Method for pipingInfo
- Publication number
- JPH07293745A JPH07293745A JP8431294A JP8431294A JPH07293745A JP H07293745 A JPH07293745 A JP H07293745A JP 8431294 A JP8431294 A JP 8431294A JP 8431294 A JP8431294 A JP 8431294A JP H07293745 A JPH07293745 A JP H07293745A
- Authority
- JP
- Japan
- Prior art keywords
- piping
- pipe
- water
- assembly
- header
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title description 6
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 63
- 239000012530 fluid Substances 0.000 claims abstract description 9
- 239000000463 material Substances 0.000 claims abstract description 5
- 238000010276 construction Methods 0.000 description 10
- -1 polyethylene Polymers 0.000 description 6
- 239000004698 Polyethylene Substances 0.000 description 5
- 229920000573 polyethylene Polymers 0.000 description 5
- 238000009428 plumbing Methods 0.000 description 3
- 229920001083 polybutene Polymers 0.000 description 3
- 229920000915 polyvinyl chloride Polymers 0.000 description 3
- 239000004800 polyvinyl chloride Substances 0.000 description 3
- 239000010935 stainless steel Substances 0.000 description 3
- 229910001220 stainless steel Inorganic materials 0.000 description 3
- RYGMFSIKBFXOCR-UHFFFAOYSA-N Copper Chemical compound [Cu] RYGMFSIKBFXOCR-UHFFFAOYSA-N 0.000 description 2
- 229910052802 copper Inorganic materials 0.000 description 2
- 239000010949 copper Substances 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000000630 rising effect Effects 0.000 description 2
- 229910000906 Bronze Inorganic materials 0.000 description 1
- 229910000881 Cu alloy Inorganic materials 0.000 description 1
- 229910052782 aluminium Inorganic materials 0.000 description 1
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 239000010974 bronze Substances 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 230000005494 condensation Effects 0.000 description 1
- 238000009833 condensation Methods 0.000 description 1
- KUNSUQLRTQLHQQ-UHFFFAOYSA-N copper tin Chemical compound [Cu].[Sn] KUNSUQLRTQLHQQ-UHFFFAOYSA-N 0.000 description 1
- 229920003020 cross-linked polyethylene Polymers 0.000 description 1
- 239000004703 cross-linked polyethylene Substances 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 230000004927 fusion Effects 0.000 description 1
- 229920001179 medium density polyethylene Polymers 0.000 description 1
- 239000004701 medium-density polyethylene Substances 0.000 description 1
- 229910052751 metal Inorganic materials 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 229920001748 polybutylene Polymers 0.000 description 1
- 239000011347 resin Substances 0.000 description 1
- 229920005989 resin Polymers 0.000 description 1
- 238000005406 washing Methods 0.000 description 1
Landscapes
- Pipeline Systems (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、主に住宅に用いられる
給水配管に係り、特にプレハブ住宅に適した配管方法に
関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a water supply pipe mainly used for houses, and more particularly to a pipe method suitable for prefabricated houses.
【0002】[0002]
【従来の技術】プレハブ住宅は住宅の各ユニット、例え
ば台所、洗面所、風呂、便所が1ユニットで、またダイ
ニングは1ユニットでというように、ユニット毎に工場
で作って、建築現場に運んで組み立てて家屋にしてい
る。これらユニットを工場で作るときに、ユニットに用
いる床下パネル、壁パネル、天井などを組み立ててい
る。この組立はベルトコンベアの上や台車の上で行われ
る。2. Description of the Related Art In a prefabricated house, each unit of the house, for example, kitchen, washroom, bath, toilet is one unit, and dining is one unit. Assembled into a house. When making these units at the factory, we assemble the underfloor panels, wall panels, and ceiling used for the units. This assembly is performed on a belt conveyor or a trolley.
【0003】このようなプレハブ住宅の水周りユニット
内の機器の配置はほぼ同じなので、配管の形、大きさが
ほぼ同じ物となる。しかし、この配管はユニットの組立
時に行われるので、きわめて短時間に完了することが要
求される。Since the arrangement of the devices in the water around unit of such a prefabricated house is almost the same, the shape and size of the pipes are almost the same. However, since this piping is done at the time of assembling the unit, it is required to be completed in an extremely short time.
