JPH0573579A - Work content switching instruction device - Google Patents

Work content switching instruction device

Info

Publication number
JPH0573579A
JPH0573579A JP26529791A JP26529791A JPH0573579A JP H0573579 A JPH0573579 A JP H0573579A JP 26529791 A JP26529791 A JP 26529791A JP 26529791 A JP26529791 A JP 26529791A JP H0573579 A JPH0573579 A JP H0573579A
Authority
JP
Japan
Prior art keywords
work
date
working
change
lot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP26529791A
Other languages
Japanese (ja)
Other versions
JP3227736B2 (en
Inventor
Yoshio Kita
良夫 北
Toshiko Sagami
俊子 佐上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sony Corp
Original Assignee
Sony Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sony Corp filed Critical Sony Corp
Priority to JP26529791A priority Critical patent/JP3227736B2/en
Publication of JPH0573579A publication Critical patent/JPH0573579A/en
Application granted granted Critical
Publication of JP3227736B2 publication Critical patent/JP3227736B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Multi-Process Working Machines And Systems (AREA)

Abstract

PURPOSE:To properly instruct the working contents of each manufacturing lot by comparing a working condition changing date with the working date of manufacturing lot changing reference work, deciding a working condition and determining the succeeding working contents. CONSTITUTION:When a change in working contents is instructed, a working condition file 6 for storing the working condition of device work stores also a changing date and changing reference work to specify a manufacturing lot to be changed. When the start of work is commanded, a work name is retrieved from a lot master file 5 and the working history of the manufacturing lot is read out from a lot working history file 7. When a change in the working condition is instructed, is compared the changing date read out from the file 6 is compared with a working date on which the manufacturing lot ends the change reference work, and when the working date is delayed from the changing date, working is executed under the unchanged working condition, and when advanced from the changing date, the changed working condition is adopted. Then the succeeding working condition of the manufacturing lot is displayed.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、作業内容切換指示装
置、特にコンピュータによる生産管理システムにおいて
作業条件の変更指令が為された場合、各製造ロットに対
して作業内容を正しく指示する作業内容切換指示装置に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a work content switching instructing device, and more particularly to a work content switching device for correctly instructing work contents for each manufacturing lot when a work condition changing command is issued in a production management system using a computer. Regarding the indicating device.

【0002】[0002]

【従来の技術】半導体装置はそれぞれのその型式に応じ
て一定の順序に従っての多数(数百)の作業を経て製造
され、その製造は例えば半導体ウェハの段階では例えば
25乃至50枚程度のウェハからなる製造ロット単位で
の製造管理の下で行われる。そして、半導体ウェハに対
する製造ロットでの生産管理は、コンピュータシステム
により情報処理して作業員を指示し、あるいは直接製造
装置を制御することにより行われる。
2. Description of the Related Art A semiconductor device is manufactured through a large number (hundreds) of operations in a certain order according to its type. For example, at the stage of a semiconductor wafer, the manufacture is performed from about 25 to 50 wafers. It is carried out under the manufacturing control in units of manufacturing lots. The production management of semiconductor wafers in a production lot is performed by information processing by a computer system to instruct a worker or by directly controlling a production apparatus.

【0003】ところで、各製造ロットはその型式が決ま
ればそれに伴って一連の作業が決まる。具体的には、各
作業の内容、条件及び作業順序が決まる。そして、一旦
その一連の作業が決まるとそれは変更しないのが原則で
ある。尚、その一連の作業は多数種あり、それぞれ一つ
ずつ異なる認識番号が与えられ、例えばプロセス01、
プロセス02というように呼ばれる。また、プロセス何
々と称される数百という多数の作業からなる一連の作業
は、コスト計算等の便宜のために複数の作業群に分割さ
れ、一つの作業群は工程と称される。
By the way, a series of operations is determined in accordance with the model of each manufacturing lot. Specifically, the content, condition, and work order of each work are determined. And, in principle, once the series of work is decided, it does not change. It should be noted that there are many types of the series of operations, and each is given a different identification number.
It is called process 02. Further, a series of works called hundreds of works called processes is divided into a plurality of work groups for convenience of cost calculation and the like, and one work group is called a process.

