JPH045389A JP10592790A JP10592790A JPH045389A JP H045389 A JPH045389 A JP H045389A JP 10592790 A JP10592790 A JP 10592790A JP 10592790 A JP10592790 A JP 10592790A JP H045389 A JPH045389 A JP H045389A
Authority
JP
Japan
Prior art keywords
stage
windows
boring
drilling head
window
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP10592790A
Other languages
Japanese (ja)
Other versions
JPH0749751B2 (en
Inventor
Tomotake Shigemori
知勇 重盛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP2105927A priority Critical patent/JPH0749751B2/en
Publication of JPH045389A publication Critical patent/JPH045389A/en
Publication of JPH0749751B2 publication Critical patent/JPH0749751B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

PURPOSE:To largely improve working efficiency by excavating first stage windows with equal intervals along a circumference of a tube body peripheral side, excavating first stage to n-th stage windows along an axial line and fixing a pit in each window. CONSTITUTION:Windows 2 on the first stage are excavated with equal intervals along a circumference of a tube 1 peripheral side while windows on the first to n-th stages are excavated along an axial line and a pit 3 is fixed in each window 2 to form an excavating head A. The windows 2 and the pits 3 are placed so that the pit 3 on the next stage may be sequentially exposed before the pit 3 on the previous stage is worn by excavation of the excavating head A. Thus operation can be continued without replacement of the excavating head A.

Description

【発明の詳細な説明】 I)・・・技術分野 現在、地中ボーリング、山止め、アンカーボルト穴の削
進ボーリング、上、下水道、電気、ガス等の配管用孔の
ボーリング等において、掘削機の回転推進主軸に掘削ヘ
ッドを取付け、掘削の進行に伴って鋼管又はロッドを次
々と連結して(掘削ヘッドは先頭の鋼管又はロッドに取
付けである)、長距離のボーリングを行うことが行われ
ているが、 本発明は上記ボーリングに用いる掘削ヘッドの構成に係
るものである。
[Detailed description of the invention] I)...Technical field At present, excavators are used in underground boring, pile stopping, drilling for anchor bolt holes, boring for pipe holes for water, sewerage, electricity, gas, etc. A drilling head is attached to the rotating propulsion main shaft of the excavator, and as the excavation progresses, steel pipes or rods are connected one after another (the drilling head is attached to the first steel pipe or rod) to perform long-distance boring. However, the present invention relates to the configuration of a drilling head used for the above-mentioned boring.

■)・・・従来技術とその課題 (1)・・・従来は、上記のようにボーリング作業にお
いて、次々と鋼管又はロッドを連結して掘削を進行して
いるとき、先端掘削ヘッドのビットが摩耗してしまって
削進能率が低下し、或は削進不能となると、 掘削機の位置において、鋼管又はロッドを引き戻し乍ら
1本ずつ取り外し、全部引き戻して先端の掘削ヘッドを
新品と交換してから、再び鋼管又は口・ノドを1本ずつ
連結して元の削進位置まで挿入して、ようやく削進再開
していたものである。
■)...Prior art and its problems (1)...Conventionally, in boring work as described above, when drilling progresses by connecting steel pipes or rods one after another, the bit of the tip drilling head If the excavation efficiency decreases due to wear, or if it becomes impossible to excavate, remove the steel pipes or rods one by one while pulling them back from the position of the excavator, then pull them all back and replace the excavation head at the tip with a new one. After that, the steel pipes or mouths and throats were connected one by one and inserted back to the original cutting position, and cutting was finally restarted.

(2)・・・従って、削進距離が長くなるほど、掘削ヘ
ッドの交換に多大の手数と時間を要することとなり、作
業能率向上、作業時間短縮の最大のネックとなっていた
(2)... Therefore, the longer the excavation distance, the more labor and time it takes to replace the excavation head, which has become the biggest bottleneck in improving work efficiency and shortening work time.

また、土質、岩質の変化によってビットの摩耗耐久時間
が種々変化するため、ピントの摩耗状態の把握、掘削ヘ
ッドの交換時機の決定等の掘削ヘッドの適正な管理が作
業者にとって常に大きな負担となっていたものである。
In addition, since the wear durability time of the bit varies depending on the soil and rock quality, proper management of the drilling head, such as understanding the wear state of the focus and deciding when to replace the drilling head, is always a heavy burden on workers. That's what it used to be.

■)・・・本発明の構成 本発明は上記従来の課題の有効な解決に成功したもので
ある。
(2) Structure of the present invention The present invention has succeeded in effectively solving the above-mentioned conventional problems.

