JPH0452666Y2 - - Google Patents

Info

Publication number
JPH0452666Y2
JPH0452666Y2 JP1987131317U JP13131787U JPH0452666Y2 JP H0452666 Y2 JPH0452666 Y2 JP H0452666Y2 JP 1987131317 U JP1987131317 U JP 1987131317U JP 13131787 U JP13131787 U JP 13131787U JP H0452666 Y2 JPH0452666 Y2 JP H0452666Y2
Authority
JP
Japan
Prior art keywords
supply
exhaust
fitting
sealing lid
fittings
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP1987131317U
Other languages
Japanese (ja)
Other versions
JPS6437642U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP1987131317U priority Critical patent/JPH0452666Y2/ja
Publication of JPS6437642U publication Critical patent/JPS6437642U/ja
Application granted granted Critical
Publication of JPH0452666Y2 publication Critical patent/JPH0452666Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Examining Or Testing Airtightness (AREA)

Description

【考案の詳細な説明】 (産業上の利用分野) 本校案は、消防法に基づいて検査を要する石油
類の危険物を貯蔵する複数地下タンク及びこれに
付属する連結配管に対して、加圧又は減圧して圧
力の変化を計算して漏洩の結果を調査するもので
あつて、その目的とする所は複数個以上の地下タ
ンクを同時に検査できるようにした複数地下タン
ク用の漏洩検査装置に関するものである。
[Detailed explanation of the idea] (Field of industrial application) Our proposal is for pressurizing multiple underground tanks and their attached connecting piping that store petroleum and other hazardous materials that require inspection based on the Fire Service Act. Or, the leakage result is investigated by calculating the change in pressure by reducing the pressure, and the purpose is related to a leakage inspection device for multiple underground tanks that can inspect multiple or more underground tanks at the same time. It is something.

(従来の技術) 従来この種の消防法による地下タンク及び付属
埋設配管の気密漏洩試験の実施方法としては、地
下タンク1基毎に単独に試験をするのが一般的で
ある。従つて、この場合は多くの検査作業と時間
とを要し、複数のタンクを検査するにはコスト的
に大変に不経済である欠点がある。
(Prior Art) Conventionally, as a method for carrying out airtight leakage tests for underground tanks and attached underground piping according to the Fire Service Act, it is common to test each underground tank individually. Therefore, in this case, a lot of inspection work and time are required, and inspection of a plurality of tanks has the drawback that it is extremely uneconomical in terms of cost.

また、一般にガソリンタンクの漏洩の有無を検
査する連結配管の入口は、気密保持の上から緊密
にキヤツプされている。従つて、連結配管の端部
に閉蓋されているキヤツプを先ず取り外し、連結
配管の入口には、送気及び吸気兼用の部品と検出
ノズル付の圧力検出部とを螺子込み等の手段によ
つて装着する方法が採用されている。然し、この
ような方法で検査する場合は、送排気部と圧力検
出部とを各々別々の位置に装着する必要があり大
変に不便である。また、該連結配管の入口のキヤ
ツプ等の付属金具が錆等の発生によつて取り外す
ことが困難となり、検査作業能率が悪く手間と時
間及び正確度の点で大変に難点が生じていた。
Additionally, the inlet of the connecting pipe that is used to check for leaks in the gasoline tank is generally tightly capped to maintain airtightness. Therefore, first remove the cap that is closed at the end of the connecting pipe, and then install a component for both air supply and intake and a pressure detection part with a detection nozzle at the inlet of the connecting pipe by screwing or other means. A method of attaching it by attaching it is used. However, when testing with such a method, it is necessary to install the air supply/exhaust section and the pressure detection section at separate positions, which is very inconvenient. In addition, attachment fittings such as caps at the entrances of the connecting pipes become difficult to remove due to the occurrence of rust, resulting in poor inspection work efficiency and great difficulties in terms of labor, time, and accuracy.