【0004】さて、製造ロットに対して行うべき一連の
作業(プロセス)が決まるとそれを変更しないのが原則
であるが、例外的に変更しなければならないときもあ
る。例えば、拡散のための工程において、前処理作業と
しての洗浄の条件を変えるとか、前処理作業を追加する
とか、削除するとかの変更をすることが好ましい場合が
ある。具体的なケースを挙げると、前処理作業による洗
浄効果が期待した程は得られずこのままでは歩留り低下
を招くので、洗浄条件を変える必要がある場合がそれで
ある。逆に、洗浄効果が過剰になりオーバーエッチング
になるので、洗浄時間を短縮するとかあるいは今まで行
っていた前処理を削除することが好ましい場合もある。
By the way, in principle, when a series of operations (processes) to be performed on a manufacturing lot is determined, it is not changed, but sometimes it is necessary to change it exceptionally. For example, in the process for diffusion, it may be preferable to change the cleaning condition as the pretreatment operation, add the pretreatment operation, or delete the pretreatment operation. In a specific case, the cleaning effect due to the pretreatment work is not obtained as expected, and the yield is reduced if it is left as it is. Therefore, it is necessary to change the cleaning conditions. On the contrary, since the cleaning effect becomes excessive and overetching occurs, it may be preferable to shorten the cleaning time or to eliminate the pretreatment that has been performed so far.

【0005】ところで、従来において、コンピュータに
よる生産管理システムは、かかる作業変更があった場
合、変更前の作業条件に関する情報を消滅させ、変更後
の作業条件、即ち新規作業条件に関する情報のみを持つ
ようにしていた。そして、変更がある毎に作業を停止し
作業者にその変更について口頭あるいは書類により説明
し、作業者により、即ち人手によりその変更に対処する
ようにしていた。
By the way, in the past, a production control system using a computer erases the information on the work condition before the change when there is such a work change and keeps only the work condition after the change, that is, the information on the new work condition. I was doing Then, every time there is a change, the work is stopped, the change is explained to the worker verbally or by documents, and the change is dealt with by the worker, that is, manually.

【0006】[0006]

【発明が解決しようとする課題】しかしながら、変更に
対する人手による対処は間違いが起き易い。というの
は、例えば123番目の作業と第156番目の作業とに
ついて変更があった場合、第123番目の作業において
新しい作業条件で作業が行われた製造ロットに対して
は、第156番目の作業においても変更後の新しい作業
条件で作業を行わなければならない。しかし、123番
目の作業において旧作業条件で作業が行われた製造ロッ
トに対しては第156番目の作業においても変更前の旧
作業条件で作業を行わなければならない。従って、第1
56番目の作業を行う作業員は製造ロットが変更の対象
であるか否かを判断しなければならず、間違い易いので
ある。
However, manual handling of changes is apt to make mistakes. This is because, for example, when there is a change in the 123rd work and the 156th work, the 156th work is performed for the manufacturing lot in which the work is performed under the new work condition in the 123rd work. In the case of, the work must be performed under the new working conditions after the change. However, for the manufacturing lot in which the work has been performed under the old work condition in the 123rd work, the work in the 156th work must be performed under the old work condition before the change. Therefore, the first
The worker who carries out the 56th work has to judge whether or not the manufacturing lot is the target of the change, which is easily mistaken.

【0007】殊に、生産システム(ライン)は多数の製
造ロットを処理する能力を持っており、ラインの構成も
きわめて複雑であり、そのため、多数の製造ロットが生
産システムに投入されて順序どおりにシステムから出さ
れるとは限らない。後から投入された製造ロットが先に
投入された製造ロットを追い越して生産システムを流れ
ることもある。従って、ある変更に係る作業のとこまで
きた製造ロットについて変更後の作業条件を行うべきか
否かについて混乱し易い。
In particular, the production system (line) has the ability to process a large number of production lots, and the configuration of the line is extremely complicated. Therefore, a large number of production lots are put into the production system in order. It is not always emitted from the system. A manufacturing lot that was input later may overtake a manufacturing lot that was input earlier and flow through the production system. Therefore, it is easy to be confused as to whether or not the changed working condition should be performed for the manufacturing lot that has reached the work related to a certain change.