【0004】また、集合住宅の場合も一戸一戸は規格化
された内部構造を取っているので、水周り配管も統一さ
れた形になっている。しかし、配管工事が一時に集中
し、その後の工程までの短い時間に施工する必要があ
る。Also, in the case of an apartment house, since each house has a standardized internal structure, the plumbing around water is also in a unified form. However, the piping work is concentrated at one time, and it is necessary to perform the work in a short time until the subsequent process.
【0005】配管施工時間を短くするために、ヘッダー
工法が採られるようになった。各戸への冷水・温水をヘ
ッダーで受けて、ヘッダーに付いた複数個の配水口の1
個1個から各器具まで可とう性のある管を接続する。こ
のようなヘッダー工法によって、配管施工時間は短縮で
きたが、更に短くするよう要求されている。In order to shorten the piping construction time, the header construction method has come to be adopted. The header receives cold and hot water for each house, and one of the multiple water outlets attached to the header
Connect flexible tubing from one piece to each device. Although the header construction method has shortened the piping construction time, it is required to further shorten the piping construction time.
【0006】[0006]
【発明が解決しようとする課題】そこで、本発明の目的
は配管施工時間を大幅に短縮でき、数十分で一戸分の配
管工事ができる配管用部材の配管方法を提供することで
ある。また、搬送や工事の時に配管内に異物の入ること
を防ぐとともに、加圧漏れ試験の容易な配管方法を提供
する。SUMMARY OF THE INVENTION Therefore, an object of the present invention is to provide a piping method for a piping member which can significantly reduce the piping construction time and can perform the plumbing work for one unit in several tens of minutes. In addition, it provides a piping method that prevents foreign matter from entering the piping during transportation and construction and facilitates a pressure leak test.
【0007】[0007]
【課題を解決するための手段】本発明の配管方法は、配
水用ヘッダーの複数個の配水口に各々所定長さの可撓性
のある材料で出来た配水パイプを取り付け、各パイプの
他端には継手を取り付けて配管組立品となし、この配管
組立品の各継手の開口に閉止プラグを取り付け、配管組
立品の内部に流体の圧力を加えて漏れ試験を行い、この
配管組立品をプレハブ住宅ユニットに取り付け配管を行
い、その後配管内に流体圧力を加えて漏れ試験を行った
後で、閉止プラグを継手の開口から取り外して、その部
分に水栓等の器具を取り付けることを特徴とするもので
ある。According to the piping method of the present invention, a water distribution pipe made of a flexible material having a predetermined length is attached to each of a plurality of water distribution ports of a water distribution header, and the other end of each pipe is attached. To form a piping assembly, attach a closing plug to the opening of each fitting of this piping assembly, apply fluid pressure to the inside of the piping assembly to perform a leak test, and pre-assemble this piping assembly. It is characterized by installing piping in a housing unit, then applying a fluid pressure to the inside of the piping to perform a leak test, then removing the closing plug from the opening of the fitting, and installing a device such as a faucet in that part It is a thing.
【0008】ここで可撓性のある材料で出来た配水パイ
プの長さを所定長さとしたが、これはプレハブ住宅ユニ
ット上で、取り付ける配水ヘッダーの位置から水栓等の
器具を取り付ける位置までをその配水パイプで接続でき
る長さという意味である。[0008] Here, the length of the water distribution pipe made of a flexible material is set to a predetermined length, but this is from the position of the water distribution header to be installed to the position of equipment such as a faucet on the prefabricated housing unit. It means the length that can be connected by the water distribution pipe.
【0009】この配水用ヘッダーは、ヘッダーの受水口
は通常1個でヘッダーからの配水口は複数個付いてお
り、冷水用ヘッダーでは配水口が5個、温水用の場合は
配湯口が4個ということが多い。ヘッダーには、ヘッダ
ーの配水口には必要によりオスアダプターを介して所定
長さのパイプを取り付ける。また不要の配水口にはメク
ラプラグがねじ込まれ水が止められている。温水用ヘッ
ダーの場合、保温用あるいは火傷防止のためにヘッダー
カバーを付けることができる。ヘッダーの受水口には必
要によりエルボが付けられ、給水パイプとの接続を容易
にしている。This water distribution header normally has one header water inlet and a plurality of water outlets from the header. The cold water header has five water outlets, and the hot water header has four water outlets. Often. If necessary, attach a pipe of a certain length to the water outlet of the header via a male adapter. In addition, a blind plug is screwed into the unnecessary water outlet to stop the water. In the case of a hot water header, a header cover can be attached to keep warm or prevent burns. An elbow is attached to the water inlet of the header if necessary to facilitate connection with the water supply pipe.
