JPH0460038A - Constructing method of large span dome roof - Google Patents

Constructing method of large span dome roof

Info

Publication number
JPH0460038A
JPH0460038A JP17119090A JP17119090A JPH0460038A JP H0460038 A JPH0460038 A JP H0460038A JP 17119090 A JP17119090 A JP 17119090A JP 17119090 A JP17119090 A JP 17119090A JP H0460038 A JPH0460038 A JP H0460038A
Authority
JP
Japan
Prior art keywords
dome roof
tower
frame
constructing
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP17119090A
Other languages
Japanese (ja)
Other versions
JP2858891B2 (en
Inventor
Takeshi Yamada
武 山田
Takeyuki Ooya
大屋 竹之
Yoshiaki Kodaira
小平 慶明
Hiroshi Nozawa
野沢 弘
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tomoe Corp
Original Assignee
Tomoe Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tomoe Corp filed Critical Tomoe Corp
Priority to JP17119090A priority Critical patent/JP2858891B2/en
Publication of JPH0460038A publication Critical patent/JPH0460038A/en
Application granted granted Critical
Publication of JP2858891B2 publication Critical patent/JP2858891B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To improve the workability and safety by assembling unit frames on both sides of a constructing tower on the ground, raising up the unit frames by wires, and lifting a frame material between adjacent unit frames by a cable crane. CONSTITUTION:Unit frames F are assembled on the ground successively from the side closer to constructing towers T, and raised up by hoisting devices 1 every completion of the assembling. Both ends situated on the outer circumference of a doom roof D are rotatably supported by anchors 3 on the ground, and a wire 4 is flatly erected between the middle part of the unit frame F and the hoisting device 1 of each constructing tower T in the direction orthogonal to the arrangement direction of the constructing tower T. The wire 4 is hoisted by the hoisting device 1, whereby, the unit frame F is successively raised up from the construction tower T side. A frame member 2 is lifted by a cable crane suspended between the constructing tower T and a cable tower.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は大スパンのドーム屋根を、その大部分を地上
で組み立てた後に起立させて構築する、大スパンドーム
屋根の構築方法に関するものである。出願人は先にこの
要領でドーム屋根を構築する方法を出願してある(特願
平2−132815号)が、本発明は前記発明を更に発
展させたものである。
[Detailed Description of the Invention] [Field of Industrial Application] The present invention relates to a method of constructing a large-span dome roof, which is constructed by assembling most of the large-span dome roof on the ground and then standing it upright. . The applicant has previously filed an application for a method of constructing a dome roof in this manner (Japanese Patent Application No. 132815/1999), and the present invention is a further development of the aforementioned invention.

〔従来技術及び発明が解決しようとする課題〕大スパン
ドーム屋根の構築は従来、主要な骨組を架設した後、こ
の骨組にトラス等を構成する単材を順次接続しながら、
もしくは予めある大きさにユニット化された単材からな
るフレームを組み込みながら行う方法が一般的であるが
、これらの方法はいずれも高所での作業に依存するため
地上から足場や支保工を多く設置することが必要となり
、施工性が悪く、また安全性にも問題がある。
[Prior Art and Problems to be Solved by the Invention] Conventionally, in the construction of a large span dome roof, after erecting the main frame, the single members constituting the trusses etc. were successively connected to this frame,
Alternatively, the common method is to incorporate a frame made of a single piece of material that has been made into units of a certain size in advance, but these methods all rely on work at heights and require a lot of scaffolding and shoring from the ground. This requires installation, which is difficult to construct, and also poses a safety problem.

そこで最近では、ドーム屋根を例えば中央部の架構とそ
の外周のリング状の架構とから構成し、その多くの部分
を地上で組み立て、両架構を接続した状態で双方をジヤ
ツキアップすることにより構築する、上記従来の問題を
解決する方法が開発されている。
Therefore, recently, dome roofs are constructed by, for example, constructing a central frame and a ring-shaped frame around the outer periphery, assembling most of the parts on the ground, and then jacking up both frames with the two frames connected. Methods have been developed to solve the above conventional problems.

