JPH064254U - Steel frame scaffolding - Google Patents

Steel frame scaffolding

Info

Publication number
JPH064254U
JPH064254U JP4207592U JP4207592U JPH064254U JP H064254 U JPH064254 U JP H064254U JP 4207592 U JP4207592 U JP 4207592U JP 4207592 U JP4207592 U JP 4207592U JP H064254 U JPH064254 U JP H064254U
Authority
JP
Japan
Prior art keywords
steel
scaffolding
scaffold
attached
support rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP4207592U
Other languages
Japanese (ja)
Other versions
JP2574017Y2 (en
Inventor
雅英 山本
正博 山野
茂 松本
正哉 桝谷
浩一 花本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP1992042075U priority Critical patent/JP2574017Y2/en
Publication of JPH064254U publication Critical patent/JPH064254U/en
Application granted granted Critical
Publication of JP2574017Y2 publication Critical patent/JP2574017Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

(57)【要約】 【目的】 軽量化させるとともに、安価な鉄骨建方用足
場を提供する。 【構成】 鉄骨建方用足場1は、前記鋼管柱2の角部に
溶接される軸受け部5と、この軸受け部5に取り付けら
れる足場本体6とからなる。軸受け部5は、鉛直方向に
貫通する貫通孔17を有する。足場本体6は、鋼棒をク
ランク状に折曲形成された支持棒8と、該支持棒8に取
り付けられる鋼製網体9と、支持棒8に取り付けられた
鋼製手摺り体10とからなる。 【効果】 囲み板、取付金物を不要にできるから、足場
本体を軽量化でき、安価な鋼を使用するから、足場本体
に要する費用を低減できる。
(57) [Summary] [Purpose] To provide a lightweight scaffold for erection of steel frames while also making it lighter. [Structure] The steel-frame-construction scaffolding 1 includes a bearing portion 5 welded to a corner portion of the steel pipe column 2 and a scaffolding main body 6 attached to the bearing portion 5. The bearing portion 5 has a through hole 17 penetrating in the vertical direction. The scaffold body 6 includes a support rod 8 formed by bending a steel rod into a crank shape, a steel net body 9 attached to the support rod 8, and a steel handrail body 10 attached to the support rod 8. Become. [Effect] Since the enclosing plate and the mounting hardware can be eliminated, the scaffold body can be made lightweight, and the cost required for the scaffold body can be reduced because inexpensive steel is used.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案は、鉄骨建方用足場にかかり、特に、鉄骨構造における柱・梁の組み立 てなどのような、現場における鉄骨部材組み立て作業に用いて好適な鉄骨建方用 足場に関するものである。 The present invention relates to a scaffold for steel erection, and more particularly to a scaffold for steel erection suitable for use in on-site assembly work of steel members such as assembling columns and beams in a steel structure.

【0002】[0002]

【従来の技術】[Prior art]

従来、一般の鉄骨建方用足場は、作業員を載せる水平状態に取り付けられるア ルミニウム作業プレートと、この作業プレートに柵状に取り付けられたアルミニ ウム製手摺り体と、この手摺り体を囲むアルミニウム製囲み板と、建築物の鋼管 柱に取り付けられる取付金物とから構成されている。前記作業プレートには、手 摺り体、囲み板、取付金物が固定されている。取付金物は、前記鋼管柱の先付金 物にボルト等の締結部材で接続される突出部と、前記鋼管柱から作業プレートを 支持する補強部材とから構成されている。 Conventionally, a general steel frame erection scaffold has an aluminum work plate that is mounted in a horizontal position on which a worker is placed, an aluminum handrail that is attached to the work plate in a fence shape, and surrounds the handrail. It consists of an aluminum enclosing board and a metal fitting that is attached to the steel pipe pillar of the building. A handrail, a surrounding plate, and a mounting hardware are fixed to the work plate. The mounting hardware is composed of a projecting portion connected to the tip metal of the steel pipe column by a fastening member such as a bolt, and a reinforcing member for supporting the work plate from the steel pipe column.

