JPH0610361A - Pedestal construction method - Google Patents
Pedestal construction methodInfo
- Publication number
- JPH0610361A JPH0610361A JP4190230A JP19023092A JPH0610361A JP H0610361 A JPH0610361 A JP H0610361A JP 4190230 A JP4190230 A JP 4190230A JP 19023092 A JP19023092 A JP 19023092A JP H0610361 A JPH0610361 A JP H0610361A
- Authority
- JP
- Japan
- Prior art keywords
- foundation
- concrete
- steel pipe
- steel
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 18
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 title abstract description 5
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 78
- 239000010959 steel Substances 0.000 claims abstract description 78
- 239000004567 concrete Substances 0.000 claims abstract description 43
- 238000000034 method Methods 0.000 claims description 17
- 238000009411 base construction Methods 0.000 claims description 10
- 238000009415 formwork Methods 0.000 claims description 8
- 230000002787 reinforcement Effects 0.000 claims description 7
- 239000011150 reinforced concrete Substances 0.000 description 7
- 230000003014 reinforcing effect Effects 0.000 description 6
- 238000009434 installation Methods 0.000 description 5
- 239000000463 material Substances 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000011440 grout Substances 0.000 description 2
- 239000004570 mortar (masonry) Substances 0.000 description 2
- 230000000149 penetrating effect Effects 0.000 description 2
- 230000001771 impaired effect Effects 0.000 description 1
- 230000002035 prolonged effect Effects 0.000 description 1
- 230000000452 restraining effect Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
Landscapes
- Foundations (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、鉄骨構造物の基礎に用
いる柱脚工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a column base construction method used for the foundation of a steel frame structure.
【0002】[0002]
【従来の技術】従来の鉄骨構造物の基礎は、図6に示す
様に鉄筋コンクリート構造で構築するのが一般的であっ
た。従来の柱脚工法の施工手順は、基礎コンクリート上
に主筋Aや帯筋B等の配筋を行い、その配筋内部にはア
ンカーボルトC等の接合部材を配置しておく。次に、型
枠Dを配筋部に外装して設置し、型枠D内にコンクリー
トEを打設し、コンクリートが硬化した後に型枠を脱型
して、柱脚基礎の構築を行っていた。そして、鉄骨柱F
を柱脚基礎上に建込んで、建方作業を行っていた。2. Description of the Related Art The foundation of a conventional steel frame structure has generally been constructed by a reinforced concrete structure as shown in FIG. In the conventional procedure of the column base construction method, reinforcing bars such as the main reinforcing bar A and the reinforcing bar B are arranged on the foundation concrete, and the joining members such as the anchor bolts C are arranged inside the reinforcing bar. Next, the form D is installed on the bar arrangement, the concrete E is placed in the form D, and the form is removed after the concrete is hardened to build the column base. It was And steel pillar F
Was erected on the pedestal foundation.
【0003】[0003]
【発明が解決しようとする問題点】前記した従来の鉄筋
コンクリートによる柱脚基礎にあっては、次のような問
題点がある。 <イ> 柱脚基礎を構築するには、根切り、配筋、型枠
設置、コンクリート打設及び型枠脱型という多くの工程
を経なければならず、工期が長期化する一因になってい
る。Problems to be Solved by the Invention The above-described conventional column base foundation made of reinforced concrete has the following problems. <a> In order to construct a column base, many processes such as root cutting, bar arrangement, formwork installation, concrete placement, and formwork demolding must be performed, which is one of the reasons for the prolonged construction period. ing.
【0004】<ロ> 鉄骨構造の柱脚を露出柱脚とする
と、柱脚基礎が柱材に対し相当大きな寸法となり、構築
後の柱脚部の外観が損なわれる。<B> When the column base having the steel frame structure is used as the exposed column base, the column base has a size considerably larger than the column material, and the appearance of the column base after construction is impaired.