しかしながら、ジヤツキアップによる方法では、屋根の
鉛直荷重を負担しながら上昇させることになるため特に
ドームの長径が数100mに及ぶ規模の場合には、ジヤ
ツキを含めた揚重装置とその付帯設備の大規模化を招き
、建方には膨大なコストを要することになる。
However, with the method of jacking up, the vertical load of the roof must be borne when the dome is lifted, so if the long diameter of the dome is several hundred meters long, the lifting equipment and its ancillary equipment, including the jacking, must be large-scale. This would lead to a huge increase in construction costs.

この発明はこうした従来の構築方法の実情を踏まえてな
されたもので、特に揚重装置の問題を克服する構築方法
を新たに提案しようとするものである。
This invention was made based on the actual situation of the conventional construction method, and particularly aims to propose a new construction method that overcomes the problems with the lifting device.

〔課題を解決するための手段〕[Means to solve the problem]

本発明では構築されるドーム屋根の中心部を通る線上に
複数本の構築用タワーを立設し、その両側にドーム屋根
の一部を構成するアーチ状の単位架構を地上で組み立て
、この単位架構の両端位置を地上に回転自在に支持させ
た状−態で、構築用タワーと単位架構の中間部間に張架
されるワイヤを巻き上げて構築を行うことにより揚重装
置の負担を軽減し、その小規模化を図る。
In the present invention, a plurality of construction towers are erected on a line passing through the center of the dome roof to be constructed, and arch-shaped unit frames forming part of the dome roof are assembled on the ground on both sides. The load on the lifting equipment is reduced by winding up the wire stretched between the construction tower and the intermediate part of the unit frame, with both ends of the unit rotatably supported on the ground. We aim to downsize it.

単位架構の引き起こしの際、鉛直荷重は地上に支持され
た状態にあるため、揚重装置は単位架構をモーメントに
抗して引き起こすのに要する能力を有すればよく、全重
量を支持しながら上昇させる、ジヤツキアップに使用さ
れる揚重装置に対し、小型で足りることになる。
When raising a unit frame, the vertical load is supported on the ground, so the lifting device only needs to have the ability to raise the unit frame against the moment, and it is possible to raise the unit frame while supporting the entire weight. This means that a smaller lifting device is sufficient for lifting equipment used for jacking up.

ワイヤの巻き上げにより引き起こされた、隣接する単位
架構間の架構は、ドーム屋根の外周に、その周方向に移
動自在に立設されたケーブルタワーと、中央部の構築用
タワー間に張架されたケーブルから懸垂するケーブルク
レーンでフレーム材を吊り上げ、その両端を単位架構に
接続することにより構築され、これによって全単位架構
が連続し、ドーム屋根が構成される。
The structure between adjacent unit frames caused by the winding of the wire is stretched between a cable tower that is movable in the circumferential direction around the outer periphery of the dome roof and a construction tower in the center. It is constructed by hoisting frame materials using a cable crane suspended from cables and connecting both ends to the unit frames, thereby making all the unit frames continuous and forming a dome roof.

ドーム屋根の内側には、ケーブルクレーンを利用してそ
の中心に位置する構築用タワーとドーム屋根の外周間に
、構築用タワーを軸として旋回自在に、半アーチ状に可
動足場が組み立てられ、この可動足場上でフレーム材同
士のボルトの本締め等が行われる。
Inside the dome roof, a movable scaffold was assembled in a semi-arch shape between the construction tower located at the center and the outer periphery of the dome roof using a cable crane, allowing it to pivot freely around the construction tower. Final tightening of bolts between frame members is performed on the movable scaffold.

ケーブルクレーンはまた、ドーム屋根上への屋根葺き材
の葺き作業に利用される。
Cable cranes are also used to install roofing material on dome roofs.

〔実施例〕〔Example〕

以下本発明を一実施例を示す図面に基づいて説明する。 The present invention will be explained below based on the drawings showing one embodiment.

この発明は第1図に示すように構築されるドーム屋[D
の中心部を通る線上に仮設される構築用タワーTを利用
して、その両側に地上で、寝た状態に組み立てられる単
位架構F、Fを引き起こすとともに、この単位架構F、
F間のフレーム材2を第3図に示すようにケーブルクレ
ーン5を用いて架設することによりドーム屋根りを構築
する方法である。
This invention is a dome shop constructed as shown in FIG.
Using the construction tower T, which is temporarily constructed on a line passing through the center of
This is a method of constructing a dome roof by erecting the frame material 2 between F using a cable crane 5 as shown in FIG.