(考案が解決しようとする問題点) 本考案は、上述の各欠点に鑑みて考案したもの
であつて、従来の如く、地下タンクの1基毎に
各々試験したのでは、その取り付け作業が非常に
面倒で手間と時間が係るばかりか、配管入口の検
査具の装着作業が長年月の錆等によつて正確に取
り付けられない等の重大な問題点が一層深刻にな
つていた。
(Problems to be solved by the invention) The present invention was devised in view of the above-mentioned drawbacks, and the installation work would be extremely difficult if each underground tank was tested separately as in the past. Not only is it troublesome and time consuming, but serious problems have become even more serious, such as the fact that the inspection tool at the pipe entrance cannot be installed correctly due to rust over the years.

本考案は、上記の如き問題点を解決したもの
で、その主たる目的とする所は、1組の圧力検出
部と送排気部との検査装置を以て複数の地下タン
クに同じ圧力を働かせることによつて、複数のタ
ンクを1基毎の単独試験の場合と同様に試験する
点にある。
The present invention solves the above-mentioned problems, and its main purpose is to apply the same pressure to multiple underground tanks using an inspection device consisting of a pressure detection part and a supply/exhaust part. The point is that multiple tanks are tested in the same way as when testing each tank individually.

(問題点を解決するための手段) 本考案の漏洩検査装置は、上述の問題点をすべ
て解決するために、緊結金具を1個の主緊結金具
5と少なくとも複数以上の副緊結金具6とで構成
する。この主緊結金具5には、圧力検出部1と送
排気部2とを連結し、この送排気部2には、少な
くとも複数以上の接続部15,15……を設けた
送排気枝管3を連結し、該接続部15……には送
排気用の接続ホース16,16……を介して該副
緊結金具6,6……を各接続させ、且つ該主緊結
金具5には、密閉蓋体18と半円形係止具19と
を設けると共に、該密閉蓋体18に検出ノズル口
8が装設されている。また、該副緊結金具6,6
にも密閉蓋体29と半円形係止具30とを装設さ
せることによつて上記目的の達成を計つている。
(Means for Solving the Problems) In order to solve all of the above-mentioned problems, the leakage testing device of the present invention uses a fastening fitting as one main fastening fitting 5 and at least a plurality of sub-fastening fittings 6. Configure. This main fastening fitting 5 connects the pressure detection part 1 and the supply/exhaust part 2, and the supply/exhaust part 2 has a supply/exhaust branch pipe 3 provided with at least a plurality of connection parts 15, 15... The secondary fastening fittings 6, 6, . . . are connected to the connecting portions 15, . A body 18 and a semicircular locking member 19 are provided, and a detection nozzle opening 8 is installed in the sealing lid body 18. In addition, the secondary fastening fittings 6, 6
The above object is achieved by installing a sealing lid 29 and a semicircular locking member 30 in the case.

(作用) 本考案は上記の如き構成からなり、今この漏洩
検査装置の使用状態を説明すると、第2図、第4
図、第6図に示す如く、地下に埋設された複数個
の地下タンクA,A……の漏洩を試験する場合に
は、地下タンクA,Aに接続されている連結配管
27,27の蓋体を外し、この注油口金28,2
8に対して、その1ケ所の注油口金28に対し
て、先ず主緊結金具5を下部の半円形係止具19
を利用して側部より第4図に示す如く注油口金2
8のフレンジに嵌め込み、注油口金28の端口を
密閉蓋体18の内面の気密パツキング材20に圧
接して密閉蓋体18と半円形係止具19とをボル
ト25及び両側又は片側のナツト26,26によ
つて螺合することによつて主緊結金具5を該注油
口金18に強固に締着する。なお、該半円形係止
具19には、内部の半円孔に相対する係止部2
3,23を摺動自在に装設して注油口金28に係
合する場合と、第5図に示す半円形係止具30の
嵌入孔33を注油口金28に係止される大きさに
形成した相対する係止部32,32に該注油口金
28を係合して該主緊結金具5を締着する場合も
ある。
(Function) The present invention has the above-mentioned configuration, and the usage state of this leakage testing device will now be explained as shown in Figures 2 and 4.
As shown in Fig. 6, when testing for leakage from a plurality of underground tanks A, A... buried underground, the lids of the connecting pipes 27, 27 connected to the underground tanks A, A, etc. Remove the body and attach this lubricating cap 28, 2.
8, first attach the main fastening fitting 5 to the one lubricating cap 28 by attaching it to the lower semicircular locking fitting 19.
Using the lubricating cap 2 from the side as shown in Figure 4.
8, and the end of the oil filler cap 28 is pressed against the airtight packing material 20 on the inner surface of the sealing lid 18, and the sealing lid 18 and the semicircular locking member 19 are connected to the bolt 25 and nuts 26 on both sides or one side. 26, the main fastening fitting 5 is firmly fastened to the oil filler cap 18. Note that the semicircular locking tool 19 has a locking portion 2 facing the internal semicircular hole.
3 and 23 are slidably installed and engaged with the oil filler cap 28, and the fitting hole 33 of the semicircular locking tool 30 shown in FIG. In some cases, the main fastening fitting 5 may be fastened by engaging the lubricating cap 28 with the opposing locking portions 32, 32.