【0003】 このような鉄骨建方用足場では、あらかじめ工場等で鋼管柱に先物金物を溶接 ・固定しておく。前記鋼管柱を立設し、この鋼管柱の先物金物に作業プレートを 取付金物で固定する。このときに、補強部材を鋼管柱に取り付けるとともに、こ の鋼管柱の先付金物に前記突出部を締結部材で取り付ける。その後、作業プレー トに鋼製手摺り体、囲み板を溶接・固定する。In such a steel structure erection scaffold, a futures metal object is welded and fixed to a steel pipe column in a factory or the like in advance. The steel pipe pillar is erected, and the working plate is fixed to the future metal fitting of the steel pipe pillar with a mounting hardware. At this time, the reinforcing member is attached to the steel pipe column, and the protruding portion is attached to the pre-attached metal object of the steel pipe column with the fastening member. After that, the steel handrail and the enclosing plate are welded and fixed to the work plate.

【0004】[0004]

【考案が解決しようとする課題】[Problems to be solved by the device]

しかしながら、前記鉄骨建方用足場にあっては、作業プレート、手摺り体、囲 み板にアルミニウム材料を使用しているため、損傷しやすく、高価である。 そして、鉄骨建方用足場は、作業プレートと、手摺り体と、囲み板と、取付金 物とから構成され、この取付金物は、突出部と、補強部材とから構成されている から、鉄骨建方用足場に多数の部材が組み込まれ、鉄骨建方用足場の重量が大き くなる。 さらに、作業プレートと、手摺り体とが別々に搬入され、現場で鉄骨建方用足 場を組み立てるため、鉄骨建方用足場の施工作業が煩雑である。 However, since the work plate, the handrail body, and the surrounding plate are made of an aluminum material, the steel frame scaffolding is easily damaged and expensive. The steel frame scaffolding is composed of a work plate, a handrail, an enclosing plate, and a mounting hardware, and the mounting hardware is composed of a protrusion and a reinforcing member. A large number of members are incorporated into the erection scaffold, which increases the weight of the steel erection scaffold. Further, since the work plate and the handrail are loaded separately and the scaffold for steel-frame erection is assembled on site, the work for constructing the scaffold for steel-frame erection is complicated.

【0005】 本考案は前記課題を有効に解決するもので、安価で軽量な鉄骨建方用足場を提 供することを目的とする。The present invention effectively solves the above problems, and an object thereof is to provide an inexpensive and lightweight scaffold for steel erection.

【0006】[0006]

【課題を解決するための手段】[Means for Solving the Problems]

本考案の鉄骨建方用足場は、角型鋼管柱の各側部から水平方向に延びる梁を固 定するときに用いられ、隣接する梁間に設置される鉄骨建方用足場であって、前 記鋼管柱の角部に溶接される軸受け部と、該軸受け部に取り付けられる足場本体 とからなり、前記軸受け部は、鉛直方向に貫通する貫通孔を有する構成にされ、 前記足場本体は、鋼棒をクランク状に折曲形成され、鉛直方向に位置させる軸部 、該軸部上端から水平方向に延びる網体取付部、該網体取付部先端から上方に延 びる手摺り体取付部からなる支持棒と、前記網体取付部に水平状態に取り付けら れる鋼製網体と、前記手摺り体取付部に取り付けられ、前記各梁に側部をそれぞ れ隣接させる鋼製手摺り体とからなり、前記足場本体は、前記支持棒の軸部を前 記軸受け部の貫通孔に取り外し可能に嵌合させてなることを特徴とするものであ る。 The steel erection scaffold of the present invention is used for fixing beams extending horizontally from each side of a rectangular steel pipe column, and is a steel erection scaffold installed between adjacent beams. The steel pipe column comprises a bearing portion welded to a corner portion of the steel pipe column, and a scaffolding body attached to the bearing portion. The bearing portion is configured to have a through hole penetrating in the vertical direction. The shaft is formed by bending the rod into a crank shape and is positioned in the vertical direction. It includes a mesh body mounting portion that extends horizontally from the upper end of the shaft portion, and a handrail body mounting portion that extends upward from the tip of the mesh body mounting portion. A supporting rod, a steel net body horizontally attached to the net attachment portion, and a steel handrail body attached to the handrail attachment portion and having side portions adjacent to the beams, respectively. The scaffold body has a shaft portion of the support rod that extends through the bearing portion. Ru der which is characterized by comprising capable fitted removably into the hole.

