JPH0549787B2 - - Google Patents
Info
- Publication number
- JPH0549787B2 JPH0549787B2 JP9354885A JP9354885A JPH0549787B2 JP H0549787 B2 JPH0549787 B2 JP H0549787B2 JP 9354885 A JP9354885 A JP 9354885A JP 9354885 A JP9354885 A JP 9354885A JP H0549787 B2 JPH0549787 B2 JP H0549787B2
- Authority
- JP
- Japan
- Prior art keywords
- steel sheet
- sheet pile
- separator
- pile wall
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Description
【発明の詳細な説明】
〔産業上の利用分野〕
この発明は、土留め用鋼矢板壁を地中コンクリ
ート構造物施工用内側型枠および外側縁切板の支
持に利用し、地中にコンクリート構造物を施工し
たのち全数の鋼矢板を引抜くことができる土留め
用鋼矢板壁を利用したコンクリート構造物の型枠
施工法に関するものである。[Detailed Description of the Invention] [Field of Industrial Application] This invention utilizes a steel sheet pile wall for earth retaining to support the inner formwork and outer edge cut plate for constructing an underground concrete structure, and The present invention relates to a formwork construction method for concrete structures using steel sheet pile walls for earth retaining, from which all the steel sheet piles can be pulled out after the structure is constructed.
一般に、地中にピツト等のコンクリート構造物
を築造する場合、その築造場所を掘削したとき地
山が崩壊するのを防止するために、第12図に示
すように、コンクリート構造物11の築造予定場
所を囲む位置の地盤12に、多数の鋼矢板10を
振動式打込装置13により打込んで、土留用鋼矢
板壁1を設置している。
Generally, when constructing a concrete structure such as a pit underground, in order to prevent the ground from collapsing when the construction site is excavated, the construction schedule of the concrete structure 11 is set as shown in Fig. 12. A steel sheet pile wall 1 for earth retention is installed by driving a large number of steel sheet piles 10 into the ground 12 at positions surrounding the site using a vibrating driving device 13.
そしてコンクリート構造物を築造する場合、周
囲の状況に応じて次の2つの方法がある。 When building a concrete structure, there are two methods depending on the surrounding situation:
(1) 第13図および第14図に示すように、外側
型枠用足場14を設置するスペース15を確保
するために、コンクリート構造物11の築造予
定位置から前記スペース15の距離だけ離れた
位置に鋼矢板10を打設し、コンクリート構造
物11を築造したのち、鋼矢板10を引抜く。(1) As shown in Fig. 13 and Fig. 14, in order to secure a space 15 for installing the outer formwork scaffold 14, a position separated by the distance of the space 15 from the planned construction position of the concrete structure 11. After driving the steel sheet piles 10 and constructing the concrete structure 11, the steel sheet piles 10 are pulled out.
(2) 第15図および第16図に示すように、外側
型枠組立用足場を設置するスペースが確保でき
ない場合は、鋼矢板10をコンクリート構造物
11の築造予定位置に近接して打設し、多数の
鋼矢板10からなる土留め用鋼矢板壁1を外側
型枠兼用とし、その鋼矢板壁1にセパレータ4
の一端部を直接固定し、そのセパレータ4の他
端部により内側型枠8を支持し、次に鋼矢板壁
1と内側型枠8との間にコンクリートを打設し
てコンクリート構造物11を築造する。鋼矢板
10はセパレータ4と固定されているので、鋼
矢板10を引抜かないで埋殺す。(2) As shown in Figures 15 and 16, if space cannot be secured to install scaffolding for outer formwork assembly, steel sheet piles 10 should be placed close to the planned construction location of concrete structure 11. , a steel sheet pile wall 1 for earth retaining consisting of a large number of steel sheet piles 10 is used also as an outer formwork, and a separator 4 is attached to the steel sheet pile wall 1.
One end is directly fixed, the inner formwork 8 is supported by the other end of the separator 4, and then concrete is poured between the steel sheet pile wall 1 and the inner formwork 8 to form the concrete structure 11. Build. Since the steel sheet pile 10 is fixed to the separator 4, the steel sheet pile 10 is buried without being pulled out.
