JPH0444520A - Timbering construction of retaining wall - Google Patents

Timbering construction of retaining wall

Info

Publication number
JPH0444520A
JPH0444520A JP15299990A JP15299990A JPH0444520A JP H0444520 A JPH0444520 A JP H0444520A JP 15299990 A JP15299990 A JP 15299990A JP 15299990 A JP15299990 A JP 15299990A JP H0444520 A JPH0444520 A JP H0444520A
Authority
JP
Japan
Prior art keywords
retaining wall
concrete
sheet pile
construction
working opening
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15299990A
Other languages
Japanese (ja)
Inventor
Hiroyuki Kono
裕之 甲野
Junro Aida
合田 潤朗
Yukimasa Yamada
山田 行正
Eiji Okubo
大久保 英二
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP15299990A priority Critical patent/JPH0444520A/en
Publication of JPH0444520A publication Critical patent/JPH0444520A/en
Pending legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PURPOSE:To make it possible to carry out easily construction work of a retaining wall by connecting continuously the upper end of the retaining wall in a state to have a small quantity of insertion to the inside of the retaining wall with a series of concrete barn members as a unit. CONSTITUTION:A sheet pile 1 as a retaining wall is driven into a specific section. Then, after concrete 4 is laced between external and internal forms 8 and 9 to cure and solidify, the external and internal forms 8 and 9 are removed, a series of RC concrete beam members 2 are connected continuously to the whole perimeter of the upper end of the sheet pile l as a unit, and a large working opening 3 is formed on the circumferential surface of each of the concrete beame members 2. After such a timbering construction of the retaining wall is constructed, a space surrounded by the sheet pile l is cut and excavated through the large working opening 3, and the foundation and basement of a building are constructed.

Description

【発明の詳細な説明】 〈産業上の利用分野〉 本発明は、建築物の基礎や地下室の施工に際し、根切り
場周辺地盤からの土圧や水圧などの側圧を山留め壁によ
って負担させながら根切り工事を進めるための山留め壁
の支保構造に関する。
[Detailed Description of the Invention] <Industrial Field of Application> The present invention is applicable to the construction of building foundations and basements, while the lateral pressure such as earth pressure and water pressure from the ground around the root cutting area is borne by a retaining wall. Regarding the supporting structure of the retaining wall for proceeding with the cutting work.

〈従来の技術〉 この種の山留め壁の支保構造としては、従来、次のもの
が知られている。
<Prior Art> The following are conventionally known as support structures for this type of retaining wall.

A、第1従来例 シートパイルなどによる山留め壁を敷地の周縁に打ち込
み、その山留め壁の内部の所定箇所にH形鋼などのスラ
ブ用支持杭を打ち込むとともに、所定深さだけ一次掘削
してコンクリート打設面を形成し、山留め壁の内周面に
腹起こしを架設するとともに切梁を架設し、切梁によっ
て形成される中央箇所などの所定の箇所を作業用開口と
して残し、他の部分に配筋を施してスラブを打設してい
た。
A. First conventional example A retaining wall made of sheet piles or the like is driven into the periphery of the site, and supporting piles for slabs such as H-shaped steel are driven into predetermined locations inside the retaining wall, and primary excavation is performed to a predetermined depth to create concrete. Form the pouring surface, erect a raised wall on the inner circumferential surface of the retaining wall, and erect a strut, leaving a predetermined location such as the center area formed by the strut as an opening for work, and opening in other parts. Reinforcement was placed and the slab was poured.

B、第2従来例 第5図の概略平面回に示すように、山留め壁01に腹起
こし02・・・を架設するとともに、対向する腹起こし
02.02にわたって十字状に切梁03.03を架設し
、火打ち梁04・・・それぞれが互いに圧縮材となるよ
うに配置しながら水平支保工05・・・を組み、中央部
に大きな作業用開口06を形成していた。
B. Second Conventional Example As shown in the schematic plan view of FIG. The flint beams 04 were erected, and horizontal supports 05 were assembled while arranging the flint beams 04 so that they were mutually compressed, and a large working opening 06 was formed in the center.

