JPH0489917A - Executing method for rubble mound - Google Patents

Executing method for rubble mound

Info

Publication number
JPH0489917A
JPH0489917A JP20507690A JP20507690A JPH0489917A JP H0489917 A JPH0489917 A JP H0489917A JP 20507690 A JP20507690 A JP 20507690A JP 20507690 A JP20507690 A JP 20507690A JP H0489917 A JPH0489917 A JP H0489917A
Authority
JP
Japan
Prior art keywords
caisson
rubble
rubble mound
sunk
mound
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP20507690A
Other languages
Japanese (ja)
Other versions
JPH0694666B2 (en
Inventor
Junichi Hamasuna
順一 浜砂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toa Corp
Original Assignee
Toa Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toa Corp filed Critical Toa Corp
Priority to JP20507690A priority Critical patent/JPH0694666B2/en
Publication of JPH0489917A publication Critical patent/JPH0489917A/en
Publication of JPH0694666B2 publication Critical patent/JPH0694666B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

PURPOSE:To perform operation accurately and effectively even in a place with large surges by installing a caisson capable of sunk installation and coming up by buoyance to the water surface in such a way as sunk at the foremost of a reclamation district, putting in rubbles and surface course finishing rubbles, and performing the grading by the use of dead-weight. CONSTITUTION:A caisson 1 capable of sunk installation and coming up by buoyancy to the water surface is furnished, comprising an upper steel pipe structure 2 and a lower caisson 3 admitting water injection and exhaust. This caisson 1 is sunk at the foremost of a rubble mound reclamation district, and there rubbles 11... are slung in. Thereon surface course finishing rubbles 7, 7 are put by a crawler crane 8 installed on the upper stage 6 of the caisson 1. Grading of the rubble mound is performed by the use of a dead-weight 13 fixed to this crawler crane 8. Then the caisson 1 is allowed to come up to the water surface and moved to the next place specified, and the same procedures are repeated.

Description

【発明の詳細な説明】 〔産業の利用分野〕 本発明は、沖合の波浪が大きい場所でも施工可能な捨石
マウントの施工方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for constructing a rubble mount that can be constructed even in offshore locations where waves are large.

(従来の技術〕 従来、防波堤などの海上構造物を築造するためには、そ
の設置位置の海底に、捨石マウンドを作ることになるが
、その捨石マウンドを施工するには、捨石マウンド造成
区域に、ガツト船で捨石を投入した後、その上にさらに
表層仕上用捨石を投入し、さらに、クレーン船に重錘を
取付け、その重錘を落下させて捨石マウンドの均しを行
なっていた。
(Conventional technology) Conventionally, in order to construct offshore structures such as breakwaters, a rubble mound is created on the seabed at the installation location, but in order to construct the rubble mound, it is necessary to After the rubble was thrown in by a Gatsuto ship, surface finishing rubble was thrown on top of it, and then a weight was attached to the crane ship and the weight was dropped to level the rubble mound.

しかしながら、波浪が大きい場所では、波浪によりクレ
ーン船の船体が動揺して、重錘を所定の捨石上の位置に
落下できず、作業が容易でないばかりでなく、作業能率
も悪く、しかも正確な捨石均し作業が行なわれないとい
う問題点があった。
However, in areas with large waves, the hull of the crane ship shakes due to the waves, making it impossible to drop the weight onto the designated rubble, making the work not only difficult but also inefficient, as well as making it difficult to accurately place the rubble. There was a problem that leveling work was not performed.

〔発明の解決しようとする課題〕[Problem to be solved by the invention]

本発明は、前記従来の問題点を解決するためになされた
ものであり、波浪が大きい場所でも、正確な捨石マウン
ドの施工が容易に、かつ能率良く行ないうる捨石マウン
ドの施工方法を提供することを解決課題としたものであ
る。
The present invention has been made in order to solve the above-mentioned conventional problems, and it is an object of the present invention to provide a method for constructing a rubble mound that allows accurate construction of a rubble mound to be carried out easily and efficiently even in places with large waves. is the problem to be solved.