【0008】また、変更に係る作業について変更後の作
業条件を行った後、次の製造ロットに対しては変更前の
作業条件を行わなければならないことも起り得るが、従
来の管理システムは変更前の作業条件に関する条件を消
滅させていたので、作業者はそのシステムから作業条件
についての指示を受け得ず、作業者の記憶、別途用意し
たマニュアルによって変更前の作業条件で作業を行わな
ければならず、間違いが起き易いうえに作業員にかかる
負担が重くなり、また、作業遅延も起きた。
[0008] Further, it is possible that after the working condition after the change is performed for the work related to the change, the working condition before the change must be performed for the next manufacturing lot, but the conventional management system is changed. Since the condition related to the previous work condition has been eliminated, the worker cannot receive an instruction about the work condition from the system, and the worker must perform the work under the work condition before the change based on the memory of the worker and a separately prepared manual. Not only that, mistakes are likely to occur, the burden on workers is heavy, and work delays occur.

【0009】本発明はこのような問題点を解決すべく為
されたものであり、作業内容の変更指令があった時それ
に応じて各製造ロットについて適切に自動的に作業内容
について指示できる作業内容切換指示装置を提供するこ
とを目的とする。
The present invention has been made to solve such a problem, and when a work content change command is issued, the work content can be appropriately and automatically instructed for each production lot in response to the command. An object is to provide a switching instruction device.

【0010】[0010]

【課題を解決するための手段】本発明作業内容切換指示
装置は、作業条件の変更日時と、製造ロットの変更基準
作業についての作業日時とを日時比較手段により比較
し、その比較結果から上記製造ロットが変更前と変更後
のいずれの作業条件で作業が行われるべきかを判断し、
それにより上記製造ロットに対する次の作業の作業条件
を決定するようにしたことを特徴とする。
In the work content switching instructing device of the present invention, the date and time of the working condition and the work date and time of the change reference work of the manufacturing lot are compared by the date and time comparing means, and the above manufacturing is performed based on the comparison result. Judge whether the lot should be operated under the condition before or after the change,
Thereby, the working condition of the next work for the manufacturing lot is determined.

【0011】[0011]

【実施例】以下、本発明作業内容切換指示装置を図示実
施例に従って詳細に説明する。図1及び図2は本発明作
業内容切換指示装置の一つの実施例を説明するためのも
ので、図1は構成図、図2は動作を示すフローチャート
である。図面において、1はCPU、2はROM、3は
RAM、4は入出力装置、5は各製造ロットについての
仕掛情報を記憶するロットマスターファイルで、具体的
にはロット番号をキーとして仕掛作業名等を記憶する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The work content switching instruction device of the present invention will be described in detail below with reference to the illustrated embodiments. 1 and 2 are for explaining one embodiment of the work content switching instruction device of the present invention. FIG. 1 is a configuration diagram and FIG. 2 is a flowchart showing the operation. In the drawings, 1 is a CPU, 2 is a ROM, 3 is a RAM, 4 is an input / output device, and 5 is a lot master file that stores in-process information for each manufacturing lot. Etc. are memorized.

【0012】6は上記仕掛作業の作業条件を記憶する作
業条件ファイルで、具体的には作業名をキーとして作業
条件を記憶する。また、作業内容の変更(単なる作業条
件の変更のほか、作業の追加、削除も含む)が指示され
た場合、変更対象の製造ロットを特定するために変更日
時と、変更基準作業も記憶する。即ち、変更の指示は、
ある日時においてある作業が終った製造ロットについて
別の一つあるいは複数の作業についてそれぞれ作業条件
をどのように変更するという形で行われる。そして、変
更基準作業とはその日時において当該製造ロットが終了
しているか否かが問われている作業のことを指す。
A work condition file 6 stores the work conditions of the work in progress. Specifically, the work conditions are stored using the work name as a key. Further, when an instruction to change the work content (including addition and deletion of work in addition to simple change of work conditions) is given, the change date and time and change reference work are also stored in order to specify the production lot to be changed. That is, the change instruction is
It is carried out in such a manner that the working condition is changed for another one or a plurality of works for a manufacturing lot for which a work is finished at a certain date and time. The change reference work refers to work in which it is asked whether or not the manufacturing lot is completed at that date and time.

