JPH07232893A - Unloading device - Google Patents

Unloading device

Info

Publication number
JPH07232893A
JPH07232893A JP4654694A JP4654694A JPH07232893A JP H07232893 A JPH07232893 A JP H07232893A JP 4654694 A JP4654694 A JP 4654694A JP 4654694 A JP4654694 A JP 4654694A JP H07232893 A JPH07232893 A JP H07232893A
Authority
JP
Japan
Prior art keywords
unloading
unloading body
building
balance weight
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP4654694A
Other languages
Japanese (ja)
Inventor
Yasuhiro Oda
康弘 小田
Hisanao Yamakage
久尚 山影
Minoru Tanaka
實 田中
Masashi Takahashi
正志 高橋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Penta Ocean Construction Co Ltd
Original Assignee
Penta Ocean Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Penta Ocean Construction Co Ltd filed Critical Penta Ocean Construction Co Ltd
Priority to JP4654694A priority Critical patent/JPH07232893A/en
Publication of JPH07232893A publication Critical patent/JPH07232893A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Abstract

(57)【要約】 (修正有) 【目的】 本発明の目的は、ビルに障害物があるために
ビル外部に資材揚重用の仮設材を突出設置する必要のな
い荷揚装置を得るにある。 【構成】 荷揚本体6の中間部をクレーン4によって吊
下し、必要に応じてこの荷揚本体6の外端にカウンター
ウエイト9を固定し、内端に荷揚用の釣り具8を設ける
と共に、上記クレーン4による上記荷揚本体6の吊下部
を中心として左右に位置調節自在なるよう上記荷揚本体
にバランスウエイト10を固定した荷揚装置。
(57) [Summary] (Modified) [Object] An object of the present invention is to obtain an unloading device that does not need to project and install a temporary material for material lifting outside the building because of an obstacle in the building. [Structure] An intermediate portion of the unloading body 6 is hung by a crane 4, a counterweight 9 is fixed to an outer end of the unloading body 6 if necessary, and a fishing tackle 8 for unloading is provided at an inner end thereof. A unloading device in which a balance weight 10 is fixed to the unloading body so that the crane 4 can adjust the position of the unloading body 6 to the left and right around the hanging portion.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は荷揚装置、特にビル建設
において外部からビル内上部への仕上げ剤等の資材の取
り入れ、または取り除きの際に使用する荷揚装置に関す
るものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an unloading apparatus, and more particularly to an unloading apparatus used when a material such as a finishing agent is taken in or removed from the outside in the building construction.

【0002】[0002]

【従来の技術】従来、ビル建設において、外部からビル
1内部の2階以上、例えば5階にタイルや仕上げ剤等の
資材2を取り入れるためには、ビル1内部のエレベータ
ー(図示せず)を使用するか、または、図5に示すよう
に5階からビル1の外部に突出せしめ、遊端をワイヤロ
ープ等を介してビル1の5階天井に固定した仮設材3を
設け、この仮設材3上に地上クレーン4により資材2を
のせ、またはのせた資材2を取り出していた。
2. Description of the Related Art Conventionally, in building construction, in order to take in materials 2 such as tiles and finishing agents from the outside to the second floor or above, for example, the fifth floor, inside the building 1, an elevator (not shown) inside the building 1 is used. The temporary material 3 which is either used or which is projected from the 5th floor to the outside of the building 1 as shown in FIG. 5 and the free end of which is fixed to the ceiling of the 5th floor of the building 1 via a wire rope or the like is provided. The material 2 was placed on the 3 by the ground crane 4, or the placed material 2 was taken out.

【0003】[0003]

【発明が解決しようとする課題】然しながら、エレベー
ターによる資材2の取り込みのみでは多くの資材を同時
に取り込むことができないため作業効率性が悪く、ま
た、ビル外部に仮設材3を設けるのは手間と時間がかか
り、仮設材3上での作業は危険を伴うこともある。
However, since it is not possible to take in many materials at the same time only by taking in the materials 2 by the elevator, work efficiency is poor, and it is troublesome and time-consuming to provide the temporary materials 3 outside the building. Therefore, work on the temporary material 3 may be dangerous.

