JPH0645977B2 - Lift up or down construction method - Google Patents
Lift up or down construction methodInfo
- Publication number
- JPH0645977B2 JPH0645977B2 JP1465588A JP1465588A JPH0645977B2 JP H0645977 B2 JPH0645977 B2 JP H0645977B2 JP 1465588 A JP1465588 A JP 1465588A JP 1465588 A JP1465588 A JP 1465588A JP H0645977 B2 JPH0645977 B2 JP H0645977B2
- Authority
- JP
- Japan
- Prior art keywords
- balance weight
- tower
- lift
- jack
- weight member
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000010276 construction Methods 0.000 title claims description 16
- 239000000463 material Substances 0.000 claims description 16
- 239000000725 suspension Substances 0.000 claims description 15
- 230000005484 gravity Effects 0.000 claims description 10
- 238000000034 method Methods 0.000 description 11
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 11
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 10
- 229910000831 Steel Inorganic materials 0.000 description 6
- 239000010959 steel Substances 0.000 description 6
- 230000001174 ascending effect Effects 0.000 description 3
- 238000002347 injection Methods 0.000 description 3
- 239000007924 injection Substances 0.000 description 3
- 239000004576 sand Substances 0.000 description 3
- 238000007796 conventional method Methods 0.000 description 2
- 239000008187 granular material Substances 0.000 description 2
- 239000007788 liquid Substances 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 238000000605 extraction Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Working Measures On Existing Buildindgs (AREA)
Description
【発明の詳細な説明】 〈産業上の利用分野〉 本発明は、バランスウエイト用部材を使用して対象物の
上昇・下降を行うリフトアップまたはダウン工法に関
し、特に頂部鉄塔等のように幅方向に比し縦方向の長さ
が極めて大きい対象物を高層構築物上へ持上げたり、あ
るいは解体時等に降ろしたりするのに適したリフトアッ
プまたはダウン工法に関する。TECHNICAL FIELD The present invention relates to a lift-up or down method of raising and lowering an object by using a balance weight member, and particularly in a width direction such as a top tower. The present invention relates to a lift-up or down method suitable for lifting an object having an extremely large length in the vertical direction onto a high-rise building or lowering it at the time of dismantling.
〈従来の技術〉 従来、電波塔,展望塔等の頂部鉄塔工事においては、鉄
塔を構成する部材をクレーン,ウインチ等にて一つずつ
頂部に持上げ、頂部にて各部材を組立て固定するか、あ
るいは地上で予め組立てた頂部鉄塔をタワークレーンて
頂部に持上げ、頂部では固定作業のみを行う工法が採ら
れていた。<Prior art> Conventionally, in the construction of a tower on the top of a radio tower, an observation tower, etc., the members that make up the tower are lifted one by one with a crane, winch, etc., and each member is assembled and fixed at the top. Alternatively, a construction method has been adopted in which a top steel tower preassembled on the ground is lifted to the top by a tower crane, and only the fixing work is performed at the top.
しかし、電波塔や展望塔が高層となると、前者の工法で
は頂部での組立て・固定作業が危険をともない、後者の
工法ではタワークレーンの使用が極めて困難ないしは不
可能となる。However, when the radio tower and the observation tower are high-rise, the former construction method poses a risk of assembling and fixing work at the top, and the latter construction method makes it extremely difficult or impossible to use the tower crane.
そこで実公昭59−11557号公報等で提案されてい
る言わゆるリフトアップ工法を応用した工法が考案され
た。Therefore, a method applying the so-called lift-up method proposed in Japanese Utility Model Publication No. 59-11557 was devised.
すなわち、例えば第2図(A)に示すように構築物1の
頂部に複数個のジャッキ2をセットし、そのジャッキ2
上にジャッキ2を介して上下移動可能に架台3を配置す
る。一方、構築物1の頂部に取付け固定される頂部鉄塔
4の上端縁に吊治具5を仮設する。そして、まず、吊治
具5と架台3とに吊材6を垂直方向に挿通し、定着ナッ
ト等の係止部材にて吊治具5の下面と吊材6とを、ま
た、架台3の上面と吊材6とをそれぞれ固定する。That is, for example, as shown in FIG. 2 (A), a plurality of jacks 2 are set on the top of the construct 1 and the jacks 2
A pedestal 3 is arranged on the top so as to be vertically movable via a jack 2. On the other hand, a suspending jig 5 is temporarily installed on the upper edge of the top tower 4 which is attached and fixed to the top of the building 1. Then, first, the suspending material 6 is vertically inserted into the suspending jig 5 and the pedestal 3, and the lower surface of the suspending jig 5 and the suspending material 6 are fixed to each other by a locking member such as a fixing nut. The upper surface and the suspension member 6 are fixed to each other.
