JPH0438030Y2 - - Google Patents

Info

Publication number
JPH0438030Y2
JPH0438030Y2 JP10317287U JP10317287U JPH0438030Y2 JP H0438030 Y2 JPH0438030 Y2 JP H0438030Y2 JP 10317287 U JP10317287 U JP 10317287U JP 10317287 U JP10317287 U JP 10317287U JP H0438030 Y2 JPH0438030 Y2 JP H0438030Y2
Authority
JP
Japan
Prior art keywords
handrail
steel
retaining wall
base plate
locking pieces
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP10317287U
Other languages
Japanese (ja)
Other versions
JPS647651U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP10317287U priority Critical patent/JPH0438030Y2/ja
Publication of JPS647651U publication Critical patent/JPS647651U/ja
Application granted granted Critical
Publication of JPH0438030Y2 publication Critical patent/JPH0438030Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Steps, Ramps, And Handrails (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【考案の詳細な説明】 〔産業上の利用分野〕 本考案は、山止め壁のH鋼(例えば、横矢板工
法において親杭となるH鋼、ソイルパイル工法に
おいてソイルパイルに埋設されるH鋼)の上端部
に安全手摺支柱を設置するのに使用される山止め
壁用の手摺支柱取付け具に関するものである。
[Detailed description of the invention] [Field of industrial application] The present invention is based on the use of H steel for retaining walls (for example, H steel that becomes the parent pile in the horizontal sheet pile construction method, and H steel that is buried in soil piles in the soil pile construction method). The present invention relates to a handrail post mount for a retaining wall used to install a safety handrail post at the upper end.

〔従来の技術〕[Conventional technology]

従来、山止め壁のH鋼の上端部に安全手摺を設
置するにあたつては、第5図に示すように、H鋼
a同士の頭繋ぎ兼歩行路となる臥梁コンクリート
bの上に単管用のベースジヤツキcをアンカーボ
ルトdで固定して、このベースジヤツキcに手摺
支柱用単管eを取り付けたり、第6図に示すよう
に、臥梁コンクリートbに鋼製スリーブfを埋め
込んで、これに手摺支柱用単管eを差し込んだり
していた。
Conventionally, when installing a safety handrail at the upper end of the H steel of a retaining wall, as shown in Fig. A base jack c for a single pipe can be fixed with an anchor bolt d, and a single pipe e for a handrail support can be attached to this base jack c, or a steel sleeve f can be embedded in the girder concrete b as shown in Fig. 6. A single tube e for the handrail support was inserted into the holder.

〔考案が解決しようとする問題点〕[Problem that the invention attempts to solve]

上記の従来例では、いずれも、臥梁コンクリー
トbを打設し、当該臥梁コンクリートbに所定の
強度が発現するまで、安全手摺を設置することが
できなかつた。このため、地盤の掘削が臥梁コン
クリートbに先行する場合、安全手摺のないまま
山止め壁の内側地盤が掘削されることになり、安
全上、問題があつた。
In all of the above conventional examples, the safety handrail could not be installed until the girder concrete b was cast and the girder concrete b developed a predetermined strength. For this reason, if the ground excavation precedes the girder concrete b, the ground inside the retaining wall will be excavated without a safety handrail, which poses a safety problem.

本考案は、上記の従来欠点に鑑みてなされたも
のであつて、その目的は、臥梁コンクリートの打
設前でも容易かつ確実に安全手摺を設置すること
ができるようにした簡単な構造の手摺支柱取付け
具を提供することにある。
The present invention was developed in view of the above-mentioned conventional drawbacks, and its purpose is to provide a handrail with a simple structure that allows safety handrails to be easily and reliably installed even before the girder concrete is poured. The purpose is to provide stanchion fittings.

〔問題点を解決するための手段〕[Means for solving problems]

上記の目的を達成するために、本考案が講じた
技術的手段は次の通りである。即ち、本考案によ
る山止め壁の手摺支柱取付け具は、ベースプレー
トの上面に手摺支柱と嵌合する軸体を立設し、下
面には、複数個の係止片を、これら係止片間にT
字状の溝が形成される状態に垂設し、このT字状
の溝を、山止め壁のH鋼のウエブと一方のフラン
ジとに嵌合させるように構成したものである。
In order to achieve the above objective, the technical measures taken by the present invention are as follows. That is, the handrail post attachment device for a retaining wall according to the present invention has a shaft body that fits the handrail post erected on the top surface of the base plate, and a plurality of locking pieces on the bottom surface, and a plurality of locking pieces between these locking pieces. T
The T-shaped groove is vertically disposed to form a groove, and the T-shaped groove is fitted into the H steel web of the retaining wall and one flange.