【0004】また、図6に示すように外壁等の障害物5
がある場合には、ビル1の外部に仮設材3を突出設置す
ることができないという欠点があった。
Further, as shown in FIG. 6, an obstacle 5 such as an outer wall
If there is such a problem, there is a drawback that the temporary material 3 cannot be installed outside the building 1.

【0005】本発明は上記の欠点を除くようにしたもの
である。
The present invention is intended to eliminate the above drawbacks.

【0006】[0006]

【課題を解決するための手段】本発明の荷揚装置は、水
平な荷揚本体と、この荷揚本体を吊り上げる手段と、上
記荷揚本体の一端を荷に連結する手段と、上記荷揚本体
の水平バランスを保つため上記荷揚本体上に位置可変に
固定したバランスウエイトとより成る。
DISCLOSURE OF THE INVENTION An unloading device of the present invention is a horizontal unloading body, a means for lifting the unloading body, a means for connecting one end of the unloading body to a load, and a horizontal balance of the unloading body. The balance weight is fixed on the unloading body in a positionally variable manner to maintain the balance weight.

【0007】また、本発明の荷揚装置は、水平な荷揚本
体と、この荷揚本体を吊り上げる手段と、上記荷揚本体
の一端を荷に連結する手段と、上記荷揚本体の他端に固
定したカウンターウエイトと、上記荷揚本体の水平バラ
ンスを保つため上記荷揚本体上に位置可変に固定したバ
ランスウエイトとより成る。
Further, the unloading device of the present invention comprises a horizontal unloading body, a means for lifting the unloading body, a means for connecting one end of the unloading body to a load, and a counterweight fixed to the other end of the unloading body. And a balance weight fixed on the unloading body in a variable position so as to maintain the horizontal balance of the unloading body.

【0008】上記荷は上記荷揚本体上に載置できる。The load can be placed on the unloading body.

【0009】上記荷揚本体を吊り上げる手段は、上記荷
揚本体の一点にその下端が接続され上端がクレーンに連
結される主ワイヤーと、その下端が上記荷揚本体の上記
一点とは異なる点に接続され上端が上記クレーンに連結
される補助ワイヤーとより成る。
The means for hoisting the unloading body includes a main wire whose lower end is connected to one point of the unloading body and whose upper end is connected to a crane, and whose lower end is connected to a point different from the above-mentioned one point of the unloading body. Comprises an auxiliary wire connected to the crane.

【0010】上記バランスウエイトの位置可変手段は、
上記荷揚本体の傾斜を検知する手段と、この手段により
制御される機械的手段または油圧式手段より成る。
The position changing means of the balance weight is
It comprises means for detecting the inclination of the unloading body and mechanical or hydraulic means controlled by this means.

【0011】[0011]

【実施例】以下図面によって本発明の実施例を説明す
る。
Embodiments of the present invention will be described below with reference to the drawings.

【0012】本発明においては、図1に示すように、棒
状の荷揚本体6の中間の異なる2個所に主ワイヤー7a
と補助ワイヤー7bの下端を夫々取り付け、この2本の
ワイヤー7a,7bの上端を夫々クレーン4のフックに
取り付ける。また、上記荷揚本体6の内端から資材揚重
用のワイヤー8を吊下し、外端に固定カウンターウエイ
ト9を固定せしめる。
In the present invention, as shown in FIG. 1, the main wire 7a is provided at two different locations in the middle of the rod-shaped unloading body 6.
And the lower ends of the auxiliary wires 7b are attached respectively, and the upper ends of the two wires 7a and 7b are attached to the hooks of the crane 4, respectively. In addition, the material lifting wire 8 is hung from the inner end of the unloading body 6 and the fixed counterweight 9 is fixed to the outer end.

【0013】また、上記荷揚本体6上に、左右に移動可
能なるようバランスウエイト10を載置する。
A balance weight 10 is placed on the unloading body 6 so as to be movable left and right.