構築用タワーTは第1図−■に示すようにドーム屋根り
の長径(直径)方向に適当な間隔を隔てて複数本立設さ
れ、その高さはドームのそれより大きく、またドームの
形態や勾配に応してそれぞれの高さが与えられる。
As shown in Figure 1-■, multiple construction towers T are erected at appropriate intervals in the long axis (diameter) direction of the dome roof, and their height is larger than that of the dome, and the shape and shape of the dome are larger than that of the dome. Each height is given depending on the slope.

この構築用タワーTの頂部の両側には単位架構F、Fを
起立させるためのウィンチ等の揚重装置1,1が設置さ
れる。
Lifting devices 1, 1 such as winches are installed on both sides of the top of the construction tower T for raising the unit frames F, F.

ケーブルクレーン5は第3図−1〜■に示すようにドー
ム屋根りの外周に、その周方向に移動自在に立設された
ケーブルタワー6と、中央部の構築用タワーTの頂部間
に張架されるケープル7から懸垂する。
The cable crane 5 is stretched between a cable tower 6 which is erected on the outer periphery of the dome roof so as to be movable in the circumferential direction, and the top of the construction tower T in the center, as shown in Fig. 3-1~■. It is suspended from the cable 7 to be hung.

ケーブルタワー6はドーム屋根りの全面を網羅するため
に第4図に示すように、ドーム屋根りの外周に敷設され
るタワー用レール8上に載り、中央部の構築用タワーT
を中心としてドーム屋根りの回りを周回自在に建てられ
、ケーフル7はこのケーブルタワー6と構築用タワーT
の両頂部間に架設される。
In order to cover the entire surface of the dome roof, the cable tower 6 rests on tower rails 8 laid around the outer periphery of the dome roof, as shown in FIG.
Cable tower 6 and construction tower T
It will be constructed between the tops of the

単位架構Fは第1図−■に一部ハッチングで示すように
平面的に、長径方向に架設されて並列するフレーム材2
.2で区切られる帯状の架構が例えば1区問おきに区分
された形に分割され、架設状態からそのまま寝かせた状
態で、アーチ状に、フレーム材2によりトラスをなして
組み立てられる。
The unit frame F is made up of frame members 2 that are installed parallel to each other in the longitudinal direction in a plane as shown by the partial hatching in Fig. 1-■.
.. A belt-shaped frame divided by 2 is divided into sections, for example, every other section, and is assembled in an arch shape with frame members 2 to form a truss in a lying state as it is from the erected state.

単位架構Fは構築用タワーTに近い側から順次地上で組
み立てられ、組み立てが完了する毎に揚重装置Iにより
引き起こされる。
The unit frames F are sequentially assembled on the ground starting from the side closest to the construction tower T, and each time the assembly is completed, they are lifted up by the lifting device I.

組み立てが完了した単位架構Fの、ドーム屋根りの外周
に位置する両端は第2図に示すように地上の例えばアン
カー3等に回転自在に軸支され、一方、単位架構Fの中
間部と各構築用タワーTの揚重装置lとの間にはワイヤ
4が架設される。
Both ends of the assembled unit frame F located on the outer periphery of the dome roof are rotatably supported on the ground, for example, by anchors 3, as shown in Figure 2, while the middle part of the unit frame F and each A wire 4 is installed between the construction tower T and the lifting device l.

ワイヤ4は平面的に構築用タワーTの配列方向に直交す
る方向に架設される。
The wire 4 is installed in a direction perpendicular to the arrangement direction of the construction towers T in a plane.

その後、揚重装置1でワイヤ4を巻き上げることにより
単位架構Fが構築用タワーT側から順次引き起こされる
Thereafter, by hoisting the wire 4 using the lifting device 1, the unit frames F are successively raised from the construction tower T side.

この引き起こし作業は構築用タワーTを挟んで両側の単
位架構F、  Fを独立して行うこともできるが、構築
用タワーTに転倒モーメントをかけず、バランスを取り
ながら行うためには、図示するように両側の単位架構F
、Fを同時に引き起こすことが好ましい。
This raising work can be done independently for the unit frames F and F on both sides of the construction tower T, but in order to do it while maintaining balance without applying any overturning moment to the construction tower T, it is necessary to do it as shown in the diagram. Unit frame F on both sides like this
, F are preferably caused simultaneously.