【0007】[0007]

【作用】[Action]

本考案の鉄骨建方用足場では、角型鋼管柱の各側部から水平方向に延びる梁を 固定するときに用いられ、隣接する梁間に鉄骨建方用足場が設置され、前記鋼管 柱の角部に軸受け部が溶接され、この軸受け部に足場本体が取り付けられるため 、この足場本体が鋼管柱と隣接する梁との間に設置される。 前記軸受け部では、鉛直方向に貫通孔が貫通するため、この貫通孔が前記鋼管 柱に平行に配される。 前記足場本体では、鋼製網体と鋼製手摺り体とが鋼棒をクランク状に折曲形成 された支持棒に取り付けられる。この支持棒では、前記軸受け部の貫通孔に軸部 が鉛直方向に取り外し可能に嵌合され、前記鋼製網体が水平方向に延びる網体取 付部に取り付けられ、手摺り体が上方に延びる手摺り取付部に取り付けられてい る。 The steel erection scaffold of the present invention is used to fix a beam extending horizontally from each side of a square steel pipe column, and the steel erection scaffold is installed between adjacent beams, and the corners of the steel pipe column are installed. Since the bearing portion is welded to the portion and the scaffold body is attached to the bearing portion, the scaffold body is installed between the steel pipe column and the adjacent beam. Since the through hole penetrates through the bearing portion in the vertical direction, the through hole is arranged in parallel with the steel pipe column. In the scaffold body, a steel net body and a steel handrail body are attached to a support rod formed by bending a steel rod into a crank shape. In this support rod, the shaft portion is detachably fitted in the through hole of the bearing portion in the vertical direction, the steel net body is attached to the horizontally extending net body attaching portion, and the handrail body is set upward. It is attached to the extended handrail attachment part.

【0008】[0008]

【実施例】【Example】

以下、本考案の鉄骨建方用足場の一実施例について、図1ないし図4を参照し ながら説明する。図1に示すように、符号1は鉄骨建方用足場であり、この鉄骨 建方用足場1は、断面視正方形状鋼管柱2の各側部3から水平方向に延びる梁4 を固定するときに用いられ、隣接する梁4間に設置されており、前記鋼管柱2の 角部に溶接される軸受け部5と、この軸受け部5に取り付けられる足場本体6と から構成されている。 Hereinafter, an embodiment of the scaffold for steel erection of the present invention will be described with reference to FIGS. 1 to 4. As shown in FIG. 1, reference numeral 1 is a steel-framed scaffolding, and this steel-framed scaffolding 1 is used to fix a beam 4 extending horizontally from each side part 3 of a square steel pipe column 2 in cross section. The bearing portion 5 is installed between the adjacent beams 4 and is welded to the corner portion of the steel pipe column 2, and the scaffold body 6 is attached to the bearing portion 5.

【0009】 前記軸受け部5は、鋼製筒状体からなり、鉛直方向に貫通する貫通孔17と、 前記鋼管柱2の角部に固定される溶接部7とを有する構成にされている。 前記足場本体6は、鋼棒をクランク状に折曲形成された支持棒8と、この支持 棒8に水平状態に取り付けられた鋼製網体9と、前記支持棒8に取り付けられた 鋼製手摺り体10とから構成されている。The bearing portion 5 is made of a steel tubular body and has a through hole 17 penetrating in the vertical direction and a welded portion 7 fixed to a corner portion of the steel pipe column 2. The scaffold body 6 includes a support rod 8 formed by bending a steel rod into a crank shape, a steel net body 9 horizontally attached to the support rod 8, and a steel rod attached to the support rod 8. It is composed of a handrail body 10.