【0014】本発明の荷揚装置は上記のような構成であ
るから、ビル1内部にある資材2を外部に運び出す場合
には、図1に示すように地上クレーン4によって上記荷
揚本体6をビル1の外壁に沿って吊り上げるが、この場
合上記荷揚本体6の内端の資材揚重用のワイヤー8には
資材が吊下されておらず、従って何等の重量も加わって
いない。然るに上記荷揚本体6の外端には固定カウンタ
ーウエイト9があるため、図1において、上記荷揚本体
6の左側と右側の重さのバランスをとるよう、上記バラ
ンスウエイト10を左方に移動せしめ、上記荷揚本体6
に固定せしめる。
Since the unloading device of the present invention has the above-mentioned structure, when the material 2 inside the building 1 is carried outside, the unloading main body 6 is moved to the building 1 by the ground crane 4 as shown in FIG. However, in this case, no material is hung on the wire 8 for hoisting material at the inner end of the unloading body 6, and therefore no weight is applied. However, since there is a fixed counterweight 9 at the outer end of the unloading body 6, in FIG. 1, the balance weight 10 is moved to the left so as to balance the weights of the left side and the right side of the unloading body 6. The unloading body 6
Fixed to.

【0015】次に、図2に示すように、ビル1内にある
資材2を揚重するため上記荷揚本体6を所望の階迄吊り
上げ、その内端を障害物5を避けながらビル1内に挿入
し、資材2上部に位置せしめ、この資材2を上記資材揚
重用のワイヤー8に取り付ける。
Next, as shown in FIG. 2, the unloading body 6 is hoisted to a desired floor in order to hoist the material 2 in the building 1, and its inner end is kept in the building 1 while avoiding the obstacle 5. It is inserted and positioned on the upper part of the material 2, and this material 2 is attached to the wire 8 for lifting the material.

【0016】この状態でクレーン4により上記荷揚本体
6を上昇せしめるが、この場合、上記荷揚本体6の左側
に重量が加わることになるので、上記バランスウエイト
10を右方に移動せしめ、左右の重量バランスをとった
後、上記バランスウエイト10を上記荷揚本体6に固定
し、上記荷揚本体6を上昇せしめ、次いで上記資材2を
ビル1外に案内し吊下せしめる。
In this state, the crane 4 raises the unloading main body 6, but in this case, since the weight is added to the left side of the unloading main body 6, the balance weight 10 is moved to the right and the left and right weights are moved. After balancing, the balance weight 10 is fixed to the unloading body 6, the unloading body 6 is raised, and then the material 2 is guided to the outside of the building 1 and hung.

【0017】また、ビル1内に資材2を取り入れる場合
には上記と逆の方法を用いる。即ち、ワイヤー8によっ
て資材2を吊り下げた状態で上記荷揚本体6の左右の重
量が釣り合うように上記バランスウエイト10を右方に
移動せしめ、固定した後上記荷揚本体6を上昇せしめ、
資材2をビル1内に離脱載置した後は、上記荷揚本体6
の左右の重量バランスが取れるように上記バランスウエ
イト10を左方に移動せしめる。図3はビル1に障害物
5のない場合の説明図である。
Further, when the material 2 is taken into the building 1, the method reverse to the above is used. That is, while the material 2 is suspended by the wire 8, the balance weight 10 is moved to the right so that the left and right weights of the unloading body 6 are balanced, and after fixing, the unloading body 6 is raised.
After the material 2 is detached and placed in the building 1, the unloading body 6 is placed.
The balance weight 10 is moved to the left so that the left and right weight balance of the FIG. 3 is an explanatory view when the building 1 has no obstacle 5.

【0018】なお、本発明の他の実施例においては、上
記荷揚本体6の外端には固定カウンターウエイトを固定
せずに、上記バランスウエイト10で上記荷揚本体6の
バランスをとるようにする。
In another embodiment of the present invention, the balance weight 10 is used to balance the unloading body 6 without fixing a fixed counterweight to the outer end of the unloading body 6.

【0019】この実施例においては資材吊り下げ時にお
いて上記バランスウエイトは荷揚本体6の右方に位置し
ておき資材を吊り下げていない場合には上記バランスウ
エイトはこれより左方に位置するようになる。
In this embodiment, the balance weight is positioned on the right side of the unloading body 6 when suspending the material, and when the material is not suspended, the balance weight is positioned on the left side of this. Become.

