JPH06229121A - Prearrangement of bearing wall reinforcing bars - Google Patents

Prearrangement of bearing wall reinforcing bars

Info

Publication number
JPH06229121A
JPH06229121A JP1741893A JP1741893A JPH06229121A JP H06229121 A JPH06229121 A JP H06229121A JP 1741893 A JP1741893 A JP 1741893A JP 1741893 A JP1741893 A JP 1741893A JP H06229121 A JPH06229121 A JP H06229121A
Authority
JP
Japan
Prior art keywords
wall
bar
ribs
bars
reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP1741893A
Other languages
Japanese (ja)
Inventor
Shunji Asanuma
俊二 浅沼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP1741893A priority Critical patent/JPH06229121A/en
Publication of JPH06229121A publication Critical patent/JPH06229121A/en
Pending legal-status Critical Current

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

(57)【要約】 【目的】 配筋に乱れを生じることなく、工程の重なり
をなくし、作業時の危険を防止しうる耐力壁鉄筋の先組
工法を提供する。 【構成】 鉄骨柱またはPC柱及び鉄骨梁の建方後、鉄
骨梁Gのウエブ1にブラケット2を梁の長手方向に適宜
間隔に取付け、各ブラケット2上に梁部の上主筋5を配
置して、同上主筋5から所定間隔毎に肋筋4を配設し、
同各肋筋4に梁部の下主筋5を配筋して、上下主筋3、
5と肋筋4を結束して梁部の配筋を行い、前記上主筋5
に壁部の縦鉄筋6をフック6aを介して懸吊し、同壁縦
鉄筋6の下部を下階の梁部に定着長6a差込み、前記壁
縦筋6に壁横筋7を配筋する。
(57) [Summary] [Purpose] To provide a pre-assembly method for load-bearing wall rebars that does not cause disorder in bar arrangement, eliminates overlapping of processes, and can prevent danger during work. [Structure] After erection of a steel frame column or a PC column and a steel frame beam, brackets 2 are attached to the web 1 of the steel frame beam G at appropriate intervals in the longitudinal direction of the beam, and an upper main bar 5 of the beam part is arranged on each bracket 2. The same as above, the ribs 4 are arranged at predetermined intervals from the main muscle 5,
The lower main bar 5 of the beam is arranged on each of the ribs 4, and the upper and lower main bars 3,
5 and the ribs 4 are tied together to arrange the beams, and the upper main bar 5
The vertical bar 6 of the wall is suspended via the hook 6a, the lower part of the vertical bar 6 of the wall is inserted into the beam part of the lower floor by the fixed length 6a, and the horizontal bar 6 of the wall is arranged.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明はSRC造の耐力壁鉄筋の
スラブコンクリート打設前に行なわれる先組工法に係る
ものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pre-assembled construction method which is carried out before placing a slab concrete of a bearing wall reinforcing bar of SRC construction.

【0002】[0002]

【従来の技術】従来、スラブコンクリート打設後、上階
の梁a、壁bの配筋を行うため、コンクリート打設前に
壁差筋cを行ない(図2参照)床コンクリート打設後、
壁鉄筋dの配筋を行なっていた。
2. Description of the Related Art Conventionally, since beam a and wall b on the upper floor are reinforced after the slab concrete is cast, a wall streak c is performed before the concrete is cast (see FIG. 2).
The reinforcement of the wall reinforcing bar d was performed.

【0003】[0003]

【発明が解決しようとする課題】前記従来工法において
は、スラブコンクリート打設前に壁差筋を行い、墨出し
後差筋を正規の位置に修正して組立てるので、作業が煩
雑となる。また差筋が上部作業時に作業員の体にささる
危険があり、コンクリート打設によって差筋が乱れる。
In the above-mentioned conventional method, the work is complicated because the wall streak is performed before the slab concrete is poured and the streak after the marking is corrected to the proper position for assembly. In addition, there is a danger that the streak sticks to the worker's body during the upper work, and the streak is disturbed by concrete placement.

【0004】更に差筋の頭部がふらついて安定せず、正
しい配筋ができず、コンクリート打設後の壁鉄筋組工程
に時間を要する。更に床コンクリート墨出しと鉄筋荷上
げのスペースと工程が重なり混乱する。本発明は前記従
来工法の問題点に鑑みて提案されたもので、その目的と
する処は、配筋に乱れを生じることがなく、工程の重な
りをなくし、作業時の危険が防止される耐力壁鉄筋の先
組工法を提供する点にある。
Further, the heads of the stiffeners fluctuate and are not stable, correct bar arrangement is not possible, and it takes time for the wall reinforcing bar assembly process after placing concrete. Furthermore, the space and process for floor concrete staking out and reinforcing bar loading overlap and become confusing. The present invention has been proposed in view of the problems of the conventional construction method, the object of which is to prevent the occurrence of disorder in the bar arrangement, eliminate the overlap of the process, and prevent the danger during work. The point is to provide a pre-assembly method for wall reinforcement.

【0005】[0005]

【課題を解決するための手段】前記の目的を達成するた
め、本発明に係る耐力壁鉄筋の先組方法によれば、鉄骨
柱またはPC柱及び鉄骨梁の建方後、鉄骨梁部のウエブ
にブラケットを梁の長手方向に沿って適宜間隔に取付け
て同各ブラケットに亘って梁部の上主筋を配設し、次い
で同上主筋に所定の間隔に肋筋を配設し、次いで梁部の
下主筋を配筋して、前記肋筋と上下主筋を結束したの
ち、前記梁部の上主筋に壁縦筋をフックを介して懸吊
し、同壁縦筋の下部を下階の梁部に定着長差込み、前記
壁縦筋に壁横筋を配筋するものである。
In order to achieve the above object, according to the method of pre-assembling a load-bearing wall reinforcing bar according to the present invention, after erection of a steel column or a PC column and a steel beam, the web of the steel beam portion is constructed. The brackets are attached at appropriate intervals along the longitudinal direction of the beam, and the upper main bars of the beam section are arranged over the respective brackets, then the ribs are arranged at predetermined intervals on the same main bar, and then the After arranging the lower main bar and binding the ribs to the upper and lower main bars, suspend the wall vertical bar on the upper main bar of the beam through a hook, and lower the wall vertical bar to the beam section of the lower floor. The fixing length is inserted into the wall to arrange the horizontal wall of the wall to the vertical wall of the wall.

【0006】[0006]

【作用】本発明によれば前記したように、鉄骨柱または
PC柱、及び鉄骨梁の建方後、同鉄骨梁のウエブに梁の
長手方向に亘って所定間隔毎に鉄筋支持用のブラケット
を取付け、同各ブラケット上に亘って梁部の上主筋を架
渡し、同上主筋に所定位置毎に肋筋を配置、懸架して同
各肋筋の下部間に亘って梁部の下主筋を通し、前記肋筋
と上下主筋を結束して耐力壁上部のSRC梁の梁鉄筋を
簡単に先組みするものである。
According to the present invention, as described above, after the steel frame or the PC column and the steel beam are erected, the reinforcing bar supporting brackets are provided on the web of the steel beam at predetermined intervals along the longitudinal direction of the beam. Install, bridge the upper main bar of the beam over the brackets, place the ribs at predetermined positions on the main bar, hang it, and pass the lower main bar of the beam over the lower part of each rib. The ribs of the SRC beam above the load-bearing wall are easily assembled in advance by binding the ribs and the upper and lower main bars together.

【0007】次いでこのように組立てられた梁鉄筋の上
主筋を利用して壁縦筋をフックを介して懸吊し、下部を
下階の梁部分に所要の定着長を差込んで壁縦筋を簡易に
配筋し、同壁縦筋に壁横筋を配筋することによって壁鉄
筋をコンクリート打設前に配筋することが可能となる。
Next, the vertical wall of the wall is suspended using a hook by utilizing the upper main bar of the beam rebar thus assembled, and the lower part of the vertical bar of the wall is inserted into the beam portion of the lower floor with a required fixing length. By simply arranging the wall and arranging the horizontal wall of the wall to the vertical wall of the same wall, it becomes possible to reinforce the wall reinforcing bar before placing concrete.

【0008】[0008]

【実施例】以下本発明を図示の実施例について説明す
る。F1 は本発明の梁、耐力壁の鉄筋の先組方法が適用
され、コンクリートの打設が完了した階である。本発明
の耐力壁鉄筋の先組方法によれば鉄骨柱(PC柱を含
む)、鉄骨梁の建方が完了したのち、鉄骨梁Gのウエブ
1にブラケット2を梁の長手方向に亘って適宜間隔毎に
突設し、同各ブラケット2に梁部の上主筋3を配設し、
次いで同上主筋3に肋筋4を所定間隔毎に懸吊し、同各
肋筋4に梁部の下主筋5を配筋してSRC耐力壁上部の
上部梁鉄筋を先組みする。
The present invention will be described below with reference to the illustrated embodiments. F 1 is a floor to which the method of assembling the beam and the reinforcing bar of the bearing wall of the present invention has been applied and the placing of concrete has been completed. According to the assembling method of the load-bearing wall rebar of the present invention, after the construction of the steel frame columns (including the PC columns) and the steel frame beams is completed, the bracket 2 is appropriately attached to the web 1 of the steel frame beam G in the longitudinal direction of the beam. Projected at intervals, the upper main reinforcement 3 of the beam is arranged on each bracket 2,
Next, the ribs 4 are suspended from the main ribs 3 at the predetermined intervals, and the lower main ribs 5 of the beam portion are arranged on the respective ribs 4 to assemble the upper beam rebars above the SRC bearing wall first.

【0009】次いで耐力壁の縦鉄筋6をフック6aを介
して前記上主筋3に懸吊し、下端部を下階部に定着長6
bだけ差し込み、前記縦鉄筋6に壁の横鉄筋7を配筋し
て、壁鉄筋の先組を行う。かくして鉄筋の先組が完了す
るとコンクリートを打設し、耐力壁、スラブを構築する
ものである。
Next, the vertical reinforcing bar 6 of the load bearing wall is suspended from the upper main reinforcing bar 3 via the hook 6a, and the lower end portion is fixed to the lower floor portion by a fixing length 6
Only b is inserted, the horizontal reinforcing bars 7 of the wall are arranged on the vertical reinforcing bars 6, and the wall reinforcing bars are assembled first. In this way, when the first assembly of the reinforcing bars is completed, concrete is poured to construct the bearing wall and slab.

【0010】本発明によれば前記したように、従来のと
おり柱、梁の鉄筋の先組に加えて、耐力壁の配筋も同時
に先組するものであり、F2 は本方法によって先組が行
なわれた階を示す。本方法によれば、従来のように耐力
壁鉄筋の先組が完了した階のコンクリートの打設が完了
した後、次の階の定着筋を差筋することなく、差筋の節
約と手間が省かれ、コンクリートの打設に左右されるこ
となく、上階を先行して作業ができる。
[0010] As described above, according to the present invention, conventional as pillars, in addition to the previous group of reinforcing bars of the beam, reinforcement of the bearing wall is also intended to previously set at the same time, F 2 is previously set by the present process Indicates the floor on which According to this method, after the placing of the concrete on the floor where the pre-assembly of the load-bearing wall reinforcing bars has been completed as in the conventional method is completed, the reinforcement bars of the next floor can be saved and the effort can be saved without arranging the anchoring bars of the next floor. It can be omitted and the work can be done ahead of the upper floor without being influenced by concrete pouring.

【0011】図中8はスラブ配筋、9はコンクリートで
ある。
In the figure, 8 is slab reinforcement and 9 is concrete.

【0012】[0012]

【発明の効果】本発明によれば前記したように、鉄筋柱
またはPC柱及び鉄骨梁の建方後、同梁のウエブから梁
の長手方向に所定間隔毎にブラケットを突設して耐力壁
上部のSRC梁の上主筋を配設し、同上主筋に肋筋を懸
吊して同肋筋に下主筋を配筋して梁筋を先組し、同梁筋
の上主筋に壁鉄筋をフックを介して懸吊して、その下部
を下階の梁部に定着長差込むとともに、壁横筋を配筋す
ることによって、梁筋、壁筋を先組することができ、前
記従来の壁差筋を省略することによって工程のラップが
なくなり、差筋による作業の危険性がなくなる。
According to the present invention, as described above, after erection of a reinforcing bar column or a PC column and a steel frame beam, brackets are projected from the web of the beam at predetermined intervals in the longitudinal direction of the beam to bear a load bearing wall. The upper reinforcement of the upper SRC beam is arranged, the ribs are suspended on the same reinforcement, and the lower reinforcement is arranged on the same reinforcement, and the beam reinforcement is assembled first, and the wall reinforcement is attached to the upper reinforcement of the reinforcement. The beam reinforcement and wall reinforcement can be assembled first by suspending them via hooks and inserting the lower part of them into the beam portion on the lower floor by fixing length, and by arranging the lateral wall reinforcement. By omitting the stagger, the process wrap is eliminated and the risk of work by the stagger is eliminated.

【0013】また床コンクリート打設前に壁筋の組立が
でき、鉄筋の乱れを防止することができ、品質のよい鉄
筋工事が行なわれる。
Further, wall reinforcement can be assembled before placing the floor concrete, and disorder of the reinforcement can be prevented, so that good quality reinforcement work can be performed.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る耐力壁鉄筋の先組方法の一実施例
の実施状況を示す縦断面図である。
FIG. 1 is a vertical cross-sectional view showing an implementation state of an embodiment of a method of preassembling a bearing wall reinforcing bar according to the present invention.

【図2】従来工法を示し、壁差筋工程を示す縦断面図で
ある。
FIG. 2 is a vertical cross-sectional view showing a conventional method and showing a wall streak step.

【図3】従来工法における上階の梁、壁の配筋状態を示
す縦断面図である。
FIG. 3 is a vertical cross-sectional view showing a state of reinforcement of beams and walls on an upper floor in a conventional method.

【符号の説明】[Explanation of symbols]

1 階 F2 階 1 梁のウエブ 2 ブラケット 3 梁部の上主筋 4 肋筋 5 梁部の下主筋 6 壁部の縦鉄筋 6a フック 6b 定着長 7 壁部の横鉄筋 8 スラブ筋 9 コンクリートF 1st floor F 2nd floor 1 Beam web 2 Brackets 3 Beam upper bars 4 Ribs 5 Beam lower bars 6 Wall vertical bars 6a Hooks 6b Anchorage length 7 Wall horizontal bars 8 Slabs 9 Concrete

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 鉄骨柱またはPC柱及び鉄骨梁の建方
後、鉄骨梁部のウエブにブラケットを梁の長手方向に沿
って適宜間隔に取付けて同各ブラケットに亘って梁部の
上主筋を配設し、次いで同上主筋に所定の間隔に肋筋を
配設し、次いで梁部の下主筋を配筋して、前記肋筋と上
下主筋を結束したのち、前記梁部の上主筋に壁縦筋をフ
ックを介して懸吊し、同壁縦筋の下部を下階の梁部に定
着長差込み、前記壁縦筋に壁横筋を配筋することを特徴
とする耐力壁鉄筋の先組方法。
1. After erection of a steel column or a PC column and a steel beam, brackets are attached to the web of the steel beam portion at appropriate intervals along the longitudinal direction of the beam, and the upper main reinforcement of the beam portion is extended across each bracket. Then, the ribs are arranged at a predetermined interval on the main bar, and then the lower main bar of the beam is arranged to bind the costal and the upper and lower main bars, and then the wall is attached to the upper main bar of the beam. Longitudinal bars are suspended via hooks, the lower part of the same wall longitudinal bars is inserted into the beam part of the lower floor by a fixed length, and the wall longitudinal bars are arranged with lateral wall reinforcing bars. Method.
JP1741893A 1993-02-04 1993-02-04 Prearrangement of bearing wall reinforcing bars Pending JPH06229121A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1741893A JPH06229121A (en) 1993-02-04 1993-02-04 Prearrangement of bearing wall reinforcing bars

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1741893A JPH06229121A (en) 1993-02-04 1993-02-04 Prearrangement of bearing wall reinforcing bars

Publications (1)

Publication Number Publication Date
JPH06229121A true JPH06229121A (en) 1994-08-16

Family

ID=11943465

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1741893A Pending JPH06229121A (en) 1993-02-04 1993-02-04 Prearrangement of bearing wall reinforcing bars

Country Status (1)

Country Link
JP (1) JPH06229121A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013091942A (en) * 2011-10-25 2013-05-16 Sumitomo Mitsui Construction Co Ltd S-beam rc earthquake-resistant wall structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013091942A (en) * 2011-10-25 2013-05-16 Sumitomo Mitsui Construction Co Ltd S-beam rc earthquake-resistant wall structure

Similar Documents

Publication Publication Date Title
JP7670753B2 (en) Beam structure, support member for beam reinforcement, and beam reinforcement method
JP3466136B2 (en) Method and apparatus for overhanging PC bridge
JPH11159143A (en) Setting-up method for beam-section concrete reinforcing net
JPH10121491A (en) Assembly method of foundation beam reinforcement
JPH0517996A (en) Building constructing method
JP2000129633A (en) Bridge slab erection method
JP2712955B2 (en) Reinforced concrete beam rebar assembly method
JP2697807B2 (en) Reinforcing cage assembly / building equipment
JPH07324376A (en) Method for constructing reinforced concrete structure
JP2759131B2 (en) Foundation beam construction method for steel reinforced concrete columns
JPS648145B2 (en)
JPH0988348A (en) Foundation beam construction method
JPH10280331A (en) Formwork unit for reinforced concrete floor slab and its installation method
JPH0949264A (en) Constructing method for reinforced concrete framework and structure, and member therefor
JPH11131692A (en) Unit insert
JP2000017727A (en) Construction method of steel frame and reinforced concrete structure
JPH076252Y2 (en) Joint structure of PC beam and beam
JPH0420639A (en) Pc small beam
JPH0558704U (en) Precast reinforced concrete structure
JPH0447107B2 (en)
JPS6039835B2 (en) Reinforced steel construction method
JPS6343281Y2 (en)
JPH07229203A (en) Joint section of precast reinforced concrete
JPH07331782A (en) Floor slab consisting of PC version
JP3002681B2 (en) Building structure