JPH0571226A - Temporarily set structure of complete weather type - Google Patents

Temporarily set structure of complete weather type

Info

Publication number
JPH0571226A
JPH0571226A JP26045391A JP26045391A JPH0571226A JP H0571226 A JPH0571226 A JP H0571226A JP 26045391 A JP26045391 A JP 26045391A JP 26045391 A JP26045391 A JP 26045391A JP H0571226 A JPH0571226 A JP H0571226A
Authority
JP
Japan
Prior art keywords
temporary
temporarily
work
construction
executed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP26045391A
Other languages
Japanese (ja)
Other versions
JP2834351B2 (en
Inventor
Ichiro Shiraishi
一郎 白石
Ichiro Kurihara
一郎 栗原
Shigeo Kitahara
成郎 北原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP3260453A priority Critical patent/JP2834351B2/en
Publication of JPH0571226A publication Critical patent/JPH0571226A/en
Application granted granted Critical
Publication of JP2834351B2 publication Critical patent/JP2834351B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To enable the temporarily set structure of all-weather type to be composed with simplified construction and mechanism. CONSTITUTION:The temporarily set supports 2 of rod antenna types are erected, and on bearing members 4, 4 set on the outermost pipes 3, temporarily set beams 5 are fixed. Roof material, horizontal braces, and the like are arranged on the temporarily set beams 5, and on them, a ceiling sheet is stretched. Besides, between the outermost pipes 3 of the temporarily set supports 2, 2 adjacent in the ridge direction, temporarily set scaffoldings are arranged. The bearing member 4, 4 are lifted up and the whole temporarily-set roof is moved up to a required level, and after that, underground work and construction work up to a floor for enabling work to be executed, are executed. After that, second internal pipes inside the temporarily-set supports 2 are lifted up, and the whole temporarily-set roof is moved up, and the construction work is executed in order up to the floor for enabling the work to be executed. The temporarily-set supports 2 are repeatedly lifted up, and the work is executed up to a top floor.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は全天候型の仮設構造物に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an all-weather temporary structure.

【0002】[0002]

【従来の技術】建設現場において、掘削、コンクリート
打設、鉄筋のガス圧接、墨出し、左官などの工事を、雨
天や強風下で実施すると種々の不都合が発生するので、
全天候型の施工システムが切望されている。即ち、建築
物の上空部と側面部とを仮設構造物で囲むことができれ
ば、その中で建築工事を実施することができるので、作
業工程が確保し易くなると共に、作業環境を改善し、か
つ、建築物の品質向上を図ることができる。
2. Description of the Related Art At a construction site, various inconveniences may occur if construction such as excavation, concrete pouring, gas pressure welding of reinforcing bars, marking out, plastering, etc. is carried out in the rain or in strong wind.
An all-weather construction system is desired. That is, if the upper part and the side part of the building can be surrounded by the temporary structure, the construction work can be carried out in the temporary structure, so that the work process can be easily secured and the work environment can be improved, and , The quality of buildings can be improved.

【0003】従来の全天候型の施工システムは、地下工
事専用または地上工事専用であり、一貫したシステムと
はなっておらず、建築工事全体を全天候型で施工する場
合には、異なる複数の施工システムを採用しなければな
らなかった。そのため、それぞれの仮設構造物の組立、
解体作業に人員、日数が余分に掛かっていた。
The conventional all-weather construction system is for exclusive use in underground construction or above-ground construction, and is not a consistent system. When constructing the entire construction construction in all-weather construction, a plurality of different construction systems are used. Had to adopt. Therefore, assembling each temporary structure,
The dismantling work required extra personnel and days.

【0004】また、極く最近になって、建築物の外周に
仮設柱を建て、その建築物のほぼ半分を覆う仮設屋根を
前記仮設柱に沿ってリフトアップさせるようにした仮設
構造物も用いられるようになってきた。
Also, most recently, a temporary structure has been used in which a temporary pillar is built around the outer periphery of a building and a temporary roof covering almost half of the building is lifted up along the temporary pillar. It has come to be.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、前記仮
設構造物は地上、地下工事一貫システムではあるもの
の、完全な全天候型ではなく、また、リフトアップ機構
も複雑なため、必ずしも満足のゆくものではなかった。
本発明は前記課題を解決しようとするものであり、その
目的は、簡易な構造と機構により全天候型の仮設構造物
を構成しようとするものである。
However, although the above-mentioned temporary structure is an integrated system for ground and underground construction, it is not completely weatherproof and the lift-up mechanism is complicated, so it is not always satisfactory. It was
The present invention is intended to solve the above problems, and an object thereof is to construct an all-weather temporary structure with a simple structure and mechanism.