【0020】本発明の他の実施例においては、図4に示
すように2本のワイヤー7a,7bの長さを互いに等し
いものとしても良い。
In another embodiment of the present invention, the lengths of the two wires 7a and 7b may be equal to each other as shown in FIG.

【0021】なお、上記荷揚本体6は資材2をその上に
載置できるように平板状のものとしてもよい。
The unloading body 6 may have a flat plate shape so that the material 2 can be placed thereon.

【0022】また、上記バランスウエイト10の移動
は、手動で行なうほか、資材2の重量を検知して、また
はレベル計により荷揚本体6の傾斜を検知し、この結果
に応じる機械的手段または油圧式手段によって行なうこ
とができる。
In addition to moving the balance weight 10 manually, the weight of the material 2 is detected, or the inclination of the unloading body 6 is detected by a level meter, and mechanical means or hydraulic type is used according to the result. It can be done by means.

【0023】[0023]

【発明の効果】上記のように本発明の荷揚装置によれ
ば、資材をビル内部に取り入れたり、ビル外部に取り出
したりする際、ビル外部に資材揚重用の仮設材を突出設
置する必要がなく、その製作のための日数、費用及び解
体時の安全性の面で極めて有利となる。
As described above, according to the unloading apparatus of the present invention, it is not necessary to project the temporary material for lifting the material outside the building when the material is taken in the building or taken out of the building. , Which is extremely advantageous in terms of the number of days for manufacturing, cost, and safety at the time of dismantling.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の荷揚装置の側面図である。FIG. 1 is a side view of an unloading device of the present invention.

【図2】ビルに障害物がある場合の本発明の荷揚装置の
使用方法説明図である。
FIG. 2 is a diagram illustrating a method of using the unloading device of the present invention when there is an obstacle in a building.

【図3】ビルに障害物がない場合の本発明の荷揚装置の
使用方法説明図である。
FIG. 3 is an explanatory diagram of how to use the unloading device of the present invention when the building has no obstacles.

【図4】本発明の荷揚装置の他の実施例を示す側面図で
ある。
FIG. 4 is a side view showing another embodiment of the unloading device of the present invention.

【図5】従来の荷揚装置の説明図である。FIG. 5 is an explanatory diagram of a conventional unloading device.

【図6】ビルに障害物のある場合の説明図である。FIG. 6 is an explanatory diagram when an obstacle is present in the building.

【符号の説明】[Explanation of symbols]

1 ビル 2 資材 3 仮設材 4 地上クレーン 5 障害物 6 荷揚本体 7a 主ワイヤー 7b 補助ワイヤー 8 ワイヤー 9 固定カウンターウエイト 10 バランスウエイト 1 Building 2 Material 3 Temporary Material 4 Ground Crane 5 Obstacle 6 Unloading Main Body 7a Main Wire 7b Auxiliary Wire 8 Wire 9 Fixed Counterweight 10 Balance Weight

───────────────────────────────────────────────────── フロントページの続き (72)発明者 高橋 正志 東京都品川区東大井1丁目11番25号 五洋 建設株式会社技術研究所内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Masashi Takahashi 1-11-25 Higashiooi, Shinagawa-ku, Tokyo Goyo Construction Co., Ltd. Technical Research Institute