次に、他の数個の地下タンクA,A……に於け
る注油口金28,28……に対して、副緊結金具
6,6,6の下部の半円形係止具30,30に設
けた嵌入孔33を第6図に示す如く側方より嵌め
込み、注油口金28の上端に密閉蓋体29の気密
パツキング材35を圧接して密閉蓋体29と半円
形係止具30とをボルト39,39及びナツト4
0,40によつて螺着して注油口金28,28…
…に強固に締着する。
Next, the semi-circular locking fittings 30, 30 at the bottom of the sub-clamping fittings 6, 6, 6 are installed for the oil filler caps 28, 28... in several other underground tanks A, A... The fitting hole 33 is inserted from the side as shown in FIG. , 39 and Natsu 4
Screw on the oil filler caps 28, 28 with 0.0 and 40...
Tightly fasten to...

以上の如く、前記主緊結金具5と副緊結金具
6,6……を装着した後に、ポンプの駆動により
地下タンクA,A内の気相部蒸気を吸引したり、
又は大気を地下タンクA,A内に圧送し、タンク
内部に微加圧を加える。この操作によつて発生さ
れる減圧あるいは微加圧の状態を検出ノズル口8
にて一定時間保持し、その間にマノメータによつ
て圧力の変動を目視観測しながら、記録計により
記録させ、変化を正確に認識して漏洩の有無を判
定するものである。なお、複数の地下タンクA,
A……内に漏洩が発見された場合は、主緊結金具
5及び副緊結金具6,6……のバルブ11及びバ
ルブ36,36を各々調整開閉することにより順
次1基毎に検査を実施して漏洩している地下タン
クを検知するようにしたものである。
As described above, after the main fastening fittings 5 and the sub-fastening fittings 6, 6, .
Alternatively, atmospheric air is forced into underground tanks A and A, and slight pressurization is applied inside the tanks. The nozzle port 8 detects the state of reduced pressure or slight increase in pressure generated by this operation.
During this period, pressure fluctuations are visually observed using a manometer and recorded using a recorder, and the changes are accurately recognized to determine the presence or absence of a leak. In addition, multiple underground tanks A,
If leakage is discovered in A..., inspect each unit one by one by adjusting and opening and closing valves 11 and 36 of the main fastening fittings 5 and sub-fastening fittings 6, 6, respectively. This system is designed to detect leaking underground tanks.

(実施例) 本考案の実施例を図面について説明すると、第
2図に示す如く、地下に埋設された地下タンク
A,A……には、通気作用をする連結配管27,
27……が連結され、この連結配管27,27…
…の端部に位置する注油口金28には、漏洩検査
の時に使用する検査装置の1個の主緊結金具5及
び複数以上の副緊結金具6,6を連結するように
なつている。
(Embodiment) To explain an embodiment of the present invention with reference to the drawings, as shown in Fig. 2, underground tanks A, A, etc. buried underground are connected to connecting pipes 27 for ventilation,
27... are connected, and these connecting pipes 27, 27...
One main fastening fitting 5 and a plurality of sub-fastening fittings 6, 6 of an inspection device used for leakage inspection are connected to the oil filler cap 28 located at the end of the leakage test device.