【0010】ヘッダーとしては青銅鋳物製のものやポリ
塩化ビニル製のものがよく使用されるが、これらのヘッ
ダーを使用する場合配水パイプとの間がネジ接続やメカ
ニカル接続となる。ヘッダーとしてポリエチレン製、ポ
リブテン製などのものを用いる場合、パイプも同じ材質
のものを用いその間を電気融着するのが望ましい。Bronze casting and polyvinyl chloride are often used as the header. When these headers are used, the connection with the water distribution pipe is screwed or mechanically connected. When using a header made of polyethylene, polybutene, or the like, it is desirable to use the same material for the pipes and to electrically fuse the pipes.
【0011】本発明に使用する配水パイプとしては、ポ
リブテンパイプ、ポリエチレンパイプのように機械的に
あるいは電気融着で接続できるパイプ、ステンレス・ス
チール・コルゲイティド・チューブ(SSCT)、銅
管、アルミニウム管の内外面に中密度ポリエチレンや架
橋ポリエチレンを被覆した金属強化ポリエチレンパイ
プ、あるいはJIS G3448に規定されている一般
配管用ステンレス鋼鋼管よりも薄肉にしたステンレス鋼
コイルド・チューブ(SCT)などを使うことができ
る。これらのパイプの内、自立性や曲げを保つ必要のあ
る場合には、銅管、金属強化ポリエチレンパイプあるい
はSCTなどが使われる。The water distribution pipe used in the present invention includes a polybutene pipe, a pipe which can be connected mechanically or by electric fusion such as a polyethylene pipe, a stainless steel corrugated tube (SSCT), a copper pipe, and an aluminum pipe. It is possible to use a metal reinforced polyethylene pipe whose inner and outer surfaces are coated with medium density polyethylene or cross-linked polyethylene, or a stainless steel coiled tube (SCT) that is thinner than the stainless steel pipe for general piping specified in JIS G3448. .. Of these pipes, copper pipes, metal-reinforced polyethylene pipes, SCTs, etc. are used when it is necessary to maintain self-supporting property and bending.
【0012】工事の時の傷を防ぐ、またパイプ周囲に結
露するのを防ぐために、これらの管はポリ塩化ビニルな
どで作られた鞘管に収められることが多い。配水パイプ
を鞘管に収める場合、ヘッダーと器具接続継手間のパイ
プに鞘管をかぶせた上で器具接続継手をパイプに取り付
ける。[0012] In order to prevent scratches during construction and to prevent dew condensation around the pipes, these pipes are often contained in a sheath pipe made of polyvinyl chloride or the like. When fitting the water distribution pipe in the sheath pipe, cover the pipe between the header and the equipment connection joint with the sheath pipe, and then attach the equipment connection joint to the pipe.
【0013】配水パイプのヘッダーと反対側の端部は、
台所用流しの給水・給湯栓、風呂の給水・給湯栓、洗面
化粧台の給水・給湯栓、便所や洗濯機の水洗と接続する
ための水洗アダプターあるいは水洗エルボなどの器具接
続継手が付けられており、これら器具接続継手の開口ネ
ジ部には搬送、工事の時に異物が入るのを防ぐために閉
止プラグがねじ込まれている。閉止プラグは、ポリエチ
レン、ポリブチレン、ポリ塩化ビニルなどの成形品であ
り、器具接続継手の開口ネジ部にねじ込まれるようにネ
ジが付いていて、各器具接続部開口を水密に閉止するよ
うにOリングがついている。器具接続継手は水栓などと
同様に銅合金で作られることが多く、これに付けられる
閉止プラグが樹脂成形品の場合、閉止プラグは繰り返し
使えるものではなく、一回使えれば十分である。The end of the water distribution pipe opposite the header is
Water sink / hot water tap for kitchen sink, water / hot water tap for bath, water / hot water tap for vanity, flush adapter for connecting to flush of toilet or washing machine or fitting connection fitting such as flush elbow In order to prevent foreign matter from entering the opening screw portion of these appliance connection joints during transportation and construction, a closing plug is screwed. The closure plug is a molded product of polyethylene, polybutylene, polyvinyl chloride, etc. It has a screw that can be screwed into the opening screw part of the instrument connection joint, and it is an O-ring to close the instrument connection part opening in a watertight manner. Is attached. Equipment connection joints are often made of copper alloys like water taps, and if the closure plug attached to this is a resin molded product, the closure plug is not a reusable one, but it is sufficient to use it once.