【0005】<ハ> 柱脚基礎が鉄筋コンクリート構造
の場合、基礎梁は鉄筋コンクリート構造に制限され、基
礎梁に鉄骨構造を採用できない。<C> When the column base is a reinforced concrete structure, the foundation beam is limited to a reinforced concrete structure, and a steel frame structure cannot be adopted for the foundation beam.
【0006】[0006]
【本発明の目的】本発明は以上の問題を解決するために
成されたもので、その目的とするところは、工期の短縮
と施工性の改善が図れる柱脚工法を提供することにあ
る。SUMMARY OF THE INVENTION The present invention has been made to solve the above problems, and an object of the present invention is to provide a column base construction method capable of shortening the construction period and improving the workability.
【0007】[0007]
【問題点を解決するための手段】すなわち本発明は、鉄
骨構造による建築物の柱脚基礎の構築工法において、建
築物の建築予定地に打設した基礎コンクリート上に基礎
鋼管を固定し、この基礎鋼管内に鉄骨柱支持用のアンカ
ーボルトをセットし、前記基礎鋼管内にコンクリートを
打設して柱脚基礎を構築することを特徴とする、柱脚工
法である。また本発明は、鉄骨構造による建築物の柱脚
基礎の構築工法において、建築物の建築予定地に打設し
た基礎コンクリート上に配筋を行い、その配筋した鉄筋
内に側面にスタッドジベルを突設した基礎鋼管を配置
し、前記鉄筋に型枠を外装し、前記型枠内にコンクリー
トを打設し、前記コンクリートが硬化した後、基礎鋼管
内に鉄骨柱支持用のアンカーボルトをセットし、前記基
礎鋼管内にコンクリートを打設して柱脚基礎を構築する
ことを特徴とする、柱脚工法である。[Means for Solving the Problems] That is, according to the present invention, in a method of constructing a column pedestal foundation of a building with a steel structure, a foundation steel pipe is fixed on a foundation concrete cast at a construction site of the building, A column base construction method, characterized in that an anchor bolt for supporting a steel frame column is set in the basic steel pipe, and concrete is placed in the basic steel pipe to construct a column base. Further, the present invention, in the construction method of the column base foundation of the building by the steel frame structure, the reinforcement is done on the foundation concrete placed in the planned construction site of the building, and the stud dowel is provided on the side surface in the reinforcement. Arrange the protruding basic steel pipe, cover the formwork on the rebar, place concrete in the formwork, and after the concrete hardens, set anchor bolts for supporting steel columns in the basic steel pipe. The column base construction method is characterized in that concrete is placed in the foundation steel pipe to construct a column base.
【0008】[0008]
【実施例1】以下図面を参照しながら柱脚工法について
説明する。 <イ>基礎コンクリートの打設(図4) 建築物基礎部の構築予定地を所定深度まで掘削する。掘
削した孔内に基礎コンクリート2を打設する。その際
に、ステコンアンカー21を鉛直方向に向け設置してお
く。ステコンアンカー21の設置位置は、その一部が基
礎コンクリート2から突出する位置とする。尚、必要に
応じて基礎コンクリート2の下方に基礎杭等を打設して
おく場合もある。First Embodiment A column base construction method will be described below with reference to the drawings. <A> Placing basic concrete (Fig. 4) Excavate the planned construction site of the building foundation to the specified depth. Foundation concrete 2 is placed in the excavated hole. At that time, the stercon anchor 21 is installed in the vertical direction. The stacon anchor 21 is installed at a position where a part of the stacon anchor 21 projects from the basic concrete 2. In addition, a foundation pile or the like may be placed below the foundation concrete 2 if necessary.