前記主緊結金具5には、上部の密閉蓋体18の
上面に圧力検出部1と送排気部2とを一体的に並
設し、これを連結管7を以て連結してある。該圧
力検出部1には、内部に検出ノズルを挿通すると
共に、その先端に検出ノズル口8が該密閉蓋体1
8を貫通して僅かに突出して取着されている。次
に、前記送排気部2には、その所定位置の略直角
方向に数個の接続部15,15を設けた送排気枝
管3を形成してある。
In the main fastening fitting 5, a pressure detecting section 1 and a supply/exhaust section 2 are integrally arranged side by side on the upper surface of an upper sealing lid 18, and these are connected by a connecting pipe 7. A detection nozzle is inserted into the pressure detection section 1, and a detection nozzle port 8 is provided at the tip of the pressure detection section 1, which is connected to the sealing lid 1.
8 and is attached so as to protrude slightly. Next, the supply/exhaust section 2 is formed with a supply/exhaust branch pipe 3 provided with several connecting portions 15, 15 in a direction substantially perpendicular to a predetermined position thereof.

また、該圧力検出部1の端部には、プラグソケ
ツト等の継手部9を介在して圧力検出用ホース1
3を接続してある。該送排気部2には、適宜位置
に開閉用のボールバルブ等のバルブ11,11を
介在すると共に、一端部にはプラグソケツト等の
継手部9を介して送排気用ホース12を接続した
構成となつている。
Further, a pressure detecting hose 1 is connected to the end of the pressure detecting section 1 through a joint section 9 such as a plug socket.
3 are connected. The air supply and exhaust section 2 has valves 11, 11 such as ball valves for opening and closing at appropriate positions, and a hose 12 for air supply and exhaust is connected to one end via a joint 9 such as a plug socket. It's summery.

次に、該連結管7に連結されている該主緊結金
具5には、上部の該密閉蓋体18と下部の半円形
係止具19とを有し、前記密閉蓋体18の外周に
は相対向する突出部21,21を突設すると共
に、内面に該注油口金28の端辺を圧接する気密
パツキング材20を接着してある。この気密パツ
キング材20の中央部分には該検出ノズル口8が
突出するように挿通されている。該半円形係止具
19には、外周に相対する鍔部22,22を設け
ると共に、該鍔部22,22に対して内方に前進
後退する摺動溝24を穿設した係止部23,23
を装設してある。また、前記突出部21,21と
鍔部22,22とには、ボルト25,25を挿通
すると共に、そのボルト25,25の片側又は両
側に蝶ナツト等のナツト26,26を螺着自在に
螺合せしめてある。
Next, the main fastening fitting 5 connected to the connecting pipe 7 has an upper sealing lid 18 and a lower semicircular locking member 19, and the outer periphery of the sealing lid 18 is Opposed protrusions 21, 21 are provided in a protruding manner, and an airtight packing material 20 is bonded to the inner surface of the lubricating spout 28 so as to press the end thereof. The detection nozzle port 8 is inserted through the center of the airtight packing material 20 so as to protrude therefrom. The semicircular locking tool 19 is provided with opposing flanges 22, 22 on the outer periphery, and a locking portion 23 with a sliding groove 24 that moves forward and backward inward with respect to the flanges 22, 22. ,23
It is equipped with. Further, bolts 25, 25 are inserted through the protrusions 21, 21 and the flanges 22, 22, and nuts 26, 26 such as wing nuts can be freely screwed onto one or both sides of the bolts 25, 25. It is screwed together.

次に、第5図、第6図に示す副緊結金具6は、
該主緊結金具5の一部構成を変えたものであつ
て、上部の密閉蓋体29の外周に相対向する突出
部31,31を突設し、下部の半円形係止具30
には、外部に相対する鍔部34,34を設け、内
部に嵌入孔33を形成すると共に、この嵌入孔3
3の大きさを該注油口金28の縁部に係合するよ
うに係止部32,32を形成した構成となつてい
る。また、該密閉蓋体29の内面には中央部分に
送排気孔を設けた気密パツキング材35を接着し
てある。前記突出部31,31と鍔部34,34
とには、ボルト39,39を挿通すると共に、ボ
ルト39,39の端部に蝶ナツト等のナツト4
0,40を螺着自在に螺合せしめてある。
Next, the secondary fastening fittings 6 shown in FIGS. 5 and 6 are as follows:
This is a partial configuration of the main fastening fitting 5, in which protrusions 31, 31 are protruded from the outer periphery of the upper sealing lid 29, and a semicircular locking fitting 30 is provided at the lower part.
is provided with flanges 34, 34 facing the outside, and has a fitting hole 33 formed inside, and this fitting hole 3.
The locking portions 32, 32 are formed to have a size of 3 and engage with the edge of the oil filler cap 28. Further, an airtight packing material 35 having an air supply/exhaust hole provided in the center portion is adhered to the inner surface of the airtight lid body 29. The protruding parts 31, 31 and the collar parts 34, 34
Insert the bolts 39, 39, and attach nuts 4, such as wing nuts, to the ends of the bolts 39, 39.
0.40 screws are screwed together so that they can be screwed freely.