【0010】 前記支持棒8は、図2に示すように、鉛直方向に位置させる軸部11と、この 軸部11上端から水平方向に延びる網体取付部12と、この網体取付部12先端 から上方に延びる手摺り体取付部13とから構成されている。前記軸部11は、 前記軸受け部5の貫通孔17に貫通され、この貫通孔17に取り外し可能に嵌合 されている。この貫通孔17から下方へ突出する軸部11には、前記貫通孔17 から軸部11の抜けを防止する割ピン25が挿入されている。As shown in FIG. 2, the support rod 8 has a shaft portion 11 positioned vertically, a net body mounting portion 12 extending horizontally from the upper end of the shaft portion 11, and a tip of the net body mounting portion 12. And a handrail body mounting portion 13 extending upward from. The shaft portion 11 penetrates the through hole 17 of the bearing portion 5 and is detachably fitted into the through hole 17. A split pin 25 for preventing the shaft portion 11 from coming off from the through hole 17 is inserted in the shaft portion 11 projecting downward from the through hole 17.

【0011】 前記手摺り体10は、前記鋼製網体9から鉛直方向に延びる複数本(図では四 本)の鉛直棒15と、これら鉛直棒15に直交する複数本(図では二本)の水平 棒16とから構成されている。この水平棒16は、網体16の縁部に沿う位置に 折曲形成され、両端部を前記各梁4に隣接させている。The handrail body 10 includes a plurality of (four in the figure) vertical bars 15 extending in the vertical direction from the steel net body 9 and a plurality of (two in the figure) orthogonal to the vertical bars 15. And a horizontal bar 16 of. The horizontal bar 16 is bent at a position along the edge of the net body 16, and both ends thereof are adjacent to the beams 4.

【0012】 前記支持棒8では、図3に示すように、軸部11と網体取付部12とが軸部用 補強板18で固定され、網体取付部12と網体9とが網体用補強板19で固定さ れている。前記軸部用補強板18は、図4に示すように、前記軸受け部5貫通孔 17に形成されたスリット20に取り外し可能に嵌合されている。一方、前記網 体用補強板19は、網体取付部12の延在方向に直交する方向に延在され、この 網体取付部12と網体9下部とに固定されている。In the support rod 8, as shown in FIG. 3, the shaft portion 11 and the mesh body mounting portion 12 are fixed by the shaft portion reinforcing plate 18, and the mesh body mounting portion 12 and the mesh body 9 are connected to each other. It is fixed by a reinforcing plate 19 for. As shown in FIG. 4, the shaft reinforcing plate 18 is detachably fitted into a slit 20 formed in the bearing hole 5 through hole 17. On the other hand, the mesh reinforcing plate 19 extends in a direction orthogonal to the extending direction of the mesh mounting portion 12, and is fixed to the mesh mounting portion 12 and the lower portion of the mesh 9.

【0013】 このような鉄骨建方用足場1では、あらかじめ工場等で鋼管柱2の角部に軸受 け部5を溶接するとともに、足場本体6を組み立てる。この足場本体6を組み立 てる場合、支持棒8を折曲形成し、この支持棒8に前記網体9、手摺り体10、 軸部用補強板18、網体用補強板19を固定する。In such a steel-frame-construction scaffolding 1, a bearing portion 5 is welded to a corner portion of a steel pipe column 2 in advance at a factory or the like, and a scaffold body 6 is assembled. When the scaffolding body 6 is assembled, the support rod 8 is bent and the net body 9, the handrail body 10, the shaft reinforcing plate 18, and the net reinforcing plate 19 are fixed to the support rod 8.

【0014】 その後、前記鋼管柱2を立設施工し、足場本体6をクレーン等の揚重設備で吊 り上げ、支持棒6の軸部11を軸受け部5の貫通孔17に挿入する。このときに 、貫通孔17のスリット20に軸部用補強板18が嵌合され、この軸部用補強板 18がスリット20で挟持されるから、足場本体6の回動が防止され、鉄骨建方 用足場1が施工される。この鉄骨建方用足場1に作業員を載せ、この作業員が隣 接する梁4を鋼管柱2に溶接等で固定する。After that, the steel pipe column 2 is erected, the scaffold body 6 is lifted by a lifting equipment such as a crane, and the shaft portion 11 of the support rod 6 is inserted into the through hole 17 of the bearing portion 5. At this time, the reinforcing plate 18 for the shaft portion is fitted into the slit 20 of the through hole 17, and the reinforcing plate 18 for the shaft portion is sandwiched by the slit 20. Therefore, the rotation of the scaffold body 6 is prevented, and the steel frame construction is prevented. The scaffold 1 for people is constructed. A worker is placed on the scaffold 1 for constructing a steel frame, and the beam 4 adjacent to the worker is fixed to the steel pipe column 2 by welding or the like.

【0015】 このような鉄骨建方用足場1によれば、角型鋼管柱2の各側部3から水平方向 に延びる梁4を固定するときに用いられ、隣接する梁4間に設置される構成にし たから、梁4の固定作業性を向上できるとともに、鉄骨建方用足場1の回動が隣 接する梁4で防止されるから、鉄骨建方用足場1の安全性を向上できる。According to such a steel-frame-construction scaffolding 1, it is used when fixing the beams 4 extending in the horizontal direction from the respective side portions 3 of the rectangular steel pipe columns 2, and is installed between the adjacent beams 4. Because of the configuration, the workability of fixing the beam 4 can be improved, and the rotation of the steel-framed scaffolding 1 is prevented by the adjacent beam 4, so that the safety of the steel-framed scaffolding 1 can be improved.

【0016】 前記鉄骨建方用足場1は、前記鋼管柱2の角部に溶接される軸受け部5と、こ の軸受け部5に取り付けられる足場本体6とから構成されているため、工場等で 軸受け部5を鋼管柱2に設けることができとともに、足場本体6を組み立てるこ とができるから、現場で足場本体6の組み立て作業を不要にでき、鉄骨建方用足 場1の施工作業性を向上できる。The steel frame erection scaffolding 1 is composed of a bearing portion 5 welded to a corner portion of the steel pipe column 2 and a scaffolding main body 6 attached to the bearing portion 5, so that it is used in a factory or the like. Since the bearing portion 5 can be provided on the steel pipe column 2 and the scaffolding body 6 can be assembled, the assembling work of the scaffolding body 6 can be eliminated on site, and the workability of the steel-frame erection scaffolding 1 can be improved. Can be improved.

【0017】 前記軸受け部5は、鉛直方向に貫通する貫通孔17を有する構成にされ、前記 足場本体6は、鋼棒をクランク状に折曲形成された支持棒8と、この支持棒8に 取り付けられる鋼製網体9と、前記支持棒8に取り付けられ、前記梁4に側部を 隣接させた鋼製手摺り体10とから構成されているため、囲み板、取付金物を不 要にでき、足場本体6の重量を少なくできる。このため、足場本体6の移動作業 性を向上でき、鉄骨建方用足場1の施工作業性を向上できるとともに、安価な鋼 を使用するから、足場本体6に要する費用を低減できる。そして、剛性の高い鋼 を用いたため、足場本体6の損傷を防止でき、鉄骨建方用足場1の健全性を維持 できる。The bearing portion 5 is configured to have a through hole 17 penetrating in the vertical direction, and the scaffold main body 6 includes a support rod 8 formed by bending a steel rod into a crank shape, and the support rod 8. Since it is composed of the steel net body 9 to be attached and the steel handrail body 10 attached to the support rod 8 and having the side portions adjacent to the beam 4, the surrounding plate and the mounting hardware are unnecessary. Therefore, the weight of the scaffolding body 6 can be reduced. Therefore, the workability of moving the scaffolding body 6 can be improved, the workability of the steel frame scaffolding 1 can be improved, and the cost required for the scaffolding body 6 can be reduced because inexpensive steel is used. Further, since the steel having high rigidity is used, damage to the scaffold main body 6 can be prevented, and the soundness of the steel structure erection scaffold 1 can be maintained.

