JPH0633123Y2 - Temporary stopper for concrete formwork - Google Patents

Temporary stopper for concrete formwork

Info

Publication number
JPH0633123Y2
JPH0633123Y2 JP1988019075U JP1907588U JPH0633123Y2 JP H0633123 Y2 JPH0633123 Y2 JP H0633123Y2 JP 1988019075 U JP1988019075 U JP 1988019075U JP 1907588 U JP1907588 U JP 1907588U JP H0633123 Y2 JPH0633123 Y2 JP H0633123Y2
Authority
JP
Japan
Prior art keywords
temporary
ring
insulating material
shaped
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1988019075U
Other languages
Japanese (ja)
Other versions
JPH01122140U (en
Inventor
輝雄 増渕
康昭 秋田
孝行 駒場
一 糸井
正博 一島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Achilles Corp
Original Assignee
Achilles Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Achilles Corp filed Critical Achilles Corp
Priority to JP1988019075U priority Critical patent/JPH0633123Y2/en
Publication of JPH01122140U publication Critical patent/JPH01122140U/ja
Application granted granted Critical
Publication of JPH0633123Y2 publication Critical patent/JPH0633123Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【考案の詳細な説明】 (産業上の利用分野) この考案は、プラスチツクフオームを芯材とする堰板兼
用断熱材を用いてコンクリート型枠を組立てる場合に、
その堰板兼用断熱材にパイプや角材の桟を仮止めするコ
ンクリート型枠用桟仮止め具に係るものである。
[Detailed Description of the Invention] (Industrial field of application) This invention is intended for assembling a concrete formwork using a heat insulating material that also serves as a weir plate and has a plastic foam as a core material.
The present invention relates to a concrete frame temporary fixture for temporarily fixing pipes and square beams to the heat insulating material that also serves as a dam plate.

(従来の技術) 従来のこの種のコンクリート型枠用桟仮止め具は、見当
らない。
(Prior Art) No conventional temporary crosspiece fixture for concrete formwork of this type is found.

(考案が解決しようとする問題点) 近年、プラスチツクフオームを芯材とし、コンクリート
型枠の堰板としての剛性と断熱効果を有する堰板兼用断
熱材が開発されたが、これを用いて型枠を組立てる場
合、その堰板兼用断熱材の外面にパイプや角材を仮止め
しなければならない。
(Problems to be solved by the invention) In recent years, a heat insulating material that also serves as a weir board has been developed, which has a plastic foam core as a core material and has rigidity and a heat insulating effect as a weir board of a concrete formwork. When assembling, the pipes and squares must be temporarily fixed to the outer surface of the insulating material that also serves as the barrier plate.

しかしながら、釘を堰板表面に打つて番線によりパイプ
や角材を仮止めする従来の仮止め手段では、釘打ち,番
線結束の二重の工程を必要として面倒な作業であつた。
However, the conventional temporary fixing means for hitting a nail on the surface of a barrier plate and temporarily fixing a pipe or a square bar with a numbered wire requires a double process of nailing and binding the numbered wire, which is a troublesome work.

(問題点を解決するための手段) この考案は、上記の問題点を解決するために、弾力性を
有する線材から成り、一部に開放部(1)を設けたリン
グ状(2)に形成し、そのリング状部線材(2)の開放
部(1)に対する両側円弧部(4),(4′)に外側へ
の凸円弧状膨出体(5),(5′)を形成して開放部
(1)に対向する円弧部(6)に外側へのコ字形膨出体
(7)を形成し、リング状部線材(2)の開放部(1)
における両端部に直線状突出片(3),(3′)を設け
てコンクリート型枠用桟仮止め具(a)を構成する。
(Means for Solving Problems) In order to solve the above problems, the present invention is made of a wire material having elasticity and is formed into a ring shape ( 2 ) partially provided with an open portion (1). Then, outward convex arcuate bulges (5), (5 ') are formed on both side arcuate parts (4), (4') with respect to the open part (1) of the ring-shaped wire ( 2 ). The arcuate portion (6) facing the open portion (1) is formed with an outward C-shaped bulge (7), and the open portion (1) of the ring-shaped wire ( 2 ) is formed.
The linear projecting pieces (3) and (3 ') are provided at both ends of the above to construct the concrete frame temporary tack (a).

