- reinforcing bar
- bar assembly
- concrete
- board
- concrete plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
本発明は、コンクリート板と該コンクリート板に半埋設
状態で設けられた鉄筋組立体とで構成されたハーフPC
板、およびその製造方法に関するものである。The present invention provides a half PC constructed of a concrete plate and a reinforcing bar assembly provided semi-buried in the concrete plate.
The present invention relates to a plate and a method for manufacturing the same.
従来より、PC板(プレキャストコンクリート板)の中
には、補強部材がコンクリート板より半分突出して成る
ハーフPC板°と称されるものが提供されている。第
7図はハーフPC板の一構成例を示したもので、符号2
はコンクリート板、3はコンクリート板2に半埋設状態
に設けられた鉄筋組立体である。図示例のものでは前記
鉄筋組立体3は、鉄筋を平行弦または多角形断面に組ん
だトラス筋4となっている。
上記の如きハーフPC4i(1を作成するには、予め前
記トラス筋4 (鉄筋組立体3)を別途作成し、そのト
ラス筋4を、前記コンクリート板2を成型すべき型枠(
図示せず)内に設置し、その後前記型枠内にコンクリー
トCを前記トラス筋4が半埋設状態となるように打設し
て、打設したコンクリートCを硬化させればよい。
上記の如きハーフPCitは、現場にてコンクリート板
2つまり前記鉄筋組立体3側にコンクリート打ち足すこ
とにより一般的なRC遣(鉄筋コンクリート造)を構成
することができ、またその場合に前記コンクリート板2
が型枠として作用するといった利点がある。BACKGROUND ART Conventionally, among PC boards (precast concrete boards), there has been provided what is called a half PC board, in which a reinforcing member protrudes half from the concrete board. Fig. 7 shows an example of the configuration of a half PC board, with reference numeral 2.
3 is a concrete plate, and 3 is a reinforcing bar assembly semi-buried in the concrete plate 2. In the illustrated example, the reinforcing bar assembly 3 is a truss bar 4 in which reinforcing bars are assembled in a parallel chord or polygonal cross section. In order to create the half PC4i (1) as described above, the truss bar 4 (reinforcing bar assembly 3) is separately created in advance, and the truss bar 4 is used in the formwork (in which the concrete plate 2 is to be formed) (
(not shown), then concrete C is cast in the formwork so that the truss reinforcements 4 are partially buried, and the cast concrete C is allowed to harden. Half PCit as described above can be constructed into a general RC construction (reinforced concrete structure) by pouring concrete onto the concrete plate 2, that is, the reinforcing bar assembly 3 side at the site, and in that case, the concrete plate 2
It has the advantage that it acts as a formwork.
ところで、上記の如き従来のハーフPC板lにおいては
下記の如き不都合があった。
つまり、第8図に示すように前記コンクリート板2に、
そのコンクリート板2の外方部が前記鉄筋組立体3側に
反る変形現象を生じる場合が多いということである。最
近では建物外壁構成用として上記の如きハーフPC[1
を使用することか多いが、このようにハーフPC板1を
建物外壁に使用した場合には建物外面がフラットとなら
ず、外観が損なわれるといった不都合があった。なお、
第8図において符号5.5.・・・は建物外面を形成す
るために前記コンクリート板2の外面に付設されたタイ
ルを示している。
上記の如きハーフPC板1の反り変形は、該ハーフPC
ifi、tの作製時における前記コンクリートの収縮に
原因かあると考えられている。つまり、舶記ハーフPC
板1の工場製作時、前記コンクリート板2を構成するコ
ンクリートCを蒸気養生する際に、打設したコンクリー
トCの上面が急激に乾燥収縮するためと思われる。また
、ハーフPC板1の反り変形は、現場にて打ち足すコン
クリートの圧力によっても生ずる。
本発明は上記事情に鑑みてなされたもので、製作時にお
けるコンクリート板の反りを有効に防止してフラットな
製品となるハーフPC板と、その製造方法を提供するこ
とを目的とするものである。By the way, the conventional half PC board 1 as described above has the following disadvantages. That is, as shown in FIG. 8, on the concrete plate 2,
This means that the outer part of the concrete plate 2 often undergoes a deformation phenomenon in which it warps toward the reinforcing bar assembly 3. Recently, the above-mentioned half PC [1
However, when the half PC board 1 is used for the outer wall of a building in this way, there is a problem that the outer surface of the building is not flat and the appearance is impaired. In addition,
In FIG. 8, reference numeral 5.5. . . . indicates tiles attached to the outer surface of the concrete plate 2 to form the outer surface of the building. The warping deformation of the half PC board 1 as described above is caused by the warpage of the half PC board 1.