しかるに、前記(1)の方法の場合は、コンクリー
ト構造物築造予定位置と鋼矢板壁1との間に比較
的広巾のスペース15を設ける必要があるので、
工事範囲が広くなると共に鋼矢板10の使用数が
多くなり、かつ鋼矢板壁により囲まれた部分の土
砂掘削等の土工量が増加し、そのため工事費が高
くなると共に工期が長くかかるという問題があ
る。 However, in the case of method (1) above, it is necessary to provide a relatively wide space 15 between the planned concrete structure construction location and the steel sheet pile wall 1.
As the scope of construction becomes wider, the number of steel sheet piles 10 used increases, and the amount of earthwork such as excavation of earth and sand in the area surrounded by the steel sheet pile wall increases, resulting in higher construction costs and longer construction periods. be.
また前記(2)の方法の場合は、コンクリート構造
物11を築造したのちも、鋼矢板10がコンクリ
ート構造物中のセパレータ4に固定されていて抜
取ることができず、全数の鋼矢板が埋殺されるの
で、工事費が著しく高くなるという問題がある。 In addition, in the case of method (2) above, even after the concrete structure 11 is constructed, the steel sheet piles 10 are fixed to the separators 4 in the concrete structure and cannot be removed, and all the steel sheet piles are buried. There is a problem that the construction cost will be significantly higher because of this.
この発明は前述の問題を有利に解決できる土留
め用鋼矢板壁を利用したコンクリート構造物の型
枠施工法を提供することを目的とするものであつ
て、この発明の要旨とするところは、コンクリー
ト構造物築造場所を囲むように打設した鋼矢板壁
1内の土砂を掘削排除したのち、鋼矢板壁1の内
側の凹部2に複数のセパレータ支持部材3を上下
方向に間隔をおいて固定し、各セパレータ支持部
材3と、上下方向に間隔をおいて配置した複数の
セパレータ4に連結されている掛止部材5とを、
それらにわたつて抜挿自在に挿通したアンカー棒
6を介して連結し、各セパレータ4を鋼矢板壁1
の内面に当接された縁切板7および内側型枠8に
挿通して、そのセパレータ4により縁切板7およ
び内側型枠8の間隔を保持し、次に縁切板7およ
び内側型枠8の間に打設したコンクリート9が硬
化したのち、前記アンカー棒6を抜取つてセパレ
ータ支持部材3と掛止部材5との連結を解き、次
に鋼矢板壁1を構成している鋼矢板10を引抜く
ことを特徴とする土留め用鋼矢板壁を利用したコ
ンクリート構造物の型枠施工法にある。 The purpose of this invention is to provide a formwork construction method for concrete structures using steel sheet pile walls for earth retaining, which can advantageously solve the above-mentioned problems, and the gist of this invention is to: After excavating and removing earth and sand from the steel sheet pile wall 1 that has been cast to surround the concrete structure construction site, a plurality of separator support members 3 are fixed in the recess 2 inside the steel sheet pile wall 1 at intervals in the vertical direction. Then, each separator support member 3 and a hooking member 5 connected to a plurality of separators 4 arranged at intervals in the vertical direction,
Each separator 4 is connected to the steel sheet pile wall 1 through an anchor rod 6 which is inserted and removably inserted across them.
The separator 4 maintains the distance between the edge cutting plate 7 and the inner formwork 8, and then the edge cutting plate 7 and the inner formwork After the concrete 9 poured between the sections 8 and 8 has hardened, the anchor rod 6 is removed and the connection between the separator support member 3 and the hooking member 5 is released, and then the steel sheet pile 10 constituting the steel sheet pile wall 1 is removed. A formwork construction method for a concrete structure using steel sheet pile walls for earth retaining, which is characterized by pulling out.
〔実施例〕
次にこの発明を第1図から第5図に示す実施例
によつて詳細に説明する。[Example] Next, the present invention will be explained in detail with reference to examples shown in FIGS. 1 to 5.