【0013】7はロット作業履歴ファイルで、各製造ロ
ットの作業履歴を記憶する。具体的には製造ロットの番
号と作業名をキーとしてその作業の終了日時を記憶す
る。8は変更日時記憶手段で、作業変更指令があった場
合の変更日時を記憶する。9は製造ロットの上記変更基
準作業についての作業終了日時を記憶する。変更日時記
憶手段8は作業条件ファイルから、作業日時記憶手段9
はロット作業履歴ファイル7からロードされた日時情報
を記憶する。
A lot work history file 7 stores the work history of each manufacturing lot. Specifically, the end date and time of the work is stored using the manufacturing lot number and the work name as keys. Reference numeral 8 is a change date / time storage means for storing the change date / time when there is a work change instruction. 9 stores the work end date and time for the above-described change standard work of the manufacturing lot. The change date / time storage means 8 stores the work date / time storage means 9 based on the work condition file.
Stores date and time information loaded from the lot work history file 7.

【0014】10は変更日時記憶手段8と作業日時記憶
手段9に記憶された日時を比較する日時比較手段、11
は作業条件指示手段で、日時比較手段10の出力に応じ
て変更に係る作業について変更後か変更前の作業条件を
指示し、例えばCRTあるいは液晶ディスプレイからな
る。具体的には、変更日時記憶手段8に記憶された変更
日時よりも作業日時記憶手段9に記憶された日時が遅い
ときは、変更前の作業条件を指示し、変更日時記憶手段
8の日時よりも作業日時記憶手段9の日時が早いときは
変更後の作業条件を指示する。
Reference numeral 10 is a date and time comparing means for comparing the dates and times stored in the change date and time storage means 8 and the work date and time storage means 9, and 11
Is a work condition instructing means for instructing the work condition after or before the change related to the work to be changed according to the output of the date and time comparing means 10, and is composed of, for example, a CRT or a liquid crystal display. Specifically, when the date and time stored in the work date and time storage means 9 is later than the change date and time stored in the change date and time storage means 8, the work condition before the change is instructed, and the date and time in the change date and time storage means 8 is changed. Also, when the date and time of the work date and time storage means 9 is early, the changed work condition is instructed.

【0015】図2は作業内容切換指示装置の動作を説明
するフローチャートである。先ず、作業開始指令が為さ
れ、作業する製造ロットのロット番号の読み込みが為さ
れる。次に、ロットマスターファイルから作業名が検索
される。次に、作業条件ファイルから作業条件について
データが読み出される。尚、作業条件の変更が指示され
ている場合には、変更日時、変更基準作業、変更前の作
業条件、変更後の作業条件が読み出される。
FIG. 2 is a flow chart for explaining the operation of the work content switching instruction device. First, a work start command is issued, and the lot number of the manufacturing lot to be worked is read. Next, the work name is retrieved from the lot master file. Next, data regarding the work condition is read from the work condition file. When the change of the work condition is instructed, the change date and time, the change reference work, the work condition before the change, and the work condition after the change are read.

【0016】次に、当該製造ロットについてのロット作
業履歴をロット作業履歴ファイルから読み出す。そし
て、作業条件ファイル6から読み出した変更日時と、ロ
ット作業履歴ファイル7から読み出したところの当該製
造ロットが変更基準作業を終了した作業日時とを比較す
る。
Next, the lot work history of the manufacturing lot is read from the lot work history file. Then, the change date and time read from the work condition file 6 is compared with the work date and time when the manufacturing lot read from the lot work history file 7 finished the change reference work.