It is thought that the cause may be the shrinkage of the concrete during the production of ifi,t. In other words, Shipki Half PC
This seems to be because the upper surface of the poured concrete C rapidly shrinks during drying when the concrete C constituting the concrete plate 2 is steam-cured during manufacture of the plate 1 in a factory. Further, the warping deformation of the half PC board 1 is also caused by the pressure of concrete added at the site. The present invention has been made in view of the above circumstances, and aims to provide a half PC board that effectively prevents warpage of the concrete board during production and produces a flat product, and a method for manufacturing the same. .
【課題を解決するための手段]
本発明の請求項1記載の発明は、コンクリート板と該コ
ンクリート板に半埋設状態で設けられた鉄筋組立体とで
構成されたハーフPC板において、前記鉄筋組立体は、
前記コンクリート板を形成するコンクリートに埋設され
る前に予めむくりを付与されかつ前記むくりが解消する
ように載荷変形されたものであって、前記コンクリート
板には該鉄筋組立体の前記むくり方向への復帰力により
該コンクリート板の中央部を前記鉄筋組立体側に引っ張
るプレストレスが導入されていることを特徴とするもの
である。
また、本発明の請求項2記載の発明は、上記請求項1記
載のハーフPC板を製造する方法であって、前記鉄筋組
立体に予め該鉄筋組立体の長手方向に沿って湾曲するむ
くりを形成しておく工程と、むくりが形成された前記鉄
筋組立体に前記むくりが解消する方向の開型を加えて該
鉄筋組立体が略直線となるように変形拘束する工程と、
上記拘束された鉄筋組立体を、前記コンクリート板を成
型するための型枠内に設置する工程と、前記型枠内に、
前記拘束された鉄筋組立体が半埋設状態となるようにコ
ンクリートを打設する工程と、前記コンクリートの硬化
後に前記鉄筋組立体への拘束力を解除することにより、
形成されたコンクリート板に該コンクリート板の中央部
を鉄筋組立体側に引っ張るプレストレスを導入する工程
と、を有することを特徴とするものである。
【作用】
鉄筋組立体を予めむくりが付与された状態に組み立て、
この鉄筋組立体に前記むくりが解消する方向の力を加え
て拘束することにより、この鉄筋組立体には元の状態に
復帰しようとする方向の力が発生する。
よって、ハーフPC板を製造するにあたり、鉄筋組立体
に上記変形拘束を与えた上でコンクリートを打設し、該
コンクリートの硬化後に鉄筋組立体の変形拘束力を解く
ことにより、コンクリートには鉄筋組立体の復帰方向の
プレストレスが導入される。これによって、コンクリー
ト板の反りを防止することができる。[Means for Solving the Problems] The invention according to claim 1 of the present invention provides a half PC board composed of a concrete plate and a reinforcing bar assembly provided in a semi-buried state in the concrete plate. The solid is
The concrete plate is provided with a bulge in advance before being buried in concrete forming the concrete plate, and is loaded and deformed so that the bulge is eliminated, and the concrete plate has the bulge of the reinforcing bar assembly. The present invention is characterized in that a prestress is introduced that pulls the central portion of the concrete plate toward the reinforcing bar assembly by a return force in the direction. Further, the invention according to claim 2 of the present invention is a method for manufacturing the half PC board according to claim 1, wherein the reinforcing bar assembly is preliminarily curved along the longitudinal direction of the reinforcing bar assembly. and a step of deforming and constraining the reinforcing bar assembly so that it becomes a substantially straight line by opening the reinforcing bar assembly in the direction in which the bulging is eliminated;
installing the constrained reinforcing bar assembly in a formwork for forming the concrete plate;
By placing concrete so that the constrained reinforcing bar assembly is in a semi-buried state, and by releasing the restraining force on the reinforcing bar assembly after the concrete hardens,
This method is characterized by the step of introducing prestress into the formed concrete plate to pull the central portion of the concrete plate toward the reinforcing bar assembly. [Operation] Assemble the reinforcing bar assembly in a state where it has been exposed in advance,
By applying a force to this reinforcing bar assembly in a direction that eliminates the swelling and restraining it, a force is generated in this reinforcing bar assembly in a direction that causes it to return to its original state. Therefore, when manufacturing a half PC board, concrete is poured after applying the above deformation restraint to the reinforcing bar assembly, and after the concrete hardens, the deformation restraining force of the reinforcing bar assembly is released, so that the reinforcing bar assembly is not placed in the concrete. A prestress in the direction of solid return is introduced. This prevents the concrete plate from warping.
以下、本発明の実施例を図面を参照しながら説明する。
なお、説明の便宜上、本実施例では本発明の請求項2に
記載したハーフPC板の製造方法から説明するものとす
る。
第1図ないし第6図はそれぞれ本発明の請求項2に記載
したハーフPC板の製造方法の一実施例を示したもので
ある。
第1図は本発明の係るハーフPC板を構成する鉄筋組立
体3を示すもので、この場合、該鉄筋組立体3は主筋6
aとラチス筋6bとから構成されたトラス筋6となって
いる。このトラス筋6としては、第6図(a)に示すよ
うな平行弦トラス6Aであっても、第6図(b)に示す
ような三角立体トラス6Bであっても、また第6図(c
)に示すような四角立体トラス6Cであってもよい。こ
のトラス筋6は、前記主筋6aとラチス筋6bとを溶接
することにより組み立てる。ただし、このトラス筋6は
、第1図に示すように、予め該トラス筋6の長手方向沿
って湾曲するむくりHを付与して組み立てられている。
予め上記の如きトラス筋6 (鉄筋組立体3)を形成し
たら、第2図に示すように該トラス筋6を、製造すべき
ハーフPC板のコンクリート板を成型するための型枠7
内に設置する。その際、トラス筋6は型枠7に対し上方
に湾曲する如く設置する。
上記の如くむくりHが付与されたトラス筋6が型枠7内
に設置されたならば、そのトラス筋6の長手方向はぼ中
央部に下向きの力を付加することにより前記むくりHを
解消させる。すなわち、上方に湾曲していたトラス筋6
を第3図に示す如くほぼ直線となるように変形させるわ
けである。上記操作は、トラス筋6の両端部を支持した
上で、その中央最高部をジヤツキで下方に押圧するか、
あるいは中央最高部にワイヤ等のアンボンド緊張材を係
着して該緊張材を下方に引っ張ることなどにより実行さ
れる。
上記操作により前記トラス筋6をほぼ直線状態となるま
で変形させたら、第4図に示すようにその状態を保持し
たまま、つまり変形力を拘束した状態のまま前記型枠7
内にコンクリートCを打設する。目的とする製造物はハ
ーフPC板であるから、コンクリートCの打設厚は前記
トラス筋6がほぼ半分まで埋設される厚さである。
上記の如(コンクリートCが打設されたならば、従来同
様に蒸気養生により該コンクリートCの養生を行う。こ
の養生期間中もトラス筋6には上記拘束力を付与してお
く。
上記の養生により前記コンクリートCに所要の強度が発
現したら、第5図に示すように前記型枠7を脱型すると
共に、上記の拘束力も解除する。
上記コンクリートCが硬化することによりコンクリート
板2が形成され、これによって前記トラス筋6と該コン
クリート2とからなるハーフPCIilOが完成される
。
上記ハーフPC板10では、前記コンクリート2に該コ
ンクリート板2の中央部を前記トラス筋6側に引っ張る
力が働く。すなわち、トラス筋6は、予めむくりHを付
与されたものであり、かつそのむくりHが解消するよう
に載荷変形・拘束されたものであるから、拘束を解除さ
れた後の該トラス筋6には原形状に戻ろうとする力、つ
まりむくろうする力が働く。これにより、前記コンクリ
ート2にはトラス筋6のむくり方向へのプレストレスが
導入されたものとなるわけである。以て、上記ハーフP
C板IOでは、従来のハーフPC板l (第8図)の如
くコンクリート板2が反りを生ずることがない。そのた
め、該ハーフPC板10を建物外壁等に用いた場合でも
、反りの無いフラットな外壁面を形成することができ外
観上の質を向上させることができる。
上記において、トラス筋6の形成の際にに予め付与する
前記むくりHの量は形成すべきハーフPC板lの長さ、
コンクリート板2の厚さ、トラス筋6の曲げ剛性、設置
するトラス筋6の本数等に鑑み適宜設定されるものであ
る。
なお、実施例では、コンクリート2に半埋設状態に設け
る鉄筋組立体3をトラス筋6として説明したが、本発明
に係るハーフPC板において鉄筋組立体3はトラス筋に
限定されない。
また実施例では、本発明に係るハーフPC板を建物外壁
面構成用のものとして説明したが、上記ハーフPC板1
0は、従来よりハーフPC板が適用されている箇所に同
様に用いることができ、かつ上記同様の効果を得ること
ができる。例えば上記ハーフPC板10を小梁あるいは
スラブに適用すれば、前記トラス筋6の発生する上方へ
のプレストレスにより、それらの曲げ耐力を向上させる
ことができ、かつ撓みを防止することができる。Embodiments of the present invention will be described below with reference to the drawings. For convenience of explanation, in this example, the method for manufacturing a half PC board according to claim 2 of the present invention will be explained. 1 to 6 each show an embodiment of the method for manufacturing a half PC board according to claim 2 of the present invention. FIG. 1 shows a reinforcing bar assembly 3 constituting a half PC board according to the present invention. In this case, the reinforcing bar assembly 3 includes main bars 6
The truss muscle 6 is composed of the muscle a and the lattice muscle 6b. This truss bar 6 may be a parallel chord truss 6A as shown in FIG. 6(a), a triangular solid truss 6B as shown in FIG. 6(b), or a c.
) may be a square solid truss 6C as shown in FIG. This truss reinforcement 6 is assembled by welding the main reinforcement 6a and the lattice reinforcement 6b. However, as shown in FIG. 1, the truss bar 6 is assembled in advance by giving a bulge H that curves along the longitudinal direction of the truss bar 6. After forming the truss bars 6 (reinforcing bar assembly 3) as described above in advance, as shown in FIG.
Installed inside. At this time, the truss bar 6 is installed so as to curve upward with respect to the formwork 7. Once the truss bar 6 with the bulge H as described above is installed in the formwork 7, the bulge H is removed by applying a downward force to the longitudinal center of the truss bar 6. make it disappear. In other words, the truss muscle 6 that was curved upward
is deformed into a substantially straight line as shown in FIG. The above operation can be carried out by supporting both ends of the truss bar 6 and pressing the highest central part downward with a jack, or
Alternatively, this may be carried out by attaching an unbonded tension material such as a wire to the highest central portion and pulling the tension material downward. After the truss bar 6 is deformed into a substantially straight state by the above operation, the formwork 7 is held in that state, that is, with the deformation force restrained, as shown in FIG.
Concrete C is poured inside. Since the intended product is a half PC board, the thickness of the concrete C is such that the truss reinforcements 6 are buried approximately half way therein. Once the concrete C has been placed as described above, the concrete C is cured by steam curing as in the conventional method.During this curing period, the above-mentioned restraining force is applied to the truss bars 6.The above-mentioned curing When the concrete C has developed the required strength, the formwork 7 is removed and the restraining force is also released as shown in FIG. 5. As the concrete C hardens, the concrete plate 2 is formed. As a result, a half PCIilO consisting of the truss reinforcement 6 and the concrete 2 is completed. In the half PC board 10, a force acts on the concrete 2 to pull the center part of the concrete plate 2 toward the truss reinforcement 6. In other words, since the truss bar 6 has been given a bulge H in advance and has been loaded and deformed and restrained so that the bulge H is eliminated, the truss bar after the restraint is released. A force that tries to return to the original shape, that is, a peeling force acts on the reinforcement 6. As a result, a prestress is introduced into the concrete 2 in the direction of peeling of the truss reinforcement 6. Therefore, the above half P
With the C board IO, the concrete board 2 does not warp unlike the conventional half PC board 1 (FIG. 8). Therefore, even when the half PC board 10 is used for the outer wall of a building, a flat outer wall surface without warping can be formed, and the quality of the appearance can be improved. In the above, the amount of the peeling H provided in advance when forming the truss muscle 6 is the length of the half PC board l to be formed,
It is appropriately set in consideration of the thickness of the concrete plate 2, the bending rigidity of the truss bars 6, the number of truss bars 6 to be installed, etc. In addition, in the embodiment, the reinforcing bar assembly 3 provided semi-buried in the concrete 2 has been described as the truss bar 6, but the reinforcing bar assembly 3 in the half PC board according to the present invention is not limited to the truss bar. In addition, in the embodiment, the half PC board according to the present invention was explained as one for configuring the outer wall of a building, but the half PC board 1
0 can be used in the same way where half PC boards have been conventionally applied, and the same effects as above can be obtained. For example, if the half PC board 10 is applied to a small beam or slab, the upward prestress generated by the truss bars 6 can improve their bending strength and prevent deflection.
以上説明したとおり本発明によれば、ハーフPC板の製
造時において、コンクリートの収縮に起因して生ずる反
りを極力防止することができ、これによって反り、撓み
の少ないハーフPC板を縄供することかでき、ハーフP
C板を用いて構成される構造体の外観上の質を向上させ
ることができる。また、ハーフPC板自体の曲げ耐力の
向上も図れるので、現場にて打ち足すコンクリートの圧
力による反り、撓みの少ないハーフPC板となる、とい
った優れた効果を奏する。As explained above, according to the present invention, it is possible to prevent warping caused by shrinkage of concrete as much as possible during the production of half PC boards, and thereby to provide half PC boards with less warpage and deflection. Yes, half P
It is possible to improve the appearance quality of a structure constructed using C plates. Furthermore, since the bending strength of the half PC board itself can be improved, excellent effects can be achieved, such as a half PC board that is less likely to warp or bend due to the pressure of concrete poured on site.
第1図ないし第5図はそれぞれ本発明のハーフPC板の
東遣方法の一実施例を工程順に示す側面図、第6図(a
)ないし第6図(c)はそれぞれ当実施例に係る鉄筋組
立体を軸に直交した断面で見た断面図、第7図は従来の
ハーフPC板の一例を示す側断面図、第8図は建物外壁
構成用として適用されたハーフPC板を示した側断面図
である。
2・・・・・・コンクリート板、
3・・・・・・鉄筋組立体、
7・・・・・・型枠、
IQ・・・・・・ハーフPC板、
C・・・・・・コンクリート、
H・・・・・・むくり。
第1図Figures 1 to 5 are a side view and Figure 6 (a
) to 6(c) are sectional views of the reinforcing bar assembly according to this embodiment taken in a cross section perpendicular to the axis, FIG. 7 is a side sectional view showing an example of a conventional half PC board, and FIG. 8 1 is a side cross-sectional view showing a half PC board applied to construct an outer wall of a building. 2...Concrete plate, 3...Reinforcement assembly, 7...Formwork, IQ...Half PC board, C...Concrete 、H・・・・・・Mukuri. Figure 1
Claims (2)
で設けられた鉄筋組立体とで構成されたハーフPC板に
おいて、 前記鉄筋組立体は、前記コンクリート板を形成するコン
クリートに埋設される前に予めむくりを付与されかつ前
記むくりが解消するように載荷変形されたものであって
、該鉄筋組立体の前記むくり方向への復帰力により前記
コンクリート板には該コンクリート板の中央部を前記鉄
筋組立体側に引っ張るプレストレスが導入されているこ
とを特徴とするハーフPC板。(1) In a half PC board composed of a concrete plate and a reinforcing bar assembly provided semi-buried in the concrete plate, the reinforcing bar assembly is pre-buried before being buried in the concrete forming the concrete plate. The concrete plate has been given a bulge and has been deformed under load so that the bulge is eliminated, and the returning force of the reinforcing bar assembly in the direction of the bulge causes the concrete plate to have a center portion of the concrete plate as described above. A half PC board characterized by introducing prestress that pulls toward the reinforcing bar assembly.
で設けられた鉄筋組立体とで構成されるハーフPC板の
製造方法であって、 前記鉄筋組立体に予め該鉄筋組立体の長手方向に沿って
湾曲するむくりを形成しておく工程と、むくりが形成さ
れた前記鉄筋組立体に前記むくりが解消する方向の荷重
を加えて該鉄筋組立体が略直線となるように変形拘束す
る工程と、 上記拘束された鉄筋組立体を、前記コンクリート板を成
型するための型枠内に設置する工程と、前記型枠内に、
前記拘束された鉄筋組立体が半埋設状態となるようにコ
ンクリートを打設する工程と、 前記コンクリートの硬化後に前記鉄筋組立体への拘束力
を解除することにより、形成されたコンクリート板に該
コンクリート板の中央部を鉄筋組立体側に引っ張るプレ
ストレスを導入する工程と、を有することを特徴とする
ハーフPC板の製造方法。(2) A method for manufacturing a half PC board consisting of a concrete plate and a reinforcing bar assembly provided in a semi-buried state in the concrete plate, the method comprising: a step of forming a curved bulge by applying a load in a direction to eliminate the bulge to the reinforcing bar assembly on which the bulge has been formed, and deforming and restraining the reinforcing bar assembly so that it becomes substantially straight; a step of installing the constrained reinforcing bar assembly in a formwork for forming the concrete plate;
A step of pouring concrete so that the restrained reinforcing bar assembly is in a semi-buried state, and releasing the binding force to the reinforcing bar assembly after the concrete hardens, so that the concrete is placed in the formed concrete plate. A method for manufacturing a half PC board, comprising the step of introducing prestress to pull the central part of the board toward a reinforcing bar assembly.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16518290A JPH0455544A (en) | 1990-06-22 | 1990-06-22 | Half PC board and its manufacturing method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16518290A JPH0455544A (en) | 1990-06-22 | 1990-06-22 | Half PC board and its manufacturing method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH0455544A true JPH0455544A (en) | 1992-02-24 |
Family
ID=15807406
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP16518290A Pending JPH0455544A (en) | 1990-06-22 | 1990-06-22 | Half PC board and its manufacturing method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0455544A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH06346541A (en) * | 1992-12-25 | 1994-12-20 | Takenaka Komuten Co Ltd | Method for controlling floor deflection, and method for constructing steel framed multilayered building |
| US8763892B2 (en) | 2007-12-31 | 2014-07-01 | Oridon Medical 1987 Ltd. | Tube verifier |
-
1990
- 1990-06-22 JP JP16518290A patent/JPH0455544A/en active Pending
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH06346541A (en) * | 1992-12-25 | 1994-12-20 | Takenaka Komuten Co Ltd | Method for controlling floor deflection, and method for constructing steel framed multilayered building |
| US8763892B2 (en) | 2007-12-31 | 2014-07-01 | Oridon Medical 1987 Ltd. | Tube verifier |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR100343960B1 (en) | Steel concrete structure | |
| KR100500156B1 (en) | Prestress composite beam and method of manufacturing the same | |
| JPH0419137Y2 (en) | ||
| JP2568319B2 (en) | Manufacturing method of precast concrete beam | |
| JPH0455544A (en) | Half PC board and its manufacturing method | |
| JPS6145042A (en) | Mold frame for casting concrete | |
| JP2001032216A (en) | Execution method of cast-in-place prestressed concrete floor slab of box girder of closed section | |
| JPH0747535A (en) | Production of precast concrete member | |
| JPH05263491A (en) | Beam and floor structure | |
| JP2947979B2 (en) | Method of forming through holes in precast concrete members | |
| JPS6134539B2 (en) | ||
| JP2533344B2 (en) | Method for manufacturing half PCa board | |
| JPS60181452A (en) | How to build floorboards | |
| JP2533345B2 (en) | Form for half PCa board | |
| JP3029908B2 (en) | Construction method of concrete structure | |
| JP3442453B2 (en) | Reinforcing unit, precast formwork with built-in rebar, and method of manufacturing precast formwork with built-in rebar | |
| JP2982023B2 (en) | Beam for precast assembly method | |
| JPH0347352A (en) | Half pca board and slab-constructing method therewith | |
| JP2001323589A (en) | Concrete base plate and constructing method for slab | |
| JPS6327642A (en) | Method for introducing prestress into concrete slab | |
| JPH0266246A (en) | Insulating concrete with space truss and construction thereof | |
| KR100631031B1 (en) | PC plate and slab construction method of bridge using PC plate | |
| JP3198642B2 (en) | Prestressed concrete board | |
| JPH05311802A (en) | Precast structural member | |
| JPH0333348A (en) | Building frame construction column members and their manufacturing method |