〈発明が解決しようとする課題〉 しかしながら、前述筒1および第2従来例それぞれには
、次のような欠点があった。
<Problems to be Solved by the Invention> However, each of the cylinder 1 and the second conventional example had the following drawbacks.

a、第1従来例の欠点 山留め壁からの土圧や水圧などの側圧に耐えさせるため
に、切梁の本数が多くなって作業用開口が小さく、コン
クリートの打設量が多くて不経済になるとともに、小さ
い作業用開口から二次掘削を行わなければならないため
に二次掘削のための作業性が低下する欠点があった。
a. Disadvantages of the first conventional example In order to withstand lateral pressure such as earth pressure and water pressure from the retaining wall, the number of struts is increased, the working opening is small, and the amount of concrete placed is large, making it uneconomical. In addition, secondary excavation must be performed through a small working opening, resulting in a reduction in workability for secondary excavation.

b、第2従来例の欠点 大きな作業用開口を形成できて二次掘削のための作業性
を向上できるが、水平支保工05,05どうしの連結箇
所が屈曲点になり、山留め壁からの土圧や水圧などの側
圧を支持するに伴う応力が屈曲点に集中して損傷しやす
く、火打ち梁04・・・の配置に精度を要求され、火打
ち梁04・・・の架設作業および水平支保工05・・・
の組み付は作業に手間を要して山留め作業の工期が増大
する欠点があった。
b. Disadvantages of the second conventional example Although a large working opening can be formed and workability for secondary excavation can be improved, the connection point between the horizontal supports 05 and 05 becomes a bending point, and soil from the retaining wall The stress associated with supporting lateral pressure such as pressure and water pressure is concentrated at the bending point and easily damaged, requiring precision in the placement of the flint beams 04..., and the erection work and horizontal support of the flint beams 04... 05...
The disadvantage was that the assembly required time and effort, increasing the period of work required for retaining the mounts.

本発明は、このような事情に鑑みてなされたものであっ
て、山留め壁内に対する掘削のための作業用開口の面積
を大きくするとともに山留め壁の構築作業を容易に行う
ことができるようにすることを目的とする。
The present invention has been made in view of the above circumstances, and it is an object of the present invention to increase the area of a work opening for excavation into a retaining wall and to facilitate construction of a retaining wall. The purpose is to

〈課題を解決するための手段〉 本発明の山留め壁の支保構造は、上述のような目的を達
成するために、所定区画に打ち込まれた山留め壁の上端
側を、その全周にわたり、前記山留め壁内側への入り込
み量が少ない状態で、一連のコンクリート梁材で一体連
接して構成する。
<Means for Solving the Problems> In order to achieve the above-mentioned purpose, the support structure for a mountain retaining wall of the present invention extends over the entire circumference of the upper end side of the mountain retaining wall driven into a predetermined section. It is constructed by connecting a series of concrete beams with a small amount of penetration into the inside of the wall.

上記コンクリート梁材としては、RC造またはSRC造
のいずれであっても良い。
The above-mentioned concrete beam material may be either RC construction or SRC construction.

く作用〉 本発明の山留め壁の支保構造の構成によれば、山留め壁
からの土圧や水圧などの側圧を支持するに伴う応力を、
山留め壁からその上端に連接したコンクリート梁材に軸
方向の圧縮力として伝達し、コンクリート梁材自体の突
っ張り力によって、その軸方向の圧縮力を良好に支持す
ることができる。
According to the configuration of the support structure for the mountain retaining wall of the present invention, the stress associated with supporting lateral pressure such as earth pressure and water pressure from the mountain retaining wall can be reduced.
The compressive force in the axial direction is transmitted from the retaining wall to the concrete beam connected to its upper end, and the compressive force in the axial direction can be well supported by the tensile force of the concrete beam itself.

〈実施例〉 次に、本発明の実施例を図面に基づいて詳細に説明する
<Example> Next, an example of the present invention will be described in detail based on the drawings.