更に、前記送排気枝管3に設けた数個の接続部
15,15……には、接続ホース16,16,1
6を連結すると共に、接続ホースの先端にプラグ
とソケツト等の継手部17,17,17を介在
し、開閉用のバルブ36,36を設けた連結管3
7,37に該副緊結金具6,6,6を連接した構
成となつている。
Furthermore, connection hoses 16, 16, 1 are connected to several connection parts 15, 15, .
6, and a connecting pipe 3 having coupling parts 17, 17, 17 such as plugs and sockets interposed at the ends of the connecting hoses, and provided with valves 36, 36 for opening and closing.
The secondary fastening fittings 6, 6, 6 are connected to the auxiliary fastening fittings 7, 37.

(考案の効果) 本考案は上記の如く構成されているので、この
漏洩検査装置を使用して気密漏洩試験を実施する
と、従来の様に地下タンク1基毎に各々単独に手
間と時間をかけて試験をする必要がなく、複数の
地下タンクを1回の検査作業と時間を以て簡単確
実に漏洩検査できる便利な効果と、複数のタンク
を漏洩検査する時に各連結配管の注油口金に主緊
結金具と副緊結金具とを以て敏速確実に連結でき
るので準備作業が著しく省略化され、且つ紊りに
該金具が脱離することがなく気密に接続できる優
れた効果がある。そして、主緊結金具5には、圧
力検出部と送排気部とを連結し、この送排気部に
複数以上の接続部を設けた送排気枝管を連結し、
この接続部に送排気用の接続ホースを介在して複
数の副緊結金具を各々連結せしめたことにより、
複数の地下タンク内に同一圧力を確実に働かせる
ことができ、且つ圧力検出部は該主緊結金具5の
上部の1ケ所に連接するだけであるから、大変に
経済的であると共に、副緊結金具の内部構造が著
しく簡単となる効果がある。
(Effects of the invention) Since the invention is configured as described above, if an airtight leakage test is performed using this leakage testing device, it will take time and effort to conduct each underground tank separately, unlike the conventional method. There is no need to conduct a separate test, and the convenient effect is that multiple underground tanks can be easily and reliably tested for leaks in a single inspection process and time, and when testing multiple tanks for leaks, the main fastening fitting can be attached to the oil filler cap of each connecting pipe. Since the connection can be made quickly and reliably using the and auxiliary fastening fittings, the preparation work can be greatly simplified, and there is an excellent effect that the fittings can be airtightly connected without coming off during the process. The main fastening fitting 5 is connected to a pressure detection part and a supply/exhaust part, and a supply/exhaust branch pipe having a plurality of connection parts or more is connected to the supply/exhaust part.
By connecting a plurality of sub-clamping fittings to each of the connection parts through connection hoses for air supply and exhaust,
Since the same pressure can be reliably applied in a plurality of underground tanks, and the pressure detection part is only connected to one place on the upper part of the main fastening fitting 5, it is very economical, and the sub-fastening fitting 5 is very economical. This has the effect of significantly simplifying the internal structure.