【0018】 前記支持棒8は、鉛直方向に位置させる軸部11と、この軸部11上端から水 平方向に延びる網体取付部12と、この網体取付部12先端から上方に延びる手 摺り体取付部13とから構成されているため、網体9と手摺り体10とを一体に 取り付けることができ、足場本体6を軽量化できる。このため、網体9と手摺り 体10とを一括して現場に搬入でき、軽量化した足場本体6を搬入できる。この 足場本体6は、前記支持棒8の軸部11を前記軸受け部5の貫通孔17に取り外 し可能に嵌合させる構成にしたから、足場本体6を鋼管柱2に容易に取り付ける ことができ、鉄骨建方用足場1の施工作業性を向上できる。The support rod 8 has a shaft portion 11 positioned in the vertical direction, a net body mounting portion 12 extending in the horizontal direction from the upper end of the shaft portion 11, and a handrail extending upward from the tip of the net body mounting portion 12. Since it is composed of the body attachment portion 13, the net body 9 and the handrail body 10 can be integrally attached, and the scaffold body 6 can be made lightweight. Therefore, the net body 9 and the handrail body 10 can be collectively carried into the site, and the lightweight scaffold body 6 can be carried in. The scaffold body 6 has a structure in which the shaft portion 11 of the support rod 8 is detachably fitted into the through hole 17 of the bearing portion 5, so that the scaffold body 6 can be easily attached to the steel pipe column 2. Therefore, the construction workability of the steel frame erection scaffold 1 can be improved.

【0019】 さらに、支持棒8の軸部11と網体取付部部12とに軸部用補強板18を固定 し、軸受け部5にスリット20を設け、このスリット20に前記軸部用補強板1 8を嵌合させたから、足場本体6が回動するのを防止でき、鉄骨建方用足場1の 安全性を向上できる。Further, a shaft reinforcing plate 18 is fixed to the shaft portion 11 and the net body mounting portion 12 of the support rod 8, and a slit 20 is provided in the bearing portion 5, and the slit 20 is provided with the shaft reinforcing plate. Since the scaffolds 18 are fitted, the scaffold body 6 can be prevented from rotating, and the safety of the steel-frame-construction scaffold 1 can be improved.

【0020】[0020]

【考案の効果】[Effect of device]

以上説明したように、本考案の鉄骨建方用足場によれば、角型鋼管柱の角部に 溶接される軸受け部と、この軸受け部に取り付けられる足場本体とから構成され ているため、工場等で軸受け部を鋼管柱に設けることができるとともに、足場本 体を組み立てることができるから、現場で足場本体の組み立て作業を不要にでき 、鉄骨建方用足場の施工作業性を向上できる。 As described above, according to the steel structure erection scaffolding of the present invention, the scaffold for the steel structure is composed of the bearing portion welded to the corner portion of the square steel tubular column and the scaffold body attached to the bearing portion. Since the bearing part can be provided on the steel pipe pillar and the scaffolding body can be assembled, it is possible to eliminate the work of assembling the scaffolding body on site and improve the workability of constructing the scaffolding for steel frame construction.

【0021】 前記軸受け部は、鉛直方向に貫通する貫通孔を有する構成にされ、前記足場本 体は、鋼棒をクランク状に折曲形成された支持棒と、この支持棒に取り付けられ る鋼製網体と、前記支持棒に取り付けられた鋼製手摺り体とから構成されている ため、囲み板、取付金物を不要にでき、足場本体を軽量化できる。このため、足 場本体の移動作業性を向上でき、鉄骨建方用足場の施工作業性を向上できるとと もに、安価な鋼を使用するから、足場本体に要する費用を低減できる。そして、 剛性の高い鋼を用いたため、足場本体の損傷を防止でき、鉄骨建方用足場の健全 性を維持できる。The bearing portion is configured to have a through hole penetrating in a vertical direction, and the scaffold body includes a support rod formed by bending a steel rod into a crank shape, and a steel attached to the support rod. Since it is composed of a net-making body and a steel handrail attached to the support rod, the surrounding plate and the mounting hardware can be eliminated, and the scaffold body can be made lightweight. Therefore, the workability of moving the scaffolding body can be improved, the workability of constructing the steel frame scaffolding can be improved, and the cost required for the scaffolding body can be reduced because inexpensive steel is used. Also, since steel with high rigidity is used, damage to the scaffold body can be prevented, and the soundness of the steel structure scaffolding can be maintained.