まず第1図から第3図に示すように、コンクリ
ート構造物築造予定位置の周囲に近接して多数の
鋼矢板10からなる鋼矢板壁1を地盤12に打設
したのち、その鋼矢板壁1により囲まれた地盤1
2を掘削し、次いで掘削後の地盤面に均しコンク
リートを打設し、かつその上にベース鉄筋を組立
てたのちベースコンクリート16を打設する。 First, as shown in FIGS. 1 to 3, a steel sheet pile wall 1 consisting of a large number of steel sheet piles 10 is placed in the ground 12 in close proximity to the planned construction location of the concrete structure, and then the steel sheet pile wall 1 Ground 1 surrounded by
2 is excavated, leveled concrete is placed on the excavated ground surface, base reinforcing bars are assembled on top of the leveled concrete, and then base concrete 16 is placed.
次に鋼矢板壁1における内側の凹部2の底板内
面に、複数の逆く字状のセパレータ支持部材3を
上下方向に間隔をおいて溶接等により固着し、セ
パレータ用外側螺杆17の一端部に連結されてい
るリングチエーンからなる掛止部材5をセパレー
タ支持部材3に載置した状態で、各掛止部材5と
各セパレータ支持部材3とにわたつて鋼製アンカ
ー棒6を抜挿自在に挿通することにより、各掛止
部材5を各セパレータ支持部材3に掛止する。 Next, a plurality of inverted dog-shaped separator support members 3 are fixed to the inner surface of the bottom plate of the inner recess 2 in the steel sheet pile wall 1 at intervals in the vertical direction by welding or the like, and attached to one end of the outer screw rod 17 for the separator. With the hooking members 5 made up of connected ring chains placed on the separator support member 3, a steel anchor rod 6 is inserted and removably inserted between each of the hooking members 5 and each separator support member 3. By doing so, each hooking member 5 is hooked to each separator support member 3.
次に第4図および第5図に示すように、前記外
側螺杆17にねじ座金またはナツト等の調節受片
18を螺合すると共に裏当板19を嵌設し、次い
で平板状の縁切板7に設けた透孔に前記外側螺杆
17を挿通すると共に、その縁切板7を鋼矢板壁
1の内面に当接し、かつ外側螺杆17に嵌通した
押え板20を縁切板7の内面に当接すると共に、
外側螺杆17にねじ座金またはナツト等の締付具
21を螺合し、前記調節受片18および締付具2
1により裏当板19および押え板20を介して縁
切板7を定位置に保持する。 Next, as shown in FIGS. 4 and 5, an adjustment receiving piece 18 such as a screw washer or a nut is screwed onto the outer screw rod 17, and a backing plate 19 is fitted, and then a flat edge cutting plate is fitted. The outer screw rod 17 is inserted into the through hole provided in the outer screw rod 7, the edge cutting plate 7 is brought into contact with the inner surface of the steel sheet pile wall 1, and the retaining plate 20 fitted into the outer screw rod 17 is inserted into the inner surface of the edge cutting plate 7. At the same time as coming into contact with
A fastener 21 such as a screw washer or a nut is screwed onto the outer screw rod 17, and the adjustment receiving piece 18 and the fastener 2 are screwed together.
1 holds the edge cutting plate 7 in place via the backing plate 19 and the holding plate 20.
次にセパレータ用内側螺杆22の内端部を外側
螺杆17の外端部に溶接または接着剤あるいはそ
の他の手段により固着し、かつ前記内側螺杆22
の中間部にゴム板または鋼板等の止水材23に貫
通して水密に取付け、さらに内側螺杆22の内端
側に型枠受片24を固着するかまたは掛止する。 Next, the inner end of the inner screw rod 22 for separator is fixed to the outer end of the outer screw rod 17 by welding, adhesive, or other means, and the inner screw rod 22
A water stop material 23 such as a rubber plate or a steel plate is penetrated into the middle part of the molding member 22 to be watertightly attached, and a formwork receiving piece 24 is fixed or hooked to the inner end side of the inner screw rod 22.
次に前記縁切板7の内側に壁鉄筋を組立設置し
たのち、その壁鉄筋の内側に配置した内側型枠8
の透孔に内側螺杆22を挿通すると共に、型枠受
片24に内側型枠8を係合し、かつ内側型枠8の
表側に縦ばた材25および横ばた材26を配置
し、さらに内側螺杆22の内側突出部に押え座金
27を嵌設すると共にナツト28を螺合して、型
枠の組立設置作業を終了する。 Next, after assembling and installing the wall reinforcing bars inside the edge cutting board 7, the inner formwork 8 is placed inside the wall reinforcing bars.