起立し、並列する単位架構F、F間の架構は第3図−■
〜■に示すように、単位架構Fと同一のフレーム材2か
らある区間だけユニット化されて組み立てられた部材を
ケーブルクレーン5で吊り上げて所定位置に配置し、こ
れを単位架構F、Fに接続することにより構築され、第
2図に示すように単位架構F、Fが連続する。
The structure between unit frames F and F that stand up and are parallel is shown in Figure 3-■
As shown in ~ ■, a certain section of the same frame material 2 as the unit frame F is assembled into a unit, and the cable crane 5 lifts it up and places it in a predetermined position, and connects it to the unit frames F and F. As shown in FIG. 2, the unit frames F and F are continuous.

第3図は各単位架構Fを引き起こす毎に、その間のフレ
ーム材2を吊り上げて接続を行う方法を示しているが、
この単位架構F、  F間へのフレーム材2の接続は全
単位架構Fの引き起こしが終了した後に行うこともでき
る。
Fig. 3 shows a method of connecting each unit frame F by lifting the frame material 2 between them each time the unit frame F is raised.
The frame material 2 can be connected between the unit frames F and F after all the unit frames F have been raised.

単位架構Fのフレーム材2と、ケーブルクレーン5で吊
り上げられるフレーム材2との接合、すなわちボルトの
本締めは、第3図−■に示すようにドーム屋IIDの内
側に、中央部の構築用タワーTとドーム屋根りの外周と
の間に組み立てられる可動足場9を利用して行われる。
The connection between the frame material 2 of the unit frame F and the frame material 2 lifted by the cable crane 5, that is, the final tightening of the bolts, is performed inside the dome building IID as shown in Figure 3-■. This is done using a movable scaffold 9 assembled between the tower T and the outer periphery of the dome roof.

可動足場9上ではまた、フレーム材2への塗装等の仕上
げ作業も行われる。
Finishing work such as painting the frame material 2 is also performed on the movable scaffold 9.

可動足場9は第4図に示すようにケーブルタワー6と同
様に、ドーム屋根りの周囲に沿って敷設される足場用レ
ール10上に載り、構築用タワーTを軸として旋回自在
に、第3図−■に示すようにケーブルクレーン5を利用
して半アーチ状に組み立てられる。可動足場9の中心側
は構築用タワーTの中間部に突設される架台ll上に載
置される。
As shown in FIG. 4, like the cable tower 6, the movable scaffold 9 rests on scaffolding rails 10 laid along the periphery of the dome roof, and is able to pivot freely around the construction tower T. As shown in Figure 2, it is assembled into a semi-arch shape using a cable crane 5. The center side of the movable scaffold 9 is placed on a pedestal 11 projecting from the middle part of the construction tower T.

可動足場9の架設時、その旋回時の衝突を避ける必要か
ら中央部以外の構築用タワーTは撤去される。
When the movable scaffold 9 is erected, the construction tower T other than the central part is removed because it is necessary to avoid collisions when the movable scaffold 9 turns.

フレーム材2.2同士の現場接合完了後、すなわちドー
ム屋根りの構築終了後、第3図−■に示すようにケーブ
ルクレーン5を利用してドーム屋根り上に屋根葺き材1
2が葺がれる。
After the on-site joining of the frame materials 2.2 is completed, that is, after the construction of the dome roof is completed, the roofing material 1 is placed on the dome roof using a cable crane 5, as shown in Fig. 3-■.
2 will be roofed.

屋根葺きの終了後、ケーブルタワー6と可動足場9を撤
去してドーム屋根りの全施工が完了する。
After the roofing is completed, the cable tower 6 and movable scaffolding 9 are removed and the entire construction of the dome roofing is completed.

〔発明の効果〕〔Effect of the invention〕

この発明は以上の通りであり、ドーム屋根を複数個のア
ーチに分割した形の単位架構を地上で組み立て、これを
ドーム屋根の中央部に仮設される構築用タワーを利用し
て引き起こすことによってドーム屋根を構築するもので
あるため、架構の多くの組み立てが地上での作業によっ
て行われ、施工性と安全性が高い。
This invention is as described above, and by assembling a unit frame in the form of a dome roof divided into a plurality of arches on the ground, and raising it using a construction tower temporarily installed in the center of the dome roof, a dome can be built. Since it is used to construct a roof, much of the frame is assembled on the ground, making it easy to construct and safe.