(課題を解決するための手段] 上記の課題を解決するための手段として、本発明の捨石
マウンドの施工方法は、捨石マウンド造成区域の先端に
、沈設及び浮上が可能なケーソンを沈設の後、その捨石
マウンド造成区域上に捨石を投入した上に、そのケーソ
ンの上部ステージに設置したクローラクレーンにより表
層仕上げ用捨石を投入し、そしてクローラクレーンに取
付けた重錘で捨石マウンドの均しを行なった後、このケ
ーソンを浮上させて適宜な位置に移動して沈設させ、上
記の手順を繰り返し行なうことを特徴としたものであり
、表層仕上用捨石の投入及び重錘による捨石マウンドの
均しか、海底上に固定されたケーソン上のクローラクレ
ーンによって安定した状態のもとで行なわれる。
(Means for Solving the Problems) As a means for solving the above problems, the method for constructing a rubble mound of the present invention includes: After sinking a caisson that can be sunk and floated at the tip of a rubble mound construction area, In addition to putting rubble onto the rubble mound creation area, a crawler crane installed on the upper stage of the caisson put in rubble for surface finishing, and the rubble mound was leveled with a weight attached to the crawler crane. After that, this caisson is floated, moved to an appropriate position, and sunk, and the above steps are repeated.The method consists of adding rubble for surface finishing and leveling the rubble mound with a weight, or placing it on the seabed. It is carried out under stable conditions by a crawler crane on a caisson fixed above.

また、上記の施工時に用いられる沈設及び浮上が可能な
ケーソンとして、注排水可能な下部ケーソン及び上部鋼
管構造部とからなるケーソンを用いることが、波浪を上
部鋼管構造部で通過させ、波浪の影響を小さくするので
好ましい。
In addition, as a caisson that can be sunk and floated during the above construction, it is possible to use a caisson consisting of a lower caisson that can be filled with water and an upper steel pipe structure, which allows waves to pass through the upper steel pipe structure and prevents the influence of waves. This is preferable because it makes it smaller.

〔実施例〕〔Example〕

以下図面を参照して本発明の施工方法により捨石マウン
ドを施工する実施例について説明するが、第1図はその
一実施例における施工例を示す捨石均し時の状況説明用
側面図、第2図から第5図までは、その捨石マウンドの
施工手順を示す一連の側面図である。
An embodiment of constructing a rubble mound using the construction method of the present invention will be described below with reference to the drawings. 5 to 5 are a series of side views showing the construction procedure of the rubble mound.

まず、この施工例に使用しているケーソン1は、第1図
に示すごとく、内部に注排水が可能な下部ケーソン3及
びその下部ケーソン3上に立ち上がった等間隔の鋼管2
Aからなる上部鋼管構造部2からなっており、各鋼管2
Aは筋違2B、水平筋違2Cで強固に補強されており、
このケーソン1を最終的に防波堤などの本体構造物とし
て使用する時に、内部に中詰材を充填するための仕切用
コンクリート版を挿入するための挿入溝゛5が各側端部
の各鋼管2Aに設けられ、また水面W付近には防舷材4
が取付けられている。
First, as shown in Fig. 1, the caisson 1 used in this construction example consists of a lower caisson 3 into which water can be poured, and 2 steel pipes 2 at equal intervals rising above the lower caisson 3.
It consists of an upper steel pipe structure section 2 consisting of A, and each steel pipe 2
A is strongly reinforced with braces 2B and horizontal braces 2C,
When this caisson 1 is finally used as a main structure such as a breakwater, an insertion groove 5 is provided at each side end of each steel pipe 2A for inserting a partition concrete slab for filling the inside with filling material. fender 4 near the water surface W.
is installed.

なお、下部ケーソン3の注排水は、上部鋼管構造部2の
複数の鋼管2A内を利用して行うようになっており、そ
の鋼管2Aの上端には開閉自在な蓋を設け、その下端は
ケーソン3内へ開口している。
In addition, the lower caisson 3 is filled with water using the inside of a plurality of steel pipes 2A of the upper steel pipe structure 2, and the upper end of the steel pipe 2A is provided with a lid that can be opened and closed, and the lower end of the caisson It opens into 3.