更に、主緊結金具と副緊結金具とに設けた、上
部の密閉蓋体と下部の半円形係止具とによつて、
側方からの注油口金への係合を容易とすると共
に、密閉蓋体が注油口金の端辺を緊密に圧接する
と云う効果と、各注油口金からの主緊結金具と副
緊結金具との脱離も極めて簡便にできると云う従
来にない能率的な効果を有するものである。
Furthermore, by the upper sealing lid and the lower semicircular locking device provided on the main fastening metal fitting and the secondary fastening metal fitting,
It is easy to engage the oil filler cap from the side, the sealing lid tightly presses the end of the oil filler cap, and the main fastening fitting and the secondary fastening fitting can be removed from each oil filler fitting. It can also be done extremely simply and has unprecedented efficiency effects.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本案の検査装置の構成側面図、第2図
は同じく本案を地下タンクに装着した実施状態を
示す側面図、第3図は主緊結金具の斜面図、第4
図は同じく縦断側面図、第5図は副緊結金具の斜
面図、第6図は同じく縦断側面図である。 符号Aは地下タンク、1は圧力検出部、2は送
排気部、3は送排気枝管、5は主緊結金具、6は
副緊結金具、7,37は連結管、8は検出ノズル
口、9,10,17は継手部、12は送排気用ホ
ース、13は圧力検出用ホース、15は接続部、
16は接続ホース、18,29は密閉蓋体、1
9,30は半円形係止具、20,35は気密パツ
キング材、27は連結配管、28は注油口金であ
る。
Figure 1 is a side view of the configuration of the inspection device of the present invention, Figure 2 is a side view of the present invention installed in an underground tank, Figure 3 is a slope view of the main fastening fittings, and Figure 4 is a side view of the proposed inspection device.
The drawings are also a vertical side view, FIG. 5 is a slope view of the sub-fastening fitting, and FIG. 6 is a vertical side view. Symbol A is an underground tank, 1 is a pressure detection part, 2 is a supply/exhaust part, 3 is a supply/exhaust branch pipe, 5 is a main fastening fitting, 6 is a sub-fastening fitting, 7 and 37 are connecting pipes, 8 is a detection nozzle port, 9, 10, 17 are joint parts, 12 is a supply/exhaust hose, 13 is a pressure detection hose, 15 is a connection part,
16 is a connection hose, 18 and 29 are sealing lids, 1
9 and 30 are semicircular locking devices, 20 and 35 are airtight packing materials, 27 is a connecting pipe, and 28 is an oil filler cap.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 複数以上の地下タンクA,A……に緊結金具を
取着して各々の地下タンクA,A及び配管等の漏
洩検査をする地下タンク用の漏洩検査装置に於い
て、前記地下タンクA,A……には、通気作用を
する連結配管27,27……を連結すると共に、
該連結配管27,27……の端部に注油口金2
8,28を位置させ、該注油口金28,28の端
部には、前記緊結金具の一個の主緊結金具5と複
数以上の副緊結金具6,6を各々連結し、該主緊
結金具5には、上部の密閉蓋体18の上面に圧力
検出部1と送排気部2とを並設して連結し、該圧
力検出部1には、内部に検出ノズルを挿通すると
共に、先端の検出ノズル口8は該密閉蓋体18を
貫通取着し、前記送排気部2には、所定位置の略
直角方向に数個の接続部15,15を設けた送排
気枝管3を形成すると共に、該送排気部2にバル
ブ11,11を介在して送排気用ホース12を接
続し、且つ該圧力検出部1の端部には、継手部9
を介して圧力検出用ホース13を接続し、連結管
7に連結される該主緊結金具5には、上部の該密
閉蓋体18と下部の半円形係止具19とをボルト
25,25を以て挿通螺着し、該密閉蓋体18の
内面には、該注油口金28に圧接する気密パツキ
ング材20を接着し、該半円形係止具19には、
相対する鍔部22,22に前進後退する係止部2
3,23を装設し、更に前記副緊結金具6には、
上部の密閉蓋体29,29と下部の半円形係止金
具30とをボルト39,39を以て挿通螺着し、
且つ該密閉蓋体29,29の内面には、送排気孔
を設けた気密パツキング材35,35を接着した
ことを特徴とする複数地下タンク用の漏洩検査装
置。
In an underground tank leakage inspection device that attaches fastening fittings to a plurality of underground tanks A, A, and performs leakage inspection of each underground tank A, A, piping, etc., the underground tanks A, A... . . . is connected with connecting pipes 27, 27 . . . for ventilation, and
A lubricating cap 2 is attached to the end of the connecting pipes 27, 27...
8, 28, and connect one main fastening fitting 5 and a plurality of sub fastening fittings 6, 6 to the ends of the oil filler fittings 28, 28, respectively, and connect the main fastening fittings 5 to the main fastening fittings 5. A pressure detection section 1 and a supply/exhaust section 2 are arranged and connected in parallel on the upper surface of an upper sealing lid 18, and a detection nozzle is inserted inside the pressure detection section 1, and a detection nozzle at the tip is inserted into the pressure detection section 1. The opening 8 is attached through the sealing lid 18, and the supply/exhaust part 2 is formed with a supply/exhaust branch pipe 3 having several connecting parts 15, 15 at predetermined positions and substantially perpendicular to the direction. A supply and exhaust hose 12 is connected to the supply and exhaust section 2 through valves 11, 11, and a joint section 9 is connected to the end of the pressure detection section 1.
The pressure detection hose 13 is connected to the main fastening fitting 5 which is connected to the connecting pipe 7, and the upper sealing lid 18 and the lower semicircular locking fitting 19 are attached with bolts 25, 25. An airtight packing material 20 is adhered to the inner surface of the sealing lid body 18 and is in pressure contact with the oil filler cap 28.
Locking portion 2 that moves forward and backward toward opposing flanges 22, 22
3 and 23, and the secondary fastening fitting 6 is further equipped with:
Insert and screw the upper sealing lid bodies 29, 29 and the lower semicircular locking fitting 30 using bolts 39, 39,
A leakage testing device for a plurality of underground tanks is characterized in that airtight packing materials 35, 35 provided with air supply and exhaust holes are adhered to the inner surfaces of the sealing lids 29, 29.
JP1987131317U 1987-08-27 1987-08-27 Expired JPH0452666Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1987131317U JPH0452666Y2 (en) 1987-08-27 1987-08-27