(作用) (1)桟に丸パイプ(A)を用いる場合には、パイプ
(A)の所要箇所において、仮止め具(a)の開放部
(1)を広げて仮止め具(a)をパイプ(A)に押込め
ば、仮止め具(a)は、その弾性によつて開閉作動しリ
ング状部(2)がパイプ(A)に圧接してパイプ(A)
に固定する。
(Operation) (1) When the round pipe (A) is used for the crosspiece, the open portion (1) of the temporary fastener (a) is widened at the required position of the pipe (A) to open the temporary fastener (a). When pushed into the pipe (A), the temporary stopper (a) is opened and closed by its elasticity, and the ring-shaped portion ( 2 ) is pressed against the pipe (A) to cause the pipe (A) to move.
Fixed to.

そこで、仮止め具(a)の直線状突出片(3),
(3′)を堰板兼用断熱材(B)に向けて仮止め具
(a)を堰板兼用断熱材(B)に押し込むと、仮止め具
(a)の直線状突出片(3),(3′)が堰板兼用断熱
材(B)内に突刺さり、堰板兼用断熱材(B)の外側に
パイプ(A)が仮止め具(a)により仮止めされてパイ
プ(A)による桟が形成される。
Therefore, the linear protruding piece (3) of the temporary stopper (a),
When the temporary stopper (a) is pushed into the insulating material (B) also used as the barrier plate, the linear protruding piece (3) of the temporary stopper (a), (3 ') is pierced into the insulating material (B) that also serves as a weir plate, and the pipe (A) is temporarily fixed to the outside of the insulating material (B) that also serves as a weir plate by the temporary fasteners (a). A crosspiece is formed.

一方、パイプ(A)を堰板兼用断熱材(B)から取外す
場合には、仮止め具(a)の両側膨出体(5),
(5′)部を挟み持つて引くか、あるいは膨出体(7)
内にてこを差込んでこじる等すると、仮止め具(a)が
堰板兼用断熱材(B)から抜け出てパイプ(A)は外れ
る。
On the other hand, when removing the pipe (A) from the heat insulating material (B) that also serves as the barrier plate, both side bulging bodies (5) of the temporary stopper (a),
Hold (5 ') part and pull, or bulge (7)
When the operator inserts a prison and twists it, the temporary fastener (a) comes out of the heat insulating material (B) that also serves as the barrier plate, and the pipe (A) comes off.

その後、仮止め具(a)の膨出体(7)を把持して引く
と、仮止め具(a)は弾性により上記と同様に開閉作動
してパイプ(A)から外れる。
After that, when the bulging body (7) of the temporary fastening tool (a) is grasped and pulled, the temporary fastening tool (a) is elastically opened and closed in the same manner as described above, and is detached from the pipe (A).

(2)桟に角材(C)を用いる場合には、堰板兼用断熱
材(B)の外面に角材(C)を当て、所定箇所において
仮止め具(a)を開放部(1)から角材(C)に嵌合し
て堰板兼用断熱材(B)に押込めば、上記と同様に作用
し、堰板兼用断熱材(B)の外側に角材(C)が仮止め
具(a)により仮止めされて角材(C)による桟が形成
される。
(2) When using a square bar (C) for the crosspiece, the square bar (C) is applied to the outer surface of the insulating material (B) that also serves as a barrier plate, and the temporary fastener (a) is released from the opening (1) at a predetermined position. If it fits into (C) and is pushed into the insulating material (B) that also serves as a weir plate, it operates in the same manner as above, and the square material (C) is temporarily attached to the outside of the insulating material (B) that serves also as a weir plate (a). And the crosspieces are formed by the square bar (C).

一方、角材(C)を堰板兼用断熱材(B)から取外す場
合には、仮止め具(a)を上記と同様に操作すると、仮
止め具(a)が堰板兼用断熱材(B)から抜け出て角材
(C)および仮止め具(a)は外れる。
On the other hand, when the square bar (C) is removed from the heat insulating material (B) also used as the dam plate, if the temporary fastener (a) is operated in the same manner as described above, the temporary fastener (a) becomes the heat insulating material (B) also used as the dam plate. The timber (C) and the temporary fixing tool (a) come off from it.