また、単位架構は単に引き起こすことのみによって所定
の架設状態となるため、組立状態から起立状態に至るま
でに揚重装置には大きな能力を必要とせず、揚重装置や
その付帯設備を小規模化することでき、建設コストの低
減を図ることができる。
In addition, since the unit frame is brought into the specified erection state simply by being raised, the lifting equipment does not require a large capacity from the assembled state to the erected state, allowing the lifting equipment and its ancillary equipment to be made smaller. Therefore, it is possible to reduce construction costs.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図−1はドーム屋根の架設例を示した平面図、■は
その中心を通る断面図、第2図はその斜視図、第3図−
■〜■は本発明の施工手順を示した立面図、第4図はケ
ーブルクレーンと可動足場の配置状態を示した平面図で
ある。 D・・・・・・ドーム屋根、T・・・・・・構築用タワ
ー、F・・・・・・単位架構、l・・・・・・揚重装置
、2・・・・・・フレーム材、3・・・・・・アンカー
、4・・・・・・ワイヤ、5・・・・・・ケーブルクレ
ーン、6・・・・・・ケーブルタワー、7・・・・・・
ケーブル、8・・・・・・タワー用レール、9・・・・
・・可動足場、10・・・・・・足場用レール、11・
・・・・・架台、12・・・・・・屋根葺き材。
Figure 1-1 is a plan view showing an example of the construction of a dome roof, ■ is a sectional view passing through its center, Figure 2 is a perspective view, and Figure 3-
(1) to (2) are elevational views showing the construction procedure of the present invention, and Fig. 4 is a plan view showing the arrangement of the cable crane and movable scaffolding. D...Dome roof, T...Construction tower, F...Unit frame, l...Lifting device, 2...Frame Material, 3... Anchor, 4... Wire, 5... Cable crane, 6... Cable tower, 7...
Cable, 8...Tower rail, 9...
...Movable scaffolding, 10...Scaffolding rail, 11.
... Frame, 12... Roofing material.

Claims (3)

【特許請求の範囲】[Claims] (1)構築されるドーム屋根の中心部を通る線上に立設
される複数本の構築用タワーを利用して大スパンのドー
ム屋根を構築する方法であり、ドーム屋根の一部を構成
するアーチ状の単位架構を構築用タワーの両側に、地上
で組み立て、この単位架構の両端を地上側に回転自在に
支持させた状態で、単位架構の中間部と構築用タワー間
に張架されるワイヤを巻き上げながら単位架構を引き起
こす一方、ドーム屋根の外周に、その周方向に移動自在
に立設されたケーブルタワーと、ドーム屋根の中心に位
置する構築用タワーとの間に張架されたケーブルから懸
垂するケーブルクレーンで隣接する単位架構間のフレー
ム材を吊り上げ、これを両単位架構に接続して隣接する
単位架構を連続させ、ドーム屋根を構築する大スパンド
ーム屋根の構築方法。
(1) A method of constructing a large-span dome roof using multiple construction towers erected on a line passing through the center of the dome roof, and an arch that forms part of the dome roof. A unit frame of the shape is assembled on the ground on both sides of the construction tower, and with both ends of the unit frame rotatably supported on the ground side, a wire is stretched between the middle part of the unit frame and the construction tower. While winding up the unit frame, the cables stretched between the cable tower, which is movable in the circumferential direction on the outer periphery of the dome roof, and the construction tower located at the center of the dome roof. A method of constructing a large-span dome roof in which a suspended cable crane lifts the frame material between adjacent unit frames, connects it to both unit frames, and connects the adjacent unit frames to create a dome roof.
(2)ケーブルクレーンを利用してドーム屋根の内側に
、その中心に位置する構築用タワーとドーム屋根の外周
間に、フレーム材同士のボルトの本締めを行うための可
動足場を、構築用タワーを軸として旋回自在に、半アー
チ状に組み立てることを特徴とする第1請求項記載の大
スパンドーム屋根の構築方法。
(2) Using a cable crane, a movable scaffold was installed inside the dome roof, between the construction tower located at the center and the outer periphery of the dome roof, in order to fully tighten the bolts between the frame materials. 2. The method of constructing a large span dome roof according to claim 1, wherein the roof is assembled in a semi-arch shape so as to be freely pivotable about the axis.
(3)ケーブルクレーンを利用してドーム屋根上に屋根
葺き材を葺くことを特徴とする第1請求項記載の大スパ
ンドーム屋根の構築方法。
(3) The method for constructing a large span dome roof according to claim 1, characterized in that the roofing material is placed on the dome roof using a cable crane.
JP17119090A 1990-06-28 1990-06-28 Construction method of large span dome roof Expired - Fee Related JP2858891B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17119090A JP2858891B2 (en) 1990-06-28 1990-06-28 Construction method of large span dome roof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17119090A JP2858891B2 (en) 1990-06-28 1990-06-28 Construction method of large span dome roof