畢土災旌■ 第1図は第1実施例を示す平面図、第2図は要部の断面
図(第1同の■−■線拡線断大断面図あり、建物の構築
地盤Gに、山留め壁としてのシートパイルlが所定範囲
に区画されて打ち込まれ、シートパイル1の上端側が構
築地盤Gの表面よりも突出されるとともに、その上端側
の全周にわたり、一連のコンクリート梁材2が一体連接
され、シートパイル1で囲まれた空間内に大きな作業用
開口3を有する山留め壁の支保構造が構成されている。
■ Figure 1 is a plan view showing the first embodiment, Figure 2 is a cross-sectional view of the main part (there is an enlarged cross-sectional view along the ■-■ line of the first embodiment, and the building is constructed on the ground G , Sheet piles l as retaining walls are divided into predetermined areas and driven, and the upper end side of the sheet pile 1 protrudes from the surface of the construction ground G, and a series of concrete beams 2 are placed over the entire circumference of the upper end side. are integrally connected to form a support structure for a retaining wall having a large working opening 3 in a space surrounded by sheet piles 1.

コンクリート梁材2は、コンクリート4中に鉄筋5・・
・およびフープ筋6を埋設したRC造で構成されている
Concrete beam material 2 has reinforcing bars 5 in concrete 4...
- It is constructed of RC construction with embedded hoop reinforcements 6.

次に、上記山留め壁の支保構造の構築手順について説明
する。
Next, the procedure for constructing the support structure for the retaining wall will be explained.

■ 第3図の(a)に示すように、山留め壁としてのシ
ートパイルlを所定区画に打ち込む。
■ As shown in FIG. 3(a), drive sheet piles l as retaining walls into predetermined sections.

■ その後に、第3図の(b)に示すように、シートパ
イルlの上端側に周方向に所定間隔を隔ててスタンドコ
ネクタ7を溶接などによって連接し、シートパイル1を
挟んで両側にわたるように鉄筋5・・・およびフープ筋
6を配筋し、シートパイル1よりもわずか内方に入り込
んだ位置に内側の型枠8を設置するとともに、その内側
の型枠8に対して所定間隔を隔てた外方位置に外側の型
枠9を設置する。
■ Thereafter, as shown in FIG. 3(b), the stand connectors 7 are connected to the upper end of the sheet pile l at a predetermined interval in the circumferential direction by welding or the like, so that they span both sides with the sheet pile 1 in between. Reinforcement bars 5... and hoop reinforcements 6 are arranged, and an inner formwork 8 is installed at a position slightly inward from the sheet pile 1, and a predetermined interval is placed with respect to the inner formwork 8. An outer formwork 9 is installed at a separated outer position.

■ しかる後に、第3図の(C)に示すように、内外の
型枠8.9間にコンクリート4を打設して養生固化させ
た後に内外の型枠8.9を撤去し、シートパイル1の上
端側の全周にわたって一連のRC造のコンクリート梁材
2を一体連接し、コンクリート梁材2の内周面側に大き
な作業用開口3を形成する。
■ After that, as shown in Fig. 3 (C), concrete 4 is poured between the inner and outer formworks 8.9, and after curing and hardening, the inner and outer formworks 8.9 are removed, and the sheet pile A series of RC concrete beams 2 are integrally connected over the entire circumference of the upper end side of the concrete beams 1, and a large working opening 3 is formed on the inner peripheral surface side of the concrete beams 2.

■ 上述のようにして山留め壁の支保構造を構築した後
、第3図の(d)に示すように、大きな作業用開口3を
通じてシートパイル1で囲まれる空間を根切り掘削し、
建物の基礎や地下室などを構築していく。
■ After constructing the support structure for the retaining wall as described above, as shown in Fig. 3(d), the space surrounded by the sheet piles 1 is cut and excavated through the large working opening 3;
Build foundations and basements for buildings.

コンクリート梁材2としては、例えば、20m×20m
の区画でシートパイル1を打ち込む場合に、厚みを10
〜201程度とし、かつ、幅を約1mに設定すれば良い
。そして、このような山留め壁の支保構造を軟弱地盤に
適用して根切り工事を行ったところ、深度が5〜6m程
度までは、極めて安定した状態で施工できることが明ら
かであった。
For example, the concrete beam material 2 is 20m x 20m.
When driving sheet pile 1 in the section, the thickness is 10
It is sufficient to set the width to approximately 1 m. When root cutting work was carried out by applying this support structure of a retaining wall to soft ground, it was clear that the work could be carried out in an extremely stable state up to a depth of about 5 to 6 m.

第1実隻■ 第4図は、第2実施例の要部の断面図であり、上記第1
実施例と異なる点は次の通りである。
1st actual ship■ Figure 4 is a cross-sectional view of the main parts of the second embodiment, and
The differences from the embodiment are as follows.