(実施例) 図面は、この考案の一実施例を示し、その構造を図面に
ついて説明すれば、(a)は弾力性を有する線材の屈曲
加工によつて構成したコンクリート型枠用桟仮止め具
で、一部に開放部(1)を設けたリング状(2)に形成
し、そのリング状部線材(2)の開放部(1)に対する
両側円弧部(4),(4′)の中間部を外側への凸円弧
状に彎曲して両側円弧部(4),(4′)の中間部にそ
れぞれ外側の凸円弧状膨出体(5),(5′)を形成
し、開放部(1)に対向する円弧部(6)を外側へのコ
字形に屈曲して円弧部(6)に外側へのコ字形膨出体
(7)を形成し、リング状部線材(2)の開放部(1)
における両端部に直線状突出片(3),(3′)を設
け、その両側の直線状突出片(3),(3′)にそれぞ
れ下方へのU字形の引掛り(8)を形成し、該両側の直
線状突出片(3),(3′)の先端を尖鋭(9)に加工
して成る。
(Embodiment) The drawings show an embodiment of the present invention, and the structure thereof will be described with reference to the drawing. (A) is a temporary tack for a concrete formwork constructed by bending a wire rod having elasticity. Then, a ring-shaped ( 2 ) partly provided with an opening (1) is formed, and the ring-shaped wire ( 2 ) is located between the arcuate portions (4), (4 ') on both sides of the opening (1). The outer curved portion is curved in an outward convex arc shape to form outer convex arcuate bulges (5) and (5 ') in the middle portions of both side arcuate portions (4) and (4'), respectively, to form an open portion. arc portion opposite the (1) to (6) bent in a U-shape to the outside U-shaped bulge of the outer (7) is formed in an arcuate portion (6), ring-shaped portion wire (2) Opening part (1)
The linear projecting pieces (3) and (3 ') are provided at both ends of the above, and the U-shaped hooks (8) are formed downward on the linear projecting pieces (3) and (3') on both sides thereof. The tips of the linear protruding pieces (3) and (3 ') on both sides are processed to be sharp (9).

(D),(E)はコンクリート建築物の壁および梁、
(B),(F)は壁(D)および梁(E)の堰板兼用断
熱材で、プラスチツクフオームを芯材としその両面に軟
質面材の表皮を貼付けて構成する。(A)は桟の丸パイ
プ、(G),(H)は根太および大引、(C)は桟の角
材である。
(D) and (E) are walls and beams of concrete buildings,
(B) and (F) are heat insulating materials that also serve as barrier plates for the walls (D) and the beams (E), and are formed by using a plastic foam as a core material and attaching soft surface skins to both surfaces thereof. (A) is a round pipe of a crosspiece, (G) and (H) are joists and Daihiki, and (C) is a square bar of the crosspiece.

次にその作用を説明する。第3図に示すように、堰板兼
用断熱材(B),(F)、根太(G),大引(H)を用
いて梁(E)付き壁(D)の型枠を構成する。
Next, the operation will be described. As shown in FIG. 3, a mold for a wall (D) with a beam (E) is formed by using the heat insulating materials (B) and (F) that also serve as barrier plates, joists (G), and Daihiki (H).

そこで、堰板兼用断熱材(B)の桟に丸パイプ(A)を
用いる場合には、パイプ(A)の適当箇所において、仮
止め具(a)の膨出体(5),(5′)部を挟み持つて
仮止め具(a)をパイプ(A)に押込めば、仮止め具
(a)は、その弾性、特に膨出体(7)による弾性によ
つて開閉作動し、第2図に示すように、両側円弧部
(4),(4′)がパイプ(A)に圧接してパイプ
(A)に固定する。
Therefore, when the round pipe (A) is used for the crosspiece of the heat insulating material (B) also serving as the barrier plate, the bulging bodies (5), (5 ') of the temporary fastener (a) are provided at appropriate places on the pipe (A). If the temporary stopper (a) is pushed into the pipe (A) by holding the portion), the temporary stopper (a) is opened and closed by its elasticity, particularly the elasticity of the bulging body (7). As shown in FIG. 2, the arcuate portions (4) and (4 ') on both sides are pressed against the pipe (A) and fixed to the pipe (A).

次いで、第4図に示すように、仮止め具(a)の直線状
突出片(3),(3′)を堰板兼用断熱材(B)に向け
て仮止め具(a)を堰板兼用断熱材(B)に押込むと、
仮止め具(a)の直線状突出片(3),(3′)がその
先端の尖鋭(9)によつて容易円滑に堰板兼用断熱材
(B)内に突刺さると共に、該直線状突出片(3),
(3′)の引掛り(8)が堰板兼用断熱材(B)内で引
掛つて仮止め具(a)は抜け難くなり、堰板兼用断熱材
(B)の外側にパイプ(4)が仮止め具(a)により仮
止めされてパイプ(A)による桟が形成される。
Then, as shown in FIG. 4, the temporary stoppers (a) are directed toward the linear projecting pieces (3) and (3 ′) of the temporary stoppers (a) and the temporary stoppers (a) are moved toward the barrier plates. When pushed into the combined heat insulating material (B),
The linear projecting pieces (3) and (3 ') of the temporary stopper (a) are easily and smoothly pierced by the sharp point (9) at the tip thereof into the insulating material (B) also used as a dam plate, and the linear shape Protruding piece (3),
The catch (8) of (3 ') is caught in the heat insulating material (B) also serving as a weir plate, and the temporary stopper (a) becomes difficult to come off, and the pipe (4) is provided outside the heat insulating material (B) also serving as a weir plate. It is temporarily fixed by the temporary stopper (a) to form a crosspiece by the pipe (A).

一方、コンクリートを打込んで壁(D)および梁(E)
を構築した後、型枠の固定部材を解体するに当つてパイ
プ(A)を堰板兼用断熱材(B)から取外す場合には、
仮止め(a)の膨出体(5),(5′)部を挟み持つて
引くか、あるいは膨出体(7)内にてこを差し込んでこ
じる等すると、仮止め(a)が堰板兼用断熱材(B)か
ら抜け出てパイプ(A)は外れる。
On the other hand, concrete is poured into the wall (D) and beam (E).
When the pipe (A) is to be removed from the heat insulating material (B) also used as the dam plate in dismantling the fixing member of the formwork after the construction of
When the swelling bodies (5) and (5 ') of the temporary fixing (a) are held and pulled, or when the swelling body (7) is inserted and pryed, the temporary fixing (a) causes the weir plate. The pipe (A) comes off from the combined heat insulating material (B).

その後、仮止め具(a)の膨出体(7)を把持して引く
と、仮止め具(a)はその弾性により上記と同様に開閉
作動してパイプ(A)から外れる。
After that, when the bulging body (7) of the temporary stopper (a) is grasped and pulled, the elasticity of the temporary stopper (a) causes the temporary stopper (a) to open and close in the same manner as described above and come off the pipe (A).

また、第5図に示すように堰板兼用断熱材(B)の桟に
角材(C)を用いる場合には、堰板兼用断熱材(B)の
外面に角材(C)を当て、所要箇所において、仮止め具
(a)のリング上部線材(2)を角材(C)に嵌合して
直線状突出片(3),(3′)を堰板兼用断熱材(B)
に押込めば、上記と同様に作用し、堰板兼用断熱材
(B)の外側に角材(C)が仮止め具(a)により仮止
めされて角材(C)による桟が形成される。
Further, as shown in FIG. 5, when the bar (C) is used for the crosspiece of the insulating plate (B) also used as the barrier plate, the rectangular member (C) is applied to the outer surface of the thermal insulator (B) which also functions as the barrier plate, and the required location In, the ring upper wire rod ( 2 ) of the temporary fastener (a) is fitted to the square rod (C), and the linear projecting pieces (3) and (3 ') are attached to the heat insulating material (B) which also serves as a dam plate.
If it is pushed in, it acts in the same manner as above, and the square bar (C) is temporarily fixed to the outside of the insulating material (B) also used as the barrier plate by the temporary stopper (a) to form a crosspiece made of the square bar (C).

一方、コンクリートを打込んで壁(D)および梁(E)
を構築した後、型枠の固定部材を解体するに当つて角材
(C)を堰板兼用断熱材(B)から取外す場合には、仮
止め部(a)を上記と同様に操作すると、仮止め具
(a)が堰板兼用断熱材(B)から抜け出て角材(C)
は外れる。
On the other hand, concrete is poured into the wall (D) and beam (E).
After disassembling the fixing member of the form after the construction, when the square bar (C) is removed from the heat insulating material (B) also used as the dam plate, the temporary fixing part (a) is operated in the same manner as above. The stopper (a) slips out of the insulating material (B) that also serves as the barrier plate, and the square bar (C)
Comes off.

(考案の効果) この考案のコンクリート型枠用桟仮止め具は、下記のよ
うな顕著な効果を有する。
(Effect of the Invention) The temporary crosspiece fixture for concrete formwork of the present invention has the following remarkable effects.