Publications (2)

Publication Number Publication Date
JPH0460038A true JPH0460038A (en) 1992-02-26
JP2858891B2 JP2858891B2 (en) 1999-02-17

Family

ID=15918681

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17119090A Expired - Fee Related JP2858891B2 (en) 1990-06-28 1990-06-28 Construction method of large span dome roof

Country Status (1)

Country Link
JP (1) JP2858891B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8649416B2 (en) 2009-04-01 2014-02-11 Sony Corporation Signal processing apparatus, information processing apparatus, signal processing method, data display method, and program
CN111395533A (en) * 2020-03-30 2020-07-10 中铁二局第一工程有限公司 Multi-mechanism resultant force air overturning construction method for large-span arc-shaped latticed shell structure
CN112962980A (en) * 2021-02-22 2021-06-15 中国二十二冶集团有限公司 Construction method applying tie method in large-span net frame walking frame

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8649416B2 (en) 2009-04-01 2014-02-11 Sony Corporation Signal processing apparatus, information processing apparatus, signal processing method, data display method, and program
CN111395533A (en) * 2020-03-30 2020-07-10 中铁二局第一工程有限公司 Multi-mechanism resultant force air overturning construction method for large-span arc-shaped latticed shell structure
CN112962980A (en) * 2021-02-22 2021-06-15 中国二十二冶集团有限公司 Construction method applying tie method in large-span net frame walking frame

Also Published As

Publication number Publication date
JP2858891B2 (en) 1999-02-17

Similar Documents

Publication Publication Date Title
CN110905261A (en) Ultra-large-span closed stock ground structure for multiple material piling and taking machines and construction method thereof
CN107816209A (en) The large-scale Roof Truss construction technology of installation is lifted across outer both sides
CN117364923B (en) A cable-stayed space frame structure and its construction method
JP3794465B2 (en) Mobile gantry for dome roof construction and construction method
CN113404199B (en) Installation method of umbrella-shaped roof structure
US4276733A (en) Method of constructing and erecting a dome-shaped structure
JPH06200625A (en) Frame method of arch truss construction
JPH0460038A (en) Constructing method of large span dome roof
JPH0571225A (en) Temporarily set roof of complete weather type
CN116122579B (en) Hoisting method for bidirectional bending dome bracket
CN114776035B (en) Construction method of oblique spoke type cable truss structure
JP2946074B2 (en) Large roof erection method
JPH09177377A (en) Tent warehouse and constructing method therefor
JPH0718743A (en) Construction method for large span domelike roof
JPH0460059A (en) Steel structure building method
JPH0427046A (en) Method for constructing large-space dome roof
JP2690822B2 (en) Steel construction method for low-rise buildings
JPH04297668A (en) Climbing type all-weather roof for construction work
CN110820564B (en) Liftable and openable bent cap construction overhaul multipurpose platform
JP2876991B2 (en) Steel frame method for high-rise buildings
JPH01295944A (en) Roofing work of large-sized construction
JPS6035512B2 (en) Erection equipment for tower-like structures
CN117166771A (en) A safe and rapid construction method for assembling and hoisting steel trusses on the roof of a gymnasium
JP2994205B2 (en) Structural assembly method
JPH10204997A (en) Cable dome erecting method

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees