JPH0438307Y2 - - Google Patents
Info
- Publication number
- JPH0438307Y2 JPH0438307Y2 JP18933786U JP18933786U JPH0438307Y2 JP H0438307 Y2 JPH0438307 Y2 JP H0438307Y2 JP 18933786 U JP18933786 U JP 18933786U JP 18933786 U JP18933786 U JP 18933786U JP H0438307 Y2 JPH0438307 Y2 JP H0438307Y2
- Authority
- JP
- Japan
- Prior art keywords
- semiconductor
- test
- test head
- measuring
- switch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000012360 testing method Methods 0.000 claims description 35
- 239000004065 semiconductor Substances 0.000 claims description 19
- 230000007274 generation of a signal involved in cell-cell signaling Effects 0.000 claims description 7
- 238000005259 measurement Methods 0.000 claims description 4
- 239000011159 matrix material Substances 0.000 description 8
- 238000010586 diagram Methods 0.000 description 5
- 230000000694 effects Effects 0.000 description 2
- 238000009413 insulation Methods 0.000 description 2
Landscapes
- Testing Of Individual Semiconductor Devices (AREA)
Description
【考案の詳細な説明】
(産業上の利用分野)
本考案は、半導体直流テスト装置に関するもの
であり、詳しくはテスト速度の改善に関するもの
である。[Detailed Description of the Invention] (Industrial Field of Application) The present invention relates to a semiconductor direct current test device, and more specifically, to an improvement in test speed.
(従来の技術)
半導体直流テスト装置の一種に、テスト速度を
高めるために、テストヘツドの各ピンと直流信号
発生測定器を1:1で対応付けるように構成され
たものである。(Prior Art) This is a type of semiconductor direct current testing device that is configured to have a 1:1 correspondence between each pin of a test head and a direct current signal generation/measuring device in order to increase the testing speed.
第3図は、従来のこのような装置の一例を示す
ブロツク図である。第3図において、1は装置本
体、2はそれぞれテスト対象半導体装置3が実装
されるテストヘツド、4は装置本体1とテストヘ
ツド2を接続するケーブルである。 FIG. 3 is a block diagram showing an example of such a conventional device. In FIG. 3, reference numeral 1 denotes an apparatus main body, 2 a test head on which a semiconductor device 3 to be tested is mounted, and 4 a cable connecting the apparatus main body 1 and the test head 2. In FIG.
装置本体1の内部には、複数の直流信号発生測
定器5、マトリクスリレー6およびマルチプレク
サ7が設けられている。直流信号発生測定器5
は、直流電流を発生するときには直流電圧が測定
でき、直流電圧を発生するときには直流電流が測
定できるように構成されている。マトリクスリレ
ー6は、それぞれの直流信号発生測定器5をマル
チプレクサ7の所定の入力端子に切換接続するた
めに用いられている。マルチプレクサ7は、それ
ぞれの直流信号発生測定器5をマトリクスリレー
6を介して所望のテストヘツド2に選択的に切換
接続するために用いられている。 Inside the device main body 1, a plurality of DC signal generation and measurement devices 5, a matrix relay 6, and a multiplexer 7 are provided. DC signal generation measuring instrument 5
is configured so that it can measure DC voltage when it generates DC current, and it can measure DC current when it generates DC voltage. Matrix relay 6 is used to switch and connect each DC signal generating and measuring device 5 to a predetermined input terminal of multiplexer 7 . A multiplexer 7 is used to selectively connect each DC signal generator 5 to a desired test head 2 via a matrix relay 6.
このように構成することにより、各テストヘツ
ド2の各ピンにはマルチプレクサ7の切換に応じ
て同時にそれぞれ所定の直流信号発生測定器5が
接続されることになり、直流信号発生測定器とテ
ストヘツドに各ピンとの接続を切り換えながらテ
ストを行う構造に比べて高速化が図れる。 With this configuration, each pin of each test head 2 is connected to a predetermined DC signal generator/measuring device 5 at the same time according to the switching of the multiplexer 7, and the DC signal generator/measuring device and the test head are connected to each other at the same time. Compared to a structure in which tests are performed while switching connections to pins, it can be faster.
(考案が解決しようとする問題点)
しかし、このような従来の構成によれば、直流
信号発生測定器5とテストヘツド2との間にはマ
トリクスリレー6とケーブル4が介在しているこ
とから、マトリクスリレー6の動作時間やテスト
対象半導体装置3に付加されるケーブル4の静電
容量による微小電流測定時の信号整定時間などに
より、テスト速度が制限されることになる。(Problems to be Solved by the Invention) However, according to such a conventional configuration, since the matrix relay 6 and the cable 4 are interposed between the DC signal generator and measuring instrument 5 and the test head 2, The test speed is limited by the operation time of the matrix relay 6 and the signal settling time when measuring a minute current due to the capacitance of the cable 4 added to the semiconductor device 3 to be tested.
本考案は、これらの問題点に着目してなされた
ものであり、その目的は、半導体装置の直流テス
トが高速で行える半導体直流テスト装置を実現す
ることにある。 The present invention has been devised in view of these problems, and its purpose is to realize a semiconductor DC test device that can perform DC tests on semiconductor devices at high speed.
(問題点を解決するための手段)
このような問題点を解決する本考案は、
テスト対象半導体装置が実装されるテストヘツ
ドと、
テストヘツドの各ピンにそれぞれ対応するよう
に設けられた複数の直流信号発生測定器と、
これらテストヘツドの対応するピンと直流信号
発生測定器とを接続するように半導体スイツチと
機械的スイツチとが直列に接続された複数の直列
回路、
とで構成されたことを特徴とする。(Means for Solving the Problems) The present invention to solve these problems consists of a test head on which a semiconductor device under test is mounted, and a plurality of DC signals provided respectively corresponding to each pin of the test head. The present invention is characterized by comprising: a generator/measuring device; and a plurality of series circuits in which semiconductor switches and mechanical switches are connected in series to connect corresponding pins of these test heads and the DC signal generator/measuring device. .
(実施例)
以下、図面を用いて本考案の実施例を詳細に説
明する。(Example) Hereinafter, an example of the present invention will be described in detail using the drawings.
第1図は本考案の一実施例を示すブロツク図で
あり、第3図と同一部分には同一符号を付けてい
る。第1図において、テストヘツド2には各ピン
に対応するように複数の直流信号発生測定器5が
設けられている。そして、これら直流信号発生測
定器5のセンス端子Sおよびフオース端子Fは、
第2図に示すように、それぞれ半導体スイツチ8
と機械的スイツチ9との直列回路を介してテスト
ヘツド2の対応するピンに接続されている。装置
本体1には、複数のその他の測定器10、テスト
ヘツド2に設けられている各直流信号発生測定器
5を制御するコントローラ11、テストヘツド2
に設けられている各直流信号発生測定器5に電源
を供給する電源部12などが設けられている。 FIG. 1 is a block diagram showing an embodiment of the present invention, and the same parts as in FIG. 3 are given the same reference numerals. In FIG. 1, the test head 2 is provided with a plurality of DC signal generators 5 corresponding to each pin. The sense terminal S and force terminal F of these DC signal generation and measuring instrument 5 are as follows.
As shown in FIG.
and a mechanical switch 9 to the corresponding pins of the test head 2 through a series circuit. The apparatus body 1 includes a plurality of other measuring instruments 10, a controller 11 that controls each DC signal generating measuring instrument 5 provided in the test head 2, and a controller 11 for controlling each of the DC signal generating and measuring instruments 5 provided in the test head 2.
A power supply section 12 for supplying power to each of the DC signal generating and measuring instruments 5 provided therein is provided.
このような構成において、テストヘツド2に設
けられている各直流信号発生測定器5は、装置本
体1に設けられているコントローラ11により制
御される。すなわち、スイツチオフ時の絶縁特性
が要求されない測定にあたつては機械的スイツチ
9をオンにしておいて半導体スイツチ8をオン、
オフ制御し、スイツチオフ時の絶縁特性が要求さ
れる測定にあたつては半導体スイツチ8をオンに
しておいて機械的スイツチ9をオン、オフ駆動す
る。 In such a configuration, each DC signal generating and measuring device 5 provided in the test head 2 is controlled by a controller 11 provided in the main body 1 of the apparatus. That is, for measurements that do not require insulation properties when the switch is turned off, the mechanical switch 9 is turned on and the semiconductor switch 8 is turned on.
For measurements requiring insulation properties when the switch is turned off, the semiconductor switch 8 is turned on and the mechanical switch 9 is turned on and off.
このように構成することにより、従来のテスト
ヘツド2の各ピンと直流信号発生測定器5の各端
子との間に存在してケーブル4、マルチプレクサ
7、マトリクスリレー6は不要になり、テスト対
象半導体装置3に付加される静電容量が大幅に減
少することから微小電流測定時の信号整定時間を
短縮でき、テスト速度を高めることができる。 With this configuration, the cable 4, multiplexer 7, and matrix relay 6 that exist between each pin of the conventional test head 2 and each terminal of the DC signal generator/measuring device 5 are no longer necessary, and the semiconductor device 3 under test is Since the capacitance added to the sensor is significantly reduced, the signal settling time when measuring small currents can be shortened, and the test speed can be increased.
また、マトリクスリレー6が不要になることか
ら、従来のマトリクスリレー6の制御に起因する
動作時間の増大を解消することもできる。 Furthermore, since the matrix relay 6 is not required, it is possible to eliminate the increase in operating time caused by conventional control of the matrix relay 6.
(考案の効果)
以上説明したように、本考案によれば、半導体
装置の直流テストが高速で行える半導体直流テス
ト装置が実現でき、実用上の効果は大きい。(Effects of the Invention) As described above, according to the present invention, it is possible to realize a semiconductor DC test device that can perform DC tests of semiconductor devices at high speed, and the practical effects are great.
第1図は本考案の一実施例を示すブロツク図、
第2図は第1図の要部回路図、第3図は従来の半
導体直流テスト装置の一例を示すブロツク図であ
る。
1……装置本体、2……テストヘツド、3……
テスト対象半導体装置、5……直流信号発生測定
器、8……半導体スイツチ、9……機械的スイツ
チ。
FIG. 1 is a block diagram showing an embodiment of the present invention.
FIG. 2 is a circuit diagram of the main part of FIG. 1, and FIG. 3 is a block diagram showing an example of a conventional semiconductor DC test device. 1...Device main body, 2...Test head, 3...
Semiconductor device to be tested, 5... DC signal generation measuring instrument, 8... Semiconductor switch, 9... Mechanical switch.
Claims (1)
ドと、 テストヘツドの各ピンにそれぞれ対応するよう
に設けられた複数の直流信号発生測定器と、 これらテストヘツドの対応するピンと直流信号
発生測定器とを接続するように半導体スイツチと
機械的スイツチとが直列に接続された複数の直列
回路、 とで構成されたことを特徴とする半導体直流テス
ト装置。[Claim for Utility Model Registration] A test head on which a semiconductor device to be tested is mounted, a plurality of DC signal generation and measurement instruments provided to correspond to each pin of the test head, and a DC signal generation device with corresponding pins of these test heads. A semiconductor direct current test device comprising: a plurality of series circuits in which a semiconductor switch and a mechanical switch are connected in series to connect a measuring device.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP18933786U JPH0438307Y2 (en) | 1986-12-09 | 1986-12-09 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP18933786U JPH0438307Y2 (en) | 1986-12-09 | 1986-12-09 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6393576U JPS6393576U (en) | 1988-06-16 |
| JPH0438307Y2 true JPH0438307Y2 (en) | 1992-09-08 |
Family
ID=31141543
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP18933786U Expired JPH0438307Y2 (en) | 1986-12-09 | 1986-12-09 |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0438307Y2 (en) |
-
1986
- 1986-12-09 JP JP18933786U patent/JPH0438307Y2/ja not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6393576U (en) | 1988-06-16 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3631275B2 (en) | Semiconductor test equipment pin test circuit | |
| RU2751647C1 (en) | Analog switch for measuring sources with semiconductor devices under test | |
| JPH052869Y2 (en) | ||
| JPH01129432A (en) | Integrated circuit | |
| CN223624371U (en) | An IGBT gate driver chip testing system | |
| JP3436138B2 (en) | Bias power supply circuit for semiconductor test equipment | |
| SE8504098D0 (en) | DEVICE FOR EXAMINING CORRECT FUNCTIONING OF A SLIDER-REGULATED BRAKE SYSTEM | |
| JPS61241673A (en) | IC test equipment | |
| JP3461258B2 (en) | Apparatus for measuring conductivity or pH | |
| JP2579883Y2 (en) | Test equipment for IC transfer equipment | |
| JPH0539496Y2 (en) | ||
| JPH0365987U (en) | ||
| KR930000513B1 (en) | Semiconductor testing equipment | |
| JPH076540Y2 (en) | Circuit operation test equipment | |
| JPH11304880A (en) | Semiconductor testing device | |
| JPH0232077U (en) | ||
| RU16973U1 (en) | TEST INSTRUMENT | |
| JP4493776B2 (en) | Test equipment for integrated circuit devices | |
| JPH02234077A (en) | Grounding circuit for relay matrix | |
| SU134140A1 (en) | Method of measuring stresses in aircraft propellers with coaxial switching scheme | |
| JPS62145170U (en) | ||
| JPH0365674A (en) | Test of semiconductor | |
| SU1401386A1 (en) | Device for measuring weak currents | |
| JPS6221069A (en) | Contact-type multi-probe | |
| JPH04148540A (en) | Testing device of integrated circuit |