stop member. A construction method for a joint part of a continuous underground wall, characterized by filling the joint and excavating an upper trench for the next element.
JP11655787A 1987-05-13 1987-05-13 Construction of joint of continuous underground wall Granted JPS63284316A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11655787A JPS63284316A (en) 1987-05-13 1987-05-13 Construction of joint of continuous underground wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11655787A JPS63284316A (en) 1987-05-13 1987-05-13 Construction of joint of continuous underground wall

Publications (2)

Publication Number Publication Date
JPS63284316A JPS63284316A (en) 1988-11-21
JPH0432169B2 true JPH0432169B2 (en) 1992-05-28

Family

ID=14690062

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11655787A Granted JPS63284316A (en) 1987-05-13 1987-05-13 Construction of joint of continuous underground wall

Country Status (1)

Country Link
JP (1) JPS63284316A (en)

Also Published As

Publication number Publication date
JPS63284316A (en) 1988-11-21

Similar Documents

Publication Publication Date Title
US3638433A (en) Method and apparatus for forming structures in the ground
JP2022502586A (en) Grouting consolidation method of ready-made piles guided by all-casing excavation, and the ready-made piles
CN108643214B (en) A kind of backfilled mixed soil composite foundation structure and its construction method
CN110896644B (en) Grouting consolidation method for full-casing drilling guide precast pile
KR101045625B1 (en) Underground continuous wall construction method using CIP method
KR101021915B1 (en) Order temporary construction method for earthquake construction
KR200362565Y1 (en) Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof
US20220356663A1 (en) Load Transfer System
CN205742191U (en) A kind of piling wall constructing device continuously
JP4485006B2 (en) Construction method for underground structures
JP3760343B2 (en) Drilling bottom stabilization method and construction method of underground building
CN219908895U (en) A kind of while drilling and pipe bag pile for bead cave and its piling equipment
CN119332672A (en) A high-bearing-capacity anchor static pressure steel pipe pile and grouting method thereof
JPS59126821A (en) Erection work of foundation pile
KR101021913B1 (en) Order temporary construction method for earthquake construction
JPS583091B2 (en) Construction method for underground column walls
KR100654973B1 (en) Block structure and construction method using precast concrete pile
JPH0432169B2 (en)
WO2009139510A1 (en) Construction method for continuous cut-off wall using overlap casing
JP4872561B2 (en) Construction method of ready-made piles
CN206570822U (en) A kind of slope retaining structure being applied in Mud Ground
JPH0325121A (en) Sinking of pile in inner drilling pile method
CN218027625U (en) Outer-pouring backfill rotary-digging pile hole pile casing structure
JPH0432168B2 (en)
KR101711393B1 (en) A method of construction for retaining wall