JPH0730748Y2 - Earth retaining frame - Google Patents

Earth retaining frame

Info

Publication number
JPH0730748Y2
JPH0730748Y2 JP13851388U JP13851388U JPH0730748Y2 JP H0730748 Y2 JPH0730748 Y2 JP H0730748Y2 JP 13851388 U JP13851388 U JP 13851388U JP 13851388 U JP13851388 U JP 13851388U JP H0730748 Y2 JPH0730748 Y2 JP H0730748Y2
Authority
JP
Japan
Prior art keywords
frame
locking
frame body
holding
bodies
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP13851388U
Other languages
Japanese (ja)
Other versions
JPH0262926U (en
Inventor
知 三橋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP13851388U priority Critical patent/JPH0730748Y2/en
Publication of JPH0262926U publication Critical patent/JPH0262926U/ja
Application granted granted Critical
Publication of JPH0730748Y2 publication Critical patent/JPH0730748Y2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

【考案の詳細な説明】 (産業上の利用分野) この考案は、地面の掘削作業の際に崩壊事故を防止する
為に使用する土留枠に関する。
DETAILED DESCRIPTION OF THE INVENTION (Industrial field of application) The present invention relates to a retaining frame used to prevent a collapse accident during excavation work on the ground.

(従来技術) 従来、地面の掘削作業の際には、木矢板を地面に建込み
ながら掘削を行ない、掘削深さの進行に伴って上記木矢
板の側面を角材等で支えながら腹起こしを行ない、上記
木矢板と角材とを釘により固定しながら順次掘削を行な
っていた。
(Prior Art) Conventionally, during excavation work on the ground, excavation is performed while building a wooden sheet pile on the ground, and with the progress of the excavation depth, the side surface of the wooden sheet pile is supported by a timber or the like to raise the belly. , The wood sheet pile and the timber were fixed by nails, and the excavation was sequentially performed.

(考案が解決しようとする問題点) しかし、上記したように木矢板と角材を使用した掘削溝
サポート作業は作業者が掘削溝内に入った状態で行なわ
れる。その作業は面倒で手間がかかる上に、釘打ちが確
実に行なわれていないと、地面が緩んで崩壊事故を招
き、掘削溝内にて作業を行なっていた作業者が生き埋め
になる危険があった。
(Problems to be solved by the invention) However, as described above, the excavation groove support work using the wood sheet pile and the square timber is performed while the operator is in the excavation groove. The work is tedious and time-consuming, and if nailing is not done securely, the ground loosens, causing a collapse accident, and there is a risk that workers who were working in the trench will be buried. It was

本考案の目的は、掘削作業と平行しながら簡単且つ安全
に設置することのできる土留枠を提供することにある。
An object of the present invention is to provide an earth retaining frame which can be installed easily and safely in parallel with excavation work.

(問題点を解決する為の手段) 上記した課題を解決する為に本考案は、枠体を、略四角
形状のパネル状に形成すると共に、その上辺両端部の角
部における枠体表面側と側面側とにわたり、枠体同士を
上下に積み重ねた際の上方に位置する枠体下辺両端部を
係止するための係止ガイドを突設して構成し、且つ、2
枚の上記枠体の表面側を互いに対向させ、その枠体同士
の両側辺部間にわたって保持パイプを着脱自在に架設す
ることにより両枠体を所定の間隔を置いて保持してなる
ものである。
(Means for Solving the Problems) In order to solve the above-mentioned problems, the present invention forms a frame into a panel shape of a substantially quadrangular shape, and at the same time, with respect to the frame body surface side at the corners of both ends of the upper side. It is configured by projecting locking guides for locking both end portions of the lower side of the frame body located above when the frame bodies are vertically stacked over the side surface side.
The front sides of the above-mentioned frame bodies are opposed to each other, and a holding pipe is detachably installed between both side portions of the frame bodies so that both frame bodies are held at predetermined intervals. .

また、上記係止ガイドの表面側の側面に挿通孔を開穿す
ると共に枠体の下辺両端部の表面側に、枠体同士を上下
に積み重ねた際に下方に位置する枠体の上記挿通孔に連
通する係止孔を開穿し、枠体同士を上下に積み重ねた
際、上記挿通孔と係止孔とに係止ピンを貫通して両枠体
を連結することができる。
In addition, an insertion hole is opened in the side surface on the front surface side of the locking guide, and the insertion hole of the frame body located below when the frame bodies are vertically stacked on the front surface side of both ends of the lower side of the frame body. When the locking holes communicating with the above are opened and the frame bodies are vertically stacked, the locking pins can be passed through the insertion holes and the locking holes to connect both frame bodies.

更に、枠体表面側における両側辺部の略中央部に、保持
パイプの端部を横方向からスライド自在に挿入する保持
溝を有する保持部を設け、保持パイプ端部を該保持部の
保持溝に係合させることにより保持パイプを対向する枠
体間に着脱自在に架設するようにするとよい。
Further, a holding portion having a holding groove into which the end portion of the holding pipe is slidably inserted from the lateral direction is provided at substantially central portions of both side portions on the surface side of the frame body, and the holding pipe end portion is provided with the holding groove of the holding portion. It is preferable that the holding pipe is detachably installed between the opposing frame bodies by engaging with each other.