【0022】 前記支持棒は、鉛直方向に位置させる軸部と、この軸部上端から水平方向に延 びる網体取付部と、この網体取付部先端から上方に延びる手摺り体取付部とから 構成されているため、網体と手摺り体とを一体に取り付けることができ、足場本 体を軽量化できる。このため、網体と手摺り体とを一括して現場に搬入でき、軽 量化した足場本体を搬入できる。この足場本体は、前記支持棒の軸部を前記軸受 け部5の貫通孔に取り外し可能に嵌合させる構成にしたから、足場本体を鋼管柱 に容易に取り付けることができ、鉄骨建方用足場の施工作業性を向上できる。The support rod includes a shaft portion that is positioned in the vertical direction, a mesh body attachment portion that extends horizontally from the upper end of the shaft portion, and a handrail attachment portion that extends upward from the tip of the mesh body attachment portion. Since it is configured, the net body and the handrail body can be integrally attached, and the scaffolding body can be reduced in weight. For this reason, the net body and the handrail body can be collectively carried to the site, and the lightweight scaffold body can be carried in. Since this scaffolding body has a structure in which the shaft portion of the support rod is detachably fitted into the through hole of the bearing portion 5, the scaffolding body can be easily attached to the steel pipe column, and the scaffolding for steel frame erection The workability of construction can be improved.

【0023】 さらに、鉄骨建方用足場は、角型鋼管柱の各側部から水平方向に延びる梁を固 定するときに用いられ、隣接する梁間に設置され、各梁に手摺り体の側部がそれ ぞれ隣接される構成にしたから、足場本体が回動するのを防止でき、鉄骨建方用 足場の安全性を維持できるという効果を奏することができる。Furthermore, the steel frame erection scaffold is used when fixing the beams that extend horizontally from each side of the rectangular steel tube column, is installed between the adjacent beams, and the side of the handrail is attached to each beam. Since the parts are adjacent to each other, the scaffold body can be prevented from rotating, and the safety of the steel frame erection scaffolding can be maintained.

【図面の簡単な説明】[Brief description of drawings]

【図1】本考案の鉄骨建方用足場を示す平面図である。FIG. 1 is a plan view showing a scaffold for steel erection according to the present invention.

【図2】図1の斜視図である。FIG. 2 is a perspective view of FIG.

【図3】図2に側面図である。FIG. 3 is a side view of FIG.

【図4】図2の正面図である。FIG. 4 is a front view of FIG.

【符号の説明】[Explanation of symbols]

1 鉄骨建方用足場 2 鋼管柱 3 側部 4 梁 5 軸受け部 6 足場本体 8 支持棒 9 網体 10 手摺り体 11 軸部 12 網体取付部 13 手摺り体取付部 17 貫通孔 1 Steel frame erection scaffolding 2 Steel pipe column 3 Side part 4 Beam 5 Bearing part 6 Scaffolding body 8 Support rod 9 Net body 10 Handrail body 11 Shaft part 12 Net body mounting portion 13 Handrail body mounting portion 17 Through hole

フロントページの続き (72)考案者 桝谷 正哉 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)考案者 花本 浩一 東京都港区芝浦一丁目2番3号 清水建設 株式会社内Front page continuation (72) Masaya Masutani, 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Koichi Hanamoto 1-3-2, Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. Within