〔作用〕[Effect]

上記の構成によれば、ベースプレート下面の係
止片間に形成されたT字状の溝を、山止め壁のH
鋼のウエブと一方のフランジとに嵌合させること
により、ベースプレートがH鋼の上端で支持さ
れ、かつT字状の溝と前記ウエブ及びフランジと
の嵌合によりベースプレート、延いてはその上面
に立設された軸体の平面的な位置ずれが阻止され
ることになる。
According to the above configuration, the T-shaped groove formed between the locking pieces on the lower surface of the base plate is connected to the H-shaped groove of the locking wall.
By fitting the steel web with one flange, the base plate is supported by the upper end of the H steel, and by fitting the T-shaped groove with the web and flange, the base plate and, by extension, the upper surface of the base plate is supported. Planar displacement of the installed shaft body is prevented.

そして、この状態において、前記軸体に手摺支
柱の下端部を嵌合し、手摺支柱間には手摺を架設
して安全手摺を構成することになる。
In this state, the lower end of the handrail post is fitted to the shaft, and a handrail is constructed between the handrail posts to form a safety handrail.

〔実施例〕〔Example〕

以下、本考案の実施例を図面に基づいて説明す
る。
Hereinafter, embodiments of the present invention will be described based on the drawings.

第1図、第2図は、本考案に係る山止め壁の手
摺支柱取付け具Aを示し、第3図、第4図は前記
手摺支柱取付け具Aの使用状態を示す。Bは山止
め壁、Cはソイルパイル、DはH鋼、Eは単管よ
りなる手摺支柱、Fは単管よりなる手摺である。
1 and 2 show a handrail post mount A for a retaining wall according to the present invention, and FIGS. 3 and 4 show the handrail post mount A in use. B is a retaining wall, C is a soil pile, D is an H steel, E is a handrail support made of a single pipe, and F is a handrail made of a single pipe.

前記手摺支柱取付け具Aは次の通りに構成され
ている。
The handrail support mount A is constructed as follows.

即ち、この手摺支柱取付け具Aは、第1図、第
2図に示すように、ベースプレート1の上面に手
摺支柱Eと嵌合する円筒状の軸体2を立設し、下
面には、少なくとも3個の係止片3,4,5、つ
まり前記H鋼Dにおける一方のフランジ6aの外
面に当接可能な係止片3と当該フランジ6aの内
面及びウエブ6bの両面に当接可能な係止片4,
5とを、これら係止片3,4,5間に、前記フラ
ンジ6a及びウエブ6bに嵌合するT字状の溝7
が形成される状態に垂設し、さらに前記ベースプ
レート1の下面に、締付けボルト8…が螺合する
ねじ孔付き突片9…を垂設して、構成したもので
ある。
That is, as shown in FIGS. 1 and 2, this handrail support mount A has a cylindrical shaft 2 erected on the upper surface of the base plate 1 to fit with the handrail support E, and has at least Three locking pieces 3, 4, and 5, that is, a locking piece 3 that can come into contact with the outer surface of one flange 6a of the H steel D, and a locking piece that can come into contact with the inner surface of the flange 6a and both sides of the web 6b. Stop piece 4,
5, and a T-shaped groove 7 between these locking pieces 3, 4, 5 that fits into the flange 6a and web 6b.
Further, on the lower surface of the base plate 1, protrusions 9 with threaded holes into which the tightening bolts 8 are screwed are provided vertically.

上記の手摺支柱取付け具Aを使用することによ
り臥梁コンクリート11の打設前に、山止め壁B
の上端部に安全手摺を設置することができる。
By using the above-mentioned handrail post attachment tool A, the retaining wall B can be installed before placing the girder concrete 11.
A safety handrail can be installed at the top end of the

即ち、第3図、第4図に示すように、ソイルパ
イルCの上端側の一部をはつり取つて、H鋼Dの
上端部を露出させ、しかる後、上述したT字状の
溝7をH鋼Dのフランジ6a及びウエブ6bに嵌
合させ、必要であれば、締付けボルト8…で締め
付けて、手摺支柱取付け具Aを複数個、H鋼D…
の上端部に固定する。この状態で、軸体2に手摺
支柱Eの下端部を嵌合し、手摺支柱E…間に手摺
Fを架設して墜落防止用の安全手摺を構成する。
That is, as shown in FIGS. 3 and 4, a part of the upper end of the soil pile C is removed to expose the upper end of the H steel D, and then the above-mentioned T-shaped groove 7 is Fit the flanges 6a and webs 6b of the steel D, tighten them with the tightening bolts 8 if necessary, and attach a plurality of handrail support fixtures A to the H steel D...
Fix it to the upper end of the In this state, the lower end of the handrail support post E is fitted to the shaft body 2, and a handrail F is constructed between the handrail support posts E to constitute a safety handrail for fall prevention.