【0017】そして、作業日時(即ち、当該製造ロット
が変更基準作業を終了した日時)の方が変更日時よりも
遅い時は変更前の作業条件で作業を行うことにする。逆
に作業日時が変更日時よりも早いときは変更後の作業条
件で作業を行うこととする。そして、決定に基づいて製
造ロットが次に行う作業条件を表示する。尚、単に作業
条件をディスプレイにより表示するのではなく、作業条
件どおりに作業が行われるように製造装置を自動的に制
御する態様でも実施できる。
Then, when the work date and time (that is, the date and time when the manufacturing lot has finished the change reference work) is later than the change date and time, the work is performed under the work condition before the change. On the contrary, when the work date and time is earlier than the change date and time, the work is performed under the changed work condition. Then, based on the determination, the working conditions to be performed next by the manufacturing lot are displayed. It should be noted that instead of simply displaying the work conditions on the display, the manufacturing apparatus can be automatically controlled so that the work is performed according to the work conditions.

【0018】図3(A)乃至(C)は作業内容の一つの
変更例を示すもので、(A)はコンピュータ上での変更
データ、(B)は変更前の作業条件で為される作業シー
ケンス、(C)は変更後の作業条件で為される作業シー
ケンスを示すものである。本変更例は、図3(A)に示
すように、第5番目の工程5の最終作業、作業番号59
が変更基準作業であり、変更日時は6日午後1:00で
ある。
FIGS. 3A to 3C show one modification example of the work contents. FIG. 3A is the modification data on the computer, and FIG. 3B is the work performed under the working conditions before the modification. Sequence (C) shows a work sequence performed under the changed work conditions. In this modification, as shown in FIG. 3A, the final work of the fifth step 5, work number 59
Is the change reference work, and the change date and time is 1:00 pm on the 6th.

【0019】そして、工程6の各作業は変更前作業条
件、即ち、旧作業条件は60、61、641 、65の順
で、変更後作業条件、即ち新作業条件61、62、6
3、642 、65の順で行わなければならないというよ
うに作業条件が設定されている。尚、641 と642
は同じ作業だが作業条件が異なるものである。また、破
線は作業を行わない場合を示す。
The work in step 6 is the work condition before change, that is, the old work condition is 60, 61, 64 1 , 65 in this order, and the post-change work condition, that is, new work condition 61, 62, 6
The work conditions are set so that the process must be performed in the order of 3 , 64 2 , and 65. It should be noted that 64 1 and 64 2 have the same work but different work conditions. The broken line shows the case where no work is performed.

【0020】そこで、若しある製造ロットが図3(B)
に示すように第5番目の工程5の最終作業、作業番号5
9の作業が6日午後5時に終了した場合、その製造ロッ
トは工程6が60、61、62、641 、65というよ
うに作業が行われることになる。
Therefore, a young production lot is shown in FIG. 3 (B).
As shown in, the final work of the fifth step 5, work number 5
When the work of 9 is completed at 5 pm on the 6th, the work of the manufacturing lot is performed in steps 6, 60, 61, 62, 64 1 , 65.

【0021】また、若し製造ロットが図3(C)に示す
ように、第5番目の工程5の最終作業、作業番号59の
作業が6日午前10時に終了した場合、その製造ロット
は61、62、63、642 、65というように行われ
ることになる。
Further, as shown in FIG. 3C, if the final work of the fifth step 5, work of work number 59, ends at 10:00 am on the 6th, the production lot is 61 , 62, 63, 64 2 , 65 and so on.