Insert the inner screw rod 22 into the through hole, engage the inner formwork 8 with the formwork receiving piece 24, and arrange the vertical beams 25 and horizontal beams 26 on the front side of the inner formwork 8, Furthermore, the presser washer 27 is fitted into the inner protrusion of the inner screw rod 22, and the nut 28 is screwed on, thereby completing the assembly and installation work of the formwork.
前記外側螺杆17、内側螺杆22、調節受片1
8、締付具21および型枠受片24等からなるセ
パレータ4により縁切板7と内側型枠8との間隔
を一定に保持した状態で、縁切板7と内側型枠8
との間に構造物を構成するコンクリート9を打設
し、そのコンクリート9を養生したのち、内側型
枠8、縦ばた材25、横ばた材26、押え座金2
7、ナツト28等を取外し、次いで内側螺杆22
の突出部を取外し、さらに前記アンカー棒6を引
抜いてセパレータ支持部材3と掛止部材5との連
結を解いたのち、鋼矢板壁1を構成している鋼矢
板10を振動式引抜装置により引抜いて回収す
る。 The outer screw rod 17, the inner screw rod 22, and the adjustment receiving piece 1
8. While keeping the distance between the edge cutting plate 7 and the inner formwork 8 constant by the separator 4 consisting of the fastener 21 and the formwork receiving piece 24, etc., the edge cutting plate 7 and the inner formwork 8 are
After pouring the concrete 9 that constitutes the structure between the two and curing the concrete 9, the inner formwork 8, the vertical beams 25, the horizontal beams 26, and the presser washers 2 are placed.
7. Remove the nut 28, etc., and then remove the inner screw rod 22.
After removing the protruding portion and further pulling out the anchor rod 6 to release the connection between the separator support member 3 and the hanging member 5, the steel sheet pile 10 constituting the steel sheet pile wall 1 is pulled out using a vibrating pulling device. and collect it.
第6図および第7図はセパレータ支持部材3に
対し他の例の掛止部材5を連結した状態を示すも
のであつて、シヤツクル29の湾曲端部に溶接等
により固着された雌ねじ筒30にセパレータ用外
側螺杆17の一端部が螺合され、連結金具31の
一端部がシヤツクル29の両腕の間に配置されて
横軸32により枢着され、かつ連結金具31の他
端部は鋼矢板10に固着されたセパレータ支持部
材3に載置されると共に、セパレータ支持部材3
の透孔と連結金具31の透孔とわたつてアンカー
棒6が挿通され、さらに連結金具31には、シヤ
ツクル29が横軸32を中心として下向きに回動
するのを防止するためのストツパピン33が嵌挿
されている。なお、第3図および第5図におい
て、34は鋼矢板に対するコンクリート付着防止
板である。 FIGS. 6 and 7 show a state in which another example of the hooking member 5 is connected to the separator support member 3, and shows a female threaded cylinder 30 fixed to the curved end of the shackle 29 by welding or the like. One end of the outer screw rod 17 for the separator is screwed together, one end of the connecting fitting 31 is arranged between both arms of the shaft 29 and pivotally connected by the horizontal shaft 32, and the other end of the connecting fitting 31 is connected to the steel sheet pile. The separator support member 3 is placed on the separator support member 3 fixed to the separator support member 10.
The anchor rod 6 is inserted through the through hole of the connecting fitting 31 and the connecting fitting 31, and the connecting fitting 31 is further provided with a stopper pin 33 for preventing the shaft 29 from rotating downward about the horizontal shaft 32. It is inserted. In addition, in FIG. 3 and FIG. 5, 34 is a concrete adhesion prevention plate to the steel sheet pile.
第8図から第11図は鋼矢板10に対し他の例
のセパレータ支持部材3を取付けた状態を示すも
のであつて、第8図および第9図の場合は、平板
状の鋼製セパレータ支持部材3の端部が鋼矢板1
0に対し溶接により固着され、また第10図およ
び第11図の場合は、溝形断面の鋼製セパレータ
支持部材3の端部が鋼矢板10に対し溶接により
固着されている。 FIGS. 8 to 11 show the state in which other examples of separator support members 3 are attached to the steel sheet pile 10. In the case of FIGS. 8 and 9, flat steel separator supports are shown. The end of the member 3 is the steel sheet pile 1
In the case of FIGS. 10 and 11, the ends of the steel separator support member 3 having a grooved cross section are fixed to the steel sheet pile 10 by welding.
前記縁切板7、裏当板19、押え板20として
は例えば木質合板、鋼板、プラスチツク板を使用
する。また前記セパレータ支持部材3および内側
型枠8の材質は例えば鋼材、木材、プラスチツク
の何れでもよい。 As the edge cutting plate 7, the backing plate 19, and the holding plate 20, for example, wooden plywood, steel plate, or plastic plate is used. The material of the separator support member 3 and the inner formwork 8 may be, for example, steel, wood, or plastic.
この発明によれば、コンクリート構造物築造場
所を囲むように打設した鋼矢板壁1内の土砂を掘
削排除したのち、鋼矢板壁1の内側の凹部2に複
数のセパレータ支持部材3を上下方向に間隔をお
いて固定し、各セパレータ支持部材3と、上下方
向に間隔をおいて配置した複数のセパレータ4に
連結されている掛止部材5とを、それらにわたつ
て抜挿自在に挿通したアンカー棒6を介して連結
し、各セパレータ4を鋼矢板壁1の内面に当接さ
れた縁切板7および内側型枠8に挿通して、その
セパレータ4により縁切板7および内側型枠8の
間隔を保持し、次に縁切板7および内側型枠8の
間に地中の構造物を構成するコンクリート9を打
設するので、コンクリート9を鋼矢板壁1に近接
させると共に鋼矢板壁1に付着しないようにして
打設することができ、かつそのコンクリート9が
硬化したのち、アンカー棒6を引抜き、次いで鋼
矢板壁1を構成している鋼矢板10を引抜いて回
収するので鋼矢板壁1とコンクリート構造物11
との間に大きなスペースを設けることなくコンク
リート構造物を築造したのち、鋼矢板壁1を構成
する鋼矢板10およびアンカー棒6を回収するこ
とができ、そのため工事範囲を縮小して土工量、
鋼矢板使用数を削減すると共に、短かい工期およ
び安い工費でコンクリート構造物を築造すること
ができ、また前記セパレータ4を鋼矢板壁1に対
し簡単な手段によつて容易にかつ迅速に掛止する
ことができる等の効果が得られる。
According to this invention, after excavating and removing the earth and sand in the steel sheet pile wall 1 that has been cast so as to surround the concrete structure construction site, a plurality of separator support members 3 are installed in the recess 2 inside the steel sheet pile wall 1 in the vertical direction. Each separator support member 3 and a hooking member 5 connected to a plurality of separators 4 arranged at intervals in the vertical direction are inserted and removably inserted into and out of each separator support member 3. Connected via anchor rods 6, each separator 4 is inserted through the edge cutting plate 7 and inner formwork 8 that are in contact with the inner surface of the steel sheet pile wall 1, and the separator 4 connects the edge cutting plate 7 and the inner formwork. 8, and then concrete 9 constituting the underground structure is poured between the edge cut plate 7 and the inner formwork 8, so that the concrete 9 is brought close to the steel sheet pile wall 1 and the steel sheet pile It can be poured without adhering to the wall 1, and after the concrete 9 has hardened, the anchor rod 6 is pulled out, and then the steel sheet piles 10 that make up the steel sheet pile wall 1 are pulled out and recovered. Sheet pile wall 1 and concrete structure 11
After constructing a concrete structure without creating a large space between them, the steel sheet piles 10 and anchor rods 6 that make up the steel sheet pile wall 1 can be recovered, reducing the construction scope and reducing the amount of earthwork.
In addition to reducing the number of steel sheet piles used, it is possible to construct a concrete structure in a short construction period and at low construction cost, and the separator 4 can be easily and quickly hung on the steel sheet pile wall 1 by a simple means. Effects such as being able to do the following can be obtained.
第1図から第5図はこの発明の実施例を示すも
のであつて、第1図は鋼矢板壁の内側に取付けら
れたセパレータ支持部材に外側螺杆に取付けられ
た掛止部材を連結した状態を示す斜視図、第2図
はその平面図、第3図は第2図のA−A線断面
図、第4図は組立てられた型枠装置を示す平面
図、第5図は第4図のB−B線断面図である。第
6図はセパレータ支持部材に対し他の例の掛止部
材を連結した状態を示す側面図、第7図はその平
面図、第8図は他の例のセパレータ支持部材を鋼
矢板に取付けた状態を示す斜視図、第9図はその
縦断側面図、第10図はもう一つの例のセパレー
タ支持部材を鋼矢板に取付けた状態を示す斜視
図、第11図はその縦断側面図である。第12図
は従来のコンクリート構造物築造方法を実施する
場合の鋼矢板打込状況を示す概略斜視図、第13
図は従来のコンクリート構造物築造方法の一例を
示す概略縦断側面図、第14図はその築造方法に
おける鋼矢板壁とコンクリート構造物との関係を
示す平面図、第15図は従来のコンクリート構造
物築造方法の他の例を示す概略縦断側面図、第1
6図はその築造方法により築造されたコンクリー
ト構造物および鋼矢板壁を示す平面図である。
図において、1は鋼矢板壁、2は凹部、、3は
セパレータ支持部材、4はセパレータ、5は掛止
部材、6はアンカー棒、7は縁切板、8は内側型
枠、9はコンクリート、10は鋼矢板、11はコ
ンクリート構造物、16はベースコンクリート、
17はセパレータ用外側螺杆、18は調節受片、
21は締付具、22はセパレータ用内側螺杆、2
4は型枠受片、25は縦ばた材、26は横ばた
材、27は押え座金、28はナツトである。
1 to 5 show an embodiment of the present invention, and FIG. 1 shows a state in which a separator support member attached to the inside of a steel sheet pile wall is connected to a separator support member attached to an outer screw rod. FIG. 2 is a plan view thereof, FIG. 3 is a sectional view taken along line A-A in FIG. 2, FIG. 4 is a plan view showing the assembled formwork device, and FIG. FIG. Figure 6 is a side view showing a separator support member connected to another hanging member, Figure 7 is a plan view thereof, and Figure 8 is another example of a separator support member attached to a steel sheet pile. FIG. 9 is a perspective view showing the state, FIG. 9 is a longitudinal side view thereof, FIG. 10 is a perspective view showing another example of a separator support member attached to a steel sheet pile, and FIG. 11 is a longitudinal side view thereof. Figure 12 is a schematic perspective view showing the steel sheet pile driving situation when implementing the conventional concrete structure construction method;
Figure 14 is a schematic longitudinal side view showing an example of a conventional concrete structure construction method, Figure 14 is a plan view showing the relationship between a steel sheet pile wall and a concrete structure in that construction method, and Figure 15 is a conventional concrete structure. Schematic vertical side view showing another example of the construction method, 1st
FIG. 6 is a plan view showing a concrete structure and a steel sheet pile wall constructed by this construction method. In the figure, 1 is a steel sheet pile wall, 2 is a recess, 3 is a separator support member, 4 is a separator, 5 is a hanging member, 6 is an anchor rod, 7 is an edge cutting plate, 8 is an inner formwork, 9 is concrete , 10 is a steel sheet pile, 11 is a concrete structure, 16 is a base concrete,
17 is an outer screw rod for the separator, 18 is an adjustment receiving piece,
21 is a tightening tool, 22 is an inner screw rod for separator, 2
4 is a formwork support piece, 25 is a vertical flap member, 26 is a horizontal flap member, 27 is a presser washer, and 28 is a nut.