【0014】配水用ヘッダーの配水口に所定長さの配水
パイプを取り付け、そのパイプの他端に継手を取り付け
その継手の開口を閉止プラグで閉止して配管組立品とし
たものの内部に流体の圧力を掛けて漏れ試験を行う。漏
れ試験に合格した配管組立品をプレハブ住宅ユニットに
取り付け配管を行い、再度配管内に流体の圧力を掛けて
漏れ試験をする。閉止プラグを各継手の開口から取り外
して、その部分に水栓等の器具を取り付ける。漏れ試験
は配水用ヘッダーの受水口に流体の圧力を掛けるための
配管及び圧力計を接続し、所定の圧力を加えある時間経
過した後の圧力の変化によって漏れの有無を知ることが
出来る。配水用ヘッダーの受水口に代えて、配水口に接
続した配水パイプのうちの1本を介して配水用ヘッダー
内に流体の圧力を掛けることもできる。A water distribution pipe of a predetermined length is attached to the water distribution port of the water distribution header, a fitting is attached to the other end of the pipe, and the opening of the fitting is closed with a closing plug to form a piping assembly. And perform a leak test. The piping assembly that passed the leak test is attached to the prefabricated housing unit, piped, and fluid pressure is applied to the pipe again to perform the leak test. Remove the closure plug from the opening of each fitting and attach a faucet or other device to that part. In the leak test, a pipe for applying a fluid pressure and a pressure gauge are connected to the water inlet of the water distribution header, and the presence or absence of a leak can be known by a change in the pressure after a predetermined time is applied. Instead of the water receiving port of the water distribution header, the pressure of the fluid can be applied to the water distribution header through one of the water distribution pipes connected to the water distribution port.
【0015】[0015]
【作用】本発明により、配管組立品を製作したときに、
その継手部の開口に閉止プラグを付けて、その後の取扱
い及び漏れ試験をするので、その取扱いの途中での配管
内へのほこり、異物の侵入の恐れがない。また、配管組
立品を組み立てたときに漏れ試験をするので、配管の後
で漏れが発生する可能性が大幅に小さくなった。住宅を
組み立てた後で閉止プラグを取り外して水栓等の器具を
取り付けるが、この取り外した閉止プラグはそこで処分
しても良い。According to the present invention, when a pipe assembly is manufactured,
Since a closing plug is attached to the opening of the joint and the subsequent handling and leakage test are performed, there is no risk of dust or foreign matter entering the piping during the handling. Also, since the leak test is performed when the pipe assembly is assembled, the possibility of leakage occurring after the pipe is greatly reduced. After assembling the house, the closure plug is removed and a device such as a faucet is attached, but the removed closure plug may be disposed of there.
【0016】[0016]
【実施例】図1は、本発明に従って配管用部材の組立品
1を組み立てた後で、漏れ試験をしている状況を示す図
である。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 is a diagram showing a situation in which a leak test is conducted after an assembly 1 of a piping member is assembled according to the present invention.
【0017】配管用部材の組立品1は、配水用ヘッダー
11と、その配水口に接続されたパイプ12(例えばポ
リブテンパイプ)、そのパイプの端部に水栓アダプター
13あるいは水栓エルボが取り付けられている。パイプ
の外周には鞘管が管保護のためにはめられており、立ち
上げ部には立ち上げコーナー管15が鞘管の端部に付け
られている。水栓アダプター13、水栓エルボ14の開
口は配管用部材の組立時に図2に示すような閉止プラグ
をねじ込む。ヘッダーの受水口には、水圧や空気圧を組
立品1の内部に加えるための配管が取り付けられて、そ
の内部圧力を圧力ゲージで読めるようになっている。例
えば5Kgの空気圧を掛けて30分経過後の圧力変化を
見て漏れの有るなしを知ることができる。The piping member assembly 1 is provided with a water distribution header 11, a pipe 12 (for example, a polybutene pipe) connected to the water distribution port, and a faucet adapter 13 or a faucet elbow attached to the end of the pipe. ing. A sheath pipe is fitted around the outer periphery of the pipe for pipe protection, and a rising corner pipe 15 is attached to the rising portion at the end of the sheath pipe. The openings of the faucet adapter 13 and the faucet elbow 14 are screwed with a closing plug as shown in FIG. 2 when the pipe member is assembled. A pipe for applying water pressure or air pressure to the inside of the assembly 1 is attached to the water inlet of the header, and the internal pressure can be read by a pressure gauge. For example, by applying an air pressure of 5 kg, it is possible to know whether or not there is a leak by looking at the pressure change after 30 minutes have passed.
【0018】工場でこのような配管用部材の組立品を組
み立てた上で、図3に示すようにヘッダーブラケット
3、配水湯用ヘッダー11、16を外にしてパイプを巻
き取る。巻き取った組立品を、配管施工を行うところに
送る。配管工事を行う場所としては、集合住宅のように
規格化された家屋の集まっている工事現場や、プレハブ
住宅の水周りユニットを作っている工場がある。図4
は、プレハブ住宅の水周りユニットの床部分であるが、
ヘッダーブラケット3を床下パネルに取り付けた上、冷
水配管、温水配管を延ばしていく。台所シンクを取り付
けるところには立ち上げコーナー管15を取り付けて、
水栓アダプター13を保持する。同様に、洗面化粧台、
風呂、便所を取り付けるところまでパイプを引き延ばし
て、各水栓アダプターを保持する。引き延ばした管は床
の適当な箇所に固定具、例えばサドルバンドで固定す
る。管の長さが少し長く余る場合には床面上でたるませ
ておけば良い。After assembling such an assembly of piping members in a factory, as shown in FIG. 3, the header bracket 3 and the hot water distribution headers 11 and 16 are removed to wind up the pipe. Send the wound assembly to the place where piping work will be performed. As the place where the plumbing work is done, there are a construction site where standardized houses are gathered like an apartment house, and a factory where a water supply unit of a prefabricated house is made. Figure 4
Is the floor part of the water supply unit of a prefabricated house,
After attaching the header bracket 3 to the underfloor panel, the cold water pipe and the hot water pipe are extended. Attach the start-up corner pipe 15 to the place where the kitchen sink is attached,
Hold the faucet adapter 13. Similarly, a vanity,
Hold each faucet adapter by extending the pipe to the point where the bath or toilet is attached. The stretched tube is secured to a suitable location on the floor with a fixture, such as a saddle band. If the length of the pipe is a little longer, you can slacken it on the floor.
【0019】このように配管したものに、配水用ヘッダ
ーの受水口に、水圧や空気圧をかけるための配管を取り
付けて、漏れ試験を行う。その後、継手に付いている閉
止プラグを取り除いて水栓等の器具をその部分に取り付
ける。A pipe for applying water pressure or air pressure to the water inlet of the water distribution header is attached to the pipe thus constructed, and a leak test is conducted. After that, remove the closure plug attached to the joint and attach a device such as a faucet to the part.
【0020】[0020]
【発明の効果】本発明にしたがって配管することで配管
時間をきわめて短縮することができる。また配管組立品
を組み立てたときに漏れ試験をするので、配管後に漏れ
が発生する可能性が大幅に小さくなった。閉止プラグは
使い捨てにすることが出来るので回収の必要がない。The piping time can be extremely shortened by piping according to the present invention. Also, since the leak test is performed when the pipe assembly is assembled, the possibility of a leak occurring after the pipe is significantly reduced. The closure plug can be disposable and does not need to be retrieved.
【図1】 本発明にしたがって配管の組立品の漏れ試験
をしている図。FIG. 1 is a diagram of a leak test of a piping assembly according to the present invention.
【図2】 本発明に使用する閉止プラグの正面図。FIG. 2 is a front view of a closing plug used in the present invention.
【図3】 本発明の配管用部材の組立品を巻き取ったも
のの側面図。FIG. 3 is a side view of a rolled up assembly of the piping member of the present invention.
【図4】 本発明に従って配管の組立品を用いて配管し
た例の斜視図。FIG. 4 is a perspective view of an example of piping using an assembly of piping according to the present invention.
11,16 ヘッダー 12,17 管 13 継手 11,16 Header 12,17 Pipe 13 Joint
Claims (1)
所定長さの可撓性のある材料で出来た配水パイプを取り
付け、各パイプの他端には継手を取り付けて配管組立品
となし、この配管組立品の各継手の開口に閉止プラグを
取り付け、配管組立品の内部に流体の圧力を加えて漏れ
試験を行い、この配管組立品をプレハブ住宅ユニットに
取り付け配管を行い、その後配管内に流体圧力を加えて
漏れ試験を行った後で、閉止プラグを継手の開口から取
り外して、その部分に水栓等の器具を取り付けることを
特徴とする配管方法。1. A water distribution pipe made of a flexible material of a predetermined length is attached to each of a plurality of water distribution ports of a water distribution header, and a joint is attached to the other end of each pipe to form a piping assembly. , Install a closing plug in the opening of each fitting of this piping assembly, apply a fluid pressure to the inside of the piping assembly to perform a leak test, mount this piping assembly to a prefabricated housing unit, and perform piping, then After performing a leak test by applying fluid pressure to the pipe, the closing plug is removed from the opening of the joint, and a device such as a water faucet is attached to the portion.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8431294A JPH07293745A (en) | 1994-04-22 | 1994-04-22 | Method for piping |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8431294A JPH07293745A (en) | 1994-04-22 | 1994-04-22 | Method for piping |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH07293745A true JPH07293745A (en) | 1995-11-10 |
Family
ID=13826993
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP8431294A Pending JPH07293745A (en) | 1994-04-22 | 1994-04-22 | Method for piping |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH07293745A (en) |
-
1994
- 1994-04-22 JP JP8431294A patent/JPH07293745A/en active Pending
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US5653254A (en) | Housing for angle stop valve for connection to hot and cold water supply line and sink faucets | |
| JP2011516762A (en) | Flexible drain trap | |
| JP6856476B2 (en) | How to maintain the drain hose connection adapter, air conditioning system, and drain piping | |
| KR100782676B1 (en) | Wall embedded faucet connection system | |
| MX2010008107A (en) | Device for mounting an connecting sanitary equipment pipes provided being a wall and corresponding method. | |
| JP3653350B2 (en) | Water heater | |
| JPH07158128A (en) | Built-up product of piping member and piping method thereof | |
| EP0521885B1 (en) | Apparatus for preventing water damage due to plumbing leaks in buildings | |
| US20130269794A1 (en) | Shower and tub fixture insert | |
| JP2001207490A (en) | Water supply apparatus | |
| JPH11210031A (en) | Method for laying water supply-drain pipe and piping device | |
| JPH1194170A (en) | Piping header and piping unit | |
| JP2601678B2 (en) | Fixing device for piping end | |
| JP3687810B2 (en) | Water heater | |
| JPH09296487A (en) | Leakage detection structure for flexible piping for hot and cold water supply | |
| JPH0420619A (en) | Tap box | |
| JP4141157B2 (en) | Piping fixing structure | |
| JP2002266390A (en) | Installation method for water supply socket to existing house | |
| JP3945726B2 (en) | How to update dwelling piping | |
| JP2001207488A (en) | Bathroom water and hot water supply piping system | |
| JP2004084401A (en) | Water supply / hot water supply piping unit and its construction method | |
| JPH02248792A (en) | Anticorrosive joint for faucet/gas plug | |
| FI78332C (en) | Junction box. | |
| JPH01224590A (en) | Arrangement of fluid tube and terminal fixing device for fluid tube used therefor | |
| JPH0420618A (en) | Tap box for sleeve pipe construction |