(1)一部に開放部を設けたリング状に形成するから、
パイプおよび角材の桟に兼用で用いることができて作業
上有益である。
(1) Since it is formed in a ring shape with an opening part provided in a part,
It can be used for both pipes and square beams, which is useful for work.

(2)弾力性を有する線材で構成すると共に、リング状
部線材の開放部における両端部に直線状突出片を設けて
その開放部に対向する円弧部に外側へのコ字形膨出体を
形成する。従って、 (イ)コ字形膨出体がスプリング作用をなし、仮止め具
が軽快に開閉作動してパイプの桟への仮止め具の着脱が
容易円滑である。
(2) It is composed of a wire material having elasticity, and linear projecting pieces are provided at both ends of the open part of the ring-shaped wire part, and a U-shaped bulge outward is formed in the arc part facing the open part. To do. Therefore, (a) the U-shaped bulging member acts as a spring, the temporary stopper is opened and closed easily, and the temporary stopper is easily attached to and detached from the rail of the pipe.

(ロ)コ字形膨出体が外側へ突出しているから、仮止め
具を取外すとき、その膨出体内にてこを差込んだり、紐
を通したり、あるいは指を入れこじつて仮止め具を取外
すことができ、該膨出体が操作部になつて取扱上便利で
ある。
(B) Since the U-shaped bulge protrudes outward, when removing the temporary stopper, insert the saw in the bulge, pass a string, or pry your fingers to remove the temporary stopper. It is possible to handle the bulging body as an operating portion, which is convenient for handling.

(3)両側円弧部に外側への凸円弧状膨出体を形成する
から、仮止め具を取付けるとき、仮止め具の両側の凸円
弧状膨出体部を挟み持つて押込めば、その両側の膨出体
により仮止め具を押込み易くて仮止め具の取付けを容易
適確になし得る。
(3) Since the convex arcuate bulges outwardly are formed in the arcuate portions on both sides, when the temporary fastener is attached, if the convex arcuate bulges on both sides of the temporary fastener are sandwiched and pushed in, the The bulging members on both sides make it easy to push in the temporary fastener, and the temporary fastener can be easily and accurately attached.

(4)構造は極めて簡単で、弾力性を有する線材によつ
て容易安価に製作できる。
(4) The structure is extremely simple, and the wire rod having elasticity can be easily manufactured at low cost.

(5)両側の直線状突出片に引掛りを形成すると、堰板
兼用断熱材に桟を仮止め具によつて取付けたとき、その
仮止め具の両側の直線状突出片の引掛りが堰板兼用断熱
材内に入り込んで引掛り、仮止め具がより抜け難くなつ
て桟の取付けを適確になし得る。
(5) When the hooks are formed on the linear protruding pieces on both sides, when the crosspiece is attached to the insulating material that also serves as the dam plate by the temporary stopper, the hooks on the linear protruding pieces on both sides of the temporary stopper are dammed. It is possible to properly mount the crosspiece by making it more difficult for the temporary fixing tool to come off because it gets into and is caught in the heat insulating material that also serves as a plate.

【図面の簡単な説明】[Brief description of drawings]

第1図はこの考案の一実施例に係るコンクリート型枠用
桟仮止め具の側面図、第2図は平面図、第3図はその仮
止め具によつて丸パイプの桟を取付けた状態の型枠要部
の側断面図、第4図は同上要部の平断面図、第5図は同
上仮止め具によつて角材の桟を取付けた状態の型枠要部
の平断面図である。 (A)…丸パイプ、(C)…角材、(a)…コンクリー
ト型枠用桟仮止め具、(1)…開放部、(2)…リング
状部線材、(3),(3′)…直線状突出片、(4),
(4′)…両側円弧部、(5),(5′)…両側の凸円
弧状膨出体、(6)…円弧部、(7)…コ字形膨出体、
(8)…引掛り、(9)…尖鋭、
FIG. 1 is a side view of a temporary tacking tool for a concrete formwork according to an embodiment of the present invention, FIG. 2 is a plan view, and FIG. 3 is a state in which a round pipe is attached by the temporary fastening tool. Fig. 4 is a side sectional view of the main part of the formwork, Fig. 4 is a plan sectional view of the main part of the same as above, and Fig. 5 is a plan sectional view of the main part of the formwork with the crosspieces of the timber attached by the temporary fasteners. is there. (A) ... Round pipe, (C) ... Square bar, (a) ... Trail temporary stop for concrete formwork, (1) ... Open part, ( 2 ) ... Ring-shaped wire, (3), (3 ') ... Linear protruding pieces (4),
(4 ') ... Arc parts on both sides, (5), (5') ... Convex arcuate bulges on both sides, (6) ... Arc parts, (7) ... U-shaped bulge,
(8) ... Hook, (9) ... Sharp,

フロントページの続き (72)考案者 一島 正博 埼玉県与野市大戸6―10―17―103 (56)参考文献 実公 昭42−19870(JP,Y1) 実公 昭40−306(JP,Y1) 実公 昭48−7162(JP,Y2)Front page continuation (72) Inventor Masahiro Ichijima 6-10-17-103 Oto, Yono-shi, Saitama (56) Bibliography 42-19870 (JP, Y1) 40-306 (JP, Y1) ) Actual public Sho 48-7162 (JP, Y2)

Claims (2)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】弾力性を有する線材から成り、一部に開放
部を設けたリング状に形成し、該リング状部線材の上記
開放部に対する両側円弧部に外側への凸円弧状膨出体を
形成して上記開放部に対向する円弧部に外側へのコ字形
膨出体を形成し、上記リング状部線材の開放部における
両端部に直線状突出片を設けてなるコンクリート型枠用
桟仮止め具。
1. A ring-shaped bulging member which is made of a wire material having elasticity and is formed in a ring shape with an opening portion provided in a part thereof, and the ring-shaped wire member has arcuate protrusions outward on both side arc portions with respect to the opening portion. To form a U-shaped bulge toward the outside in the arc portion facing the open portion, and linear projecting pieces are provided at both ends of the open portion of the ring-shaped wire rod. Temporary fastener.
【請求項2】リング状部線材の開放部の両端部に設ける
直線状突出片に引掛りを形成してなる実用新案登録請求
の範囲第1項記載のコンクリート型枠用桟仮止め具。
2. A temporary fixture for a concrete formwork according to claim 1, wherein a hook is formed on linear projecting pieces provided at both ends of the open portion of the ring-shaped wire.
JP1988019075U 1988-02-16 1988-02-16 Temporary stopper for concrete formwork Expired - Lifetime JPH0633123Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1988019075U JPH0633123Y2 (en) 1988-02-16 1988-02-16 Temporary stopper for concrete formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1988019075U JPH0633123Y2 (en) 1988-02-16 1988-02-16 Temporary stopper for concrete formwork

Publications (2)

Publication Number Publication Date
JPH01122140U JPH01122140U (en) 1989-08-18
JPH0633123Y2 true JPH0633123Y2 (en) 1994-08-31

Family

ID=31234265

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1988019075U Expired - Lifetime JPH0633123Y2 (en) 1988-02-16 1988-02-16 Temporary stopper for concrete formwork

Country Status (1)

Country Link
JP (1) JPH0633123Y2 (en)

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4219870Y1 (en) * 1964-06-15 1967-11-17
JPS487162U (en) * 1971-06-10 1973-01-26

Also Published As

Publication number Publication date
JPH01122140U (en) 1989-08-18

Similar Documents

Publication Publication Date Title
US4340200A (en) Spring clip and molding form utilizing same
JPH0586687A (en) Intersecting point binding bearing device of pc slab sheath
KR200303756Y1 (en) A square wooden fixture for a cast
JP2534769Y2 (en) Concrete frame fixture
JP4136362B2 (en) Faint
JP3348987B2 (en) Concrete formwork panel clip
JP2549940Y2 (en) Wall insulation support bracket
JPH07241782A (en) Floor plate drawing tool
JPS5814757Y2 (en) Safety net stopper
JPH075159Y2 (en) Formwork clamp
JP3002317U (en) Floorboard tool
US1846872A (en) Fastener
JP2569420Y2 (en) Reinforcing bar support
JP3849104B2 (en) Face wood with ears
JPH0526199Y2 (en)
JPS636368Y2 (en)
KR200271550Y1 (en) The tool of removing the form of a steel sheet used in a concrete building
JPH0130647Y2 (en)
JP3028030U (en) Temporary peg
JPH0212063Y2 (en)
JP2003013597A (en) A method of attaching the lumber with ears and the joint rod with ears to the formwork by using a tucker.
JPH074038A (en) Temporary pipe-mounting jig for form holding
JP3065741U (en) Nail with stopper
JPH0319535Y2 (en)
JP3873893B2 (en) Heel support