すなわち、コンクリート梁材2が、コンクリート4中に
鉄筋5・・・およびフープ筋6に加えてH形鋼10を埋
設したSRC造で構成されている。他の構成は第1実施
例と同じであり、同一の番号を付すことによって説明は
省略する。
That is, the concrete beam material 2 is made of SRC construction in which H-shaped steel 10 is embedded in concrete 4 in addition to reinforcing bars 5 . . . and hoop reinforcing bars 6. The other configurations are the same as those in the first embodiment, and the explanation will be omitted by assigning the same numbers.

この第2実施例によれば、第1実施例の場合に比べて、
コンクリート梁材2の幅を短くでき、敷地の外周と構築
しようとする建物外周面との距離が短い場合にも好適に
適用できる利点がある。
According to this second embodiment, compared to the first embodiment,
There is an advantage that the width of the concrete beam 2 can be shortened, and it can be suitably applied even when the distance between the outer circumference of the site and the outer circumferential surface of the building to be constructed is short.

上述第1および第2実施例において、コンクリート梁材
2のシートパイル1内側への入り込み量、すなわち、コ
ンクリート梁材2のシートパイルlの内面から内方に突
出する長さは、例えば、20m×20mの区画でシート
パイル1を打ち込む場合であれば、20〜30ai程度
で済むなど、要するに、シートパイル1の長手方向長さ
に対して、1〜1.5%に相当する分の長さだけ入り込
ませるだけで良い。
In the first and second embodiments described above, the amount of penetration of the concrete beam 2 into the sheet pile 1, that is, the length of the concrete beam 2 protruding inward from the inner surface of the sheet pile 1 is, for example, 20 m× If the sheet pile 1 is to be driven in a 20 m section, approximately 20 to 30 ai will be sufficient.In short, the length will be equivalent to 1 to 1.5% of the longitudinal length of the sheet pile 1. You just have to let it in.

山留め壁としては、上述のようなシートパイル1を打ち
込んで形成するものに限らず、例えば、ソイルパイルを
打ち込んで形成するものなども適用できる。
The retaining wall is not limited to one formed by driving sheet piles 1 as described above, but may also be formed by driving soil pile, for example.

本発明としては、上述第1および第2実施例におけるス
タッドコネクタ7を設けないものでも良い。
According to the present invention, the stud connector 7 in the first and second embodiments described above may not be provided.

〈発明の効果〉 本発明の山留め壁の支保構造によれば、山留め壁からの
土庄や水圧などの側圧を支持するに伴う応力を、山留め
壁の上端に山留め壁内側への入り込み量が少ない状態で
連接したコンクリート梁材で良好に支持するから、山留
め壁内に切梁や火打ち梁といった梁材とか腹起こし、更
には支持杭などの支保部材を設けずに済むとともに、支
保構造の構成のために一次掘削をもせずに済み、山留め
壁の構築作業を容易に行うことができるようになった。
<Effects of the Invention> According to the support structure of the mountain retaining wall of the present invention, the stress associated with supporting the lateral pressure such as the earthen wall and water pressure from the mountain retaining wall can be transferred to the upper end of the mountain retaining wall in a state where the amount of penetration into the inside of the mountain retaining wall is small. Since it is well supported by connected concrete beams, there is no need to install beam materials such as cut beams or flint beams, or support members such as support piles within the retaining wall, and the structure of the support structure This has made it possible to easily construct retaining walls without the need for primary excavation.