このような状態で、架台3と吊材6とを一体的にジャッ
キアップし、定着ナット等の係止部材にて構築物1の頂
部と吊材6とを固定して吊材6の下降を阻止すると同時
に、架台3の上面と吊材6との固定を外してジャッキ2
を下降させる。In such a state, the pedestal 3 and the suspending member 6 are integrally jacked up, and the top of the building 1 and the suspending member 6 are fixed by a locking member such as a fixing nut to prevent the suspending member 6 from descending. At the same time, the upper surface of the pedestal 3 and the suspension member 6 are removed from the jack 2
To lower.
以後、ジャッキ2の上下移動に対応して架台3上面の係
止部材と構築物1頂部の係止部材を締付けたりゆるめた
りして、吊材6を徐々に上昇移動させ、この上昇移動に
より頂部鉄塔4をその上端が構築物1の頂部に至るまで
上昇させる。After that, the locking member on the upper surface of the pedestal 3 and the locking member on the top of the structure 1 are tightened or loosened in response to the vertical movement of the jack 2, and the suspending member 6 is gradually moved up. 4 is raised until its top reaches the top of construct 1.
その後、構築物1の頂部と吊材6を停止部材で固定する
と共に、第2図(B)に示すように、頂部鉄塔4の下端
縁に設けられている構築物1への取合部4′と架台3と
に吊材6′を垂直方向に挿通し、係止部材にて取合部
4′の下面と吊材6′とを、また架台3の上面と吊材
6′とを夫々固定する。次いで、構築物1頂部と吊材6
の固定を外し、かつ吊材6と頂部鉄塔4上端縁の吊治具
5とを除去する。After that, the top of the building 1 and the suspending member 6 are fixed by a stop member, and as shown in FIG. 2 (B), a connecting portion 4'to the building 1 provided on the lower end edge of the top tower 4 is provided. The suspending member 6'is vertically inserted into the frame 3, and the lower surface of the connecting portion 4'and the suspending member 6'are fixed by locking members, and the upper surface of the frame 3 and the suspending member 6'are fixed respectively. . Then, the top of the structure 1 and the hanger 6
Is removed, and the hanging material 6 and the hanging jig 5 at the upper edge of the top tower 4 are removed.
このような状態で、上記と同様にしてジャッキ2の上下
移動を繰返し、頂部鉄塔4の下端が構築物1の頂部に至
るまで上昇させ、頂部鉄塔4をその取合部4′にて構築
物1に固定する。In such a state, the jack 2 is repeatedly moved up and down in the same manner as above, and the lower end of the top tower 4 is raised to reach the top of the building 1, and the top tower 4 is attached to the building 1 at its connecting portion 4 '. Fix it.
〈発明が解決しようとする課題〉 ところで、前記の頂部鉄塔4は、横方向に比べ縦方向の
長さ(以下、縦横比)が一般に極めて大であり、重心は
縦方向の長さの1/2より下に存在することが多い。<Problems to be Solved by the Invention> By the way, the top tower 4 has a length in the vertical direction (hereinafter referred to as an aspect ratio) that is generally very large as compared with the horizontal direction, and the center of gravity is 1 / l of the length in the vertical direction. Often below 2.
斯る場合、頂部鉄塔4の上端が構築物1の頂部に至まで
の上昇操作では頂部鉄塔4の上端縁を吊点13として行
うため、重心は吊点13の下方に位置し、縦横比が極め
て大の頂部鉄塔4であっても、これを安定して上昇させ
ることができる。また、なんらかの原因でこの上昇操作
中に頂部鉄塔4が多少振れることがあっても、構築物1
で頂部鉄塔4が支えられ、振れが停止されるため、ジャ
ッキ2,架台3,吊治具5,吊材6の破損あるいはこれ
らの破損に伴う頂部鉄塔4の落下等の事故の生じる可能
性は少ない。In such a case, since the upper end of the top tower 4 is raised to the top of the structure 1 in the ascending operation, the upper edge of the top tower 4 is used as the hanging point 13, so the center of gravity is located below the hanging point 13 and the aspect ratio is extremely high. Even the large top tower 4 can be stably raised. In addition, even if the top tower 4 swings to some extent during this raising operation for some reason, the structure 1
Since the top tower 4 is supported by and the swinging is stopped, there is a possibility that an accident such as damage to the jack 2, the pedestal 3, the suspension jig 5, the suspension material 6 or a drop of the top tower 4 due to these damages will occur. Few.
しかし、吊点13を頂部鉄塔4の下端縁に移動させた後
の上昇操作は、重心が吊点13の上方に位置することに
なるため、縦横比の極めて大きな頂部鉄塔4の場合、極
めて不安定となる。However, since the center of gravity is located above the suspension point 13 in the ascending operation after the suspension point 13 is moved to the lower end edge of the top tower 4, it is extremely unsatisfactory in the case of the top tower 4 having an extremely large aspect ratio. Be stable.
まして、構築物1の上方には、この不安定な頂部鉄塔4
の支えになるものが何も存在せず、一旦頂部鉄塔4に僅
かでも振れが生じれば、この振れは抑制されることなく
増大し、ついにはジャッキ2,架台3,取合部4′,吊
材6′の破損,あるいは頂部鉄塔4の転倒や落下事故等
の危険を招く。Furthermore, above the building 1, above this unstable top tower 4
There is nothing to support, and once the top tower 4 shakes even a little, this shake increases without being suppressed, and finally the jack 2, the mount 3, the connecting portion 4 ', There is a risk that the suspension member 6'is damaged, or the top tower 4 falls or falls.
また、この振れを各ジャッキ2の上昇量や下降量の制御
により抑制する方法では、操作が煩雑となる。Further, in the method of suppressing this shake by controlling the amount of rise and the amount of fall of each jack 2, the operation becomes complicated.
更に、構築物1の上方の頂部鉄塔4の立設位置にガイド
柱を仮設し、このガイド柱により頂部鉄塔4を支え、振
れを抑制して、転倒や落下事故を防止する方法も考えら
れる。Further, a method of temporarily installing a guide pillar at the standing position of the top steel tower 4 above the structure 1 and supporting the top steel tower 4 by this guide pillar to suppress the shake and prevent a fall or a fall accident is also considered.
しかし、構築物1が高層のものの場合、このガイド柱の
上昇・仮設・撤去工事自体が困難であり、費用が増大
し、実用的な方法とはいえない。However, if the structure 1 is a high-rise building, it is difficult to raise / temporarily install / remove the guide pillars, and the cost increases, which is not a practical method.
本発明は、以上の諸点に鑑みてなされたもので、その目
的とするところは、構築物への上昇、また構築物からの
対象物の下降、特に、電波塔や展望塔等の高層の構築物
の頂部への、頂部鉄塔等のように縦横比が極めて大きい
対象物の上昇、また上記高層構築物の頂部に既設されて
いる上記対象物の地上への下降を、安全に、かつ煩雑な
操作を要することなく、低コストで行うことのできる実
用的な工法を提供するにある。The present invention has been made in view of the above points, and an object thereof is to ascend to a structure and to descend an object from the structure, particularly, a top part of a high-rise structure such as a radio tower or an observation tower. It is necessary to safely and cumbersomely raise an object with a very large aspect ratio, such as a top tower, or descend the above-mentioned object already installed at the top of the high-rise building to the ground. It is to provide a practical construction method that can be performed at low cost.
〈課題を解決するための手段〉 本発明は、上記目的をジャッキ及び同ジャッキと対象物
とをつなぐ吊材を使用するリフトアップまたはダウン工
法において、構築物の所要位置から頂部までの間の対象
物の上昇又は下降を、該対象物の下端部を前記吊材の吊
点とし、かつ該対象物の下方にバランスウエイト用部材
を取付けて該対象物の吊点より下方に重心が位置するよ
うにして行うことを特徴とするリフトアップまたはダウ
ン工法により達成するものである。<Means for Solving the Problems> The present invention is a lift-up or down construction method that uses a jack and a suspending member that connects the jack and an object for the above object, and an object from a required position to a top of the structure. The lower end of the object is used as the hanging point of the hanging material, and a balance weight member is attached below the object so that the center of gravity is located below the hanging point of the object. It is achieved by a lift-up or down method characterized by being performed by
またバランスウエイト用体と同バランスウエイト用体収
納容器とからなるバランスウエイト用部材を用い、該バ
ランスウエイト用部材を仮設柱により対象物の下方に取
付けるのが好ましい。Further, it is preferable that a balance weight member composed of the balance weight member and the balance weight member storage container is used, and the balance weight member is attached below the object by a temporary column.
さらにバランスウエイト用体と、該バランスウエイト用
体を収納するフレキシブル容器とからなるバランスウエ
イト用部材を使用し、対象物の上昇に際しては、該対象
物の下部に予め前記の収納容器を取付けて置き、該対象
物が構築物の所要位置まで上昇した時点で、該収納容器
にバランスウエイト用体を収納し、対象物の下降に際し
ては該対象物の下部に取付けられた前記収納容器にバラ
ンスウエイト用体を収納して下降を開始し、該対象物か
らバランスウエイト用体を抜出すようにしても良い。Further, a balance weight member composed of a balance weight body and a flexible container for accommodating the balance weight body is used, and when the target object is raised, the storage container is previously attached and placed under the target object. A balance weight body is housed in the storage container when the target object rises to a required position of the structure, and the balance weight body is mounted in the storage container attached to the lower part of the target object when the target object is lowered. Alternatively, the balance weight body may be pulled out from the target object by starting to descend after housing.
〈作用〉 本発明では、構築物、特に高層の構築物の頂部への対象
物の上昇、あるいは頂部からの対象物の下降を、ジャッ
キ及び同ジャッキと対象物とをつなぐ吊材を使用して言
わゆるリフトアップまたはダウン工法により行う。<Operation> In the present invention, the raising of an object to the top of a structure, particularly a high-rise structure, or the lowering of an object from the top is referred to by using a jack and a suspending member connecting the jack and the object. Lift up or down construction method.
このとき、構築物の所要位置から頂部までの間の対象物
の上昇,下降をバランスウエイト用部材の使用により行
うのである。At this time, the target weight is raised and lowered from the required position to the top of the structure by using the balance weight member.
すなわち、この間の対象物の上昇は、対象物の下端部に
吊材の吊点を置く。このままで上昇を行えば、対象物の
重心が吊点より上方にあるため、前述したように転倒等
の危険がある。そこで本発明では、対象物の下方に、例
えば仮設柱等によりバランスウエイト用部材を取付け、
重心を吊点より下方に移動させ、ジャッキと吊材とによ
る対象物のリフトアップの作業を安定して行う。That is, during the ascent of the object, the hanging point of the hanging material is placed at the lower end of the object. If the object is raised as it is, the center of gravity of the object is above the suspension point, and there is a risk of falling as described above. Therefore, in the present invention, a balance weight member is attached below the object by, for example, a temporary column,
The center of gravity is moved below the hanging point, and the work of lifting up the object with the jack and the hanging material is stably performed.
また、上記間の対象物の下降は、対象物の下端部に吊点
を置き、対象物の下方に上記のバランスウエイト用部材
を取付けて行う。このようにすれば、重心は吊点の下方
に位置する為、ジャッキと吊材とに与る対象物のリフト
ダウンは安定する。Further, the lowering of the object during the above period is performed by placing a suspension point on the lower end of the object and attaching the above-mentioned balance weight member below the object. By doing so, the center of gravity is located below the hanging point, so that the lift down of the object applied to the jack and the hanging material is stabilized.
ところで、上記の構築物の所要位置とは、対象物の上端
部を吊点としてリフトアップまたはダウンが行えない位
置や、対象物の下方にバランスウエイト用部材を取付け
得る程度の空間が確保できる位置等である。By the way, the required position of the above structure is a position where the object cannot be lifted up or down with the upper end of the object as a suspension point, or a position where a space for attaching a balance weight member can be secured below the object. Is.
前者の位置は、前述の従来技術で説明したように、対象
物が例えば縦横比の極めて大きい頂部鉄塔の場合、この
頂部鉄塔の上端部と構築物の頂部とがほぼ一致する位置
である。As described in the above-mentioned prior art, the former position is a position where the upper end of the top tower and the top of the structure are substantially coincident with each other when the object is, for example, a top tower having an extremely large aspect ratio.
すなわち、この頂部鉄塔を構築物の頂部に持上げるに際
しては、上記の位置までは従来どおり上端部を吊点とし
て上昇させ、この位置から上方へは、本発明に係る工法
により、吊点を下端部に移し、かつバランスウエイト用
部材を頂部鉄塔の下方に取付けて上昇させるのである。That is, when the top tower is lifted to the top of the structure, the upper end is lifted up to the above position as in the conventional manner, and the hanging point is moved upward from this position by the construction method according to the present invention. Then, the balance weight member is attached below the top tower and lifted.
既設の頂部鉄塔を構築物の頂部から地上へ下降させるに
際しては、下降開始時から頂部鉄塔の上端部から構築物
の頂部に至るまでの下降を本発明に係る工法で行うので
ある。When descending the existing top steel tower from the top of the structure to the ground, the descending from the start of descent to the top of the structure from the upper end of the top steel tower is performed by the construction method according to the present invention.
また、バランスウエイト用部材として、バランスウエイ
ト用体と、これを収納するフレキシブル容器、例えば袋
とからなるものを用いる場合は、対象物の上昇に際して
は、予め対象物の下部に袋を取付けて置き、対象物が上
記の所要位置まで上昇させた時点で袋内にバランスウエ
イト用体を収納する。対象物の下降に際しては、バラン
スウエイト用体を収納した袋を、下部に取付けて下降開
始し、上記の所要位置まで下降した点で袋からバランス
ウエイト用体を抜出せばよい。When a balance weight member and a flexible container that stores the balance weight member, such as a bag, is used as the balance weight member, the bag is attached to the lower part of the object in advance when the object is raised. The balance weight body is housed in the bag when the object is raised to the required position. When lowering the object, a bag accommodating the balance weight body may be attached to the lower portion to start the descent, and the balance weight body may be pulled out from the bag at the point where the bag is lowered to the required position.
〈実施例〉 第1図(A)〜(D)は、本発明に係る工法の第1実施
例を示し、高層構築物の頂部まで頂部鉄塔を持上げる場
合の態様をステップ毎に示している。<Example> FIGS. 1 (A) to 1 (D) show a first example of the construction method according to the present invention, and show, for each step, a mode in which the top tower is lifted to the top of the high-rise building.
まず、第1図(A)のステップにおいて、前述の従来技
術と同様に高層構築物(以下、構築物)1の頂部に複数
個セットされたジャッキ2の上に、ジャッキ2を介して
上下移動可能な架台3を配置し、この架台3と頂部鉄塔
4の上端縁に仮設された吊治具5とに吊材6を垂直方向
に挿通し、定着ナット等の係止部材で架台3と吊材6、
吊材6と吊治具5をそれぞれ固定する。この状態で、前
述の従来技術と同様のジャッキ2の上下移動,係止部材
の締弛を行い、頂部鉄塔4を構築物1の所要位置、本例
では第1図(B)に示すように、頂部鉄塔4の下方にバ
ランスウエイト用部材10を取付けることができる空間
が確保できる位置まで上昇させる。First, in the step of FIG. 1 (A), it is possible to move up and down through the jacks 2 on a plurality of jacks 2 set on the top of a high-rise building (hereinafter, building) 1 in the same manner as the above-mentioned conventional technique. The pedestal 3 is arranged, and the hung material 6 is vertically inserted through the pedestal 3 and the hanging jig 5 temporarily provided at the upper end edge of the top steel tower 4, and the pedestal 3 and the hanging material 6 are locked by a locking member such as a fixing nut. ,
The hanging material 6 and the hanging jig 5 are fixed, respectively. In this state, the jack 2 is vertically moved and the locking member is tightened and loosened in the same manner as in the above-described conventional technique, and the top tower 4 is moved to the required position of the structure 1, in this example, as shown in FIG. 1 (B), Below the top tower 4, the balance weight member 10 is moved up to a position where a space can be secured in which the member 10 can be attached.
そして、第1図(B)のステップにおいて、頂部鉄塔4
の底部に仮設梁11を頂部鉄塔4の下端部に設けられて
いる取合部4′に取付け、仮設梁材11の下方に仮設柱
12を介してバランスウエイト用部材10を取付ける。
次いで、仮設梁11と架台3とに吊材6′を垂直方向に
挿通し、仮設梁11の下面と吊材6′とを係止部材で固
定し、第1図(A)のステップで使用した吊治具5と吊
材6を外す。Then, in the step of FIG. 1 (B), the top tower 4
A temporary beam 11 is attached to the bottom of the temporary beam member 11 at an attachment portion 4'provided at the lower end of the top tower 4, and a balance weight member 10 is attached below the temporary beam member 11 via a temporary column 12.
Next, the suspending member 6'is vertically inserted through the temporary beam 11 and the pedestal 3, and the lower surface of the temporary beam 11 and the suspending member 6'are fixed by a locking member, which is used in the step of FIG. 1 (A). The hanging jig 5 and the hanging material 6 are removed.
ところで、バランスウエイト用部材10としては、水,
砂,その他の適宜のバランスウエイト用体を収納する容
器、例えば水タンクを取付け、ホース等により水を注水
し、全体の重心が吊点13より下に位置するように注水
量を調整する。By the way, as the balance weight member 10, water,
A container for accommodating sand or other suitable balance weight body, for example, a water tank is attached, water is injected by a hose, and the amount of water injection is adjusted so that the center of gravity of the whole is located below the hanging point 13.
なお、バランスウエイト用部材10としては、予め上記
のバランスウエイト用体を収納容器に収納したものを用
いることもできるし、あるいは適当な重量を有する岩,
廃材等を用いてもよい。It should be noted that the balance weight member 10 may be one in which the above balance weight body is stored in a storage container in advance, or a rock having an appropriate weight,
You may use scrap materials.
この状態で、第1図(A)のステップと同様、ジャッキ
2の上下移動,係止部材の締弛を行い、第1図(C)に
示すように、構築物の頂部まで頂部鉄塔4を上昇させ
る。In this state, as in the step of FIG. 1 (A), the jack 2 is moved up and down and the locking member is tightened, and the top tower 4 is raised to the top of the structure as shown in FIG. 1 (C). Let
第1図(C)のステップにおいては、頂部鉄塔4の取合
部4′と構築物1とを結合して、頂部鉄塔4の構築物1
への固定を行う。In the step of FIG. 1 (C), the connecting portion 4 ′ of the top tower 4 and the structure 1 are joined together to form the structure 1 of the top tower 4.
Fixed to.
しかる後、第1図(D)のステップにおいて、仮設梁1
1,仮設柱12及びバランスウエイト用部材10をジャ
ッキダウンし、地上にて解体する。Then, in the step of FIG. 1 (D), the temporary beam 1
1. The temporary pillar 12 and the balance weight member 10 are jacked down and disassembled on the ground.
なお、バランスウエイト用部材10として水タンクを用
いている場合は、第1図(C)のステップの頂部鉄塔4
と構築物1との固定が修了した時点で、水をタンクから
抜出しておき、第1図(D)のステップでは空のタンク
10をジャッキダウンするようにしてもよい。When a water tank is used as the balance weight member 10, the top tower 4 of the step in FIG. 1 (C) is used.
The water may be drained from the tank when the fixing of the structure 1 and the construction 1 is completed, and the empty tank 10 may be jacked down in the step of FIG. 1 (D).
また、構築物1に既設されている頂部鉄塔4を取替えや
撤去等のために地上へリフトダウンさせるには、上記の
逆ステップで行えばよい。Further, in order to lift down to the ground for replacing or removing the top tower 4 which is already installed in the structure 1, the above reverse steps may be performed.
すなわち、まず第1図(D)のステップにおいて、仮設
梁11と仮設柱12と空のタンク10とを地上で組立
て、構築物1の頂部までジャッキアップし、頂部鉄塔4
の取合部4′に取付け、タンク10に水を注水する。次
ぎに、第1図(C)のステップで、頂部鉄塔4を下部に
水タンク10を取付けた状態でジャッキダウンさせる。
そして、第1図(B)のステップで仮設梁11,仮設柱
12,水タンク10を取外し、第1図(A)のステップ
で頂部鉄塔4を地上へ降ろす。That is, first, in the step of FIG. 1 (D), the temporary beam 11, the temporary column 12, and the empty tank 10 are assembled on the ground and jacked up to the top of the building 1, and the top tower 4
It is attached to the connecting portion 4'of, and water is poured into the tank 10. Next, in the step of FIG. 1 (C), the top tower 4 is jacked down with the water tank 10 attached to the lower part.