また、このケーソン1の上には、上部ステージ6が水面
Wの上になるように設けられており、この上部ステージ
6上には、表層仕上げ用捨石7が載置されると共に、ク
ローラクレーン8が設置されている。
Further, an upper stage 6 is provided above the caisson 1 so as to be above the water surface W, and on this upper stage 6, rubble 7 for finishing the surface layer is placed, and a crawler crane 8 is installed.

次に、上記のケーソン1を用いて捨石マウンドの施工を
行なう手順について第2図から第5図の順に説明する。
Next, the procedure for constructing a rubble mound using the above caisson 1 will be explained in the order of FIGS. 2 to 5.

まず、上記ケーソン1を第2図のごとく、捨石マウンド
造成区域の先端の海底B上に、下部ケーソン3内に注水
することで沈設した後、ガツト船10などにより捨石1
1をその捨石マウンド造成区域の海底B上に投入する。
First, as shown in Figure 2, the caisson 1 is sunk on the seabed B at the tip of the rubble mound creation area by injecting water into the lower caisson 3, and then the rubble
1 onto the seabed B in the rubble mound creation area.

この場合のケーソン1の移動、沈設は、下部ケーソン3
内を排水して、ケーソンlを浮上させ、アンカーにより
所定位置まで移動させ、下部ケーソン3内へ注水して行
なうものである。
In this case, the movement and sinking of caisson 1 is carried out by lower caisson 3.
This is done by draining the inside of the lower caisson 3, floating the caisson 1, moving it to a predetermined position using an anchor, and injecting water into the lower caisson 3.

次に、ケーソンlの上部ステージ6に運搬して載置され
た表層仕上用捨石7を、第3図のごとく、上部ステージ
6上に設置されたクローラクレーン8により、第2図で
投入の捨石ll上の所定の位置に投入する。
Next, the surface finishing rubble 7 transported and placed on the upper stage 6 of the caisson 1 is transported and placed on the upper stage 6 of the caisson l by a crawler crane 8 installed on the upper stage 6, as shown in Fig. 2. Insert it into the designated position on the ll.

その後、上記クローラクレーン8に重錘13を取付け、
第4図のごとく、投入された表層仕上用捨石7の上から
捨石マウンドの均しを行なう。
After that, the weight 13 is attached to the crawler crane 8,
As shown in FIG. 4, the rubble mound is leveled from above the surface finishing rubble 7 that has been thrown in.

以上のごとく、所定の捨石マウンド造成区域の均しか終
了したら、下部ケーソン3内を排水してケーソンlを浮
上させ、第5図のごとく、適宜な位置に移動し沈設させ
た上で、第2図以降の手順を繰り返し行なうどとで捨石
マウンドの施工が行なわれる。
As described above, when the leveling of the designated rubble mound creation area is completed, the inside of the lower caisson 3 is drained, the caisson L is floated, and as shown in Fig. 5, the caisson L is moved to an appropriate position and sunk, and then the second The rubble mound is constructed by repeating the steps shown in the figure.

さらに、すべての均し作業が終了した後に、ケーソン1
を捨石マウンド上に据え付け、下部ケーソン内に複数の
鋼管2A内を通じて中詰砂をスラリー輸送により注入し
、上部鋼管構造部2の各側端部の各鋼管に設けられた挿
入溝5に仕切用コンクリート版を挿入して、鋼管の間の
隙間を塞ぎ、中詰材を充填してケーソンlを防波堤など
の本体構造物として使用することも可能である。
Furthermore, after all leveling work is completed, caisson 1
is installed on a rubble mound, and filler sand is injected into the lower caisson through a plurality of steel pipes 2A by slurry transport, and into the insertion grooves 5 provided in each steel pipe at each side end of the upper steel pipe structure 2 for partitioning. It is also possible to use the caisson I as a main structure such as a breakwater by inserting concrete slabs to close the gaps between the steel pipes and filling them with filler material.