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 水平な荷揚本体と、この荷揚本体を吊り
上げる手段と、上記荷揚本体の一端を荷に連結する手段
と、上記荷揚本体の水平バランスを保つため上記荷揚本
体上に位置可変に固定したバランスウエイトとより成る
ことを特徴とする荷揚装置。
1. A horizontal unloading body, a means for hoisting the unloading body, a means for connecting one end of the unloading body to a load, and a variably fixed position on the unloading body for maintaining a horizontal balance of the unloading body. A lifting device comprising a balanced weight.
【請求項2】 水平な荷揚本体と、この荷揚本体を吊り
上げる手段と、上記荷揚本体の一端を荷に連結する手段
と、上記荷揚本体の他端に固定したカウンターウエイト
と、上記荷揚本体の水平バランスを保つため上記荷揚本
体上に位置可変に固定したバランスウエイトとより成る
ことを特徴とする荷揚装置。
2. A horizontal unloading body, means for lifting the unloading body, means for connecting one end of the unloading body to a load, counterweight fixed to the other end of the unloading body, and horizontal for the unloading body. A unloading device comprising a balance weight fixed on the unloading body in a variable position to maintain balance.
【請求項3】 上記荷が上記荷揚本体上に載置されるこ
とを特徴とする請求項1または2記載の荷揚装置。
3. The unloading device according to claim 1, wherein the load is placed on the unloading body.
【請求項4】 上記荷揚本体を吊り上げる手段が、上記
荷揚本体の一点にその下端が接続され上端がクレーンに
連結される主ワイヤーと、その下端が上記荷揚本体の上
記一点とは異なる点に接続され上端が上記クレーンに連
結される補助ワイヤーとより成ることを特徴とする請求
項1,2または3記載の荷揚装置。
4. A means for hoisting the unloading body is connected to a main wire whose lower end is connected to one point of said unloading body and whose upper end is connected to a crane, and whose lower end is different from said one point of said unloading body. An unloading device according to claim 1, 2 or 3, characterized in that it comprises an auxiliary wire whose upper end is connected to the crane.
【請求項5】 上記バランスウエイトの位置可変手段
が、上記荷揚本体の傾斜を検知する手段と、この手段に
より制御される機械的手段または油圧式手段より成るこ
とを特徴とする請求項1,2,3または4記載の荷揚装
置。
5. The balance weight position changing means comprises a means for detecting an inclination of the unloading body, and a mechanical means or a hydraulic means controlled by this means. , 3 or 4, the unloading device.
JP4654694A 1994-02-22 1994-02-22 Unloading device Pending JPH07232893A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4654694A JPH07232893A (en) 1994-02-22 1994-02-22 Unloading device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4654694A JPH07232893A (en) 1994-02-22 1994-02-22 Unloading device

Publications (1)

Publication Number Publication Date
JPH07232893A true JPH07232893A (en) 1995-09-05

Family

ID=12750317

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4654694A Pending JPH07232893A (en) 1994-02-22 1994-02-22 Unloading device

Country Status (1)

Country Link
JP (1) JPH07232893A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101436735B1 (en) * 2013-04-19 2014-09-02 주식회사 필룩스 lighting apparatus
KR20190135351A (en) * 2018-05-28 2019-12-06 삼성중공업 주식회사 A lighting system installed in a ship or an offshore structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101436735B1 (en) * 2013-04-19 2014-09-02 주식회사 필룩스 lighting apparatus
KR20190135351A (en) * 2018-05-28 2019-12-06 삼성중공업 주식회사 A lighting system installed in a ship or an offshore structure

Similar Documents

Publication Publication Date Title
CN113428811A (en) Corridor ceiling mounting plate hoisting structure and construction method thereof
JPH0829904B2 (en) Elevator installation method
JP2756466B2 (en) Method for controlling lifting posture of curved plate and hanging tool for curved plate
GB2249581A (en) Elevator travelling cable grip
JPH07232894A (en) Load lifting device
JPS5935822B2 (en) Construction elevator installation method
JPH092774A (en) Heavy object suspending device
JP2001354374A (en) Lifting device in elevator shaft
JP2681066B2 (en) Method and device for steadying suspended load in crane
JPH09290991A (en) Lifting equipment for lifting
JP3811419B2 (en) Building material lifting device and building material lifting method
JPH02176075A (en) Hanging method and apparatus of wall pannel for building
JPH07189230A (en) Mat cage method
JP2504541Y2 (en) Movable hanging jig device
JP3004731U (en) Multi-point hanging jig
JPH0728179Y2 (en) Lifting device for tower erection crane
JPH10167668A (en) Vertical and horizontal transporting device and its operation
JP2001316074A (en) Hanging jig for hanging load and method of using the same
JPH06298500A (en) Automatic eccentric traverser
JP2003306289A (en) Construction method of long member and load jig for long member
JPH092767A (en) How to lift escalator truss
JPH02300081A (en) Installation work method for elevator
JPS6019107Y2 (en) Crane lifting balancer device
JPH0672499B2 (en) Panel material placement method
JP2000274080A (en) Wall member mounting method for building frame and traverser for mounting the wall member