Claims (1)
設した鋼矢板壁1内の土砂を掘削排除したのち、
鋼矢板壁1の内側の凹部2に複数のセパレータ支
持部材3を上下方向に間隔をおいて固定し、各セ
パレータ支持部材3と、上下方向に間隔をおいて
配置した複数のセパレータ4に連結されている掛
止部材5とを、それらにわたつて抜挿自在に挿通
したアンカー棒6を介して連結し、各セパレータ
4を鋼矢板壁1の内面に当接された縁切板7およ
び内側型枠8に挿通して、そのセパレータ4によ
り縁切板7および内側型枠8の間隔を保持し、次
に縁切板7および内側型枠8の間に打設したコン
クリート9が硬化したのち、前記アンカー棒6を
抜取つてセパレータ支持部材3と掛止部材5との
連結を解き、次に鋼矢板壁1を構成している鋼矢
板壁10を引抜くことを特徴とする土留め用鋼矢
板壁を利用したコンクリート構造物の型枠施工
法。1 After excavating and removing the earth and sand within the steel sheet pile wall 1 that was placed to surround the concrete structure construction site,
A plurality of separator support members 3 are fixed to a recess 2 inside a steel sheet pile wall 1 at intervals in the vertical direction, and each separator support member 3 is connected to a plurality of separators 4 arranged at intervals in the vertical direction. The separators 4 are connected to the retaining members 5 through the anchor rods 6 which are removably inserted therethrough, and each separator 4 is connected to the edge cutting plate 7 and the inner mold which are in contact with the inner surface of the steel sheet pile wall 1. The concrete 9 is inserted into the frame 8 and the spacing between the edge cutting plate 7 and the inner formwork 8 is maintained by the separator 4, and then the concrete 9 poured between the edge cutting plate 7 and the inner formwork 8 is hardened. A steel sheet pile for earth retaining characterized in that the anchor rod 6 is pulled out to release the connection between the separator support member 3 and the hanging member 5, and then the steel sheet pile wall 10 constituting the steel sheet pile wall 1 is pulled out. Formwork construction method for concrete structures using walls.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP9354885A JPS61254754A (en) | 1985-05-02 | 1985-05-02 | Mold frame construction method of concrete structure utilizing steel sheet pile wall for sheathing |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP9354885A JPS61254754A (en) | 1985-05-02 | 1985-05-02 | Mold frame construction method of concrete structure utilizing steel sheet pile wall for sheathing |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS61254754A JPS61254754A (en) | 1986-11-12 |
| JPH0549787B2 true JPH0549787B2 (en) | 1993-07-27 |
Family
ID=14085312
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP9354885A Granted JPS61254754A (en) | 1985-05-02 | 1985-05-02 | Mold frame construction method of concrete structure utilizing steel sheet pile wall for sheathing |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS61254754A (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2011084938A (en) * | 2009-10-15 | 2011-04-28 | Nippon Kankyo Seizo Kk | Earth retaining wall and method of constructing the same |
| JP6202496B2 (en) * | 2013-10-23 | 2017-09-27 | 譲二 山下 | Welding auxiliary member and welding method using welding auxiliary member |
-
1985
- 1985-05-02 JP JP9354885A patent/JPS61254754A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS61254754A (en) | 1986-11-12 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US2772560A (en) | Pick-up device for pre-cast concrete slabs | |
| JPH0549787B2 (en) | ||
| JP3029343U (en) | Form tool for mortar material injection in exposed elastic fixed column base method | |
| JPS63280153A (en) | Reverse construction method for underground framework | |
| JPH0549786B2 (en) | ||
| JPS6054459B2 (en) | Slope protection method | |
| JPH0549788B2 (en) | ||
| JPH08284113A (en) | Structure of bridge and constructing method thereof | |
| JP2552864B2 (en) | Wall panels such as basements | |
| JPH04111813A (en) | Retaining wall structure and its construction | |
| JP2988814B2 (en) | Precast concrete foundation structure | |
| JPS6124623Y2 (en) | ||
| JPH01271526A (en) | Construction method for foundation | |
| JPS6215292Y2 (en) | ||
| JP3020882B2 (en) | Construction method of building structure with underground space | |
| KR20000059203A (en) | Retaining Wall Construction Method | |
| JPH069069Y2 (en) | Retaining wall | |
| JPH01223219A (en) | Retaining wall construction for slope surface | |
| JPH0742705B2 (en) | Method of constructing underground girder and earth slab on concrete foundation | |
| JPS5936056B2 (en) | Law frame construction method and formwork for constructing the law frame | |
| JPH07166652A (en) | Casing for mounting anchor bolt and mounting method of anchor bolt | |
| JP3023266B2 (en) | Precast concrete foundation and foundation structure | |
| JP2536742Y2 (en) | Box mounting tube fittings for concrete casting | |
| JPH01163320A (en) | Method and apparatus for fixing anchor bolt | |
| JPH02153119A (en) | Constructing method for concrete foundation |