なお、上記の施工例では、上方に上部鋼管構造部2を、
そして下方に注排水可能な下部ケーソン3を有するケー
ソン1を使用することで、上方で波浪が通過しやすい構
造として、波浪に対する抵抗を小さくするようにしてい
るが、勿論上記実施例のケーソンlに限定するものでは
なく、そのケーソン本体内部の注排水により沈設及び浮
上が可能な、上下一体のケーソンなど、どのようなケー
ソンを用いても本発明の捨石マウンド施工方法を適用す
ることができる。
In addition, in the above construction example, the upper steel pipe structure section 2 is placed above.
By using a caisson 1 having a lower caisson 3 that can pour water downward, the structure allows waves to easily pass through the upper part and reduces resistance to waves.Of course, the caisson 1 of the above embodiment The rubble mound construction method of the present invention can be applied to any type of caisson, including, but not limited to, a caisson with an upper and lower structure that can be sunk and floated by water injected into the caisson body.

〔発明の効果] 以上に説明したごとく、本発明の施工方法によれば、捨
石上に投入される表層仕上用捨石の投入作業及び均し作
業を、海底上に固定されたケーソンの上部ステージから
行なうので、波浪が大きい場所でも正確に、かつ能率良
く行なうことができるという効果がある。
[Effects of the Invention] As explained above, according to the construction method of the present invention, the work of charging and leveling the surface finishing rubble to be thrown onto the rubble is carried out from the upper stage of the caisson fixed on the seabed. This has the advantage that it can be carried out accurately and efficiently even in areas with large waves.

また、上部鋼管構造部のごとく波浪が通過する構造を有
するケーソン1を用いれば、ケーソンの波浪に対する抵
抗が少なくなり、それだけケーソンの構造を小さくでき
て経済的であるとともに、この場合、ケーソンの沈設及
び浮上のための注排水に、上部鋼管構造部の鋼管を利用
できるので、注排水の作業が容易になるという利点があ
る。
In addition, if the caisson 1 is used, which has a structure through which waves pass, such as the upper steel pipe structure, the resistance of the caisson to waves will be reduced, and the structure of the caisson can be made smaller, which is economical. And since the steel pipe of the upper steel pipe structure can be used for the water supply for flotation, there is an advantage that the work for the water supply becomes easy.

さらに、ケーソンを均し作業が終了した後に本体構造物
として使用すれば、捨石マウンド施工用の設備を本体構
造物に転用することになり、経済的である。
Furthermore, if the caisson is used as the main structure after the leveling work is completed, equipment for constructing rubble mounds can be used for the main structure, which is economical.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の捨石マウンド施工方法により捨石マウ
ンドを施工する一実施例による捨石均し時の状況説明用
側面図、第2図から第5図までは、第1図による施工手
順を示す一連の側面図である。 1・・・ケーソン、2・・・上部鋼管構造部、3・・・
下部ケーソン、6・・・上部ステージ、7・・・表層仕
上用捨石、8・・・クローラクレーン、11・・・捨石
、13・・・重錘。 代理人 弁理士 小 川 信 −
Fig. 1 is a side view for explaining the situation during leveling of rubble according to one embodiment of constructing a rubble mound by the rubble mound construction method of the present invention, and Figs. 2 to 5 show the construction procedure according to Fig. 1. FIG. 3 is a series of side views. 1... Caisson, 2... Upper steel pipe structure, 3...
Lower caisson, 6... Upper stage, 7... Rubble for surface finishing, 8... Crawler crane, 11... Rubble, 13... Weight. Agent Patent Attorney Nobuo Ogawa −

Claims (1)

