JPH0674608B2 - Beam-column joining method - Google Patents
Beam-column joining methodInfo
- Publication number
- JPH0674608B2 JPH0674608B2 JP6270187A JP6270187A JPH0674608B2 JP H0674608 B2 JPH0674608 B2 JP H0674608B2 JP 6270187 A JP6270187 A JP 6270187A JP 6270187 A JP6270187 A JP 6270187A JP H0674608 B2 JPH0674608 B2 JP H0674608B2
- Authority
- JP
- Japan
- Prior art keywords
- column
- reinforcement
- spiral hoop
- muscle
- hoop
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000000034 method Methods 0.000 title claims description 5
- 210000003205 muscle Anatomy 0.000 claims description 26
- 230000002787 reinforcement Effects 0.000 claims description 24
- 239000004567 concrete Substances 0.000 claims description 8
- 238000009415 formwork Methods 0.000 claims description 8
- 241000272165 Charadriidae Species 0.000 claims 2
- 238000010276 construction Methods 0.000 description 5
- 230000000694 effects Effects 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Landscapes
- Rod-Shaped Construction Members (AREA)
- Joining Of Building Structures In Genera (AREA)
Description
【発明の詳細な説明】 (産業上の利用分野) 本発明は鉄筋コンクリート柱とPC梁との接合工法に係る
ものである。DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method for joining a reinforced concrete column and a PC beam.
(従来の技術) 従来この種の工法においては、柱型枠内に柱コンクリー
トを柱頭(梁下)まで打設し、次いで同柱頭にPC梁を架
設した後、第4図に示すように、相隣る柱主筋突出端部
(a)(a)間に直線状の割フープ筋(b)を配筋して
いた。(Prior Art) Conventionally, in this type of construction method, pillar concrete is placed in the pillar form up to the pillar head (below the beam), and then a PC beam is erected on the pillar head, as shown in FIG. A straight split hoop muscle (b) was arranged between the projecting end portions (a) and (a) of the adjacent column main muscles.
(発明が解決しようとする問題点) 前記従来の工法では、柱頭部においてPC梁の梁主筋突出
端部が交錯し、またPC梁架設時には柱型枠が組込まれた
ままになっているので、スパイラル状のフープ筋を柱筋
の突出端部に組付けることはできず、前記したように割
りフープ筋を使用し、個々の割りフープ筋毎に柱筋の突
出端部に結束しなければならず、多大の手間を要し、取
付精度もよくないという問題点があった。(Problems to be solved by the invention) In the conventional construction method, the projecting end portions of the beam main bars of the PC beams intersect at the column heads, and the column formwork is still incorporated when the PC beams are erected. A spiral hoop muscle cannot be attached to the protruding end of the columnar muscle, and as described above, the split hoop muscle must be used, and each split hoop muscle must be tied to the protruding end of the columnar muscle. However, there is a problem that it requires a lot of labor and the mounting accuracy is not good.
(問題点を解決するための手段) 本発明はこのような問題点を解決するために提案された
もので、柱型枠を所定位置にセットし、同柱型枠内にコ
ンクリートを柱頭まで打設し、次いで梁主筋の突出端部
に、折畳み状態のスパイラルフープ筋が水平に仮止めさ
れたPC梁の端部を前記柱型枠の柱頭部に載架するととも
に、前記スパイラルフープ筋を柱頭部における柱筋突出
部に嵌合し、次いで前記梁主筋の突出端部とスパイラル
フープ筋との仮止めを解除し、同スパイラルフープ筋を
前記柱突出部の全長に亘って伸長し、同柱筋突出部に固
定することを特徴とする柱梁の接合工法に係るものであ
る。(Means for Solving Problems) The present invention has been proposed in order to solve such problems, in which a pillar formwork is set at a predetermined position, and concrete is cast in the pillar formwork up to the stigma. Installed, and then the protruding end of the main beam of the beam, the end of the PC beam in which the spiral hoop reinforcement in the folded state is temporarily fixed horizontally is mounted on the column head of the column formwork, and the spiral hoop reinforcement is used as the stigma. Fitting to the column bar projecting portion in the section, then release the temporary fixing of the projecting end of the beam main bar and the spiral hoop muscle, and extend the spiral hoop muscle over the entire length of the column projecting section. The present invention relates to a beam-column joining method characterized by being fixed to a projecting portion.
(作用) 本発明においては前記したように、所定位置にセットさ
れた柱型枠に柱頭まで柱コンクリートを打設したのち、
同柱頭部にPC梁を架設する際、同PC梁における梁主筋の
突出端部に折畳み状態にしたスパイラルフープ筋を結束
線等によって水平に仮止めし、同PC梁を柱頭部に架設す
る際スパイラルフープ筋を柱頭部からの柱筋突出端部に
嵌合し、しかるのち前記スパイラルフープ筋と梁筋突出
部との仮止めを解除し、同スパイラルフープ筋を梁上端
筋と下端筋との間に亘って伸長するとともに、同柱筋突
出端部に固定し、柱梁接合部におけるフープ筋の配筋を
完了し、同接合部に接合コンクリートを打設して柱梁を
接合する。(Operation) In the present invention, as described above, after the column concrete is cast up to the column head in the column form set at the predetermined position,
When installing a PC beam on the same pillar head, temporarily fold the spiral hoop reinforcement in the folded state to the projecting end of the main beam of the PC beam horizontally with a tie wire, etc., and then install the PC beam on the pillar head. Fit the spiral hoop muscle to the protruding end of the column muscle from the stigma, and then release the temporary fixing of the spiral hoop muscle and the protruding portion of the beam reinforcement, While extending over the space, it is fixed to the projecting end portion of the same column reinforcement, the arrangement of the hoop reinforcement at the column-beam connection is completed, and joint concrete is placed at the connection to join the column-beam.
(発明の効果) このように本発明によれば、従来柱頭部の柱梁接合空間
における柱梁突出端部に配筋されるフープ筋を、PC梁架
設後に割りフープして組込んでいたものを、PC梁の梁主
筋突出端部に折畳み状態のスパイラルフープ筋を水平に
仮止めしておくことによって、PC梁の架設と同時に前記
柱筋突出端部に組込み、かくして施工を著しく簡略化
し、作業能率を向上するものである。(Effects of the Invention) As described above, according to the present invention, the hoop reinforcement that is conventionally arranged at the column-beam protruding end in the column-beam joint space of the column head is incorporated by split hooping after the PC beam is erected. , By temporarily fixing the spiral hoop reinforcement in the folded state to the projecting end of the main beam of the PC beam, it is incorporated into the projecting end of the column at the same time as the PC beam is erected, thus significantly simplifying the construction, It improves work efficiency.
また前記折畳み状態のスパイラルフープ筋を前記柱筋突
出端部の全長に亘って伸長して同突出端部に配筋するこ
とによって、配筋精度が向上する。Further, by extending the spiral hoop muscle in the folded state over the entire length of the protruding end portion of the columnar bar and arranging the protruding hoop end portion, the reinforcing bar arrangement accuracy is improved.
(実施例) 以下本発明を図示の実施例について説明する。(Examples) The present invention will be described below with reference to illustrated examples.
所定位置にセットされた柱型枠内に柱コンクリート
(1)を柱頭部(梁下)まで打設し、しかるのち後述の
ようにPC梁を架設する。The column concrete (1) is placed up to the column head (under the beam) in the column form set at the specified position, and then the PC beam is erected as described later.
なおこの段階では柱型枠は組立てられたままになってい
る。At this stage, the pillar formwork is still assembled.
(3A)(3B)(3C)(3D)はPC梁で、夫々接合端部より
梁主筋(4)が突設されている。(3A), (3B), (3C), and (3D) are PC beams, and beam main bars (4) project from the joint ends.
前記PC梁(3B)の下端梁主筋(4)の突出端部には、PC
ヤードからの吊上げ時に、水平に折畳まれた状態のスパ
イラルフープ筋(5)が結束線等によって仮止めされて
いる。図中(6)はスパイラルフープ筋(5)を折畳み
状態に結束した線条である。At the protruding end of the lower beam main bar (4) of the PC beam (3B), PC
At the time of hoisting from the yard, the spiral hoop muscles (5) that are horizontally folded are temporarily fixed by a binding wire or the like. In the figure, (6) is a line formed by binding the spiral hoop muscle (5) in a folded state.
而して柱を挟んで相対するPC梁(3A)(3C)の端部を柱
頭部に載架し、(第1図参照)次いでPC梁(3B)(3D)
を柱頭部に載架するとともに、第2図に示す如くPC梁
(3B)(3D)の梁主筋(4)の突出端部に仮止めされた
水平折畳み状態のスパイラルフープ筋(5)を柱頭部よ
り突出された柱筋(7)に嵌合する。なお前記PC梁端部
は柱上端面外周縁における柱筋(7)のかぶり部分に載
架してPC梁と柱筋が干渉しないようにする。次いで、前
記スパイラルフープ筋(5)とPC梁(3B)の梁主筋
(4)の突出端部との線条(6)による仮止めを解除す
るとともに、第3図に示すように、同スパイラルフープ
筋(5)を梁上端筋と梁下端筋との間に亘って伸長し、
前記フープ筋(5)の上端部及び下端部を夫々柱筋
(7)の柱頭からの突出部に結束しスパイラルフープ筋
(5)の配筋を完了し、柱梁接合コンクリートを打設し
て、柱梁を接合する。なお同打設コンクリート硬化後型
枠を脱型する。Then, the ends of the PC beams (3A) (3C) facing each other across the column are placed on the column head (see Fig. 1), and then the PC beams (3B) (3D).
And the spiral hoop muscles (5) in the horizontally folded state temporarily fixed to the projecting ends of the beam main bars (4) of the PC beams (3B) and (3D) as shown in Fig. 2. The column bar (7) projected from the section is fitted. The PC beam end is placed on the cover portion of the column bar (7) at the outer peripheral edge of the column upper end surface so that the PC beam and the column bar do not interfere with each other. Then, the temporary fixing by the line (6) between the spiral hoop reinforcement (5) and the protruding end of the beam main reinforcement (4) of the PC beam (3B) is released, and as shown in FIG. Extend the hoop muscle (5) between the upper beam and lower beam of the beam,
The upper end and the lower end of the hoop reinforcement (5) are bound to the protrusions of the column reinforcement (7) from the stigma, respectively, and the spiral hoop reinforcement (5) is completed. , Join the columns and beams. In addition, the mold is removed from the mold after the concrete is poured and cured.
図中(8)は前記各PC梁の上端部に突出した肋筋(9)
間に挿通、配筋された梁上端筋である。In the figure, (8) is a rib (9) protruding from the upper end of each PC beam.
It is a beam upper end streak that is inserted and arranged between.
前記実施例によればこのように、PC梁(3A)(3B)(3
C)(3D)の架設と同時にスパイラルフープ筋(5)を
柱頭部より突出した柱筋(7)に組込むことによって施
工が著しく簡略化され、この際スパイラルフープ筋
(5)とPC梁(3B)の梁主筋(4)の突出端部との仮止
めを解除し、最上段フープと最下段フープとを前記柱筋
(7)の柱頭突出部に本結束することによって、前記ス
パイラルフープ筋(5)のPC梁主筋に対する結束の解
除、これに伴って伸長したスパイラルフープ筋の柱主筋
に対する結束作業が柱頭上部からの作業によって可能と
なり、作業性が向上される。また前記スパイラルフープ
筋(5)を柱筋(7)の突出部全長に亘って伸長するこ
とによって、フープ間隔の精度がよくなる。According to the above-described embodiment, the PC beams (3A) (3B) (3
C) (3D) is installed and the spiral hoop reinforcement (5) is incorporated into the column reinforcement (7) protruding from the column head, so that the construction is significantly simplified. At this time, the spiral hoop reinforcement (5) and the PC beam (3B) are installed. ) Of the beam main bar (4) is temporarily fixed to the projecting end, and the uppermost hoop and the lowermost hoop are finally bound to the stigma projecting part of the columnar bar (7). It is possible to release the binding to the PC beam main bar in 5) and to bind the spiral hoop muscle that extends along with it to the column main bar by working from the upper part of the stigma, improving workability. Further, by extending the spiral hoop muscle (5) over the entire length of the protruding portion of the columnar muscle (7), the accuracy of the hoop interval is improved.
このように前記実施例によれば施工能率、精度が著しく
向上されるものである。As described above, according to the above-mentioned embodiment, the construction efficiency and accuracy are remarkably improved.
図面は本発明に係る柱梁の接合工法の一実施例の工程を
示す斜視図で、第1図は柱を挟んで相対する一双のPC梁
の柱頭部に対する載架工程、第2図はスパイラルフープ
筋を仮止めした他の一双のPC梁の柱頭部に対する載架前
の状態を示す斜視図、第3図は柱頭に対するPC梁の載架
が完了しスパイラルフープ筋を伸長し、柱筋に捲装する
工程を示す斜視図、第4図は従来の柱筋に対するフープ
筋の配筋状態を示す斜視図である。 (1)……柱コンクリート、(3A)(3B)(3C)(3D)
……PC梁、(4)……PC梁の梁主筋、(5)……スパイ
ラルフープ筋、(6)……線条、(7)……柱筋The drawings are perspective views showing the steps of an embodiment of the method of joining beam-columns according to the present invention. FIG. 1 is a step of mounting a pair of PC beams facing each other across a column, and FIG. 2 is a spiral. A perspective view showing the state before mounting the other two PC beams with the hoop muscle temporarily fixed to the stigma, Fig. 3 shows that the mounting of the PC beam on the stigma is completed and the spiral hoop muscle is extended to FIG. 4 is a perspective view showing a winding step, and FIG. 4 is a perspective view showing a state of arranging the hoop muscle with respect to the conventional columnar muscle. (1) …… Column concrete, (3A) (3B) (3C) (3D)
…… PC beam, (4) …… Main beam of PC beam, (5) …… Spiral hoop bar, (6) …… Line, (7) …… Column bar
───────────────────────────────────────────────────── フロントページの続き (72)発明者 岩田 丈 愛知県名古屋市千種区南明町2―44 (72)発明者 宮崎 直志 東京都町田市玉川学園1−5−36 (72)発明者 中島 成之 埼玉県狭山市下広瀬274−1 ─────────────────────────────────────────────────── ─── Continuation of front page (72) Inventor Takeshi Iwata 2-44 Minamiaki-cho, Chikusa-ku, Nagoya-shi, Aichi (72) Inventor Naoshi Miyazaki 1-5-36 Tamagawa Gakuen, Tokyo Machida-shi (72) Inventor Satoru Nakajima 274-1 Shimohirose, Sayama City, Saitama Prefecture
Claims (1)
にコンクリートを柱頭まで打設し、次いで梁主筋の突出
端部に、折畳み状態のスパイラルフープ筋が水平に仮止
めされたPC梁の端部を前記柱型枠の柱頭部に載架すると
ともに、前記スパイラルフープ筋を柱頭部における柱筋
突出部に嵌合し、次いで前記梁主筋の突出端部とスパイ
ラルフープ筋との仮止めを解除し、同スパイラルフープ
筋を梁上端筋と梁下端筋との間に亘って伸長し、同柱筋
突出部に固定することを特徴とする柱梁の接合工法。1. A pillar formwork is set at a predetermined position, concrete is placed in the pillar formwork up to the pillar head, and then a spiral hoop reinforcement in a folded state is temporarily temporarily fixed to the projecting end of the beam main reinforcement. While mounting the end of the PC beam on the stilt of the column formwork, the spiral hoop muscle is fitted to the column reinforcement protrusion in the stilt, and then the protruding end of the beam main reinforcement and the spiral hoop muscle. The method of joining a beam and a column is characterized in that the temporary hose is released, the spiral hoop reinforcement is extended between the beam upper end reinforcement and the beam lower end reinforcement, and is fixed to the same column reinforcement projection.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP6270187A JPH0674608B2 (en) | 1987-03-19 | 1987-03-19 | Beam-column joining method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP6270187A JPH0674608B2 (en) | 1987-03-19 | 1987-03-19 | Beam-column joining method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS63233134A JPS63233134A (en) | 1988-09-28 |
| JPH0674608B2 true JPH0674608B2 (en) | 1994-09-21 |
Family
ID=13207872
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP6270187A Expired - Lifetime JPH0674608B2 (en) | 1987-03-19 | 1987-03-19 | Beam-column joining method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0674608B2 (en) |
-
1987
- 1987-03-19 JP JP6270187A patent/JPH0674608B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPS63233134A (en) | 1988-09-28 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2535722B2 (en) | Reinforcement concrete column and steel beam connection structure and building construction method | |
| JPH0674608B2 (en) | Beam-column joining method | |
| JP3008795B2 (en) | Joint structure of reinforced concrete beams | |
| JP2759010B2 (en) | Precast concrete wall column joining method | |
| JP2643641B2 (en) | Building method using PC members | |
| JP2955964B2 (en) | Precast reinforced concrete beam-column jointing equipment | |
| JP3114569B2 (en) | Joint structure of precast formwork | |
| JPH06146439A (en) | Joining method for precast wall | |
| JP2864905B2 (en) | Precast wall joining method | |
| JPH06322820A (en) | Precast concrete column-beam joint structure | |
| JP2893406B2 (en) | Precast concrete beam-column joining method | |
| JP2635872B2 (en) | How to build a composite structure | |
| JP2574630Y2 (en) | Half PC beam structure | |
| JP2001164688A (en) | Construction method of precast concrete beam and precast concrete slab and reinforced concrete structure | |
| JP2910551B2 (en) | Lap joint method of main reinforcement of SRC column | |
| JP3864236B2 (en) | Reinforcing bar composition and its pre-assembly processing method | |
| JP2629496B2 (en) | Construction method of structure | |
| JP3312945B2 (en) | Construction method of concrete structure | |
| JPH06336732A (en) | Slope-stabilizing construction method | |
| JPH0558704U (en) | Precast reinforced concrete structure | |
| JPH0738390Y2 (en) | Formwork for legal form | |
| JPS5853152B2 (en) | Joining method in prefabricated construction method | |
| JPH1068133A (en) | Construction method of foundation structure in lightweight building | |
| JPH09217448A (en) | Wall structure | |
| JPH0643237Y2 (en) | Formwork for legal form |