Then, the temporary beam 11, the temporary column 12, and the water tank 10 are removed in the step of FIG. 1 (B), and the top tower 4 is lowered to the ground in the step of FIG. 1 (A).
尚、実施例では吊材6,6′の上,下動を、ジャッキ2
を介して上下移動可能な架台3を用いた場合について説
明したが、本発明はこれに限定されるものではなく、架
台3を用いずジャッキ2自体に吊材6,6′を咬持する
機能を有するセンターホールジャッキを用いても良い。In the embodiment, the jack 2 is used to move the suspension members 6, 6'up and down.
Although the case of using the gantry 3 that can be moved up and down via the above is not limited to this, the function of holding the suspension members 6, 6'on the jack 2 itself without using the gantry 3. You may use the center hole jack which has.
〈発明の効果〉 以上詳述したように、本発明に係るリフトアップまたは
ダウン工法によれば、頂部鉄塔のように縦横比が極めて
大きい対象物であっても高層構築物の頂部に、対象物の
転倒や落下等の危険な事故を生じることなく、安全に上
昇させることができる。<Effects of the Invention> As described in detail above, according to the lift-up or down method according to the present invention, even if an object with an extremely large aspect ratio, such as a top tower, has an object at the top of the high-rise building, It can be safely raised without causing a dangerous accident such as a fall or a fall.
また、従来の、ガイド柱等が不要となり、これら柱材の
構築物頂部への上昇、あるいは仮設・撤去工事が一切不
要となり、一つの上昇工程のみで対象物を構築物頂部へ
持上げることができる。In addition, the conventional guide pillars are not required, and there is no need to raise these pillars to the top of the structure or temporary installation / removal work, and the object can be lifted to the top of the structure with only one ascending step.
更に、バランスウエイト用部材は、水,砂等の安価なバ
ランスウエイト用体と、これを単に収納できる安価な容
器とからなるものか、あるいは、廃材等の安価なもので
充分であり、しかもこれらは繰返し使用できるものであ
り、リフトアップまたはダウンの工事費が大幅に低減す
る。Further, it is sufficient that the balance weight member is composed of an inexpensive balance weight body such as water or sand and an inexpensive container that can simply store it, or an inexpensive material such as waste material. Can be used repeatedly, and the construction cost for lifting up or down is greatly reduced.
また、バランスウエイト用体として、水,砂,砂利,そ
の他の液体や粒状物を使用すれば重心の位置決めをこれ
ら部材の注入量の調整により容易に行うことができる。
しかも、これらの液体や粒状物の注入,抜出しは対象物
の上昇・下降の途中でも容易に行うことができるため、
余分な重量増を招くことなく、対象物の上昇・下降が行
える。If water, sand, gravel, other liquids or granular materials are used as the balance weight body, the center of gravity can be easily positioned by adjusting the injection amount of these members.
Moreover, since the injection and extraction of these liquids and granules can be easily performed during the ascent and descent of the object,
The object can be raised or lowered without causing an extra weight increase.
第1図(A)〜(D)は本発明に係るリフトアップまた
はダウン工法の第1実施例をステップ毎に示す説明図、
第2図(A),(B)は従来のリフトアップまたはダウ
ン工法を示す説明図である。 1……構築物、2……ジャッキ 3……架台、4……対象物 4′……取合部、5……吊治具 6,6′……吊材 10……バランスウエイト用部材 11……仮設梁、12……仮設柱 13……吊点FIGS. 1 (A) to (D) are explanatory views showing, step by step, a first embodiment of a lift-up or down method according to the present invention,
2 (A) and 2 (B) are explanatory views showing a conventional lift-up or down method. 1 ... Construct, 2 ... Jack 3 ... Stand, 4 ... Object 4 '... Connection part, 5 ... Suspension jig 6,6' ... Suspension material 10 ... Balance weight member 11 ... … Temporary beams, 12… Temporary columns 13… Hanging points
Claims (2)
ぐ吊材を使用するリフトアップまたはダウン工法におい
て、構築物の所要位置から頂部までの間の対象物の上昇
又は下降を、該対象物の下端部を前記吊材の吊点とし、
かつ該対象物の下方にバランスウエイト用部材を取付け
て該対象物の吊点より下方に重心が位置するようにして
行うことを特徴とするリフトアップまたはダウン工法。1. In a lift-up or down construction method using a jack and a suspending member connecting the jack and an object, the object is lifted or lowered from a required position to the top of the structure, and a lower end of the object is used. Part as the hanging point of the hanging material,
Further, a lift-up or down construction method, characterized in that a balance weight member is attached below the object so that the center of gravity is located below the suspension point of the object.
ト用体収納容器とからなるバランスウエイト用部材を用
い、該バランスウエイト用部材を仮設柱により対象物の
下方に取付ける請求1項記載のリフトアップまたはダウ
ン工法。2. The lift-up according to claim 1, wherein a balance weight member composed of the balance weight member and the balance weight member storage container is used, and the balance weight member is attached below an object by a temporary column. Down construction method.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1465588A JPH0645977B2 (en) | 1988-01-27 | 1988-01-27 | Lift up or down construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1465588A JPH0645977B2 (en) | 1988-01-27 | 1988-01-27 | Lift up or down construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH01190883A JPH01190883A (en) | 1989-07-31 |
| JPH0645977B2 true JPH0645977B2 (en) | 1994-06-15 |
Family
ID=11867230
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP1465588A Expired - Lifetime JPH0645977B2 (en) | 1988-01-27 | 1988-01-27 | Lift up or down construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0645977B2 (en) |
Families Citing this family (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4701047B2 (en) * | 2005-09-07 | 2011-06-15 | 株式会社竹中工務店 | Wind power tower construction method |
| JP4722630B2 (en) * | 2005-09-07 | 2011-07-13 | 株式会社竹中工務店 | Method for constructing tower structure and slip foam apparatus used in the method |
| DK2374966T3 (en) | 2010-04-06 | 2016-11-07 | Soletanche Freyssinet | A method of building a hybrid tower for a wind turbine |
| ES2407756B1 (en) * | 2011-12-09 | 2014-06-10 | Esteyco Energía S.L. | ASSEMBLY PROCEDURE OF A TELESCOPIC TOWER |
| JP6937627B2 (en) * | 2016-07-13 | 2021-09-22 | 戸田建設株式会社 | Offshore wind power generation equipment and its construction method |
| BR102016023743B1 (en) * | 2016-10-11 | 2022-11-29 | Protende Sistemas E Métodos De Construções Ltda | STRUCTURAL CONCRETE TOWER AND ASSEMBLY METHOD |
| JP7144471B2 (en) * | 2020-03-10 | 2022-09-29 | 太平電業株式会社 | Method for stacking tower members and lifting equipment used in method for stacking tower members |
-
1988
- 1988-01-27 JP JP1465588A patent/JPH0645977B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH01190883A (en) | 1989-07-31 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH0645977B2 (en) | Lift up or down construction method | |
| US3998029A (en) | Tower crane climbing | |
| JPH09177070A (en) | Method and apparatus for constructing rebar cage for deep foundation | |
| JP3053296B2 (en) | Pillar hanging jig | |
| JP2890341B2 (en) | Method and apparatus for lifting up top-level frame for structure construction | |
| JP3176251U (en) | Portable silo hanging device | |
| CN221919567U (en) | High-rise building vertical component cuts, rises and entangles device of toppling and prevent toppling | |
| JP2504293Y2 (en) | Lifting device for bogies for ship mounting | |
| JP3234125B2 (en) | Hanging jig for heavy object moving device | |
| JPH0617544A (en) | Automatic beam reinforcement device under the load of temporary machinery | |
| CN119503618A (en) | A mud slag lifting device for pile hole construction | |
| JP3008431U (en) | Hanging jig for wall joint material | |
| JPS581557Y2 (en) | Temporary lifting scaffolding device | |
| JPS5846993B2 (en) | Method of constructing a steel tower using a lifting crane | |
| JPS6152305B2 (en) | ||
| JPH0144681Y2 (en) | ||
| JPH04115883U (en) | Climbing crane lower support | |
| JPS6218621Y2 (en) | ||
| JP2527282B2 (en) | Iron pillar assembly device | |
| JP2000064598A (en) | Scaffolding device for constructing tower-shaped structure | |
| JP2527488B2 (en) | Gas tank dismantling method | |
| JPH074056A (en) | Erecter for wall | |
| JP2802568B2 (en) | Construction method | |
| JPS59170366A (en) | Assembling of accessories in tank | |
| JPH0316877Y2 (en) |