【0009】<ロ>基礎鋼管の設置(図2、図4) 基礎コンクリート2上にレベルモルタル22を打設し
て、基礎鋼管3の高さの位置修正を行った後に、基礎鋼
管3を載置する。すなわち、ベースプレート32の孔3
4に前記ステコンアンカー21を貫通させ、ナットでベ
ースプレート32を締結して、基礎鋼管3を基礎コンク
リート2上に固定する。図2に示す様に基礎鋼管3は、
断面を矩形とし一端を開口した中空体で、中空体の閉塞
している一端にはその中空体の断面より大きく矩形に形
成した板状のベースプレート32が形成されている。基
礎鋼管3の胴部33の断面寸法は、後述する鉄骨柱5の
下部に形成しているベースプレート51の寸法に対しや
や大きめに選択する。ベースプレート32には複数の孔
34が開設されている。この孔33の孔径は、孔34を
貫通するステコンアンカー21の径に応じて設定され
る。ステコンアンカー21の設置については、基礎コン
クリート2打設後、基礎コンクリート2にアンカー孔を
穿孔し、そのアンカー孔へステコンアンカー21を挿入
し定着させても良い。<B> Installation of basic steel pipe (FIGS. 2 and 4) After level mortar 22 is placed on the basic concrete 2 and the height of the basic steel pipe 3 is adjusted, the basic steel pipe 3 is mounted. Place. That is, the holes 3 of the base plate 32
The stecon anchor 21 is passed through the base plate 4, and the base plate 32 is fastened with a nut to fix the base steel pipe 3 on the base concrete 2. As shown in FIG. 2, the basic steel pipe 3 is
A hollow body having a rectangular cross section and one end opened, and a plate-shaped base plate 32 formed in a rectangle larger than the cross section of the hollow body is formed at one closed end of the hollow body. The cross-sectional dimension of the body portion 33 of the basic steel pipe 3 is selected to be slightly larger than the dimension of the base plate 51 formed in the lower portion of the steel frame column 5 described later. The base plate 32 has a plurality of holes 34 formed therein. The hole diameter of the hole 33 is set according to the diameter of the stencon anchor 21 penetrating the hole 34. With respect to the installation of the stacon anchor 21, it is also possible that after the concrete 2 is cast, an anchor hole is drilled in the basic concrete 2 and the stacon anchor 21 is inserted and fixed in the anchor hole.
【0010】 <ハ>基礎鋼管内へのコンクリート打設(図4) 基礎鋼管3内でアンカーボルト4を位置決めを行い、鉛
直方向に向けて仮設しておく。アンカーボルト4の仮設
位置は、鉄骨柱5の設置位置を考慮して鉄骨柱5の孔5
2に合う様に決定する。そして、基礎鋼管3内にコンク
リート42を打設する。その際、コンクリート42を基
礎鋼管3の開口部35の上端まで充填せず、ある程度隙
間を設けて行う。コンクリート42が硬化した後、レベ
ルモルタル41をコンクリート42上に打設し、接合予
定の鉄骨柱5の上下方向に位置出しを行う。<C> Concrete Placing in the Basic Steel Pipe (FIG. 4) The anchor bolts 4 are positioned in the basic steel pipe 3 and are temporarily installed in the vertical direction. The anchor bolts 4 are temporarily installed at the holes 5 of the steel column 5 in consideration of the installation position of the steel column 5.
Decide to fit 2. Then, concrete 42 is placed in the base steel pipe 3. At this time, the concrete 42 is not filled up to the upper end of the opening 35 of the basic steel pipe 3, but a gap is provided to some extent. After the concrete 42 is hardened, the level mortar 41 is placed on the concrete 42 to position the steel frame column 5 to be joined in the vertical direction.
【0011】<ニ>基礎鋼管と基礎梁との接合(図4) 基礎鋼管3の側面部31に基礎梁6を溶接することによ
り接合する。基礎梁6としてH鋼等の鉄骨材を用いるこ
とできるので、配筋、型枠設置およびコンクリート打設
等の作業が不要となるので、基礎梁6の施工期間を短縮
することができる。また、基礎部全体を鉄骨構造で構成
することにより重量を軽減できるので、基礎杭7の省略
化が可能である。<D> Joining of Basic Steel Pipe and Foundation Beam (FIG. 4) The basic beam 6 is welded to the side surface portion 31 of the basic steel pipe 3 for joining. Since the steel beams such as H steel can be used as the foundation beams 6, the work such as bar arrangement, formwork installation and concrete placement is unnecessary, so that the construction period of the foundation beams 6 can be shortened. Moreover, since the weight can be reduced by constructing the entire foundation portion with a steel frame structure, the foundation pile 7 can be omitted.