【0022】このように、本作業内容切換指示装置によ
れば、作業条件の変更があったとき変更後の新作業条件
だけでなく変更前の旧作業条件も作業条件ファイルに記
憶しておき、変更日時記憶手段と作業日時記憶手段で記
憶された日時どうしを日時比較手段により比較して製造
ロットについて変更前と変更後のどの作業条件で作業を
行うべきかを決定し、それに伴って各作業について作業
条件を決定して指示あるいは制御できる。従って、人手
による場合とは異なり製造ロットに対して新旧作業条件
の間で間違いを侵す虞れがなく、変更前の作業条件を適
用しなければならないときにおいても正しく作業条件を
示すことができる。
As described above, according to the work content switching instruction device, when the work condition is changed, not only the new work condition after the change but also the old work condition before the change are stored in the work condition file, The date and time stored in the change date and time storage means and the work date and time storage means are compared with each other by the date and time comparison means to determine which work condition before and after the production lot should be performed. Can determine and instruct or control work conditions. Therefore, unlike the case of manual operation, there is no risk of making a mistake between the old and new working conditions for the manufacturing lot, and the working conditions can be correctly indicated even when the working conditions before the change have to be applied.

【0023】[0023]

【発明の効果】本発明作業内容切換指示装置は、製造ロ
ットの仕掛情報を記憶するロットマスターファイルと、
該仕掛作業での作業条件についての情報である作業情報
を記憶する作業条件ファイルと、前記製造ロットの加工
履歴をロット作業履歴ファイルと、前記作業情報として
少なくとも作業条件の変更日時を記憶する変更日時記憶
手段と、加工履歴のうちの作業日時を記憶する作業日時
記憶手段と、上記変更日時記憶手段に記憶された変更日
時と、上記作業日時記憶手段に記憶された作業日時とを
比較する比較手段と、を少なくとも備え、上記比較手段
による比較の結果から当該製造ロットが作業条件変更前
の旧作業条件で処理すべき製造ロットであるか、作業条
件変更後の新作業条件で処理すべき製造ロットであるか
を判断して次の作業内容を決定するようにしてなること
を特徴とするものである。従って、本発明によれば、変
更日時記憶手段と作業日時記憶手段で記憶された日時ど
うしを日時比較手段により比較して製造ロットについて
変更前と変更後のどの作業条件で作業を行うべきかを決
定し、それに伴って各作業について作業条件を決定して
指示あるいは制御できる。従って、人手による場合とは
異なり、製造ロットに対して指示する条件が新旧作業条
件の間で間違いを侵す虞れがなく、変更前の作業条件を
適用しなければならないときにおいても正しく作業条件
を示すことができる。
The work content switching instructing device of the present invention comprises a lot master file for storing in-process information of manufacturing lots,
A work condition file that stores work information that is information about work conditions in the work in progress, a lot work history file that is a processing history of the manufacturing lot, and a modification date and time that stores at least the modification date and time of the work condition as the work information. Storage means, work date / time storage means for storing the work date / time of the processing history, comparison means for comparing the change date / time stored in the change date / time storage means with the work date / time stored in the work date / time storage means According to the result of the comparison by the comparison means, the manufacturing lot is a manufacturing lot to be processed under the old working condition before the working condition is changed, or a manufacturing lot under the new working condition after the working condition is changed. It is characterized in that the next work content is determined by determining whether or not it is. Therefore, according to the present invention, the date and time stored in the change date and time storage means and the work date and time storage means are compared by the date and time comparison means to determine which work condition should be performed before and after the production lot is changed. The work conditions can be determined and the work conditions can be determined and instructed or controlled accordingly. Therefore, unlike the case of manual operation, there is no risk that the conditions instructing the manufacturing lot will make a mistake between the old and new working conditions, and the correct working conditions must be applied even when the working conditions before the change must be applied. Can be shown.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明作業内容切換指示装置の一つの実施例を
示す構成図である。
FIG. 1 is a configuration diagram showing an embodiment of a work content switching instruction device of the present invention.

【図2】上記実施例の動作を示すフローチャートであ
る。
FIG. 2 is a flowchart showing the operation of the above embodiment.

【図3】(A)乃至(C)は作業条件の変更例を示す図
である。
FIG. 3A to FIG. 3C are diagrams showing examples of changing work conditions.