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 角型鋼管柱の各側部から水平方向に延び
る梁を固定するときに用いられ、隣接する梁間に設置さ
れる鉄骨建方用足場であって、 前記鋼管柱の角部に溶接される軸受け部と、該軸受け部
に取り付けられる足場本体とからなり、 前記軸受け部は、鉛直方向に貫通する貫通孔を有する構
成にされ、 前記足場本体は、鋼棒をクランク状に折曲形成され、鉛
直方向に位置させる軸部、該軸部上端から水平方向に延
びる網体取付部、該網体取付部先端から上方に延びる手
摺り体取付部からなる支持棒と、前記網体取付部に水平
状態に取り付けられる鋼製網体と、前記手摺り体取付部
に取り付けられ、前記各梁に側部をそれぞれ隣接させる
鋼製手摺り体とからなり、 前記足場本体は、前記支持棒の軸部を前記軸受け部の貫
通孔に取り外し可能に嵌合させてなることを特徴とする
鉄骨建方用足場。
1. A steel-frame-construction scaffolding used to fix a beam extending horizontally from each side of a rectangular steel pipe column and installed between adjacent beams, wherein the steel pipe column has a corner portion. It comprises a bearing part to be welded and a scaffolding body attached to the bearing part. The bearing part is configured to have a through hole penetrating in the vertical direction. The scaffolding body is formed by bending a steel rod into a crank shape. A support rod formed of a shaft portion to be positioned in the vertical direction, a mesh body mounting portion extending horizontally from the upper end of the shaft portion, and a handrail body mounting portion extending upward from the tip of the mesh body mounting portion; And a steel handrail attached to the handrail body attachment portion and having side portions adjacent to the beams, respectively, the scaffold body is the support rod. The shaft part can be removed from the through hole of the bearing part. Steel construction lateral scaffolding, characterized by comprising fitted to.
JP1992042075U 1992-06-18 1992-06-18 Steel frame scaffolding Expired - Lifetime JP2574017Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1992042075U JP2574017Y2 (en) 1992-06-18 1992-06-18 Steel frame scaffolding

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1992042075U JP2574017Y2 (en) 1992-06-18 1992-06-18 Steel frame scaffolding

Publications (2)

Publication Number Publication Date
JPH064254U true JPH064254U (en) 1994-01-21
JP2574017Y2 JP2574017Y2 (en) 1998-06-11

Family

ID=12625946

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1992042075U Expired - Lifetime JP2574017Y2 (en) 1992-06-18 1992-06-18 Steel frame scaffolding

Country Status (1)

Country Link
JP (1) JP2574017Y2 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS53159627U (en) * 1977-05-20 1978-12-14
JPH0164537U (en) * 1987-10-20 1989-04-25

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS53159627U (en) * 1977-05-20 1978-12-14
JPH0164537U (en) * 1987-10-20 1989-04-25

Also Published As

Publication number Publication date
JP2574017Y2 (en) 1998-06-11

Similar Documents

Publication Publication Date Title
JPH04111829A (en) Construction method for large span roofs
JP3244161B2 (en) Steel column base using reinforced wire mesh
JP2022177571A (en) Construction method of structure
JPH064254U (en) Steel frame scaffolding
JP3029324B2 (en) Temporary enclosures and foundations for temporary enclosures
JPH08113982A (en) Device for joining column and beam of steel framed building
JP2017155489A (en) Construction method of outer wall panel ground frame and outer wall material
JP2575796Y2 (en) External curing frame
JP2792806B2 (en) Construction method and capital piece of steel frame house
JP7811513B2 (en) Reinforced Concrete Frame and Wall Construction Methods
JP2550507Y2 (en) Scaffolding bracket
JP3139854B2 (en) Collapse prevention frame
JP2776140B2 (en) Temporary beam assembly equipment for building construction
JP2842034B2 (en) Lifting device for building frame
JPH0740029Y2 (en) Work scaffold mounting jig to steel column
JP2795025B2 (en) Roof unit suspension structure
JP2867172B2 (en) Mounting structure of folded plate to beam steel frame
JP2572353Y2 (en) Temporary scaffolding for construction
JP2524213Y2 (en) Tower crane fixing device
JP2989337B2 (en) Pre-assembly method of beam in steel reinforced concrete structure
JPH04315639A (en) Eaves fitting structure for building unit
JPH0762726A (en) Balcony connection structure
JP3324807B2 (en) Column-beam pre-assembled reinforced body and pre-assembled reinforced construction method using it
JPH09217357A (en) Anchor frame
JP2808448B2 (en) Roof construction method

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19980127

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080327

Year of fee payment: 10