【特許請求の範囲】 1、捨石マウンド造成区域の先端に、沈設及び浮上が可
能なケーソンを沈設の後、その捨石マウンド造成区域上
に捨石を投入した上に、該ケーソンの上部ステージに設
置したクローラクレーンにより表層仕上用捨石を投入し
、そしてクローラクレーンに取付けた重錘で捨石マウン
ドの均しを行なった後、該ケーソンを浮上させ適宜な位
置に移動して沈設させて上記の手順を繰り返し行なう捨
石マウンドの施工方法。 2、沈設及び浮上が可能なケーソンに、注排水可能な下
部ケーソン及び上部鋼管構造部とからなるケーソンを使
用する請求項1記載の捨石マウンドの施工方法。
[Claims] 1. After a caisson that can be sunk and floated is placed at the tip of a rubble mound creation area, rubble is thrown onto the rubble mound creation area, and then installed on the upper stage of the caisson. After loading rubble for surface finishing using a crawler crane and leveling the rubble mound with a weight attached to the crawler crane, the caisson is floated, moved to an appropriate position, set down, and the above steps are repeated. Construction method of rubble mound. 2. The method for constructing a rubble mound according to claim 1, wherein a caisson that can be sunk and floated includes a lower caisson capable of pouring water and an upper steel pipe structure.
JP20507690A 1990-08-03 1990-08-03 Construction method of rubble mound Expired - Lifetime JPH0694666B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP20507690A JPH0694666B2 (en) 1990-08-03 1990-08-03 Construction method of rubble mound

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20507690A JPH0694666B2 (en) 1990-08-03 1990-08-03 Construction method of rubble mound

Publications (2)

Publication Number Publication Date
JPH0489917A true JPH0489917A (en) 1992-03-24
JPH0694666B2 JPH0694666B2 (en) 1994-11-24

Family

ID=16501029

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20507690A Expired - Lifetime JPH0694666B2 (en) 1990-08-03 1990-08-03 Construction method of rubble mound

Country Status (1)

Country Link
JP (1) JPH0694666B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108149690A (en) * 2018-01-02 2018-06-12 中铁广州工程局集团有限公司 A kind of microtidal range marine site breakwater jackstone auxiliary device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108149690A (en) * 2018-01-02 2018-06-12 中铁广州工程局集团有限公司 A kind of microtidal range marine site breakwater jackstone auxiliary device

Also Published As

Publication number Publication date
JPH0694666B2 (en) 1994-11-24

Similar Documents

Publication Publication Date Title
CN109780325A (en) A kind of water factory's water intaking tunnel submarine pipeline installation method
CN103103972B (en) Prefabricate type nautical fixed platform and installing method
CN108505529A (en) A kind of construction method of the bearing platform construction steel cofferdam of Through Steel case arch bridge
KR100383409B1 (en) Construction Method of Direct Foundation for using Caisson
Rasmussen Concrete immersed tunnels—Forty years of experience
KR102097580B1 (en) A Method for the Construction of Offshore Structures Using General Concrete
JP3599431B2 (en) Construction method of temporary deadline
CN109518674B (en) Artificial island segment, assembled artificial island and construction method of assembled artificial island
JP2000290936A (en) Construction method of pier footing and caisson for pier footing construction
JPH0489917A (en) Executing method for rubble mound
JP2004108078A (en) Construction method of underwater shaft, underwater shaft, connection method of shaft and side shaft, shaft structure
JPH09316894A (en) Bridge pier foundation structure, and construction method thereof
KR100884050B1 (en) Foundation construction method for steel wells using steel pontoons
JP2022144881A (en) Installation guide member for immersed tunnel and method for constructing immersed tunnel
CN105350493B (en) Methods and structures for rapidly expanding the area of islands and reefs
JPS5934331A (en) How to build a sewage treatment facility
KR102169627B1 (en) Installation method of concrete sinker for floating structure
JP3851150B2 (en) Offshore structure and offshore structure construction method
GB2121854A (en) Marine structure constructing method
JPH06116957A (en) Construction method of underwater foundation in break-water, etc.
JP2536108B2 (en) Foundation construction method for offshore structures
Tsinker Gravity-Type Quay Walls
JPS6134534B2 (en)
CN120443676A (en) A construction method for offshore pile-free expanded foundation
JPS5947765B2 (en) Construction method of simple vertical self-supporting wall for seawall