しかる後、臥梁コンクリート11の打設、山止
め壁Bの内側地盤の掘削を行うことになる。
After that, the girder concrete 11 will be placed and the ground inside the retaining wall B will be excavated.

また臥梁コンクリート11を打設するにあたつ
ては、第4図に示すように、前記ベースプレート
1の上に、幅木兼コンクリート止め枠12を、手
摺支柱E(又は軸体2)の側面に当て付けた状態
に設置し、この状態で臥梁コンクリート11を打
設することができる。
In addition, when pouring the girder concrete 11, as shown in FIG. The girder concrete 11 can be placed in this state.

尚、図示の実施例では、前記ベースプレート1
が、前記軸体2の下端が溶接された上プレート1
aと、前記係止片3,4,5の上端が溶接された
下プレート1bとを複数のボルト・ナツト10…
で互いに連結することによつて構成されている
が、一枚物のプレートであつてもよいこと勿論で
ある。また上記の実施例では、軸体2の外側に手
摺支柱Eを嵌合しているが、軸体2を図示のよう
に円筒状とする場合であれば、その内径を手摺支
柱Eの外径よりも若干大きく設定して、軸体2の
内側に手摺支柱Eを嵌合するようにしてもよい。
さらに前記係止片3,4,5の上下寸法(溝7の
深さ)と係止片3,4,5同士の間隔(溝7の
幅)の設定如何によつては、締付けボルト8…で
H鋼Dに締め付け固定しなくても、手摺支柱Eの
グラツキや手摺支柱取付け具Aの不測な脱落がな
いので、締付けボルト8…及びねじ孔付き突片9
…は必ずしも必要ではなく、これらを省略して実
施することが可能である。また、上記の実施例で
はソイルパイル柱列による山止め壁Bを図示した
が、前記手摺支柱取付け具Aは横矢板工法におけ
るH鋼の上端部にも同様に装着することができ
る。
In the illustrated embodiment, the base plate 1
is the upper plate 1 to which the lower end of the shaft body 2 is welded.
a and the lower plate 1b to which the upper ends of the locking pieces 3, 4, 5 are welded together with a plurality of bolts and nuts 10...
Although it is constructed by connecting the plates to each other, it goes without saying that it may be a single plate. Furthermore, in the above embodiment, the handrail support post E is fitted to the outside of the shaft body 2, but if the shaft body 2 is cylindrical as shown, the inner diameter is the outside diameter of the handrail support post E. It is also possible to set the handrail support post E to the inside of the shaft body 2 by setting it slightly larger than the above.
Furthermore, depending on the settings of the vertical dimensions of the locking pieces 3, 4, 5 (depth of the groove 7) and the spacing between the locking pieces 3, 4, 5 (width of the groove 7), the tightening bolts 8... Even if the handrail post E is not tightened and fixed to the H steel D, the handrail post E will not wobble or the handrail post attachment fixture A will not come off unexpectedly.
... are not necessarily necessary, and it is possible to omit them. Further, in the above embodiment, the retaining wall B is illustrated using a row of soil pile columns, but the handrail column attachment tool A can be similarly attached to the upper end of the H steel in the horizontal sheet pile construction method.

〔考案の効果〕[Effect of idea]

本考案は、上述した構成よりなるから、臥梁コ
ンクリートの打設前に、山止め壁のH鋼の上端部
に安全手摺を設置して墜落事故を防止することが
できる。
Since the present invention has the above-described configuration, a safety handrail can be installed at the upper end of the H steel of the retaining wall before pouring concrete to prevent falls.

しかも、ベースプレート下面の係止片間に形成
されたT字状の溝を、山止め壁のH鋼のウエブと
一方のフランジとに嵌合させることにより、ベー
スプレートがH鋼の上端で支持され、かつT字状
の溝と前記ウエブ及びフランジとの嵌合によりベ
ースプレート、延いてはその上面に立設された軸
体の平面的な位置ずれが阻止されるので、安全手
摺の取付けが確実である。
Moreover, by fitting the T-shaped groove formed between the locking pieces on the lower surface of the base plate into the web of the H steel of the retaining wall and one flange, the base plate is supported by the upper end of the H steel. In addition, the fit between the T-shaped groove and the web and flange prevents the base plate and, by extension, the shaft mounted on its upper surface from shifting in planar position, so that the safety handrail can be installed reliably. .

【図面の簡単な説明】[Brief explanation of the drawing]

第1図乃至第4図は本考案の一実施例を示し、
第1図は山止め壁の手摺支柱取付け具の斜視図、
第2図は前記手摺支柱取付け具の裏面図、第3図
と第4図と前記手摺支柱取付け具の使用状態を示
す概略斜視図と縦断面図である。第5図と第6図
は従来例の説明図である。 A……手摺支柱取付け具、B……山止め壁、D
……H鋼、E……手摺支柱、1……ベースプレー
ト、2……軸体、3,4,5……係止片、7……
溝。
1 to 4 show an embodiment of the present invention,
Figure 1 is a perspective view of the handrail post attachment for the retaining wall;
FIG. 2 is a rear view of the handrail post mount, FIGS. 3 and 4, and a schematic perspective view and longitudinal sectional view showing the handrail post mount in use. FIGS. 5 and 6 are explanatory diagrams of conventional examples. A...Handrail support mount, B...Holding wall, D
...H steel, E ... handrail support, 1 ... base plate, 2 ... shaft body, 3, 4, 5 ... locking piece, 7 ...
groove.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] ベースプレートの上面に手摺支柱と嵌合する軸
体を立設し、下面には、複数個の係止片を、これ
ら係止片間にT字状の溝が形成される状態に垂設
し、このT字状の溝を、山止め壁のH鋼のウエブ
と一方のフランジとに嵌合させるように構成した
ことを特徴とする山止め壁用の手摺支柱取付け
具。
A shaft body that fits with the handrail support is erected on the top surface of the base plate, and a plurality of locking pieces are vertically installed on the bottom surface with T-shaped grooves formed between these locking pieces, A handrail support mount for a mountain retaining wall, characterized in that the T-shaped groove is configured to fit into the H steel web of the mountain retaining wall and one flange.
JP10317287U 1987-07-03 1987-07-03 Expired JPH0438030Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10317287U JPH0438030Y2 (en) 1987-07-03 1987-07-03

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10317287U JPH0438030Y2 (en) 1987-07-03 1987-07-03

Publications (2)

Publication Number Publication Date
JPS647651U JPS647651U (en) 1989-01-17
JPH0438030Y2 true JPH0438030Y2 (en) 1992-09-07

Family

ID=31333753

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10317287U Expired JPH0438030Y2 (en) 1987-07-03 1987-07-03

Country Status (1)

Country Link
JP (1) JPH0438030Y2 (en)

Also Published As

Publication number Publication date
JPS647651U (en) 1989-01-17

Similar Documents

Publication Publication Date Title
US3837127A (en) Mobile home leveling and hold-down support
JPS639622Y2 (en)
JPH0536042Y2 (en)
JPH0514061B2 (en)
JPH0438038Y2 (en)
JP2876182B2 (en) Joint foundation for temporary shutter
JP3061593B2 (en) Concrete block connection method and connection metal fittings
JP2750338B2 (en) Anchor frame
KR20220080604A (en) Mounting apparatus for wall form supporter
KR102817831B1 (en) Structure for connecting modular unit to foundation
JPS5920489Y2 (en) Anchor bolt mounting structure
KR100212022B1 (en) Basic structural method of plinth using high strength concrete P.C block
KR200362839Y1 (en) Fixing structure for big-size concrete form
JPH0345479Y2 (en)
JPH0438039Y2 (en)
JPH0423156Y2 (en)
JP3066458U (en) Construction fence support
KR20010044822A (en) A pile head reinforcement structure of precast concrete pile
JPH0754488A (en) Construction method of structure pillar and mounting stand for structure pillar
JPH02164933A (en) Architecture foundation construction method
JP4412826B2 (en) Scaffolding jig for scaffolding
JPS6035639Y2 (en) Hardware for installing foundations of tower-like structures
JPS6123065Y2 (en)
KR930002968B1 (en) How to install a slab form of a marine pile
JPH04323445A (en) Structure of joint part of concrete filling steel pipe column and flat slab