【0006】[0006]

【課題を解決するための手段】上記目的を達成するため
に、本発明に係る全天候型仮設構造物は、対向して設け
られた仮設柱間に仮設梁を横架し、該仮設梁の上に仮設
屋根を載せ、かつ、前記仮設柱を多重管構造として伸縮
自在とすることによって課題を解決したものである。
In order to achieve the above object, an all-weather temporary structure according to the present invention has a structure in which a temporary beam is laid horizontally between opposing temporary columns, and The problem is solved by mounting a temporary roof on the, and making the temporary columns expandable and contractable as a multi-tube structure.

【0007】また、本発明に係る全天候型仮設構造物
は、更に、桁行方向に隣接する仮設柱の最外管に仮設足
場を設置することによって課題を解決したものである。
Further, the all-weather temporary structure according to the present invention further solves the problem by installing a temporary scaffold on the outermost pipe of the temporary columns adjacent in the girder direction.

【0008】[0008]

【作用】多重管構造の仮設柱を建て込み、その最外管に
に仮設梁を固定する。仮設梁の上には仮設屋根を設置す
る。仮設屋根全体を所定の高さに上昇させた後、地下工
事と施工可能な階までの建築工事を行う。次に、仮設柱
の内側から2番目の内管をリフトアップして、仮設屋根
全体を上昇させ、施工可能な階までの建築工事を順次行
う。この仮設柱のリフトアップを繰り返して、最上階ま
で建築工事を施工する。
[Operation] A temporary column having a multi-pipe structure is built and a temporary beam is fixed to the outermost pipe. A temporary roof will be installed on the temporary beam. After raising the entire temporary roof to a predetermined height, the underground construction and the construction work up to the constructable floor will be performed. Next, the second inner pipe from the inside of the temporary column is lifted up, the entire temporary roof is raised, and construction work up to the floors where construction is possible is performed sequentially. By repeating the lift-up of this temporary column, construction work will be carried out to the top floor.

【0009】[0009]

【実施例】以下、本発明に係る全天候型仮設構造物を用
いた好適な施工システムを、図1に示す施工手順図によ
り説明する。第1工程 仮設柱の建込・仮設梁の地組〔図1(1)〕 敷地内に仮設用フーチング1をセットし、フーチング1
のアンカーに仮設柱2を固定する。仮設柱2の構造は各
々の長さがほぼ等しく、断面のサイズが少しずつ異なる
角型または丸型の鋼管を、複数本重ね合わせたロッドア
ンテナ形式であり、仮設柱2の最外管3の外周面には後
記する仮設梁5を固定するための支持部材4を設ける。
EXAMPLES A preferred construction system using the all-weather temporary structure according to the present invention will be described below with reference to the construction procedure diagram shown in FIG. 1st step Construction of temporary columns and foundation of temporary beams [Fig. 1 (1)] Set footing 1 for temporary construction on the site, and footing 1
Fix the temporary column 2 to the anchor. The structure of the temporary column 2 is a rod antenna type in which a plurality of square or round steel pipes having substantially equal lengths and slightly different cross-sectional sizes are superposed, and the outermost pipe 3 of the temporary column 2 is A support member 4 for fixing a temporary beam 5, which will be described later, is provided on the outer peripheral surface.

【0010】仮設柱2を建て込んだ後、隣接する仮設柱
2、2の桁行方向を横繋ぎ材で緊結し、同時に仮設梁5
を地上にて組み立てる。仮設梁5は、鋼管からなるラチ
ス構造で3m程度の長さでユニット化し、現場で組み立
てる。種々の長さの仮設梁5を予め用意しておくことに
より、建築物の大きさに対応させることができる。
After the temporary columns 2 have been built in, the columns of the adjacent temporary columns 2 and 2 are tightly connected to each other in the direction of the girders by a horizontal tie member, and at the same time the temporary beams 5 are connected.
Is assembled on the ground. The temporary beam 5 has a lattice structure made of steel pipe and is unitized with a length of about 3 m and assembled on site. By preparing the temporary beams 5 of various lengths in advance, it is possible to correspond to the size of the building.