また、山留め壁内に大きな作業用開口を形成できるから
、山留め壁内に対する掘削作業を能率良く行うことがで
き、山留め壁の構築作業ならびにそれに引き続いての建
物の構築作業の施工効率を向上できて工期を短縮できる
ようになった。
In addition, since a large working opening can be formed within the retaining wall, excavation work within the retaining wall can be carried out efficiently, improving the construction efficiency of retaining wall construction work and subsequent building construction work. It has become possible to shorten the construction period.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図ないし第3図は、本発明に係る山留め壁の支保構
造の第1実施例を示し、第1図は全体概略平面図、第2
図は、第1図の■−■線拡線断大断面図3図は、山留め
壁の支保構造の構築手順を説明する概略断面図である。 第4図は、山留め壁の支保構造の第2実施例を示す要部
の断面図である。 第5図は、従来例の概略平面図である。 l・・・山留め壁としてのシートパイル2・・・コンク
リート梁材
1 to 3 show a first embodiment of the support structure for a retaining wall according to the present invention, FIG. 1 is an overall schematic plan view, and FIG.
The figure is an enlarged cross-sectional view taken along the line ■--■ in FIG. 1. FIG. 3 is a schematic cross-sectional view illustrating the procedure for constructing the supporting structure of the retaining wall. FIG. 4 is a cross-sectional view of the main parts of a second embodiment of the support structure for the retaining wall. FIG. 5 is a schematic plan view of a conventional example. l... Sheet pile as a retaining wall 2... Concrete beam material

Claims (3)

【特許請求の範囲】[Claims] (1)所定区画に打ち込まれた山留め壁の上端側を、そ
の全周にわたり、前記山留め壁内側への入り込み量が少
ない状態で、一連のコンクリート梁材で一体連接してあ
ることを特徴とする山留め壁の支保構造。
(1) The upper end side of the retaining wall driven into a predetermined section is integrally connected with a series of concrete beams over the entire circumference, with a small amount of penetration into the inside of the retaining wall. Support structure for retaining walls.
(2)請求項第(1)項に記載のコンクリート梁材がR
C造である山留め壁の支保構造。
(2) The concrete beam material according to claim (1) is R
The supporting structure of the mountain retaining wall is C construction.
(3)請求項第(1)項に記載のコンクリート梁材がS
RC造である山留め壁の支保構造。
(3) The concrete beam material according to claim (1) is S
The supporting structure of the mountain retaining wall is made of RC.
JP15299990A 1990-06-12 1990-06-12 Timbering construction of retaining wall Pending JPH0444520A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15299990A JPH0444520A (en) 1990-06-12 1990-06-12 Timbering construction of retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15299990A JPH0444520A (en) 1990-06-12 1990-06-12 Timbering construction of retaining wall

Publications (1)

Publication Number Publication Date
JPH0444520A true JPH0444520A (en) 1992-02-14

Family

ID=15552742

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15299990A Pending JPH0444520A (en) 1990-06-12 1990-06-12 Timbering construction of retaining wall

Country Status (1)

Country Link
JP (1) JPH0444520A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4957625A (en) * 1972-10-03 1974-06-04

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4957625A (en) * 1972-10-03 1974-06-04

Similar Documents

Publication Publication Date Title
JP2000352296A (en) Method o constructing passage just under underground structure
JP2001303584A (en) Connection structure between foundation pile head and footing
KR100640244B1 (en) Construction Method of Slab-Outer Wall Simultaneous Placement Using Basement File Without Edge Beam
JPH08193330A (en) Construction method of beam material for cut beam in underground structure
JPH05179647A (en) Supporting structure for earth retaining wall
JPS61191715A (en) Method of building underground continuous wall in pile support building having underground floor and cast-in-place concrete pile
JPH0444520A (en) Timbering construction of retaining wall
JPH0684622B2 (en) Parent-side Yokoyaita method
JPS63280153A (en) Reverse construction method for underground framework
JP3156025B2 (en) Independent open cut method for large scale and large depth
JP3109038B2 (en) Underground skeleton structure and construction method
JP4449595B2 (en) Column-beam joint structure, method for constructing column-beam joint structure, method for constructing underground structure, and building
JPH03253613A (en) Underground excavation mountain stop construction method
JP2002115324A (en) Column base unit, column integrated column base fixing foundation structure using the column base unit, and construction method therefor
JPH0441817A (en) Sheathing method
JP7788586B1 (en) Method for constructing underground structures
JPH10299003A (en) Foundation method using precast concrete members
JP2000273880A (en) Pile head connection method
JP7726606B2 (en) Ground excavation method
JP2763488B2 (en) Prefabricated pillar and inverted ramen prefabricated construction method
JPS6217233A (en) Foundation base column
JPH07103583B2 (en) Construction method for large span underground structure
JP7283659B2 (en) Mountain retaining structure
JP2572680B2 (en) Underground structure by reverse strike method
JP3725005B2 (en) Flat panel and its construction method