(1)・・・即ち、本発明は、掘削機の回転推進主軸に
セットしてボーリングを行う鋼管タイプの掘削ヘッドで
あり、管体周面の、円周方向に第1段の窓を等間隔に穿
設すると共に、軸線方向に該第1段乃至第n段の窓を等
間隔に穿設し、各窓内にビットを固設して成る、ボーリ
ング用掘削ヘッドである。
(1)...That is, the present invention is a steel tube type excavation head that is set on the rotary propulsion main shaft of an excavator for boring. This is a drilling head for boring, in which holes are drilled at intervals, windows of the first to nth stages are bored at equal intervals in the axial direction, and a bit is fixedly installed in each window.

(2)・・・以下、本発明の実施例を図面につき説明す
ると、 掘削機(図示せず)の回転推進主軸にセットしてボーリ
ングを行う鋼管タイプの掘削へ・7ドAであり、管体1
周面の、円周方向に第1段の窓2を等間隔に穿設すると
共に、軸線方向に該1段から第n段の窓2を順々に等間
隔に穿設し、各窓2内にビット3を固設してボーリング
用掘削ヘッドAを設けたものである。
(2)...Hereinafter, embodiments of the present invention will be explained with reference to the drawings.This is a 7-door A steel pipe type excavation machine that is set on the rotary propulsion main shaft of an excavator (not shown) for boring. body 1
First-stage windows 2 are bored at equal intervals in the circumferential direction of the circumferential surface, and windows 2 from the first stage to the n-th stage are sequentially bored at equal intervals in the axial direction, and each window 2 A drilling head A for boring is provided with a bit 3 fixed therein.

(3)・・・而して、掘削ヘッドAは、掘削により前段
のビット3が摩耗消滅する前に、次段のビット3が順に
露出するように、管体1周面に窓2及びビット3を配設
する。
(3)...Thus, the drilling head A has windows 2 and bits on the circumferential surface of the pipe body 1 so that the bits 3 in the next stage are sequentially exposed before the bits 3 in the previous stage are worn out due to excavation. Place 3.

(4)・・・また、ビット3は各窓2の底辺部4に、ろ
−着け、溶接等で固設し、ビット3の一部を管体1の外
周面及び内周面から交互に僅かずつ突出して窓2の底辺
部4に固設して設ける。
(4) ...Also, the bit 3 is fixed to the bottom part 4 of each window 2 by brazing, welding, etc., and part of the bit 3 is alternately inserted from the outer circumferential surface and the inner circumferential surface of the tube body 1. It is fixedly provided on the bottom side 4 of the window 2 so as to protrude little by little.

■)・・・作用、効果 (1)・・・上記構成の本発明掘削ヘッドを掘削機に取
付けてボーリングを行うと、第1段のビットが摩耗する
と第2段のビットが現われて掘削し、第2段のビットが
摩耗すると第3段のビットが現われ、以下第n段まで次
段のビットが次々と現われて掘削するので、長距離のボ
ーリングでも掘削ヘッドの交換なしに作業を続行し得る
極めて秀れた効果を発揮し得る。
■) Actions and effects (1) When the drilling head of the present invention with the above configuration is attached to an excavator and boring is performed, when the first stage bit wears out, the second stage bit appears and excavates. When the second stage bit wears out, the third stage bit appears, and the next stage bits appear one after another up to the nth stage for drilling, so you can continue drilling long distances without replacing the drilling head. It can produce extremely excellent effects.

(2)・・・従って、前記従来の如き面倒な掘削へ・7
ドの交換、管理等が全て不用となって、従来の課題を有
効に解決し得る。
(2)...Therefore, the troublesome excavation as mentioned above is required.7
This eliminates the need for exchanging and managing all the codes, and the problems of the past can be effectively solved.

(3)・・・上記の如く、本発明掘削ヘッドによれば、
長距離掘削になるほど、その特長を発揮できて、従来に
比し格段に有利となり、作業簡単となり、作業時間、作
業人員、作業コス斗等の大幅な軽減を実現し得るもので
ある。
(3)...As mentioned above, according to the drilling head of the present invention,
The longer the distance is excavated, the more its features can be demonstrated, and it becomes much more advantageous than the conventional method, making the work easier and realizing a significant reduction in work time, work manpower, work cost, etc.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明掘削ヘッドの正面図、第2図は一部側面
図、第3図は展開説明図である。 付号 A・・・掘削ヘッド、 ノド、4・・・底辺部。 1・・・管体、2・・・窓、3・・・ビ葛 ビ・、l− 底辺郁
FIG. 1 is a front view of the excavation head of the present invention, FIG. 2 is a partial side view, and FIG. 3 is a developed explanatory view. Number A...Drilling head, throat, 4...Bottom part. 1...Tube body, 2...Window, 3...Bikatsubi...,l- Iku the bottom

Claims (4)

【特許請求の範囲】[Claims] (1)、掘削機の回転推進主軸にセットしてボーリング
を行う鋼管タイプの掘削ヘッドであり、管体周面の、円
周方向に第1段の窓を等間隔に穿設すると共に、軸線方
向に該第1段乃至第n段の窓を等間隔に穿設し、 各窓内にビットを固設して成る、 ボーリング用掘削ヘッド。
(1) It is a steel pipe type drilling head that is set on the rotary propulsion main shaft of an excavator to perform boring, and the first stage windows are bored at equal intervals in the circumferential direction on the circumferential surface of the pipe, and the axis A drilling head for boring, comprising windows of the first to nth stages drilled at equal intervals in the direction, and a bit fixed in each window.
(2)、掘削により前段のビットが摩耗消滅する前に、
次段のビットが順に露出するように、管体周面に窓及び
ビットを配設した、請求項1記載のボーリング用掘削ヘ
ッド。
(2) Before the bit in the previous stage wears out due to drilling,
2. The drilling head for boring according to claim 1, wherein windows and bits are arranged on the circumferential surface of the tube so that the bits of the next stage are sequentially exposed.
(3)、ビットを各窓の底辺部に、ろー着け、溶接等で
固設した、請求項1記載のボーリング用掘削ヘッド。
(3) The drilling head for boring according to claim 1, wherein the bit is fixed to the bottom of each window by brazing, welding, or the like.
(4)、ビットの一部を管体の外周面及び内周面から交
互に僅かずつ突出して窓の底辺部に固設した、請求項1
記載のボーリング用掘削ヘッド。
(4) Claim 1, wherein parts of the bits are alternately protruded slightly from the outer circumferential surface and inner circumferential surface of the tube and are fixed to the bottom part of the window.
Drilling head for boring as described.
JP2105927A 1990-04-21 1990-04-21 Drilling head for boring Expired - Lifetime JPH0749751B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2105927A JPH0749751B2 (en) 1990-04-21 1990-04-21 Drilling head for boring

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2105927A JPH0749751B2 (en) 1990-04-21 1990-04-21 Drilling head for boring

Publications (2)

Publication Number Publication Date
JPH045389A true JPH045389A (en) 1992-01-09
JPH0749751B2 JPH0749751B2 (en) 1995-05-31

Family

ID=14420492

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2105927A Expired - Lifetime JPH0749751B2 (en) 1990-04-21 1990-04-21 Drilling head for boring

Country Status (1)

Country Link
JP (1) JPH0749751B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004520944A (en) * 2000-10-17 2004-07-15 エフピーティー インダストリー エス.ピー.エー. 2-axis rotatable spindle head for machine tools

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55140580U (en) * 1979-03-26 1980-10-07

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55140580U (en) * 1979-03-26 1980-10-07

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004520944A (en) * 2000-10-17 2004-07-15 エフピーティー インダストリー エス.ピー.エー. 2-axis rotatable spindle head for machine tools

Also Published As

Publication number Publication date
JPH0749751B2 (en) 1995-05-31

Similar Documents

Publication Publication Date Title
CN113187499A (en) Weathering alteration belt TBM card machine escaping method
CN111441786A (en) Be applied to entry driving machine in special-shaped section tunnel
US4611417A (en) Non-rotatable tooth for a cylindrical socket bore
JPH045389A (en) Excavating head for boring
CN114439479A (en) A milling head for a shaft boring machine
CN217270189U (en) Milling head for drilling circular shafts
CN214886838U (en) A drill pipe guide device for assisting an impact rotary rock drill to complete the grooving operation
JPH09105289A (en) Drilling blade for all casing method
JP3245984U (en) Cut bucket for excavator
JP2001073663A (en) First tube for all-casing construction
JPH07324591A (en) Construction method of shield construction corresponding to geological changes
TW210371B (en) Digging operation method and device
CN217270188U (en) A milling head for a shaft boring machine
CN115748650B (en) Construction method of steel tube concrete wall structure for soft geological structure
KR20040012286A (en) A method for the trenchless horizontal tunnel using a pilot lod trench method and its apparatus
JP3267571B2 (en) Ground reinforcement method
JP3069190U (en) Screw for drilling and its head
CN221144311U (en) Reaming bit of rotary drilling rig
JP2531513B2 (en) Digging device
JPH1181369A (en) Excavator and its cutter bit for underground continuous wall
JP2861833B2 (en) Construction method of joints in continuous underground wall
JP2000160979A (en) Spiling pipe construction method for tunnel
CN114439480A (en) Milling head for drilling circular shafts
JPH06346699A (en) Underground space excavation method
JPH03180614A (en) Construction of retaining wall for underground structure

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090531

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100531

Year of fee payment: 15

EXPY Cancellation because of completion of term