【0011】第2工程 仮設梁および仮設足場の取付け
〔図1(2)〕 地組された仮設梁5を支持部材4、4に固定する。その
後、図示しない屋根材、水平ブレース等を仮設梁5の上
に設置し、更にこれら屋根材、水平ブレースの上に天井
シートを張る。天井シートは透光性を有する膜材が快適
な作業環境を確保する上で好ましい。また、必要に応じ
て壁面にもシートをセットしてもよい。仮設梁5の下に
は、ホイストレール6およびホイスト7を設置して、建
築資材の搬入、移動の利用に供する。また、桁行方向に
隣接する仮設柱2、2の間には、仮設足場8を設ける。
同足場8は、施工手順の最終段階を示す図2(2)に表
されたように、仮設柱2、2の最外管3、3に取り付け
る。本工程における全ての作業は地上にて行うことがで
きる。
Second Step Attachment of Temporary Beam and Temporary Scaffold [FIG. 1 (2)] The temporary beam 5 assembled to the base is fixed to the supporting members 4 and 4. After that, a roof material, a horizontal brace, etc. (not shown) are installed on the temporary beam 5, and a ceiling sheet is stretched on the roof material and the horizontal brace. The ceiling sheet is preferably a translucent film material to ensure a comfortable working environment. Moreover, you may set a sheet | seat also on a wall surface as needed. A hoist rail 6 and a hoist 7 are installed under the temporary beam 5 for use in carrying in and moving building materials. Further, a temporary scaffold 8 is provided between the temporary columns 2 and 2 that are adjacent to each other in the column direction.
The scaffold 8 is attached to the outermost pipes 3 and 3 of the temporary columns 2 and 2, as shown in FIG. 2B showing the final stage of the construction procedure. All operations in this process can be performed on the ground.

【0012】第3工程 仮設梁のリフトアップ〔図1
(3)〕 支持部材4、4を、油圧ジャッキ式、ラック&ピニオン
ギア式またはワイヤー式等の適宜の手段によりリフトア
ップして、仮設屋根全体を所望の高さに上昇させる。所
定の高さまでリフトアップしたら、支持部材4、4をボ
ルトなどで仮設柱2、2の最外管3、3に固定すると共
に、ピン止めを行い支持部材4、4の落下を防止する。
なお、隣接する仮設柱2、2の桁行方向にはブレースを
設ける。上記のようにして仮設屋根が所定の高さまで上
昇した後、地下工事と施工可能な階まで建築工事を行
う。
Third step Lift-up of temporary beams [Fig. 1
(3)] The supporting members 4 and 4 are lifted up by an appropriate means such as a hydraulic jack type, a rack and pinion gear type, or a wire type to raise the entire temporary roof to a desired height. When the support members 4 and 4 are lifted up to a predetermined height, the support members 4 and 4 are fixed to the outermost pipes 3 and 3 of the temporary columns 2 and 2 with bolts or the like, and pinned to prevent the support members 4 and 4 from falling.
A brace is provided in the column direction of the adjacent temporary columns 2 and 2. After the temporary roof has been raised to a predetermined height as described above, underground construction and construction work up to a floor where construction is possible are performed.

【0013】第4工程 仮設屋根のリフトアップ〔図1
(4)〕 仮設柱2、2の内側から2番目の内管(第2内管)をリ
フトアップすることにより、仮設屋根全体を上昇させ
る。図3(1)にワイヤー式のリフトアップ機構の一例
を示す。同図において、符号10はワイヤー、符号11
はウィンチである。図3(2)は、リフトアップ前の状
態における、図3(1)のII−II線切断断面図である。
リフトアップ後、前記第3工程と同様にして第2内管の
固定と落下防止措置を講じる。仮設柱2、2の最も内側
の内管(最内管)を繋ぎ材9にて建築物の躯体に緊結す
ることにより、仮設構造物の安定を確保するのがよい。
Fourth step Lift up of the temporary roof [Fig. 1
(4)] By lifting up the second inner pipe (second inner pipe) from the inside of the temporary columns 2 and 2, the entire temporary roof is raised. FIG. 3 (1) shows an example of a wire-type lift-up mechanism. In the figure, reference numeral 10 is a wire, and reference numeral 11
Is a winch. FIG. 3B is a sectional view taken along the line II-II of FIG. 3A in the state before the lift-up.
After the lift-up, the second inner tube is fixed and the fall prevention measures are taken in the same manner as the third step. It is preferable to secure the stability of the temporary structure by tightly connecting the innermost inner pipes (innermost pipes) of the temporary columns 2 and 2 to the skeleton of the building with the connecting material 9.

【0014】第5工程 建築工事〔図1(5)〕 施工可能な階まで、建築工事を順次行う。 Fifth step construction work [Fig. 1 (5)] Construction work is sequentially performed up to the floors where construction is possible.

【0015】第6工程 リフトアップ、建築工事〔図1
(6)〕 第4および第5工程を繰り返し、最上階まで施工する。
図2はこの状態を示しており、同図(1)は平面図、同
図(2)は正面図、同図(3)は側面図である。仮設屋
根は建築物より1スパン程度大きくし、これによって形
成された空間12を荷上げ作業等に利用するのがよい。
6th process Lift-up, construction work [Fig. 1
(6)] The fourth and fifth steps are repeated to build up to the top floor.
FIG. 2 shows this state, in which FIG. 1A is a plan view, FIG. 2B is a front view, and FIG. 3C is a side view. It is preferable that the temporary roof has a span larger than that of the building by about 1 span, and the space 12 formed thereby is used for loading work or the like.

【0016】続いて、上記のようにして組み立てた全天
候型仮設構造物を解体する手順について説明する。建築
工事完了後、仮設構造物の解体時に、構造物の両側から
タワークレーン等がアクセスできれば、同クレーンによ
って、仮設柱2や仮設梁5を吊り降ろすことができる。
一方、構造物の片側にしかタワークレーン等の設置場所
が確保できないときには、図4に示すように、タワーク
レーン(またはトラッククレーン)12を用いて高所作
業車13とミニクレーン14を建築物の屋上に吊り上
げ、タワークレーン12の吊り降ろし作業ができない部
分は、ミニクレーン14との協力により吊り降ろし作業
を行えばよい。
Next, a procedure for disassembling the all-weather temporary structure assembled as described above will be described. After the construction work is completed, if the tower crane or the like can be accessed from both sides of the structure when dismantling the temporary structure, the temporary pillar 2 and the temporary beam 5 can be hung by the crane.
On the other hand, when the installation location of the tower crane or the like can be secured only on one side of the structure, the tower crane (or truck crane) 12 is used to install the aerial work vehicle 13 and the mini crane 14 as shown in FIG. The portion of the tower crane 12 that cannot be lifted up and lifted down on the rooftop may be lifted down in cooperation with the mini crane 14.

【0017】[0017]

【発明の効果】本発明に係る全天候型仮設構造物は、簡
易な構造と機構により、工事の進捗状況に合わせて仮設
構造物を上昇させることができるので、建設現場におけ
る生産性と作業効率を低コストで改善することができ
る。また、仮設梁や仮設足場などの構造物を地上で組み
立てることにより、高所での危険作業を減らすことがで
き、安全性に寄与する。更に、組立および解体も極めて
容易であるという効果を有する。
EFFECTS OF THE INVENTION The all-weather temporary structure according to the present invention can raise the temporary structure according to the progress of the construction with a simple structure and mechanism, so that productivity and work efficiency at the construction site can be improved. It can be improved at low cost. Also, by assembling structures such as temporary beams and temporary scaffolds on the ground, it is possible to reduce dangerous work at high places and contribute to safety. Furthermore, it has the effect that it is extremely easy to assemble and disassemble.

【図面の簡単な説明】[Brief description of drawings]

【図1】全天候型仮設構造物の施工手順図である。FIG. 1 is a construction procedure diagram of an all-weather temporary structure.

【図2】施工手順の最終段階における全天候型仮設構造
物の平面図(1)、正面図(2)および側面図(3)で
ある。
FIG. 2 is a plan view (1), a front view (2) and a side view (3) of the all-weather temporary structure at the final stage of the construction procedure.

【図3】ワイヤー式のリフトアップ機構の一例を示す概
要図である。
FIG. 3 is a schematic view showing an example of a wire type lift-up mechanism.

【図4】全天候型仮設構造物の解体手順図である。FIG. 4 is a disassembly procedure diagram of an all-weather temporary structure.

【符号の説明】[Explanation of symbols]

2 仮設柱 3 最外管 4 支持部材 5 仮設梁 8 仮設足場 11 ウィンチ 12 タワークレーン 2 Temporary column 3 Outermost tube 4 Support member 5 Temporary beam 8 Temporary scaffolding 11 Winch 12 Tower crane

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 対向して設けられた仮設柱間に仮設梁を
横架し、該仮設梁の上に仮設屋根を載せ、かつ、前記仮
設柱を多重管構造として伸縮自在としたことを特徴とす
る全天候型仮設構造物。
1. A temporary beam is laid horizontally between opposing temporary columns, a temporary roof is placed on the temporary beam, and the temporary column is made expandable and contractable as a multi-tube structure. An all-weather temporary structure.
【請求項2】 桁行方向に隣接する前記仮設柱の最外管
に、仮設足場を設置した請求項1記載の全天候型仮設構
造物。
2. The all-weather temporary structure according to claim 1, wherein a temporary scaffold is installed on the outermost pipe of the temporary columns adjacent to each other in the column direction.
JP3260453A 1991-09-12 1991-09-12 All-weather temporary structure Expired - Fee Related JP2834351B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3260453A JP2834351B2 (en) 1991-09-12 1991-09-12 All-weather temporary structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3260453A JP2834351B2 (en) 1991-09-12 1991-09-12 All-weather temporary structure

Publications (2)

Publication Number Publication Date
JPH0571226A true JPH0571226A (en) 1993-03-23
JP2834351B2 JP2834351B2 (en) 1998-12-09

Family

ID=17348159

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3260453A Expired - Fee Related JP2834351B2 (en) 1991-09-12 1991-09-12 All-weather temporary structure

Country Status (1)

Country Link
JP (1) JP2834351B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2026003966A (en) * 2024-06-25 2026-01-14 青木あすなろ建設株式会社 Steel frame construction method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04146372A (en) * 1990-10-08 1992-05-20 Kajima Corp Constructing method for frame

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04146372A (en) * 1990-10-08 1992-05-20 Kajima Corp Constructing method for frame

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2026003966A (en) * 2024-06-25 2026-01-14 青木あすなろ建設株式会社 Steel frame construction method

Also Published As

Publication number Publication date
JP2834351B2 (en) 1998-12-09

Similar Documents

Publication Publication Date Title
EP0480683B1 (en) Erection workbench and construction process
JPH0571225A (en) Temporarily set roof of complete weather type
CN117536335B (en) BIM-based starry sky garden steel structure hinge installation method
JP2979039B2 (en) Large space building construction equipment
JP2834351B2 (en) All-weather temporary structure
JP3399873B2 (en) How to build a dome structure
CN213204913U (en) Modular prefabricated staircase operation platform
JPH05133016A (en) Peripheral supporting self-rising type building engineering method
JP3066460B2 (en) How to build a tower
JP2945917B2 (en) Construction method of large space building
JP3328790B2 (en) High-rise building assembly method
KR20220165039A (en) Construction method for turbular supporting pole
CN112431431A (en) Reinforcement construction method for steel structure factory building in crane beam dismantling
JP2621748B2 (en) All-weather temporary shed
JPH05179707A (en) Truss manufacturing method and dome construction method using truss
JPH03235838A (en) Lift up method of construction using temporary pillar
JP2876991B2 (en) Steel frame method for high-rise buildings
JP2779258B2 (en) Roof lift-up method
JP2696486B2 (en) Building construction method
JP3060333B2 (en) Construction method of building frame
JPH0540492U (en) Automatic lifting work platform
JP2002371711A (en) How to build a building
KR20250061777A (en) Construction method of the structure of the elevator machine room on the rooftop of an apartment building by recycling the gangform of typical floor
JP3185069B2 (en) How to build structures using tower cranes
JP2785112B2 (en) All-weather construction method for high-rise buildings

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19980908

LAPS Cancellation because of no payment of annual fees