【0012】 <ホ>基礎鋼管と鉄骨柱との接合(図3、図4) 埋戻しを行い、基礎部を埋設する。次に基礎鋼管3と鉄
骨柱5との接合であるが、鉄骨柱5について説明する。
鉄骨柱5は、建築物の骨組みを構成する柱であり、例え
ば四角柱形の中空体で形成され、その端部には上記基礎
鋼管3と同様にベースプレート51が形成されている。
ベースプレート51には複数の孔52が開設されてい
る。この孔52の孔径は、孔52を貫通するアンカーボ
ルト41の径に応じて設定される。基礎鋼管3と鉄骨柱
5との接合工程について説明する。基礎鋼管3内のコン
クリート42より突出するアンカーボルト4をベースプ
レート51に開設した孔52に貫通させて、鉄骨柱5を
基礎鋼管3上に建込む。アンカーボルト41にナットを
装着してベースプレート51を締結する。そして、コン
クリート42とベースプレート51との隙間にグラウト
材を注入する。この時、基礎鋼管3の胴部33がベース
プレート51の周囲を囲っているので、別途にシール型
枠を必要とせず、グラウト材の注入を行える。<E> Joining of Basic Steel Pipe and Steel Column (FIGS. 3 and 4) Backfilling is performed to embed the foundation part. Next, regarding the joining of the basic steel pipe 3 and the steel frame column 5, the steel frame column 5 will be described.
The steel frame column 5 is a column that constitutes a framework of a building, and is formed of, for example, a rectangular column-shaped hollow body, and a base plate 51 is formed at the end thereof similarly to the basic steel pipe 3.
The base plate 51 has a plurality of holes 52. The hole diameter of the hole 52 is set according to the diameter of the anchor bolt 41 penetrating the hole 52. The process of joining the basic steel pipe 3 and the steel column 5 will be described. The anchor bolt 4 protruding from the concrete 42 in the base steel pipe 3 is passed through the hole 52 formed in the base plate 51, and the steel frame column 5 is built on the base steel pipe 3. A nut is attached to the anchor bolt 41 and the base plate 51 is fastened. Then, the grout material is injected into the gap between the concrete 42 and the base plate 51. At this time, since the body portion 33 of the basic steel pipe 3 surrounds the periphery of the base plate 51, it is possible to inject the grout material without requiring a separate seal form.
【0013】<ヘ>鉄骨建方 上記の様に、鉄骨柱5を次々に建込み、鉄骨の建方を行
って行く。<F> Steel frame erection As described above, the steel frame columns 5 are successively erected and the steel frame is erected.
【0014】[0014]
【実施例2】本実施例の柱脚基礎は、図5に示す様に、
基礎鋼管3aを基礎梁61から露出されて構築し、基礎
梁61を鉄筋コンクリート構造により構築したものであ
る。柱脚施工工程は、まず建築物の建築予定地に打設し
た基礎コンクリート2上に配筋を行い、その配筋内に基
礎鋼管3aを配置しておく。基礎鋼管3aは、外面にス
タッドジベル36を突設したものを用いる。そして、配
筋した鉄筋に型枠を外装し、型枠内にコンクリート7を
打設する。コンクリート7が硬化した後、基礎鋼管3a
内に鉄骨柱5支持用のアンカーボルト4をセットし、前
記基礎鋼管3a内にコンクリート42を打設して柱脚基
礎を構築する。基礎鋼管3aの外面に設置した複数のス
タットジベル36は、コンクリート7との接合性を高め
ている。このように、鉄筋コンクリート構造の基礎梁に
も本発明の柱脚工法は適用可能である。[Second Embodiment] As shown in FIG. 5, the column base of the present embodiment is
The foundation steel pipe 3a is constructed by being exposed from the foundation beam 61, and the foundation beam 61 is constructed by a reinforced concrete structure. In the column base construction process, first, reinforcement is arranged on the foundation concrete 2 placed in the planned construction site of the building, and the foundation steel pipe 3a is arranged in the reinforcement. As the basic steel pipe 3a, one having a stud dowel 36 projecting from the outer surface is used. Then, the form is exteriorly mounted on the reinforced reinforcing bar, and concrete 7 is placed in the form. After concrete 7 hardens, foundation steel pipe 3a
An anchor bolt 4 for supporting a steel column 5 is set inside, and concrete 42 is placed in the foundation steel pipe 3a to construct a column base. The plurality of stat dowels 36 installed on the outer surface of the base steel pipe 3a enhance the bondability with the concrete 7. As described above, the column base construction method of the present invention can be applied to a foundation beam having a reinforced concrete structure.
【0015】[0015]
【発明の効果】本発明は以上説明したようになるから次
のような効果を得ることができる。 <イ> 柱脚基礎を鉄骨構造により構成したので、構築
時において配筋および型枠の設置作業等が不要である。Since the present invention is as described above, the following effects can be obtained. <A> Since the column base is made of a steel structure, there is no need to install reinforcements and formwork at the time of construction.
【0016】<ロ> 柱脚基礎と鉄骨による基礎梁との
接合を容易に行えるので、基礎部全体を鉄骨構造で構築
することができ、各部材のプレハブ化を図ることができ
る。<B> Since the column base and the foundation beam made of steel can be easily joined, the entire foundation can be constructed with a steel structure, and each member can be prefabricated.
【0017】<ハ> 基礎部構築工期を大幅に短縮する
ことができる。<C> It is possible to greatly reduce the construction period of the foundation portion.
【0018】<ニ> 従来の鉄筋コンクリート構造に比
べ、柱脚基礎を細く形成できる。このため、柱脚基礎と
接合する鉄骨材との整合状態が良好であり、柱脚基礎を
露出して施工を行う場合など、優れた外観性を付与する
ことができる。<D> The column base can be formed thinner than the conventional reinforced concrete structure. For this reason, the state of alignment with the steel aggregate to be joined to the column base is good, and excellent appearance can be imparted when, for example, construction is performed with the column base exposed.
【0019】<ホ> 基礎鋼管内にコンクリートを充填
することでコンクリートの拘束効果が得られ、コンクリ
ート上に鉄骨柱を建込むことによりコンクリートの圧縮
強度が増大する。<E> By filling the basic steel pipe with concrete, the effect of restraining the concrete is obtained, and by constructing the steel column on the concrete, the compressive strength of the concrete is increased.
【0020】<ヘ> 基礎鋼管が補強部材として機能す
る為、柱脚基礎の剛性が向上する。<F> Since the basic steel pipe functions as a reinforcing member, the rigidity of the column base is improved.
【図1】 実施例1の柱脚基礎の斜視図FIG. 1 is a perspective view of a column base according to a first embodiment.
【図2】 基礎鋼管の斜視図[Fig. 2] Perspective view of basic steel pipe
【図3】 柱脚基礎と鉄骨柱の接合方法の説明図FIG. 3 is an explanatory diagram of a method of joining a column base and a steel column.
【図4】 実施例1の基礎部の断面図FIG. 4 is a cross-sectional view of the base portion of the first embodiment.
【図5】 実施例2の基礎部の断面図FIG. 5 is a cross-sectional view of the base portion of the second embodiment.
【図6】 従来の柱脚基礎の説明図FIG. 6 is an explanatory diagram of a conventional column base.
Claims (2)
工法において、 建築物の建築予定地に打設した基礎コンクリート上に基
礎鋼管を固定し、 この基礎鋼管内に鉄骨柱支持用のアンカーボルトをセッ
トし、 前記基礎鋼管内にコンクリートを打設して柱脚基礎を構
築することを特徴とする、 柱脚工法。1. A method for constructing a column base foundation for a building having a steel structure, in which a base steel pipe is fixed on a foundation concrete placed in a planned construction site of the building, and an anchor for supporting the steel column is provided in the base steel pipe. A column base construction method, characterized in that a column base is constructed by setting bolts and placing concrete in the foundation steel pipe.
工法において、 建築物の建築予定地に打設した基礎コンクリート上に配
筋を行い、 配筋する鉄筋内に、側面にスタッドジベルを突設した基
礎鋼管を配置し、 前記鉄筋に型枠を外装し、 前記型枠内にコンクリートを打設し、 前記コンクリートが硬化した後、基礎鋼管内に鉄骨柱支
持用のアンカーボルトをセットし、 前記基礎鋼管内にコンクリートを打設して柱脚基礎を構
築することを特徴とする、 柱脚工法。2. A method of constructing a column base foundation for a building using a steel frame structure, wherein reinforcement is laid on the foundation concrete placed in the planned construction site of the building, and stud dowels are provided on the sides within the reinforcement. Arrange the projecting basic steel pipe, cover the formwork on the rebar, place concrete in the formwork, and after the concrete has hardened, set anchor bolts for supporting steel columns in the basic steel pipe. The column base construction method, characterized in that concrete is placed in the foundation steel pipe to construct a column base.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19023092A JP3232487B2 (en) | 1992-06-25 | 1992-06-25 | Construction method of column base and column base structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19023092A JP3232487B2 (en) | 1992-06-25 | 1992-06-25 | Construction method of column base and column base structure |
Related Child Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP11180333A Division JP2000034733A (en) | 1999-06-25 | 1999-06-25 | Footing structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0610361A true JPH0610361A (en) | 1994-01-18 |
| JP3232487B2 JP3232487B2 (en) | 2001-11-26 |
Family
ID=16254658
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP19023092A Expired - Lifetime JP3232487B2 (en) | 1992-06-25 | 1992-06-25 | Construction method of column base and column base structure |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3232487B2 (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109235776A (en) * | 2018-10-31 | 2019-01-18 | 吉林省建苑设计集团有限公司 | Plug-in type Prefabricated concrete-filled steel tube column and foundation connection structure and attaching method thereof |
| CN112878668A (en) * | 2021-02-07 | 2021-06-01 | 东南大学建筑设计研究院有限公司 | Column foot device of independent adjustable steel column template system |
| CN116837886A (en) * | 2023-07-31 | 2023-10-03 | 中国能源建设集团陕西省电力设计院有限公司 | A kind of integrated foundation of bus bridge bracket support and cable double groove |
| CN117926911A (en) * | 2024-03-11 | 2024-04-26 | 中信建筑设计研究总院有限公司 | High bearing capacity net rack support node structure convenient to installation |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS54107109A (en) * | 1978-02-10 | 1979-08-22 | Isamu Kubota | Method of anchor construction and frame anchor |
| JPH0288818A (en) * | 1988-09-26 | 1990-03-29 | Hiromi Yamada | Method and apparatus for leveling surface of column for foundation |
| JPH02115416A (en) * | 1988-10-25 | 1990-04-27 | Mitsui Constr Co Ltd | Structure of pillar leg section by steel pipe pillar |
| JPH02164930A (en) * | 1988-12-19 | 1990-06-25 | Asahi Chem Ind Co Ltd | Foundation structure for building |
| JPH0393923A (en) * | 1989-09-06 | 1991-04-18 | Mitsui Constr Co Ltd | Connection method of steel pillar of cast-in-place pile and connection structure |
| JPH04254616A (en) * | 1991-02-07 | 1992-09-09 | Yamatomi Sangyo Kk | Construction of foundation for building |
-
1992
- 1992-06-25 JP JP19023092A patent/JP3232487B2/en not_active Expired - Lifetime
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS54107109A (en) * | 1978-02-10 | 1979-08-22 | Isamu Kubota | Method of anchor construction and frame anchor |
| JPH0288818A (en) * | 1988-09-26 | 1990-03-29 | Hiromi Yamada | Method and apparatus for leveling surface of column for foundation |
| JPH02115416A (en) * | 1988-10-25 | 1990-04-27 | Mitsui Constr Co Ltd | Structure of pillar leg section by steel pipe pillar |
| JPH02164930A (en) * | 1988-12-19 | 1990-06-25 | Asahi Chem Ind Co Ltd | Foundation structure for building |
| JPH0393923A (en) * | 1989-09-06 | 1991-04-18 | Mitsui Constr Co Ltd | Connection method of steel pillar of cast-in-place pile and connection structure |
| JPH04254616A (en) * | 1991-02-07 | 1992-09-09 | Yamatomi Sangyo Kk | Construction of foundation for building |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109235776A (en) * | 2018-10-31 | 2019-01-18 | 吉林省建苑设计集团有限公司 | Plug-in type Prefabricated concrete-filled steel tube column and foundation connection structure and attaching method thereof |
| CN112878668A (en) * | 2021-02-07 | 2021-06-01 | 东南大学建筑设计研究院有限公司 | Column foot device of independent adjustable steel column template system |
| CN116837886A (en) * | 2023-07-31 | 2023-10-03 | 中国能源建设集团陕西省电力设计院有限公司 | A kind of integrated foundation of bus bridge bracket support and cable double groove |
| CN117926911A (en) * | 2024-03-11 | 2024-04-26 | 中信建筑设计研究总院有限公司 | High bearing capacity net rack support node structure convenient to installation |
Also Published As
| Publication number | Publication date |
|---|---|
| JP3232487B2 (en) | 2001-11-26 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH09209451A (en) | Joint construction of up and down columns with beam and joint method | |
| JPH1096210A (en) | Construction method of pier overhang | |
| JP3232487B2 (en) | Construction method of column base and column base structure | |
| JPH02164931A (en) | Foundation construction method for building | |
| JP2002030672A (en) | Joint structure between foundation pile and column base and its construction method | |
| JPH07247557A (en) | Foundation, column mold, and underground beam made of precast reinforced concrete | |
| JP2000034733A (en) | Footing structure | |
| JPH02164934A (en) | Foundation construction method | |
| JPH02164930A (en) | Foundation structure for building | |
| JPH116162A (en) | Construction method for reinforced concrete underground external wall | |
| JPH09256383A (en) | Steel pillar construction method | |
| JP2677174B2 (en) | Column base structure of steel column | |
| JP2784450B2 (en) | Reinforced concrete foundation | |
| JPH0754355A (en) | Foundation for small-scale building | |
| JPH0544219A (en) | Base structure for steel-framed column and construction thereof | |
| JPH0598653A (en) | Steel pipe concrete pillar in underground inverter construction method | |
| JP2805154B2 (en) | Construction method of concrete panel and cloth foundation used for it | |
| JPH07103620B2 (en) | Construction method for steel structure | |
| JP2025139821A (en) | Wall construction method and anchor member | |
| JPH10252144A (en) | Erection method for steel pipe column | |
| JP3792276B2 (en) | Building foundations and construction methods | |
| JP2578671B2 (en) | Column and beam construction method | |
| JP2003147855A (en) | Fixing method for column body to concrete footing | |
| JPH0376929A (en) | Steel-framed foundation | |
| JPS6217233A (en) | Foundation base column |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080921 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080921 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090921 Year of fee payment: 8 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100921 Year of fee payment: 9 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100921 Year of fee payment: 9 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110921 Year of fee payment: 10 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110921 Year of fee payment: 10 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120921 Year of fee payment: 11 |
|
| EXPY | Cancellation because of completion of term | ||
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120921 Year of fee payment: 11 |