JPH04360986A - Underground joining method for shield machine - Google Patents
Underground joining method for shield machineInfo
- Publication number
- JPH04360986A JPH04360986A JP13424691A JP13424691A JPH04360986A JP H04360986 A JPH04360986 A JP H04360986A JP 13424691 A JP13424691 A JP 13424691A JP 13424691 A JP13424691 A JP 13424691A JP H04360986 A JPH04360986 A JP H04360986A
- Authority
- JP
- Japan
- Prior art keywords
- diameter
- joint
- joining
- shield machine
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【0001】0001
【産業上の利用分野】この発明は、地表部からのアクセ
スが困難な大深度の長距離地下鉄や道路、共同溝などを
構築するシールド工法、又は海底区間が長く、しかも海
面の占有が不可能なルートによる海底横断トンネルなど
を構築する長距離シールド工法の施工において実施され
る、シールド機同士の地中における水平方向の接合方法
に関する。[Industrial Application Field] This invention is applicable to shield construction methods for constructing long-distance subways, roads, public ditches, etc. at deep depths that are difficult to access from the surface, or where the seabed section is long and it is impossible to occupy the sea surface. This paper relates to a method for horizontally joining shield machines underground, which is carried out in the construction of long-distance shield construction methods for constructing undersea tunnels, etc., using long routes.
【0002】0002
【従来の技術】従来、シールド機の地中接合の方法、技
術は、既にいくつか公知に属する(例えば特開昭62−
288298号、特開昭63−167895号公報など
を参照)。シールド機の地中接合方法を精度良く、経済
的に実施できれば、立坑を省略でき、長距離シールド工
法の施工を楽に経済的に行なえる。また、長距離の海底
横断シールド工法も、海底下の地中接合方法を実施する
ことによって安全に、経済的に施工できる。このような
次第で、現在、シールド機の地中接合に関する技術的ニ
ーズは増加しており、研究が進められている。[Prior Art] Conventionally, several methods and techniques for underground bonding of shield machines have already been known (for example, Japanese Patent Application Laid-Open No.
288298, JP-A-63-167895, etc.). If the underground joining method using a shield machine can be implemented accurately and economically, vertical shafts can be omitted and long-distance shield construction can be carried out easily and economically. In addition, long-distance trans-seafloor shield construction can be carried out safely and economically by using the sub-seafloor underground bonding method. As a result, technical needs regarding underground bonding of shield machines are increasing, and research is currently underway.
【0003】0003
【本発明が解決しようとする課題】シールド機の地中接
合方法に関しては、現在のところ、凍結工法併用の地中
接合方法が唯一信頼性のある実用化技術と考えられてい
る。しかし、この地中接合方法は地盤の凍結に長時間を
要し、凍結費用も高価なので、工期、コストの面からみ
て一般的に利用できる技術とは言い難い。[Problems to be Solved by the Invention] Regarding the underground joining method for shield machines, the underground joining method combined with the freezing method is currently considered to be the only reliable practical technology. However, this underground bonding method requires a long time to freeze the ground, and the freezing costs are high, so it is difficult to say that it is a technology that can be used generally in terms of construction period and cost.
【0004】その他の上記特開昭62−288298号
、特開昭63−167895号公報記載の接合方法を縦
覧しても、前記凍結工法併用の地中接合方法にとって代
るだけの確立された技術は未だ完成されていないので、
この点が本発明の解決すべき課題になっている。[0004] Even if the other joining methods described in the above-mentioned JP-A-62-288298 and JP-A-63-167895 are examined, they are established techniques that can replace the above-mentioned underground joining method combined with the freezing method. is not yet completed, so
This point is a problem to be solved by the present invention.
【0005】[0005]
【課題を解決するための手段】上記従来技術の課題を解
決するための手段として、第1の発明に係るシールド機
の地中接合方法は、図面に実施例を示したとおり、地中
で接合される2台のシールド機は、一方が拡径ビット3
を備えた拡径接合用シールド機1で、他方は拡径ビット
を有しない通常型シールド機2とし、まず拡径接合用シ
ールド機1が接合計画線4の手前数mの位置から拡径ビ
ット3による拡径の前進掘削を行ないながらそのまま接
合計画線4の位置を超えて数mまで拡径掘削を行なう。
次に前記拡径掘削部5に泥水と置換しながら水中コンク
リート6を打設する。前記コンクリート6が強度を発現
した後に、他側から通常型シールド機2により前記コン
クリート塊6を接合計画線4の位置まで通常径の前進掘
削を行ないシールド機同士の接合を達成することを特徴
とする(図1)。[Means for Solving the Problems] As a means for solving the problems of the prior art described above, a method for underground joining of a shield machine according to a first invention is provided, as an example shown in the drawings. Two shield machines are used, one of which has diameter expansion bit 3.
The shield machine 1 for diameter expansion welding is equipped with a diameter expansion welding machine 1, and the other is a regular shield machine 2 that does not have a diameter expansion bit. While carrying out forward excavation to expand the diameter according to step 3, the excavation to expand the diameter is continued to several meters beyond the position of the joint planned line 4. Next, underwater concrete 6 is placed in the enlarged diameter excavation section 5 while replacing muddy water. After the concrete 6 has developed strength, the concrete mass 6 is excavated from the other side by a conventional shielding machine 2 to a position of the planned joining line 4, and the concrete mass 6 is excavated forward with a normal diameter to achieve joining between the shielding machines. (Figure 1).
【0006】第2の発明は、やはり一方が拡径接合用シ
ールド機1で、他方が通常型シールド機2とし、前記拡
径接合用シールド機1が接合計画線4を数m超えた位置
から拡径の後退掘削を行ない、かくして形成した拡径掘
削部5に打設され強度を発現したコンクリート塊6を、
他側から通常型シールド機2が通常径による前進掘削を
接合計画線4の位置まで行ない地中接合を達成する方法
である(図2)。[0006] In the second invention, one is a shielding machine 1 for expanding the diameter and the other is a regular type shielding machine 2, and the shielding machine 1 for expanding the diameter is connected from a position several meters beyond the planned joining line 4. Reverse excavation with an enlarged diameter is performed, and the concrete mass 6 which has developed strength by being cast in the enlarged diameter excavation portion 5 thus formed is
In this method, the conventional shield machine 2 performs forward excavation with a normal diameter from the other side to the position of the planned joint line 4 to achieve the underground joint (FIG. 2).
【0007】第3の発明は、2台とも拡径接合用シール
ド機1A、1Bとし、一方の拡径接合用シールド機1A
が接合計画線4の手前数mの位置から同接合計画線4を
超えて数mまで前進の拡径の前進掘削を行ない、接合計
画線4の位置まで後退した後にその拡径掘削部5へコン
クリート打設を行ない、次に他側の拡径接合用シールド
機1Bがやはり拡径ビット3による拡径の前進掘削を接
合計画線4の位置まで行ない、そのままの位置で拡径掘
削部5にコンクリート6を打設して地中接合を達成する
方法である(図3)。[0007] In the third invention, both shield machines 1A and 1B are used for expanding diameter joining, and one of the shielding machines 1A and 1B is used for expanding diameter joining.
performs forward diameter-expanding excavation from a position several meters in front of the joint planned line 4 to several meters beyond the joint planned line 4, and after retreating to the position of the joint planned line 4, goes to the expanded diameter excavation portion 5. Concrete is poured, and then the shield machine 1B for diameter expansion and joining on the other side performs forward excavation of the diameter expansion using the diameter expansion bit 3 up to the position of the joint planned line 4, and continues at that position to the diameter expansion excavation part 5. This method achieves underground bonding by placing concrete 6 (Figure 3).
【0008】第4、5の発明は、やはり2台とも拡径接
合用シールド機1A、1Bとし、一方の拡径接合用シー
ルド機1Aが接合計画線4の位置から手前数mまで拡径
の後退掘削を行ない、その拡径掘削部5に水中コンクリ
ート6の打設を行ない、そのコンクリート6が強度を発
現した後に、当該コンクリート塊6を再び接合計画線4
の位置まで通常径の前進掘削をする段階までは共通する
。つづいて他方の拡径接合用シールド機1Bが拡径ビッ
ト3による拡径の前進掘削を接合計画線4の位置まで行
ない、その位置でコンクリート6を打設するのが第4の
発明(図4)であり、逆に接合計画線4の位置から拡径
の後退掘削を行ない、その拡径掘削部5にコンクリート
6を打設して地中接合を達成する方法が第5の発明であ
る。[0008] In the fourth and fifth inventions, both shield machines 1A and 1B are used for diameter expansion and welding, and one of the shield machines for diameter expansion and welding 1A expands the diameter from the position of the welding plan line 4 to several meters in front. Backward excavation is performed, and underwater concrete 6 is placed in the enlarged diameter excavation portion 5. After the concrete 6 has developed strength, the concrete mass 6 is rejoined along the planned line 4.
The process is common up to the stage of forward excavation of a normal diameter up to the position. Subsequently, the other shield machine 1B for expanding the diameter joint performs forward excavation of the diameter expansion with the diameter expanding bit 3 to the position of the joint planned line 4, and pours concrete 6 at that position (Fig. 4). ), and the fifth invention is a method of performing backward excavation with an enlarged diameter from the position of the joint planned line 4, and placing concrete 6 in the enlarged diameter excavated portion 5 to achieve underground joint.
【0009】[0009]
【作用】拡径ビット3を備えた拡径接合用シールド機1
又は1Aと1Bがそれぞれ地中で出会う接合計画線4の
位置に、通常掘削径よりも半径にして1〜2m程度大き
い拡径掘削をして、拡径掘削部5を形成し、そこに打設
された水中コンクリートのコンクリート塊6をくり抜い
た形で2台のシールド機の地中接合を達成するから、く
り抜かれたコンクリート塊6の筒状体が地中接合部の補
強殻及び止水壁として働く。また、地中で出会う2台の
シールド機が相互に多少位置ずれを生じても、前記拡径
掘削部5に打設されたコンクリート塊6の層厚の範囲で
前記位置ずれを安全に吸収可能である。[Function] Diameter expansion joining shield machine 1 equipped with diameter expansion bit 3
Alternatively, at the position of the joint planned line 4 where 1A and 1B meet underground, expand the diameter by about 1 to 2 m larger radius than the normal excavation diameter to form an expanded diameter excavation part 5, and then drill there. Since the underground connection of the two shield machines is achieved by hollowing out the concrete block 6 of the installed underwater concrete, the hollowed-out cylindrical body of the concrete block 6 serves as a reinforcing shell and a water-stop wall for the underground joint. Work as. Furthermore, even if the two shield machines that meet underground are slightly misaligned with each other, the misalignment can be safely absorbed within the layer thickness of the concrete block 6 cast in the enlarged diameter excavation section 5. It is.
【0010】0010
【実施例】次に、図示した本発明の実施例を説明する。
図1Aは地中で水平に接合される2台のシールド機1と
2が接合計画線4の近辺に接近した段階を示している。
2台のシールド機は共に泥水加圧式シールド機であるが
、図中右側のシールド機1は、カッターヘッド部の外周
部に、通報掘削径よりも半径にして1m〜2mも大きい
拡径掘削を可能にする拡径ビット3を備えた拡径接合用
シールド機である。同左側のシールド機2は、前記拡径
ビットを有さない通常型シールド機である。図1Aにお
いて、右側の拡径接合用シールド機1は、接合計画線4
の手前2mの位置から、拡径ビット3を使用した拡径の
前進掘削を開始した段階を示している。その間、左側の
通常型シールド機2は、接合計画線4の手前数mの位置
に到達して待機する。Embodiments Next, illustrated embodiments of the present invention will be described. FIG. 1A shows a stage in which two shield machines 1 and 2, which are to be joined horizontally underground, have approached the vicinity of a joint planned line 4. Both shield machines are mud water pressurization type shield machines, but the shield machine 1 on the right side of the figure excavates an enlarged diameter that is 1 m to 2 m larger in radius than the reported excavation diameter on the outer periphery of the cutter head. This is a shield machine for diameter expansion joining, which is equipped with a diameter expansion bit 3 that enables this. The shield machine 2 on the left side is a normal type shield machine that does not have the diameter expansion bit. In FIG. 1A, the diameter expansion joining shield machine 1 on the right side has a joining planned line 4
This shows the stage at which forward drilling with an expanded diameter using the expanded diameter bit 3 has started from a position 2 m in front of the . Meanwhile, the left conventional shield machine 2 reaches a position several meters in front of the welding planned line 4 and waits.
【0011】図1Bは右側の拡径接合用シールド機1に
よる拡径の前進掘削が接合計画線4の位置を超えて進ん
だ段階を示し、図1Cは前記拡径の前進掘削が接合計画
線4の位置を超えて3mまで進んだ段階で前記拡径ビッ
ト3を収納せしめ、シールド機1を接合計画線4の位置
まで後退させた状態を示している。つまり、拡径掘削部
5の長さは5mである。前記シールド機1の後退の過程
で、又は図1Cのように後退しきった位置において、シ
ールド機側の上部から拡径掘削部5に連通する泥水管7
を通じて泥水を排除しながら、他方、シールド機側の下
部から拡径掘削部5に連通するコンクリート管8を通じ
て水中コンクリート6が打設される。FIG. 1B shows a stage in which the diameter-expanding forward excavation by the diameter-expanding welding shield machine 1 on the right has progressed beyond the joint planned line 4, and FIG. 1C shows the stage where the diameter-expanding forward excavation has progressed beyond the joint planned line 4. The figure shows a state in which the diameter expanding bit 3 is retracted after the shield machine 1 has advanced to 3 m beyond the position 4, and the shielding machine 1 is retreated to the position of the welding plan line 4. In other words, the length of the enlarged diameter excavated portion 5 is 5 m. During the retreating process of the shield machine 1 or at the fully retreated position as shown in FIG.
On the other hand, underwater concrete 6 is poured through a concrete pipe 8 communicating with the enlarged diameter excavation part 5 from the lower part of the shield machine side while removing muddy water through the shield machine.
【0012】なお、上記拡径接合用シールド機1による
拡径掘削部5の掘削時又は同拡径掘削部5へ泥水置換の
方法でコンクリートを打設する時に、周辺地盤の安定性
に不安がある場合には、予め事前に水ガラス系注入材等
による薬液注入によって拡径掘削部5の周辺地盤の改良
補強を行なうのが好ましい。この点は以下に述べる各実
施例にも共通する事項である。[0012] When excavating the enlarged diameter excavation part 5 using the shield machine 1 for diameter enlargement joining, or when pouring concrete into the enlarged diameter excavation part 5 by a mud water displacement method, there may be concerns about the stability of the surrounding ground. In some cases, it is preferable to improve and reinforce the ground around the enlarged diameter excavation section 5 in advance by injecting a chemical solution with a water glass injection material or the like. This point is common to each of the embodiments described below.
【0013】図1Dは上記の各工程の間待機していた左
側の通常型シールド機2が、前記のようにして打設され
た水中コンクリート6が所定の強度を発現した後に通常
径の前進掘削を開始して、構築されたコンクリート塊6
を掘削して接合計画線4の位置に到達し、右側の拡径接
合用シールド機1と出会った状態を示している。このあ
との手順としては、双方のシールド機1、2のカッター
フェイス構造部分を解体し、さらに両者の間に残存して
いる厚さおよそ1mのコンクリート壁を破壊し除去する
ことによってシールドトンネルが貫通される。その後、
各シールド機外殻体の内側に2次覆工を施工して地中接
合の工事は完成する。FIG. 1D shows that the conventional shield machine 2 on the left side, which was on standby during each of the above steps, excavates a normal diameter forward after the underwater concrete 6 placed as described above has developed a predetermined strength. Concrete mass built by starting 6
The figure shows the state in which the welding plan line 4 has been excavated and the welding shield machine 1 on the right side has been met. The next step is to dismantle the cutter face structure of both shield machines 1 and 2, and then destroy and remove the approximately 1m thick concrete wall that remains between them to allow the shield tunnel to penetrate. be done. after that,
A secondary lining will be constructed inside the outer shell of each shield machine, and the underground connection work will be completed.
【0014】なお、前記シールドトンネルを貫通させる
工事に際して、地下水の出水を止める止水性に不安のあ
るときは、各シールド機外殻体の外周及び二つのカッタ
ーフェイス間のコンクリートに、例えばタックス(登録
商標)の如き止水性の優れた止水材の2次注入を事前に
行なって対処する。この点も以下に述べる各実施例に共
通する事項である。[0014] When carrying out construction work to penetrate the shield tunnel, if there is any concern about the water-tightness of stopping underground water from flowing out, apply, for example, tax (registered To deal with this problem, perform a secondary injection of a water-stopping material with excellent water-stopping properties, such as (Trademark), in advance. This point is also common to each of the embodiments described below.
【0015】[0015]
【第2の実施例】図2の実施例においても、図中右側の
シールド機1は半径にして1m〜2mも大きい拡径掘削
を可能にする拡径ビット3を備えた拡径接合用シールド
機であり、同左側のシールド機2は拡径ビットを有さな
い通常型シールド機である。図2Aにおいて、右側の拡
径接合用シールド機1は、拡径ビットを使用しない通常
径の前進掘削が接合計画線4の位置を超えて進んだ段階
を示している。その間、左側の通常型シールド機2は、
接合計画線4の手前数mの位置に到達して待機している
。[Second Embodiment] Also in the embodiment of FIG. 2, the shield machine 1 on the right side of the figure is a shield for diameter expansion joining equipped with a diameter expansion bit 3 that enables diameter expansion excavation with a radius of 1 m to 2 m. The shield machine 2 on the left is a normal shield machine without a diameter expansion bit. In FIG. 2A, the shield machine 1 for diameter expansion joining on the right side shows a stage in which forward drilling of a normal diameter without using a diameter expansion bit has progressed beyond the position of the joint planning line 4. Meanwhile, the normal shield machine 2 on the left,
It has reached a position several meters in front of the joint planned line 4 and is waiting.
【0016】図2Bは、右側の拡径接合用シールド機1
による通常径の前進掘削が接合計画線4の位置を超えて
約2.5mまで進んだ段階で当該シールド機1が具備し
ている拡径ビット3を突き出させ、拡径の後退掘削とし
てシールド機1を接合計画線4の位置よりも手前約2.
5mまで後退させ拡径掘削部5の形成を完成した状態を
示している。つまり、拡径掘削部5の長さは5mである
前記シールド機1の後退掘削の過程で、又は図1Bのよ
うに後退しきった位置において、シールド機側から拡径
掘削部5に連通する泥水管を通じて泥水を排除しながら
、他方、シールド機側の下部から拡径掘削部5に連通す
るコンクリート管を通じて水中コンクリート6が打設さ
れる。FIG. 2B shows the shielding machine 1 for diameter expansion joining on the right side.
When the normal diameter forward drilling has progressed to approximately 2.5 m beyond the joint planned line 4, the diameter expanding bit 3 of the shield machine 1 is pushed out, and the shield machine performs diameter expanding backward drilling. 1 approximately 2.
The state is shown in which the diameter-enlarged excavation portion 5 has been formed by retreating to 5 m. In other words, during the retreating process of the shield machine 1, which has a length of 5 m, or at the position where the shield machine 1 has completely retreated as shown in FIG. While muddy water is removed through the water pipe, underwater concrete 6 is placed through a concrete pipe that communicates with the enlarged diameter excavation section 5 from the lower part of the shield machine side.
【0017】図2Cは、前記のようにして打設したコン
クリート6が強度を発現した後に、同じ右側のシールド
機1が拡径ビット3を収納した通常径の前進掘削として
コンクリート塊6を接合計画線4の位置まで掘進した状
態を示している。図2Dは上記の各工程の間待機してい
た左側の通常型シールド機2が、前記のようにして構築
されたコンクリート塊6を前進掘削して接合計画線4の
位置に到達し、右側の拡径接合用シールド機1と出合っ
た状態を示している。このあと、双方のシールド機1、
2のカッターフェイス構造部分を解体し、さらに両者の
間に残存している厚さ約1mのコンクリート壁を破壊し
除去することによりシールドトンネルを貫通させる工程
などは、上記第1の実施例と同じである。FIG. 2C shows a plan in which, after the concrete 6 placed as described above has developed strength, the shielding machine 1 on the right side joins the concrete mass 6 as a forward excavation of a normal diameter with the enlarged diameter bit 3 accommodated. This shows the state where the excavation has been made to the position of line 4. In FIG. 2D, the conventional shielding machine 2 on the left side, which was on standby during each of the above steps, moves forward to excavate the concrete mass 6 constructed as described above and reaches the position of the joint planned line 4, and then on the right side It shows the state where it meets the shield machine 1 for diameter expansion joining. After this, both shield machines 1,
The process of dismantling the cutter face structure part 2 and further destroying and removing the approximately 1 m thick concrete wall remaining between the two to penetrate the shield tunnel is the same as in the first embodiment above. It is.
【0018】[0018]
【第3の実施例】図3の実施例では、両側の2台のシー
ルド機1A、1Bは共に通常掘削径よりも半径にして1
m〜2mも大きい拡径掘削を可能にする拡径ビット3を
備えた拡径接合用シールド機である。勿論、泥水加圧式
シールド機でもある。図3Aは、右側の拡径接合用シー
ルド機1Aが、接合計画線4の手前約2.5mの位置か
ら拡径ビット3を使用した拡径の前進掘削を開始した段
階を示している。このとき左側のシールド機1Bは、接
合計画線4の手前数mの位置に到達して待機する。[Third Embodiment] In the embodiment shown in FIG. 3, the two shield machines 1A and 1B on both sides have a radius of 1
This is a shield machine for diameter expansion joining that is equipped with a diameter expansion bit 3 that enables diameter expansion excavation as large as 2 m to 2 m. Of course, it is also a pressurized muddy water shield machine. FIG. 3A shows a stage in which the diameter-expanding welding shield machine 1A on the right has started forward excavation of the diameter-expanding joint using the diameter-expanding bit 3 from a position approximately 2.5 m before the welding planned line 4. At this time, the shield machine 1B on the left side reaches a position several meters in front of the welding planned line 4 and waits.
【0019】図3Bは右側の拡径接合用シールド機1A
による拡径の前進掘削が接合計画線4の位置を超えて約
1m進んだ段階を示している。図3Cは前記図3Bの段
階で拡径ビット3を収納せしめ、当該シールド機1Aを
接合計画線4の位置まで後退させた状態を示している。
前記シールド機1Aの後退の過程で、又は図3Cのよう
に後退しきった位置において、シールド機側の上部から
拡径掘削部5に連通する泥水管7を通じて泥水を排除し
ながら、他方、シールド機側の下部から拡径掘削部5に
連通するコンクリート管8を通じて水中コンクリート6
が打設される。FIG. 3B shows the shielding machine 1A for diameter expansion joining on the right side.
This shows a stage in which the diameter-expanding forward excavation has progressed approximately 1 m beyond the position of the joint planned line 4. FIG. 3C shows a state in which the diameter expanding bit 3 has been retracted at the stage shown in FIG. 3B and the shielding machine 1A has been retreated to the position of the welding plan line 4. In the course of the retreat of the shield machine 1A, or at the fully retreated position as shown in FIG. Underwater concrete 6 is passed through a concrete pipe 8 that communicates with the enlarged diameter excavation part 5 from the lower part of the side.
is poured.
【0020】図3Dは、前記のようにして打設された水
中コンクリート6が所定の強度を発現した後に、上記の
各工程の間待機していた左側の拡径接合用シールド機1
Bが、接合計画線4の手前約2.5mの位置から拡径ビ
ット3を使用した拡径の前進掘削を開始し、上記のよう
にして構築されたコンクリート塊6も掘削して接合計画
線4の位置に到達し、右側の拡径接合用シールド機1A
と出会った状態を示している。このあと、やはり当該シ
ールド機1Bの泥水管7とコンクリート管8を使用した
泥水置換の方法で拡径掘削部5の中に水中コンクリート
6が打設される。このコンクリート6が強度を発現した
後に、双方のシールド機1A、1Bのカッターフェイス
構造部分を解体し、さらに両者の間に残存している厚さ
およそ1mのコンクリート壁を破壊し除去することによ
ってシールドトンネルが貫通される。さらに各シールド
機外殻体の内側に2次覆工を施工して地中接合の工事が
完成される。FIG. 3D shows that after the underwater concrete 6 cast as described above has developed a predetermined strength, the shielding machine 1 for expanding the diameter and joining on the left side, which was on standby during each of the above steps, is moved.
B starts forward excavation to expand the diameter using the diameter-expanding bit 3 from a position approximately 2.5 m before the joint planned line 4, and excavates the concrete mass 6 constructed as described above to reach the joint planned line. Reach position 4 and move the diameter expansion joining shield machine 1A on the right side.
It shows the state in which it was encountered. Thereafter, underwater concrete 6 is poured into the diameter-expanded excavation section 5 by the method of replacing muddy water using the muddy water pipe 7 and concrete pipe 8 of the shield machine 1B. After this concrete 6 has developed strength, the cutter face structure parts of both shield machines 1A and 1B are dismantled, and the concrete wall approximately 1 m thick remaining between the two is destroyed and removed to provide a shield. The tunnel is penetrated. Furthermore, a secondary lining is constructed inside the outer shell of each shield machine, and the underground connection work is completed.
【0021】[0021]
【第4の実施例】図4の実施例も、両側のシールド機1
Aと1Bは共に通常掘削径よりも半径にして1m〜2m
も大きい拡径掘削を可能にする拡径ビット3を備えた拡
径接合用シールド機であり、泥水加圧式シールド機でも
ある。図4Aは、右側の拡径接合用シールド機1Aが、
拡径ビットを使用しない通常径の前進掘削を接合計画線
4の位置まで進めた段階を示している。その間、左側の
シールド機1Bは、接合計画線4の手前数mの位置に到
達して待機している。[Fourth Embodiment] The embodiment of FIG. 4 also has shield machines 1 on both sides.
Both A and 1B are 1m to 2m in radius from the normal excavation diameter.
This is a shield machine for diameter expansion joining that is equipped with a diameter expansion bit 3 that enables large diameter expansion excavation, and is also a mud water pressurization type shield machine. In FIG. 4A, the diameter expansion joining shield machine 1A on the right side is
This shows a stage in which forward excavation of a normal diameter without using an enlarged diameter bit has been advanced to the position of joint planned line 4. Meanwhile, the shield machine 1B on the left side has reached a position several meters in front of the welding planned line 4 and is on standby.
【0022】図4Bは、右側の拡径接合用シールド機1
が、接合計画線4の位置から、当該シールド機1Aが具
備している拡径ビット3を突き出させた拡径の後退掘削
を行ない、接合計画線4の位置より手前約3mまで後退
掘削をして拡径掘削部5を形成した状態を示している。
前記シールド機1Aの後退掘削の過程で、又は図4Bの
ように後退しきった位置において、シールド機側から拡
径掘削部5に連通する泥水管を通じて泥水を排除しなが
ら、他方、シールド機側の下部から拡径掘削部5に連通
するコンクリート管を通じて水中コンクリート6が打設
される。FIG. 4B shows the shielding machine 1 for diameter expansion joining on the right side.
However, from the position of the joint planned line 4, we performed backward drilling to expand the diameter by protruding the diameter expanding bit 3 that the shield machine 1A is equipped with, and performed backward drilling to about 3 m before the position of the joint planned line 4. This shows a state in which the enlarged diameter excavated portion 5 is formed. In the process of retreating excavation of the shield machine 1A, or at the position where it has completely retreated as shown in FIG. Underwater concrete 6 is placed through a concrete pipe that communicates with the enlarged diameter excavation section 5 from the lower part.
【0023】図4Cは、前記のようにして打設したコン
クリート6が強度を発現した後に、右側のシールド機1
Aが拡径ビット3を収納した通常径の前進掘削としてコ
ンクリート塊6を接合計画線4の位置まで掘進した状態
を示している。図4Dは前記のようにして打設された水
中コンクリート6が所定の強度を発現した後に、上記の
各工程の間待機していた左側の拡径接合用シールド機1
Bが、接合計画線4の手前約2.5mの位置から拡径ビ
ット3を使用した拡径の前進掘削を開始し、上記のよう
にして構築されたコンクリート塊6も掘削して接合計画
線4の位置に到達し、右側の拡径接合用シールド機1A
と出会った状態を示している。このあと、当該シールド
機1Bの泥水管7とコンクリート管8を使用した泥水置
換の方法で拡径掘削部5中に水中コンクリート6が打設
される。このコンクリート6が強度を発現した後に、双
方のシールド機1A、1Bのカッターフェイス構造部分
を解体し、さらに両者の間に残存している厚さ約1mの
コンクリート壁を破壊し除去することによってシールド
トンネルが貫通される。さらに各シールド機外殻体の内
側に2次覆工を施工して地中接合の工事が完成される。FIG. 4C shows that after the concrete 6 placed as described above has developed strength, the shielding machine 1 on the right side is
A shows a state in which the concrete mass 6 has been excavated to the position of the joint planned line 4 as normal diameter forward excavation with the expanded diameter bit 3 accommodated. FIG. 4D shows the diameter expansion joining shield machine 1 on the left, which was on standby during each of the above steps, after the underwater concrete 6 cast as described above has developed a predetermined strength.
B starts forward excavation to expand the diameter using the diameter-expanding bit 3 from a position approximately 2.5 m before the joint planned line 4, and excavates the concrete mass 6 constructed as described above to reach the joint planned line. Reach position 4 and move the diameter expansion joining shield machine 1A on the right side.
It shows the state in which it was encountered. Thereafter, underwater concrete 6 is poured into the diameter-expanded excavation section 5 by a muddy water replacement method using the muddy water pipe 7 and concrete pipe 8 of the shield machine 1B. After this concrete 6 has developed strength, the cutter face structure parts of both shield machines 1A and 1B are dismantled, and the concrete wall approximately 1 m thick remaining between them is destroyed and removed to provide a shield. The tunnel is penetrated. Furthermore, a secondary lining is constructed inside the outer shell of each shield machine, and the underground connection work is completed.
【0024】[0024]
【第5の実施例】図5の実施例は、右側の拡径接合用シ
ールド機1Aが接合計画線4の位置から後退の拡径掘削
を行ない、コンクリートを打設し、コンクリート塊6を
完成した後、そのコンクリート塊6を通常径の前進掘削
で接合計画線4の位置に到達する段階(図5C)までは
、上記第4実施例の図4Cまでの工程と共通する。本実
施例はその後の工程が次のように異なる。左側の拡径接
合用シールド機1Bは、拡径ビットを使用しない通常径
の前進掘削を接合計画線4の位置まで行なう。そして、
接合計画線4の位置からは図5Cのように拡径ビット3
を使用した拡径の後退掘削を開始する。[Fifth Embodiment] In the embodiment shown in FIG. 5, the shield machine 1A for expanding the diameter joining on the right performs backward diameter expanding excavation from the position of the joint planned line 4, pours concrete, and completes the concrete mass 6. After that, the steps up to the step (FIG. 5C) in which the concrete mass 6 is advanced excavated with a normal diameter to reach the position of the joint planned line 4 (FIG. 5C) are the same as the steps up to FIG. 4C of the fourth embodiment. This embodiment differs in subsequent steps as follows. The diameter expansion welding shield machine 1B on the left performs forward excavation of a normal diameter up to the position of the joint planned line 4 without using a diameter expansion bit. and,
From the position of the joint planning line 4, expand the diameter bit 3 as shown in Fig. 5C.
Start backward excavation of diameter expansion using.
【0025】図5Dは、前記拡径の後退掘削が接合計画
線4の位置より手前側約2.5mまで進んだ段階を示し
ている。そして、前記シールド機1Bの後退掘削の過程
で、又は図5Dのように後退しきった位置において、シ
ールド機側の上部から拡径掘削部5に連通する泥水管を
通じて泥水を排除しながら、他方、シールド機側の下部
から拡径掘削部5に連通するコンクリート管を通じて水
中コンクリート6が打設される。FIG. 5D shows a stage in which the diameter-expanding backward excavation has progressed to about 2.5 m in front of the joint planned line 4. In the process of retreating excavation of the shield machine 1B, or at the position where it has completely retreated as shown in FIG. Underwater concrete 6 is poured through a concrete pipe that communicates with the enlarged diameter excavation section 5 from the lower part of the shield machine side.
【0026】図5Eは、前記のようにして打設された水
中コンクリート6が所定の強度を発現した後に、左側の
シールド機1Bは拡径ビット3を使用しない通常径の前
進掘削を開始し、構築されたコンクリート塊6を掘進し
て接合計画線4の位置に到達し、右側の拡径接合用シー
ルド機1Aと出会った状態を示している。このあと、双
方のシールド機1A、1Bのカッターフェイス構造部分
を解体し、さらに両者の間に残存している厚さおよそ1
mのコンクリート壁を破壊し除去することによってシー
ルドトンネルが貫通されることは、上記の各実施例と同
じ手順である。FIG. 5E shows that after the underwater concrete 6 placed as described above has developed a predetermined strength, the shielding machine 1B on the left side starts forward excavation of the normal diameter without using the diameter expanding bit 3. The constructed concrete mass 6 is excavated to reach the position of the joint planned line 4, and the state is shown where it meets the diameter-expanding joint shield machine 1A on the right side. After this, the cutter face structure parts of both shield machines 1A and 1B are disassembled, and the remaining thickness of approximately 1
The shield tunnel is penetrated by destroying and removing m concrete walls, which is the same procedure as in each of the above embodiments.
【0027】[0027]
【本発明が奏する効果】本発明に係るシールド機の地中
接合方法によれば、現在の凍結工法を併用した地中接合
方法と同程度の信頼性を確保しながらも、工期を著しく
短縮できる上に、著しく簡易な施工装備によって施工性
の良い実施ができ、大幅なコストダウンも図れる。また
、地中接合される2台のシールド機の位置ずれに関して
も、許容範囲の広い実施ができ融通性に富むので、長距
離シールド工法の容易で経済的な実施に寄与する。[Effects achieved by the present invention] According to the underground bonding method for a shield machine according to the present invention, the construction period can be significantly shortened while ensuring the same level of reliability as the current underground bonding method that uses a combination of freezing methods. In addition, extremely simple construction equipment allows for good construction efficiency and significant cost reductions. Furthermore, regarding the positional deviation of the two shield machines that are to be joined underground, it can be implemented with a wide tolerance range and is highly flexible, contributing to the easy and economical implementation of long-distance shield construction methods.
【図1】A〜Dは第1実施例の施工要領図である。FIGS. 1A to 1D are construction procedure diagrams of a first embodiment.
【図2】A〜Dは第2実施例の施工要領図である。FIGS. 2A to 2D are construction procedure diagrams of the second embodiment.
【図3】A〜Eは第3実施例の施工要領図である。FIGS. 3A to 3E are construction procedure diagrams of a third embodiment.
【図4】A〜Dは第4実施例の施工要領図である。FIGS. 4A to 4D are construction procedure diagrams of a fourth embodiment.
【図5】A〜Eは第5実施例の施工要領図である。FIGS. 5A to 5E are construction procedure diagrams of the fifth embodiment.
1、1A、1B 拡径接合用シールド機2
通常型シールド機
3 拡径ビット
4 接合計画線
5 拡径掘削部
6 コンクリート1, 1A, 1B Diameter expansion joining shield machine 2
Normal type shield machine 3 Diameter expansion bit 4 Joint planning line 5 Diameter expansion excavation section 6 Concrete
Claims (5)
、一方が拡径ビットを備えた拡径接合用シールド機で、
他方は拡径ビットを有しない通常型シールド機とし、ま
ず拡径接合用シールド機が接合計画線の手前数mの位置
から拡径ビットによる拡径の前進掘削を行ないながらそ
のまま接合計画線の位置を超えて数mまで拡径掘削を行
ない、次に前記拡径接合用シールド機は接合計画線の位
置まで後退させ、前記拡径掘削部に泥水と置換しながら
水中コンクリートを打設し、前記コンクリートが強度を
発現した後に、他側から通常型シールド機が前記コンク
リート塊を接合計画線の位置まで通常径の前進掘削を行
ないシールド機同士の接合を達成することを特徴とする
、シールド機の地中接合方法。[Claim 1] Of the two shield machines that are joined underground, one is a shield machine for diameter expansion joining equipped with a diameter expansion bit,
The other is a regular type shield machine that does not have a diameter expansion bit. First, the diameter expansion joining shield machine performs forward drilling to expand the diameter with the diameter expansion bit from a position several meters in front of the joint planned line. Diameter expansion excavation is carried out to several meters beyond the diameter, and then the shield machine for diameter expansion joining is retreated to the position of the joint planned line, and underwater concrete is placed in the diameter expansion excavation part while replacing it with muddy water. After the concrete has developed strength, a conventional shield machine performs forward excavation of a normal diameter from the other side to the position of the joint planned line to achieve the joint between the shield machines. Underground bonding method.
、一方が拡径ビットを備えた拡径接合用シールド機で、
他方は拡径ビットを有しない通常型シールド機とし、ま
ず拡径接合用シールド機が拡径ビットを使用しない通常
径の前進掘削を接合計画線の位置を超えて数mまで行な
い、次には拡径ビットを使用した拡径の後退掘削を接合
計画線より手前側数mまで行ない、前記拡径掘削部に泥
水と置換しながら水中コンクリートを打設し、前記コン
クリートが強度を発現した後に、前記拡径接合用シール
ド機は前記コンクリート塊を接合計画線の位置まで通常
径の前進掘削を行ない、次に他側から通常型シールド機
が前記コンクリート塊に接合計画線の位置まで通常径の
前進掘削を行ないシールド機同士の接合を達成すること
を特徴とする、シールド機の地中接合方法。[Claim 2] Of the two shield machines that are joined underground, one is a shield machine for diameter expansion joining equipped with a diameter expansion bit,
The other is a regular shield machine that does not have a diameter expansion bit. First, the diameter expansion joint shield machine performs forward drilling of a normal diameter without using a diameter expansion bit to a depth of several meters beyond the position of the joint planning line, and then Backward drilling with an enlarged diameter using an enlarged diameter bit is carried out several meters in front of the joint planned line, and underwater concrete is placed in the enlarged diameter excavated part while replacing mud with water. After the concrete has developed strength, The diameter-expanding joint shield machine excavates the concrete mass forward to the position of the joint planned line, and then the conventional shield machine excavates the concrete mass from the other side to the position of the joint planned line. A method for underground joining of shield machines, which is characterized by performing excavation to achieve the joining of shield machines.
共に拡径ビットを備えた拡径接合用シールド機とし、ま
ず一方の拡径接合用シールド機が接合計画線の手前数m
の位置から拡径ビットによる拡径の前進掘削を行ないな
がらそのまま接合計画線の位置を超えて数mまで拡径掘
削を行ない、次に前記拡径接合用シールド機を少なくと
も接合計画線の位置まで後退させ、前記拡径掘削部に泥
水と置換しながら水中コンクリートを打設し、前記コン
クリートが強度を発現した後に、他方の拡径接合用シー
ルド機が接合計画線の手前数mの位置から前記コンクリ
ート塊を接合計画線の位置まで拡径の前進掘削を行ない
、その拡径掘削部に泥水と置換しながらコンクリートを
打設しシールド機同士の接合を達成することを特徴とす
る、シールド機の地中接合方法。[Claim 3] Both of the two shielding machines for joining underground are diameter expanding joining shield machines equipped with a diameter expanding bit, and first, one of the diameter expanding joining shield machines is installed several meters before the joining planned line.
While performing forward drilling to expand the diameter with the diameter-expanding bit from the position, continue to expand the diameter by several meters beyond the position of the joint planned line, and then use the shield machine for diameter-expanding joining to at least the position of the joint planned line. Then, underwater concrete is placed in the diameter-expanding excavation part while replacing it with muddy water, and after the concrete has developed strength, the other diameter-expanding joint shield machine starts from a position several meters in front of the joint planned line and places underwater concrete in the diameter-expanding excavation part while displacing muddy water. A shielding machine characterized by performing forward excavation of a concrete block with an enlarged diameter to the position of a joint planned line, and placing concrete in the enlarged diameter excavation part while displacing muddy water to achieve joining between shield machines. Underground bonding method.
共に拡径ビットを備えた拡径接合用シールド機とし、一
方の拡径接合用シールド機が拡径ビットを使用しない通
常径の前進掘削を接合計画線の位置まで行ない、次には
拡径ビットを使用した拡径の後退掘削を接合計画線より
手前側数mまで行ない、前記拡径掘削部に泥水と置換し
ながら水中コンクリートを打設し、前記コンクリートが
強度を発現した後に、前記拡径接合用シールド機が前記
コンクリート塊を接合計画線の位置まで通常径の前進掘
削を行ない、次に他方の拡径接合用シールド機が接合計
画線の手前数mの位置から拡径ビットを使用した拡径の
前進掘削を接合計画線の位置まで行ない、その拡径掘削
部へコンクリートを打設しシールド機同士の接合を達成
することを特徴とする、シールド機の地中接合方法。Claim 4: Both of the two shielding machines for joining underground are diameter expanding joining shield machines equipped with a diameter expanding bit, and one of the diameter expanding joining shield machines is a regular diameter joining shield machine that does not use a diameter expanding bit. Perform forward excavation to the position of the planned joint line, then perform backward excavation with an enlarged diameter using an enlarged diameter bit to several meters before the planned joint line, and pour underwater concrete into the enlarged diameter excavated area while replacing it with muddy water. is cast and after the concrete has developed strength, the shield machine for expanding the diameter joint excavates the concrete mass forward to the position of the planned joining line, and then the other shield machine for expanding the diameter joint excavates the concrete mass to the position of the planned joint line. From a position several meters in front of the joint planned line, use an expanding diameter bit to perform forward excavation to expand the diameter to the joint planned line position, and pour concrete into the expanded diameter excavation to achieve the joint between the shield machines. An underground joining method for a shield machine, which is characterized by the following.
共に拡径ビットを備えた拡径接合用シールド機とし、一
方の拡径接合用シールド機が拡径ビットを使用しない通
常径の前進掘削を接合計画線の位置まで行ない、次には
拡径ビットを使用した拡径の後退掘削を接合計画線より
手前側数mまで行ない、前記拡径掘削部に泥水と置換し
ながら水中コンクリートを打設し、前記コンクリートが
強度を発現した後に、前記拡径接合用シールド機によっ
て前記コンクリート塊を接合計画線の位置まで通常径の
前進掘削を行ない、次に他方の拡径接合用シールド機が
前記接合計画線の位置まで拡径ビットを使用しない通常
径の前進掘削を行ない、拡径ビットを使用した拡径の後
退掘削を接合計画線の手前数mまで行ない、前記拡径掘
削部に泥水と置換しながらコンクリートの打設を行ない
、そのコンクリートが強度を発現した後、そのコンクリ
ート塊を前記拡径接合用シールド機が拡径ビットを使用
しない通常径の前進掘削を接合計画線の位置まで行ない
シールド機同士の接合を達成することを特徴とする、シ
ールド機の地中接合方法。5. Both of the two shield machines used for joining underground are diameter expansion joining shield machines equipped with a diameter expansion bit, and one diameter expansion joining shield machine is a regular diameter joining shield machine that does not use a diameter expansion bit. Perform forward excavation to the position of the planned joint line, then perform backward excavation with an enlarged diameter using an enlarged diameter bit to several meters before the planned joint line, and pour underwater concrete into the enlarged diameter excavated area while replacing it with muddy water. is cast, and after the concrete has developed strength, the concrete mass is excavated forward with a normal diameter to the position of the planned joint line by the shield machine for expanding the diameter, and then the other shield machine for expanding the diameter joins. perform forward drilling of normal diameter without using an enlarged diameter bit to the position of the planned joint line, perform backward drilling of enlarged diameter using an enlarged diameter bit up to several meters in front of the planned joint line, and then Concrete is placed while displacing muddy water, and after the concrete has developed strength, the diameter expansion joining shield machine performs forward excavation of a normal diameter without using a diameter expansion bit to place the concrete mass at the joint planned line position. An underground joining method for shield machines, which is characterized in that the shield machines are joined together by performing the steps up to the point of joining the shield machines.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP13424691A JPH04360986A (en) | 1991-06-05 | 1991-06-05 | Underground joining method for shield machine |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP13424691A JPH04360986A (en) | 1991-06-05 | 1991-06-05 | Underground joining method for shield machine |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH04360986A true JPH04360986A (en) | 1992-12-14 |
Family
ID=15123814
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP13424691A Pending JPH04360986A (en) | 1991-06-05 | 1991-06-05 | Underground joining method for shield machine |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH04360986A (en) |
-
1991
- 1991-06-05 JP JP13424691A patent/JPH04360986A/en active Pending
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2006348718A (en) | Construction method of underground structure and underground structure | |
| JP2751636B2 (en) | Tunnel construction method and underground space construction method | |
| JP2001349173A (en) | Shield starting tunneling method | |
| JP3834571B2 (en) | Construction method for underground structures | |
| JP2007077677A (en) | Construction method of underground structure | |
| JPH04360986A (en) | Underground joining method for shield machine | |
| JP2742026B2 (en) | Underground tunnel joining method and segment | |
| JP4083336B2 (en) | How to build a tunnel | |
| CN116357333A (en) | A Construction Method for Subway Pipe Jacking Passage in Complicated Strata with Upper Soft and Lower Hard | |
| JP2004060266A (en) | Non-open-cut construction method for underground structure | |
| JP3221895B2 (en) | Construction method of large-diameter underground wall body and excavation equipment for burying pipes | |
| JP2663106B2 (en) | Construction method of outer wall of propulsion pipe and large cavity | |
| JP3616898B2 (en) | Method for joining underground structures using propulsion device | |
| JP2950166B2 (en) | Starting method of shield machine from existing tunnel | |
| JP2766352B2 (en) | Shield machine | |
| JP2002194988A (en) | Method and equipment for receiving a tunnel excavator into an arrival shaft | |
| JPH0369438B2 (en) | ||
| JPH06105029B2 (en) | Freezing protection method for launching and reaching shield of deep shaft | |
| JPH05195689A (en) | Splicing construction method of expanded concrete block for underground joining of shield machine | |
| JP2000328560A (en) | Construction method of steel pipe column retaining wall | |
| JPH0538093U (en) | Shield excavator capable of underground docking | |
| JP2001020657A (en) | Long tip receiving method | |
| JPS6332087A (en) | Construction method for improving ground of shield tunnel connection part under surface of water | |
| JPH09328987A (en) | Tunnel and construction method | |
| JPH0333397A (en) | Shield tunnel joining method |