【符号の説明】[Explanation of symbols]

5 ロットマスターファイル 6 作業条件ファイル 7 ロット作業履歴ファイル 8 変更日時記憶手段 9 作業日時記憶手段 10 日時比較手段 5 lot master file 6 work condition file 7 lot work history file 8 change date / time storage means 9 work date / time storage means 10 date / time comparison means

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 製造ロットの仕掛情報を記憶するロット
マスターファイルと、 前記仕掛作業での作業条件についての情報である作業情
報を記憶する作業条件ファイルと、 前記製造ロットの加工履歴をロット作業履歴ファイル
と、 前記作業情報として少なくとも作業条件の変更日時を記
憶する変更日時記憶手段と、 加工履歴のうちの作業日時を記憶する作業日時記憶手段
と、 上記変更日時記憶手段に記憶された変更日時と、上記作
業日時記憶手段に記憶された作業日時とを比較する比較
手段と、 を少なくとも備え、 上記比較手段による比較の結果から当該製造ロットが作
業条件変更前の旧作業条件で処理すべき製造ロットであ
るか、作業条件変更後の新作業条件で処理すべき製造ロ
ットであるかを判断して次の作業内容を決定するように
してなることを特徴とする作業内容切換指示装置
1. A lot master file for storing work-in-process information of a production lot, a work condition file for storing work information that is information about work conditions in the work-in-progress, and a lot work history for processing history of the production lot. A file, a change date and time storage means for storing at least the change date and time of the work condition as the work information, a work date and time storage means for storing the work date and time of the processing history, and a change date and time stored in the change date and time storage means A manufacturing lot to be processed under the old working condition before the working condition is changed from the result of the comparison by the comparing device, and at least a comparing unit for comparing the working date and time stored in the working date and time storing unit. Or the production lot to be processed under the new work condition after changing the work condition, determine the next work content. Work switching instruction apparatus characterized by comprising
JP26529791A 1991-09-17 1991-09-17 Work content switching instruction device Expired - Fee Related JP3227736B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26529791A JP3227736B2 (en) 1991-09-17 1991-09-17 Work content switching instruction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26529791A JP3227736B2 (en) 1991-09-17 1991-09-17 Work content switching instruction device

Publications (2)

Publication Number Publication Date
JPH0573579A true JPH0573579A (en) 1993-03-26
JP3227736B2 JP3227736B2 (en) 2001-11-12

Family

ID=17415248

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26529791A Expired - Fee Related JP3227736B2 (en) 1991-09-17 1991-09-17 Work content switching instruction device

Country Status (1)

Country Link
JP (1) JP3227736B2 (en)

Also Published As

Publication number Publication date
JP3227736B2 (en) 2001-11-12

Similar Documents

Publication Publication Date Title
CN106796425A (en) The control device of lathe
JPH06252020A (en) Chip managing system and its input processing method and lot processing method
US7742839B2 (en) Robot system provided with robot controller
JPH05143613A (en) Production planning system
JPH10118896A (en) Schedule creation support device
JPS59214964A (en) Conversational scheduling system
KR102291974B1 (en) Semiconductor system and method for supporting data editing
JP2739858B2 (en) Production control system and device
JPH0573579A (en) Work content switching instruction device
JPH05283308A (en) Control method of semiconductor manufacturing apparatus and control apparatus thereof
JPH06218659A (en) Preparation replacing instruction device and manufacturing system
JPH03239460A (en) Production completion schedule calculating method and device
JP3049871B2 (en) Reference wafer single wafer management system
JPH0966442A (en) Process control device
JPH0830679A (en) Creating and updating process control line table
JP2003303008A (en) Process control method
JPH07168881A (en) Work control system
JPH0935103A (en) Device for managing production planning information
JPH05109596A (en) Manufacturing and controlling method for semiconductor device
JPH07262210A (en) Drawing display device
JPH07230499A (en) Work instruction change processor
JP2001236112A (en) Process flow management method
JPH09216146A (en) How to create work plans for multiple automated machine tools
JPH0764624A (en) Production control device and production control method
JPH05304064A (en) Work instruction and control device of semiconductor wafer process

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees