JPH07207619A - Main tower of long bridge provided with laterally extended beam and side cable - Google Patents

Main tower of long bridge provided with laterally extended beam and side cable

Info

Publication number
JPH07207619A
JPH07207619A JP2467294A JP2467294A JPH07207619A JP H07207619 A JPH07207619 A JP H07207619A JP 2467294 A JP2467294 A JP 2467294A JP 2467294 A JP2467294 A JP 2467294A JP H07207619 A JPH07207619 A JP H07207619A
Authority
JP
Japan
Prior art keywords
cable
main tower
bridge
main
laterally
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2467294A
Other languages
Japanese (ja)
Inventor
Hiroyuki Mizukami
裕之 水上
Mikiyuki Mizukami
幹之 水上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP2467294A priority Critical patent/JPH07207619A/en
Publication of JPH07207619A publication Critical patent/JPH07207619A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE:To stabilize a long bridge against wind load and reduce the weight, by supporting beams laterally extended from the main tower by support cables and supporting and fixing side cables by the laterally extended beams. CONSTITUTION:Laterally stretched beams 11... laterally extending from both right and left side faces of the mast of the main tower 3 of a long bridge are provided. And the beams 11 laterally stretched to the right and left sides are suspended by cables 16, 16 for the laterally stretched beams through the main tower 3. Next, side support saddles 13, 13 or side anchors are provided to support/fix the side cables 9... with the laterally stretched beams 11. In this way, the wind load is supported by a cable system chiefly made of the side cables 9, a long span bridge can be constructed with less steel materials.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、長大橋及び超長大橋に
用いられる主塔及びケーブルに関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a main tower and a cable used for a long bridge and a super long bridge.

【0002】[0002]

【従来の技術】従来、橋梁に用いられる主塔は、例え
ば、吊橋におけるメインケーブルの支持や斜張橋のケー
ブルの支持のように、ケーブルを介して橋桁の重量を支
持し、その鉛直荷重を下部構造に伝達する機能を有する
ための構造物であり、主塔には鉛直方向の圧縮力が作用
することになる。
2. Description of the Related Art Conventionally, main towers used for bridges support the weight of bridge girders through cables and support the vertical load thereof, such as the support of main cables in suspension bridges and the support of cables in cable-stayed bridges. It is a structure that has the function of transmitting to the lower structure, and vertical compressive force acts on the main tower.

【0003】また、橋桁の揺れを防止する方策として、
橋桁の下側にアーチ状に張られるストームケーブル(ス
トームロープ)がある。
Further, as a measure to prevent the shaking of the bridge girder,
There is an arched storm cable (storm rope) below the bridge girder.

【0004】一般的に上記のストームケーブルが使用さ
れるのは、架設時のメインロープの耐風安定性向上のた
めである。(例えば、特許公告,平成2年−5924
5,ストームロープの架設工法など。)
The above-mentioned storm cable is generally used for the purpose of improving the wind resistance stability of the main rope at the time of installation. (For example, Patent Publication, 1990-5924.
5, construction method of storm rope, etc. )

【0005】さらに、耐風対策として、桁の横剛性を高
める方策として、開口部であるグレーチングを設けた、
トラスの捕剛桁などがある。
Furthermore, as a measure against wind resistance, a grating which is an opening is provided as a measure for increasing the lateral rigidity of the girder.
There are truss girders.

【0006】[0006]

【発明が解決しようとする課題】長大橋及び超長大橋を
架ける際、橋桁に働く外力としては、スパンが長くなれ
ばなる程、風荷重が最も支配的な荷重となる。特に横方
向の風荷重及び風による崩壊的な自励振動となり得る捩
じれ外力に対処するため、橋桁の横剛性及び捩じれ剛性
を高める必要があるが、従来はこれらの剛性を高める方
法として、補剛桁の断面を大きな断面として設計し、各
々の断面2次モーメントを大きくして、橋桁自体の横剛
性及び捩じれ剛性を高めることによって対処していた。
As the external force acting on the bridge girder when the long bridge and the ultra-long bridge are bridged, the wind load becomes the most dominant load as the span becomes longer. In particular, it is necessary to increase the lateral rigidity and torsional rigidity of bridge girders in order to deal with the lateral wind load and the external torsional force that can cause disintegrated self-excited vibration due to the wind. This has been dealt with by designing the cross section of the girder as a large cross section and increasing the second moment of area of each girder to increase the lateral rigidity and torsional rigidity of the bridge girder itself.

【0007】しかし、このような従来の方法・構造形式
では、大きな断面の補剛桁や箱桁構造を用意してしまう
こととなり、しかも、捕剛桁や箱桁には、橋軸方向に引
張力が与えられていないので、風などで横方向の曲げ力
がかかると、必ず、補剛桁や箱桁の一端には圧縮力が作
用することになる。長大橋の捕剛桁としては、一般的に
は鋼製のトラスが多いが、鉄は圧縮力には弱いので、過
大な横方向の曲げ応力がかかると一端は座屈してしまう
ことになる。箱桁も一般には鋼製であるが、橋軸方向の
圧縮力には弱い。そうならないためには、引張力に強い
鉄の特徴を生かす必要があり、そのため引っ張りのプレ
ストレスを補剛桁や箱桁に与えておけば効果的である
が、これまでには、ブロックごとで橋桁を吊りながら架
設するなどの架設工法上の課題もあって、このような考
慮はなされていなかった。従って、単に桁の断面2次モ
ーメントの増大だけで、横荷重や捩じれ振動に対処して
いたので、必然的に断面が大きくなり、益々重い橋桁と
なってしまい、結果として橋桁を吊るケーブルの引張強
度の限界により、スパンの限界長さが短くなるという問
題点があった。
However, in such conventional methods and structural forms, stiffening girders and box girder structures with a large cross section are prepared, and furthermore, the girders and box girders are pulled in the bridge axis direction. Since no force is applied, a compressive force is always applied to one end of the stiffening girder or box girder when a lateral bending force is applied by wind or the like. Generally, many steel trusses are used as a girder for long bridges, but iron is weak against compressive force, so if one receives excessive lateral bending stress, one end will buckle. The box girder is also generally made of steel, but it is weak against the compressive force in the bridge axial direction. In order to prevent this, it is necessary to take advantage of the characteristics of iron that is strong in tensile force, and therefore it is effective to apply pre-stressing tension to stiffening girders and box girders, but until now, it has been necessary to use individual blocks. Due to problems in the construction method, such as erection while suspending the bridge girder, such consideration was not taken. Therefore, since the lateral load and torsional vibration were dealt with only by increasing the second moment of area of the girder, the cross section inevitably became large and the bridge girder became heavier and, as a result, the tension of the cable for hanging the girder was pulled. There is a problem that the limit length of the span is shortened due to the limit of strength.

【0008】また、橋桁の揺れを抑制・防止するため、
ストームケーブル(耐風安定索−ストームロープ)を設
ける場合がある。このストームケーブルは、一般的には
橋粱部を架設している時、一時的に設けられることが多
い。ストームケーブルの留め具は主塔に設置される。従
って、左右のストームケーブルの間隔は最大で主塔の幅
でのみ取ることしかできないので、左右のストームケー
ブル間の距離は短くなり、横方向の風荷重及び捩じれ振
動に対しては効果的に作用しないという問題点があっ
た。
Further, in order to suppress / prevent the shaking of the bridge girder,
A storm cable (wind resistant rope-storm rope) may be installed. This storm cable is generally provided temporarily when the bridge section is being erected. Storm cable fasteners are installed on the main tower. Therefore, since the distance between the left and right storm cables is maximum and can be taken only by the width of the main tower, the distance between the left and right storm cables becomes short, and it effectively acts against the lateral wind load and torsional vibration. There was a problem not to do.

【0009】本発明は、上記の問題点を解決するため、
横方向の風荷重及び風などによる捩じれ振動に対してよ
り強い剛性を有し、かつ桁の重量を軽量化して、長大橋
の限界長をこれまで以上に延長できる主塔とケーブルの
形式を得ることを目的としている。
In order to solve the above problems, the present invention provides
A type of main tower and cable that has stronger rigidity against lateral wind load and torsional vibration due to wind, etc., and has a lighter girder weight, and can extend the limit length of long bridges more than ever Is intended.

【0010】[0010]

【課題を解決するための手段】橋粱の主塔において、該
主塔のマストの側面から横方向に張出す横張り出し粱部
を設け、該横張り出し梁部に設けられたサイド支持サド
ルまたはサイドアンカーにてサイドケーブルを支持また
は固定して主塔間に水平方向に張る。
[Means for Solving the Problems] In a main tower of a bridge, a side support saddle portion or a side provided on the horizontal projection beam portion is provided, which is provided with a lateral overhang portion which laterally extends from a side surface of a mast of the main tower. Side cables are supported or fixed by anchors and stretched horizontally between the main towers.

【0011】上記において、該横張り出し粱部にサイド
支持サドルを設ける際には、サイドケーブルの緊張を得
るため、両岸にアンカーレイジを設ける。
In the above description, when the side support saddle is provided on the laterally projecting slag portion, anchor rages are provided on both banks in order to obtain tension of the side cable.

【0012】上記サイドケーブルから橋桁本体まで連結
ケーブルまたは連結フレームで連結し、サイドケーブル
と橋桁を一体化して、横方向ないし捩じれの力に対して
サイドケーブルで相当分を分担させる。
The side cable and the bridge girder main body are connected by a connecting cable or a connecting frame, and the side cable and the bridge girder are integrated so that the side cable shares a considerable portion with respect to a lateral or twisting force.

【0013】橋粱の主塔において、該主塔のマストの側
面から横方向に張出す横張り出し粱部を設け、該横張り
出し梁部どうしを該主塔を介して横張り出し粱部支持ケ
ーブルで吊る。
[0013] In the main tower of the bridge tower, a horizontally projecting leech part which laterally overhangs from the side surface of the mast of the main tower is provided, and the horizontally projecting beam portions are laterally overhanging via the main tower by means of a leech support cable. Hang.

【0014】横張り出し梁部をサイドケーブルを引っ張
るため、もしくは支持するために該当する力の方向に対
してアーチ作用で強度を保持できるように、横張り出し
梁部をアーチ部材で構成する。または、横張り出し梁部
をトラス作用で同様に強度を保持できるように、横張り
出し粱部をトラス部材で構成する。
The laterally projecting beam portion is formed of an arch member so that the laterally projecting beam portion can maintain its strength by an arch action in the direction of a force for pulling or supporting the side cable. Alternatively, the lateral overhanging grove portion is formed of a truss member so that the lateral overhanging beam portion can similarly retain its strength by the truss action.

【0015】[0015]

【作用】サイドケーブルは、主塔間または橋全体長にわ
たって、左右各々の側面に水平方向にて張られるケーブ
ルであり、高張力で緊張される。橋桁は、このサイドケ
ーブルに、橋軸直角方向に張られる連結ケーブルもしく
は連結フレームで連結され、一体化されることになる。
従って、緊張されたサイドケーブルは、橋桁の横方向の
剛性に多大に寄与するが、サイドケーブルが橋の中心位
置から相当離れて設置されること(横方向の断面2次モ
ーメントを算出する上での距離が長い。)しかも高張力
で張られるので、相当の断面2次モーメントを増加さ
せ、一体構造の横剛性を著しく高めるという働きを有す
る。
The side cables are cables that are stretched horizontally on the left and right sides between the main towers or over the entire length of the bridge, and are tensioned with high tension. The bridge girder is connected to this side cable with a connecting cable or a connecting frame stretched in the direction perpendicular to the bridge axis to be integrated.
Therefore, although the strained side cable contributes significantly to the lateral rigidity of the bridge girder, the side cable should be installed at a considerable distance from the center position of the bridge (for calculating the lateral moment of inertia of the cross section). Moreover, since it is stretched with a high tension, it has a function of significantly increasing the second moment of area and significantly increasing the lateral rigidity of the integral structure.

【0016】サイドケーブルによる横剛性の増加は、サ
イドケーブルが橋軸中心から距離を取った方が、断面2
次モーメントが距離の2乗で増大するため、一層効果的
である。そのためには、主塔の幅よりも大きくその距離
を取る必要があるが、本発明では、主塔に横張り出し梁
部を設けたことにより、サイドケーブル間の距離は主塔
の幅よりも相当長く取ることが可能となる。
Regarding the increase in lateral rigidity due to the side cable, the cross section 2 is obtained when the side cable is located at a distance from the center of the bridge axis.
This is more effective because the second moment increases with the square of the distance. For that purpose, it is necessary to make the distance larger than the width of the main tower, but in the present invention, the distance between the side cables is considerably larger than the width of the main tower because the horizontal tower is provided in the main tower. It can be taken for a long time.

【0017】左右に張られるサイドケーブルの隔たり距
離を長くするためには、横張り出し梁部の張り出し長さ
をより長くし、かつサイドケーブルをしっかりと支持し
たり、緊張・固定したりする必要がある。そのため、横
張り出し梁部をトラス構造にしたり、アーム構造にした
りすると、効果的に張り出しの剛性を高めることができ
る。また、主塔の両側から張り出した、横張り出し粱部
どうしを主塔を介して、横張り出し粱部支持ケーブルで
お互いの粱部の端部どうしを連結することにより、より
長く張り出した横張り出し粱部を形成することが可能と
なる。
In order to increase the distance between the side cables stretched to the left and right, it is necessary to further lengthen the overhanging length of the lateral overhanging beam portion and to firmly support the side cables or to tighten and fix them. is there. Therefore, if the lateral projecting beam portion is formed into a truss structure or an arm structure, the rigidity of the projecting portion can be effectively increased. In addition, by connecting the laterally-extended leech parts that are jutting out from both sides of the main tower through the main tower with the laterally-extended leech part support cables, the laterally-extended leech parts that are extended over a longer period can be connected. It is possible to form a part.

【0018】サイドケーブルは、スパン間に張られる
が、主塔で支持する必要がある。さて、主塔の主たる働
きはメインケーブルを支持することによって橋桁全体の
鉛直荷重を支えるということである。サイドケーブルを
張る本橋粱形式では、主塔の働きとしてメインケーブル
以外に、サイドケーブルを支持し、かつ緊張させる必要
がある。主塔に設けられる、横張り出し梁部は、該サイ
ドケーブルの自重を支持する働きを持つ。また主塔に設
けられる横張り出し梁部は、サイドケーブル間の距離を
長くして、サイドケーブルが橋桁と一体化してもたらす
桁断面の横方向の断面2次モーメントを増大させ、横剛
性や捩じれ剛性を高めるという働きを有する。
The side cables are stretched between the spans but must be supported by the main tower. Now, the main function of the main tower is to support the vertical load of the entire girder by supporting the main cable. In the main bridge type where side cables are stretched, it is necessary to support and tension the side cables in addition to the main cable as the function of the main tower. The laterally projecting beam portion provided in the main tower has a function of supporting the weight of the side cable. In addition, the horizontal overhanging beam portion provided on the main tower increases the distance between the side cables to increase the lateral moment of inertia of the girder cross section that the side cables integrate with the bridge girder, increasing lateral rigidity and torsional rigidity. Has the function of increasing

【0019】上記のサイドケーブルの張り方としては、
サイドケーブルを主塔間のみ張る方法と橋長全体にわた
って張るなどの方法がある。前記では、主塔の横張り出
し粱部にサイドアンカーを設け、サイドケーブルの自重
を支持するだけでなく、張力を与えアンカーにて固定す
る必要がある。また後記では、主塔の横張り出し粱部に
サドルを設けサイドケーブルの自重を支えると同時に、
両岸にはアンカレイジを設け、サイドケーブルを固定・
緊張させる必要がある。
As a method of tensioning the above side cable,
There are methods to stretch the side cables only between the main towers and to stretch the entire length of the bridge. In the above description, it is necessary to provide side anchors on the horizontally projecting lees of the main tower so as to not only support the weight of the side cables but also to provide tension to fix the side cables. In addition, in the postscript, at the same time as supporting the own weight of the side cable by installing a saddle on the overhang of the main tower,
Anchorage is provided on both banks to fix the side cables.
I need to be nervous.

【0020】さて、サイドケーブルを両岸のアンカーレ
イジで固定し、該サイドケーブルを緊張させると、サイ
ドケーブルの張力を最大限まで高めることが可能なの
で、横方向に荷重が作用した場合、ケーブルの緊張力に
よって、圧縮力が働かないようにすることが可能とな
り、より横方向の剛性が高くなるという働きがある。
By fixing the side cables with anchorages on both banks and tensioning the side cables, the tension of the side cables can be maximized. Therefore, when a lateral load is applied, The tension force makes it possible to prevent the compressive force from acting, which has the effect of increasing the rigidity in the lateral direction.

【0021】さらに、風荷重によって自励振動が橋桁に
生じ、捩じれ荷重が橋桁に掛かるような場合であって
も、緊張されたサイドケーブルによって、一体となった
橋桁には高い捩じれ剛性が与えられているのと同様であ
り、効果的に対応できる。また、サイドケーブルだけで
なく、ストームケーブルも併設する場合は、その相乗効
果によって横方向の剛性、桁の捩じれ剛性が極めて高く
なるという働きを有することになる。
Further, even when the self-excited vibration is generated in the bridge girder due to the wind load and the torsional load is applied to the bridge girder, the tensioned side cables give the integrated bridge girder a high torsional rigidity. It can be dealt with effectively. When not only the side cables but also the storm cables are installed together, the synergistic effect has a function of significantly increasing the lateral rigidity and the torsional rigidity of the girder.

【0022】[0022]

【実施例】実施例について図面を参照して説明する。図
1において、岸1の間には海峡2が存在する。海峡2に
は、主塔3が立っており、メインケーブル4とハンガー
6を介して橋桁(捕剛桁)5を支持している。主塔3は
橋軸直角断面では、A型をしており、メインケーブル4
は一本であり、両岸に設置されているアンカーレイジ7
にて固定・緊張されている。サイドケーブル9は主塔3
に設けられた横張り出し梁部11に設置されているサイ
ド支持サドル13に支持されており、又両岸に設置され
たアンカーレイジ7に固定され緊張されている。本実施
例では、メインケーブル4とサイドケーブル9を固定す
るアンカーレイジ7は共通のアンカーレイジであるが、
勿論別々でも可能である。連結ケーブル/連結フレーム
10はサイドケーブル9と橋桁(捕剛桁)5及びストー
ムケーブル14と橋桁(補剛桁)5とを連結する。ま
た、ストームケーブル14は橋桁(捕剛桁)5よりも下
側に設置され、橋桁(捕剛桁)5が風などで持ち上げら
れ上に動こうとする運動/振動を阻止する。
EXAMPLES Examples will be described with reference to the drawings. In FIG. 1, there is a strait 2 between shores 1. A main tower 3 stands on the strait 2 and supports a bridge girder (rigging girder) 5 via a main cable 4 and a hanger 6. The main tower 3 has an A shape in a cross section perpendicular to the bridge axis, and the main cable 4
There is only one and anchor rage 7 installed on both banks
It is fixed and tense. Side cable 9 is the main tower 3
It is supported by the side support saddles 13 installed on the laterally projecting beam portion 11 provided on the shore, and is fixed and tensioned by the anchor rages 7 installed on both banks. In this embodiment, the anchor rage 7 for fixing the main cable 4 and the side cable 9 is a common anchor rage,
Of course, it is possible to use them separately. The connecting cable / connecting frame 10 connects the side cable 9 to the bridge girder (stiffening girder) 5 and the storm cable 14 to the bridge girder (stiffening girder) 5. The storm cable 14 is installed below the bridge girder (rigging girder) 5 to prevent movement / vibration of the bridge girder (rigging girder) 5 which is lifted by wind or the like to move upward.

【0023】図2の実施例について説明する。岸1の間
には海峡2が存在する。海峡2には、主塔3が立ってお
り、メインケーブル4とハンガー6を介して橋桁(捕剛
桁)5を支持している。メインケーブル4は両岸に設置
されているアンカーレイジ7にて緊張されている。サイ
ドケーブル9は主塔3に設けられた横張り出し粱部11
に設置されているサイドアンカー17で緊張・支持され
ている。連結ケーブル/連結フレーム10はサイドケー
ブル9と橋桁(捕剛桁)5及びストームケーブル14と
橋桁(補剛桁)5とを連結する。また、ストームケーブ
ル14は主塔3に設けられたケーブル定着/支持部15
によって固定・緊張され、中央スパン間に張られる。橋
桁(捕剛桁)5よりも下側に設置され、橋桁(捕剛桁)
5が風などで持ち上げられ、上に動こうとする運動/振
動を阻止する。
The embodiment shown in FIG. 2 will be described. There is a strait 2 between the shores 1. A main tower 3 stands on the strait 2 and supports a bridge girder (rigging girder) 5 via a main cable 4 and a hanger 6. The main cable 4 is tensioned by anchorages 7 installed on both banks. The side cable 9 is a horizontally projecting leech section 11 provided in the main tower 3.
It is tensioned and supported by the side anchors 17 installed at. The connecting cable / connecting frame 10 connects the side cable 9 to the bridge girder (stiffening girder) 5 and the storm cable 14 to the bridge girder (stiffening girder) 5. Further, the storm cable 14 is a cable fixing / supporting portion 15 provided in the main tower 3.
It is fixed and tensioned by and is stretched between the central spans. It is installed below bridge girder (holding girder) 5 and bridge girder (holding girder)
5 is lifted by wind or the like to prevent movement / vibration to move upward.

【0024】図3に示される実施例は、図1と同じ構造
を持つ橋梁の実施例であり、ひとつの主塔3付近を上か
ら見た平面図である。主塔3は4つの主塔基礎8の上に
設置され、左右に横張り出し梁部11を有する。この実
施例の横張り出し梁部11はアーチ構造を有している。
横張り出し粱部11にはサイド支持サドル13が設けら
れ、該サイド支持サドル13がサイドケーブル9を支持
している。メインケーブル4はメインサドル12にて支
持される。
The embodiment shown in FIG. 3 is an embodiment of a bridge having the same structure as in FIG. 1, and is a plan view of the vicinity of one main tower 3 as seen from above. The main tower 3 is installed on four main tower foundations 8 and has lateral beam portions 11 on the left and right. The laterally projecting beam portion 11 of this embodiment has an arch structure.
A side support saddle 13 is provided on the laterally projecting grout portion 11, and the side support saddle 13 supports the side cable 9. The main cable 4 is supported by the main saddle 12.

【0025】図4に示される実施例は、図1、図3と同
じ構造を持つ橋粱の実施例であり、主塔3付近を横から
見た側面図である。主塔3は4つの主塔基礎8の上に設
置され、左右に横張り出し粱部11を有する。横張り出
し粱部11にはサイド支持サドル13が設けられ、該サ
イド支持サドル13がサイドケーブル9を支持してい
る。メインケーブル4はメインサドル12にて支持され
る。ストームケーブル14が主塔3の下部に設けられて
いる、ケーブル定着/支持部15に支持されて、緊張さ
れており、ストームケーブル14と橋桁(捕剛桁)5間
に連結ケーブル/連結フレーム10で連結される。
The embodiment shown in FIG. 4 is an example of a bridge which has the same structure as in FIGS. 1 and 3, and is a side view of the vicinity of the main tower 3 as seen from the side. The main tower 3 is installed on the four main tower foundations 8 and has laterally overhanging slag sections 11 on the left and right. A side support saddle 13 is provided on the laterally projecting grout portion 11, and the side support saddle 13 supports the side cable 9. The main cable 4 is supported by the main saddle 12. A storm cable 14 is provided in the lower part of the main tower 3, is supported by a cable fixing / supporting portion 15, and is tensioned, and a connecting cable / connecting frame 10 is provided between the storm cable 14 and the bridge girder (rigging girder) 5. Are connected by.

【0026】図5に示される実施例は、図1、図3、図
4と同じ構造を持つ橋粱の実施例であり、主塔3付近の
断面図である。主塔3は4つの主塔基礎8の上に設置さ
れ、左右に横張り出し粱部11を有する。横張り出し梁
部11にはサイド支持サドル13が設けられ、該サイド
支持サドル13がサイドケーブル9を支持している。メ
インケーブル4はメインサドル12にて支持される。ス
トームケーブル14が主塔3の下部に設けられている、
ケーブル定着/支持部15に支持されて、緊張されてい
る。連結ケーブル/連結フレーム10は橋桁(捕剛桁)
5とストームケーブル14及びサイドケーブル9を連結
するものである。また、ハンガー6はメインケーブル4
によって橋桁(捕剛桁)5を吊るものである。ストーム
ケーブル14と橋桁(捕剛桁)5間に連結ケーブル/連
結フレーム10で連結される。
The embodiment shown in FIG. 5 is an embodiment of a bridge sill having the same structure as in FIGS. 1, 3 and 4, and is a cross-sectional view near the main tower 3. The main tower 3 is installed on the four main tower foundations 8 and has laterally overhanging slag sections 11 on the left and right. A side support saddle 13 is provided on the laterally projecting beam portion 11, and the side support saddle 13 supports the side cable 9. The main cable 4 is supported by the main saddle 12. A storm cable 14 is provided at the bottom of the main tower 3,
The tension is supported by the cable fixing / supporting portion 15. Connecting cable / connecting frame 10 is a bridge girder (rigid girder)
5, the storm cable 14 and the side cable 9 are connected. Also, the hanger 6 is the main cable 4
The bridge girder (rigging girder) 5 is hung by. A connecting cable / connecting frame 10 is connected between the storm cable 14 and the bridge girder (rigging girder) 5.

【0027】図6に示される実施例は、図1、図3、図
4、図5と同じ構造を持つ橋粱の実施例であり、主塔3
付近の斜視図である。主塔3は4つの主塔基礎8の上に
設置され、左右に横張り出し粱部11を有する。横張り
出し粱部11にはサイド支持サドル13が設けられ、該
サイド支持サドル13がサイドケーブル9を支持してい
る。メインケーブル4はメインサドル12にて支持され
る。ストームケーブル14は主塔3の下部に設けられて
いるケーブル定着/支持部15に支持されて、緊張され
ている。連結ケーブル/連結フレーム10は橋桁(捕剛
桁)5とストームケーブル14及びサイドケーブル9を
連結するものである。また、ハンガー6はメインケーブ
ル4によって橋桁(捕剛桁)5を吊るものである。スト
ームケーブル14と橋桁(捕剛桁)5間に連結ケーブル
/連結フレーム10で連結される。
The embodiment shown in FIG. 6 is an embodiment of bridge sill having the same structure as in FIGS. 1, 3, 4 and 5, and the main tower 3
It is a perspective view of the vicinity. The main tower 3 is installed on the four main tower foundations 8 and has laterally overhanging slag sections 11 on the left and right. A side support saddle 13 is provided on the laterally projecting grout portion 11, and the side support saddle 13 supports the side cable 9. The main cable 4 is supported by the main saddle 12. The storm cable 14 is supported by a cable fixing / supporting portion 15 provided in the lower part of the main tower 3 and is strained. The connecting cable / connecting frame 10 connects the bridge girder (rigging girder) 5, the storm cable 14 and the side cable 9. Further, the hanger 6 suspends the bridge girder (rigging girder) 5 by the main cable 4. A connecting cable / connecting frame 10 is connected between the storm cable 14 and the bridge girder (rigging girder) 5.

【0028】図7に示される実施例は、主塔3が門型の
橋梁の実施例であり、その斜視図である。左右にメイン
ケーブル4が設置されているものである。橋桁(捕剛
桁)5を連結ケーブル/連結フレーム10が支持してい
る。主塔3は4つの主塔基礎8の上に設置され、左右に
横張り出し梁部11を有する。横張り出し梁部11には
サイド支持サドル13が設けられ、該サイド支持サドル
13がサイドケーブル9を支持している。メインケーブ
ル4はメインサドル12にて支持される。連結ケーブル
/連結フレーム10は橋桁(捕剛桁)5とサイドケーブ
ル9を連結するものである。また、ハンガー6はサイド
ケーブル9を吊る。橋桁(捕{u桁)5間に連結ケーブ
ル/連結フレーム10で連結される。
The embodiment shown in FIG. 7 is an example of a bridge in which the main tower 3 is a gate type, and is a perspective view thereof. The main cables 4 are installed on the left and right. A bridge girder (rigging girder) 5 is supported by a connecting cable / connecting frame 10. The main tower 3 is installed on four main tower foundations 8 and has lateral beam portions 11 on the left and right. A side support saddle 13 is provided on the laterally projecting beam portion 11, and the side support saddle 13 supports the side cable 9. The main cable 4 is supported by the main saddle 12. The connecting cable / connecting frame 10 connects the bridge girder (rigging girder) 5 and the side cable 9. Further, the hanger 6 suspends the side cable 9. The bridge girders (capture {u girders) 5 are connected by a connecting cable / connecting frame 10.

【0029】図8に示される実施例は、主塔3が門型の
橋梁の実施例であり、その主塔3付近の断面図であり、
この場合は、実施例6と違いストームケーブル14が設
置されている。左右にメインケーブル4が設置されてい
る。橋桁(捕剛桁)5を連結ケーブル/連結フレーム1
0が支持している。主塔3は4つの主塔基礎8の上に設
置され、左右に横張り出し粱部11を有する。主塔3の
左右に設置される横張り出し粱部11には、主塔3を介
して、横張り出し梁部11どうしを連結する横張り出し
粱部支持ケーブル16で吊る。横張り出し梁部11には
サイド支持サドル13が設けられ、該サイド支持サドル
13がサイドケーブル9を支持している。メインケーブ
ル4はメインサドル12にて支持される。ストームケー
ブル14が主塔3の下部に設けられている、ケーブル定
着/支持部15に支持されて、緊張されている。連結ケ
ーブル/連結フレーム10は橋桁(捕剛桁)5とストー
ムケーブル14及びサイドケーブル9を連結するもので
ある。また、ハンガー6はメインケーブル4によって橋
桁(捕剛桁)5を吊るものである。
The embodiment shown in FIG. 8 is an embodiment in which the main tower 3 is a gate-shaped bridge, and is a cross-sectional view near the main tower 3,
In this case, unlike the sixth embodiment, the storm cable 14 is installed. Main cables 4 are installed on the left and right. Bridge girder (capture girder) 5 connecting cable / connecting frame 1
0 supports it. The main tower 3 is installed on the four main tower foundations 8 and has laterally overhanging slag sections 11 on the left and right. The horizontal overhanging section 11 installed on the left and right of the main tower 3 is hung by the horizontal overhanging section support cables 16 connecting the horizontal overhanging beam sections 11 via the main tower 3. A side support saddle 13 is provided on the laterally projecting beam portion 11, and the side support saddle 13 supports the side cable 9. The main cable 4 is supported by the main saddle 12. A storm cable 14 is supported and strained by a cable anchoring / supporting portion 15 provided at the bottom of the main tower 3. The connecting cable / connecting frame 10 connects the bridge girder (rigging girder) 5, the storm cable 14 and the side cable 9. Further, the hanger 6 suspends the bridge girder (rigging girder) 5 by the main cable 4.

【0030】[0030]

【発明の効果】本発明は、以上説明したように構成され
ているので、以下に記載されるような効果を奏する。
Since the present invention is constructed as described above, it has the following effects.

【0031】主塔間が、長いスパンになればなる程、外
力として支配的となる風荷重は、本発明の構造において
は主にサイドケーブルを中心とするケーブルシステムが
分担することになる。そのサイドケーブルには予め高張
力が入っており効率的に風荷重などの外力による荷重を
分担することができることになる。よって少ない鋼の材
料で非常に長いスパンの橋を得ることになる。橋桁の重
量を増大させることなく、橋桁の横方向剛性を著しく高
めることができ、従って、長大橋の設計において最も考
慮しなければならない風荷重に効果的に対処でき、より
長いスパンの橋を形成することが可能となる。即ち本発
明の橋梁形式によって、従来の斜長橋や吊橋では得られ
ない、超長大橋を構成することができ、橋のスパンを非
常に長くとることが可能となる。
As the span between the main towers becomes longer, the wind load that becomes more dominant as an external force is shared by the cable system centering on the side cables in the structure of the present invention. High tension is applied to the side cable in advance, so that the load due to external force such as wind load can be efficiently shared. So you get a very long span bridge with less steel material. The lateral stiffness of the bridge girder can be significantly increased without increasing the weight of the bridge girder, thus effectively addressing the wind loads that must be considered most in the design of long bridges and forming longer span bridges. It becomes possible to do. That is, according to the bridge type of the present invention, it is possible to construct a super-long bridge, which cannot be obtained by a conventional cable-stayed bridge or suspension bridge, and it is possible to make the span of the bridge extremely long.

【0032】上記のように、材料を効果的に使用するこ
とになるので、使用する鋼材などが少なくても済み、橋
全体の工費を削減できることになる。また、自重を減ら
すことができるので、上部工事の工費の節減となるばか
りか、塔にかかる荷重を減らすことができ、支える橋桁
の自重が相対的に軽くて済み、下部工事の費用も減らす
ことができる。材料を効果的に使用することになるの
で、使用する鋼材などが少なくてもよくなり、橋全体の
工費を削減できることになる。さらにスパンが長く取れ
るので、海峡を横断する橋の場合、少ない数の橋脚で済
むことになり、工事の費用が少なくてもよくなる。
As described above, since the material is effectively used, it is possible to reduce the construction cost of the entire bridge even if the amount of steel material used is small. Also, since the self-weight can be reduced, not only the construction cost of the upper construction can be saved, but also the load on the tower can be reduced, the self-weight of the supporting bridge girder can be relatively light, and the cost of the lower construction can be reduced. You can Since the materials will be used effectively, less steel will be used and the construction cost of the entire bridge can be reduced. Furthermore, since the span can be taken longer, in the case of a bridge that crosses the strait, a small number of piers will suffice, and construction costs will be low.

【0033】風に対しては、本発明の主塔とサイドケー
ブルを使用した橋粱部形式であると、殆どの主要構造が
オープン構造で形成されるため、風が吹き抜けてしま
い、風の外力は大幅に逓減されたものとなる。従って、
風荷重の大幅な軽減を図ることができ、通常でも揺れの
少ない橋が形成され、風による揺れも少なく、また、メ
ンテナンス上も有利で使用上安定的な橋ができる。
With respect to the wind, in the bridge girder type using the main tower and side cables of the present invention, most of the main structure is formed as an open structure, so the wind blows through and the external force of the wind is applied. Is greatly reduced. Therefore,
The wind load can be significantly reduced, and a bridge with less shaking is formed even under normal conditions. There is little shaking due to the wind, and it is advantageous for maintenance and a stable bridge can be used.

【0034】サイドケーブルとメインケーブル、サイド
ケーブルやストームケーブルと橋桁間を結ぶ上下の連結
ケーブル/連結フレーム、横張り出し粱部が設けられた
主塔は、従来にないデザインを提供することになる。要
するにこの橋の形式であると、3次元的にデザインする
ことになるので、一気にデザインのバリエーションが豊
富となり、また、横張り出し梁部の張り出し長さやサイ
ドケーブルの設定高さなど設計のパラメータも増え、設
計の許容範囲が広いので、様々な地域の特徴を組み入れ
て、柔軟で最適な設計ができる。また、近年橋は文化資
産としての価値も有するようになっているが、本発明の
橋の形式であると、今までにない、全く新しい橋の美観
を提供することが可能となる。
The main tower provided with the side cable and the main cable, the upper and lower connecting cables / connecting frames for connecting the side cable and the storm cable and the bridge girder, and the laterally projecting sill portion provides a design which has never been seen before. In short, this type of bridge requires three-dimensional design, so there are many variations in the design at once, and the design parameters such as the length of the lateral beam and the set height of the side cable are also increased. Since the design tolerance is wide, flexible and optimal design can be performed by incorporating the characteristics of various regions. In addition, although bridges have become valuable as cultural assets in recent years, the bridge form of the present invention makes it possible to provide a completely new aesthetic appearance of bridges.

【図面の簡単な説明】[Brief description of drawings]

【図1】横張り出し梁部を有した主塔とサイドケーブ
ル、サイドケーブルを支持するサイド支持サドルを主塔
の横張り出し梁部に設け、サイドケーブルを固定・緊張
するアンカレイジを設けた本発明の橋梁形式の全体の斜
視図である。
FIG. 1 is a view showing a main tower having a laterally projecting beam portion, a side cable, and a side support saddle for supporting the side cable provided on the laterally projecting beam portion of the main tower, and an anchorage for fixing and tensioning the side cable. It is a perspective view of the whole bridge type.

【図2】横張り出し梁部を有した主塔とサイドケーブ
ル、サイドケーブルを支持・固定・緊張するサイドアン
カーを横張り出し梁部に設けた本発明の橋梁形式の全体
の斜視図である。
FIG. 2 is an overall perspective view of a bridge type of the present invention in which a main tower having a laterally projecting beam portion, a side cable, and a side anchor for supporting / fixing / tensioning the side cable are provided on the laterally projecting beam portion.

【図3】本発明の橋梁形式の主塔近辺の上から見た平面
図である
FIG. 3 is a plan view seen from above in the vicinity of the main tower of the bridge type of the present invention.

【図4】本発明の橋粱形式の主塔近辺の側面から見た平
面図である。
FIG. 4 is a plan view seen from a side surface near a main tower of the bridge type of the present invention.

【図5】本発明の橋梁形式の主塔近辺の断面図である。FIG. 5 is a cross-sectional view near the main tower of the bridge type of the present invention.

【図6】本発明の橋梁形式の主塔近辺の斜視図である。FIG. 6 is a perspective view of the vicinity of a bridge type main tower of the present invention.

【図7】主塔が門型の橋梁の主塔近辺の斜視図である。FIG. 7 is a perspective view near a main tower of a bridge whose main tower is a gate type.

【図8】主塔が門型の橋梁の実施例の主塔近辺の断面図
である。
FIG. 8 is a cross-sectional view in the vicinity of the main tower of an embodiment of a bridge whose main tower is a gate type.

【符号の説明】[Explanation of symbols]

1 岸 2 海峡 3 主塔 4 メインケーブル 5 橋桁(捕剛桁) 6 ハンガー 7 アンカーレイジ 8 主塔基礎 9 サイドケーブル 10 連結ケーブル/連結フレーム 11 横張り出し梁部 12 メインサドル 13 サイド支持サドル 14 ストームケーブル 15 ケーブル定着/支持部 16 横張り出し梁部支持ケーブル 17 サイドアンカー 1 shore 2 strait 3 main tower 4 main cable 5 bridge girder (holding girder) 6 hanger 7 anchorage 8 main tower foundation 9 side cable 10 connecting cable / connecting frame 11 side overhanging beam 12 main saddle 13 side support saddle 14 storm cable 15 Cable anchoring / supporting part 16 Horizontal overhanging beam supporting cable 17 Side anchor

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 橋粱の主塔において、該主塔のマストの
側面から橋軸直角方向かつ外側に張り出す横張り出し粱
部を設け、該横張り出し粱部にてサイドケーブルを支持
/固定するサイド支持サドルまたはサイドアンカーを設
けたことを特徴とする横張り出し梁部を備えた長大橋主
塔。
1. A bridge tower main tower is provided with a laterally projecting leash part projecting outward from the side surface of the mast of the main tower in a direction perpendicular to the bridge axis and outside, and the side cable is supported / fixed by the horizontally projecting leech part. A long bridge main tower equipped with a laterally projecting beam, which is equipped with side support saddles or side anchors.
【請求項2】 橋粱の主塔において、該主塔のマストの
側面から横方向に張出す横張り出し粱部を設け、左右両
側に張り出す該横張り出し梁部どうしを該主塔を介して
横張り出し梁部支持ケーブルにて吊って支持し、該横張
り出し粱部にてサイドケーブルを支持/固定するサイド
支持サドルまたはサイドアンカーを設けたことを特徴と
する横張り出し梁部を備えた長大橋主塔。
2. A bridge tower main tower is provided with lateral projecting bar sections that laterally project from the side surface of the mast of the main tower, and the lateral projecting beam sections projecting to both left and right sides are provided through the main tower. A long bridge having a laterally extending beam portion, which is provided with a side support saddle or a side anchor for suspending and supporting the laterally extending beam portion supporting cable and supporting / fixing the side cable at the laterally extending beam portion. Main tower.
【請求項3】 横張り出し粱部がアーチ構造またはトラ
ス構造で形成された請求項1又は2記載の横張り出し梁
部を備えた長大橋主塔。
3. The main tower of a long bridge having a lateral beam portion according to claim 1 or 2, wherein the laterally projecting grout portion has an arch structure or a truss structure.
【請求項4】 請求項1〜3のいずれか一項に記載の該
横張り出し粱部に設けられるサイドアンカーに固定さ
れ、主塔間に水平方向に張られるサイドケーブル。
4. A side cable which is fixed to a side anchor provided in the lateral overhanging section according to any one of claims 1 to 3 and which is horizontally stretched between main towers.
【請求項5】 請求項1〜3のいずれか一項に記載の横
張り出し梁部に設けられるサイド支持サドルに支持さ
れ、全スパンにわたり水平方向に張られ、かつアンカー
レイジに固定されたサイドケーブル。
5. A side cable supported by a side support saddle provided on the laterally projecting beam portion according to claim 1, stretched horizontally in the entire span, and fixed to an anchor rage. .
JP2467294A 1994-01-12 1994-01-12 Main tower of long bridge provided with laterally extended beam and side cable Pending JPH07207619A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2467294A JPH07207619A (en) 1994-01-12 1994-01-12 Main tower of long bridge provided with laterally extended beam and side cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2467294A JPH07207619A (en) 1994-01-12 1994-01-12 Main tower of long bridge provided with laterally extended beam and side cable

Publications (1)

Publication Number Publication Date
JPH07207619A true JPH07207619A (en) 1995-08-08

Family

ID=12144633

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2467294A Pending JPH07207619A (en) 1994-01-12 1994-01-12 Main tower of long bridge provided with laterally extended beam and side cable

Country Status (1)

Country Link
JP (1) JPH07207619A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010048238A (en) * 1999-11-25 2001-06-15 염병대 Arch type pier
FR2830548A1 (en) * 2001-10-04 2003-04-11 Andre Marc Reimbert Reinforcement for suspension bridge comprises crosspiece with ballast at each end supported by cable fastened to each roadway suspension cable
CN102644241A (en) * 2012-04-05 2012-08-22 广东省长大公路工程有限公司 Space curved cable bent tower of cable-stayed bridge
CN106758815A (en) * 2016-12-29 2017-05-31 中铁第四勘察设计院集团有限公司 Bridge floor bridge tower structure is worn in one kind
CN107964865A (en) * 2018-01-08 2018-04-27 河北工业大学 A kind of girder severe and the short beam suspension bridge of rigidity function separate type lightweight
CN113123211A (en) * 2021-05-25 2021-07-16 甘肃省交通规划勘察设计院股份有限公司 Root-shaped arrangement main cable self-anchored suspension bridge
CN119321090A (en) * 2024-12-18 2025-01-17 贵州交通建设集团有限公司 Light main cable saddle and installation method thereof

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010048238A (en) * 1999-11-25 2001-06-15 염병대 Arch type pier
FR2830548A1 (en) * 2001-10-04 2003-04-11 Andre Marc Reimbert Reinforcement for suspension bridge comprises crosspiece with ballast at each end supported by cable fastened to each roadway suspension cable
CN102644241A (en) * 2012-04-05 2012-08-22 广东省长大公路工程有限公司 Space curved cable bent tower of cable-stayed bridge
CN102644241B (en) * 2012-04-05 2014-07-30 广东省长大公路工程有限公司 Space curved cable bent tower of cable-stayed bridge
CN106758815A (en) * 2016-12-29 2017-05-31 中铁第四勘察设计院集团有限公司 Bridge floor bridge tower structure is worn in one kind
CN106758815B (en) * 2016-12-29 2018-12-14 中铁第四勘察设计院集团有限公司 Bridge floor bridge tower structure is worn in one kind
CN107964865A (en) * 2018-01-08 2018-04-27 河北工业大学 A kind of girder severe and the short beam suspension bridge of rigidity function separate type lightweight
CN107964865B (en) * 2018-01-08 2024-04-02 河北工业大学 Light short girder suspension bridge with separated girder weight and rigidity functions
CN113123211A (en) * 2021-05-25 2021-07-16 甘肃省交通规划勘察设计院股份有限公司 Root-shaped arrangement main cable self-anchored suspension bridge
CN119321090A (en) * 2024-12-18 2025-01-17 贵州交通建设集团有限公司 Light main cable saddle and installation method thereof

Similar Documents

Publication Publication Date Title
US5513408A (en) Frame structured bridge
JP4957295B2 (en) Seismic control pier structure
JP2011214221A (en) Stiffening girder of suspension bridge, and method for constructing the same
CN107761542A (en) One kind arch oblique pull combined system bridge and its construction method
KR101251298B1 (en) Precast segment fixing the connection member of closed structure and method constructing a stress ribbon bridge therewith
JP2967874B1 (en) How to build an overhead suspension bridge
CN112227216A (en) Triangular area cable buckling and sling combined construction method for steel diagonal bracing continuous rigid frame bridge
JP3737475B2 (en) Box girder bridge structure and construction method
CN102277836A (en) Construction method of tilting concrete tower base
US5727272A (en) Composite structure, especially bridge
KR100376162B1 (en) Advanced TEC beam with unsymmetric steel section
JPH01299943A (en) Truss structure
CN210140764U (en) Double-fold-line-shaped bridge span assembly stiffened through inhaul cable
KR101352956B1 (en) Cable-stayed bridge construction method
JPH07216820A (en) Arched bridge
CN217811586U (en) Large-span overhanging steel structure supporting component
JPH09256326A (en) Timbering for closed part of side span
KR100436747B1 (en) Apparatus and method for repairing and reinforcing bridge by using truss members
JP3600006B2 (en) Small suspension bridge
KR102173687B1 (en) Soundproof tunnel for bridge
JPH0860617A (en) Cable structure of suspension bridge and construction method of the bridge
JPH0693603A (en) Beam structure by use of inverted arched member and slantingly extended structure and arched member thereof
CN116927069B (en) A saddle-shaped cable-girder composite beam for pedestrian suspension bridges, the suspension bridge itself, and its construction method.
JP2635757B2 (en) Stiffening girder of suspension bridge with double concrete slab
KR20090083501A (en) Temporary bridge