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1987131317U JPH0452666Y2 (en) 1987-08-27 1987-08-27

Publications (2)

Publication Number Publication Date
JPS6437642U JPS6437642U (en) 1989-03-07
JPH0452666Y2 true JPH0452666Y2 (en) 1992-12-10

Family

ID=31387269

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1987131317U Expired JPH0452666Y2 (en) 1987-08-27 1987-08-27

Country Status (1)

Country Link
JP (1) JPH0452666Y2 (en)

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4720291U (en) * 1971-02-09 1972-11-07
JPS5093688A (en) * 1973-12-21 1975-07-25
JPS6093938U (en) * 1983-12-05 1985-06-26 日機装株式会社 water pressure jig

Also Published As

Publication number Publication date
JPS6437642U (en) 1989-03-07

Similar Documents

Publication Publication Date Title
US5295760A (en) Testable bulkhead
CN221350450U (en) Air tightness detection device of three-way high-pressure valve
JP5616715B2 (en) Piping construction confirmation method
EP0045167B1 (en) Engine cylinder head port closure pad clamp
CN112697354A (en) Valve helium leak detection tool and leak detection method
JPH0452666Y2 (en)
JPH0430515Y2 (en)
US20050200130A1 (en) Radiator inlet adapter
CA2999502A1 (en) A system and method for measuring pressure and removing fluid from behind a flange of a pipeline
JPH0526398Y2 (en)
US4086934A (en) Pipeline weld repair cap
CN213120481U (en) Square pipeline wall thickness monitoring device
JP2549744Y2 (en) Pipe fittings
JP2504068Y2 (en) Pipe fitting
EP0604486A1 (en) Interchangeable process connection resistant to installation errors
JPH0313036Y2 (en)
CN220912578U (en) Pipeline leak detection tool and helium mass spectrum negative pressure leak detection system
JPS628509Y2 (en)
JPH058397Y2 (en)
JPH11207485A (en) Welding plug airtightness test equipment
JPS6212275Y2 (en)
JP3720122B2 (en) Pipe fitting for repair
JP2860355B2 (en) Sealing device at branch connection of gas conduit
JPH0545957Y2 (en)
JPS623711Y2 (en)