また、枠体は、両側辺を角形鋼管で構成し、上下辺を溝
形鋼で構成すると共に、上下左右辺間の隙間部分にデッ
キプレートをはめ込んでなるようにするとよい。
Further, it is preferable that the frame body has rectangular steel pipes on both sides, grooved steel on the upper and lower sides, and a deck plate fitted in a gap between the upper, lower, left, and right sides.

(作用) 以上の手段によれば、2枚の枠体の両側辺部間にわたっ
て保持パイプを架設するだけで、両枠体は保持パイプに
より所定の間隔を置いて対向した状態で保持される。そ
して、このように組み立てた土留枠を掘削した溝穴内に
設置すると、両枠体によって掘削溝の壁面が支えられ、
崩壊が防止される。
(Operation) According to the above means, the holding pipes are installed over the both side portions of the two frame bodies, and the two frame bodies are held by the holding pipes in a state of being opposed to each other at a predetermined interval. And when the soil retaining frame assembled in this way is installed in the excavated slot, the wall surface of the excavation groove is supported by both frame bodies,
Collapse is prevented.

また、掘削が深くなる場合には、溝穴内に設置した土留
枠の各枠体の上に別の土留枠の枠体を載せ、下方に位置
する土留枠の枠体上辺両端部に突設する係止ガイドによ
って上方に位置する土留枠の枠体下辺両端部を係止させ
る。これにより上下の土留枠同士は係止ガイドによって
適正に位置決めされて積み重ねられる。
When the excavation becomes deeper, another frame of the soil retaining frame is placed on each frame of the soil retaining frame installed in the slot, and it is projected at both ends of the upper side of the frame of the soil retaining frame located below. By the locking guide, both ends of the lower side of the frame of the soil retaining frame located above are locked. As a result, the upper and lower soil retaining frames are properly positioned and stacked by the locking guide.

更に、掘削溝穴が延長される場合には、上記土留枠を溝
穴内において隣合わせに設置することにより溝穴の長さ
に合わせて土留枠を延長することができる。
Further, when the excavation slot is extended, the soil retaining frames can be extended according to the length of the slot by installing the soil retaining frames next to each other in the slot.

(実施例) 以下本考案の一実施例を図面に基づいて説明する。Embodiment An embodiment of the present invention will be described below with reference to the drawings.

土留枠aは、2枚の枠体1,1の表面側を対向させ、これ
ら枠体1,1の両側辺部間にわたって2本の保持パイプ2,2
を着脱自在に架設することにより構成する。
The earth retaining frame a has two frame bodies 1 and 1 with their front surfaces facing each other, and has two holding pipes 2 and 2 extending between both side portions of the frame bodies 1 and 1.
It is configured by erection of the detachable.

枠体1は、第1図に示すように、横長四角形状のパネル
状に形成し、その上下両辺部を軽量溝形鋼1aにより、左
右両側辺と横通材とを角形鋼管1bにより構成すると共
に、上下両辺の軽量溝形鋼1aに沿って山形鋼1dを取付け
固定し、この上下山形鋼1d間にわたって多数の縦通材1c
を等間隔をおいて縦通させてあり、各縦通材1cの間には
デッキプレート1eをはめ込んで隙間を塞いである。
As shown in FIG. 1, the frame 1 is formed in a horizontally long rectangular panel shape, and the upper and lower sides of the frame 1 are made of lightweight grooved steel 1a, and the left and right sides of the frame 1 are made of square steel pipes 1b. At the same time, the angle steel 1d is attached and fixed along the lightweight channel steels 1a on both upper and lower sides.
Are longitudinally arranged at equal intervals, and a deck plate 1e is fitted between the longitudinal members 1c to close the gap.

該枠体1の表面側の両側辺部の略中央位置には、第1図
に示すように前記保持パイプ2を保持するための保持部
3を設けてある。保持部3は第5図にて示すように、四
角形状の当板3aの外側一側及び上下両側の3辺に断面L
形の山形鋼3bを固着することにより、その内部に枠体1
中央へ向けて開口する保持溝3cを形成してある。
As shown in FIG. 1, a holding portion 3 for holding the holding pipe 2 is provided at substantially central positions of both side portions on the front surface side of the frame body 1. As shown in FIG. 5, the holding portion 3 has a cross section L on one side on the outer side of the rectangular contact plate 3a and on three sides on both upper and lower sides.
By fixing the angle-shaped angle steel 3b, the frame 1
A holding groove 3c that opens toward the center is formed.

一方、保持パイプ2の両端には上記保持溝3c内に対して
着脱自在に挿入する保持板4が取付固定してある。そし
て、上記保持板4を上記保持溝3c内に横方向からスライ
ド状に挿入することにより保持パイプ2の両端が両枠体
1,1の側辺部に係止され、その結果、2枚の枠体1,1が所
定の間隔(保持パイプ2の長さ)を置いて対向した状態
で保持される。したがって、保持パイプ2は掘削溝孔の
幅と略同じ長さをもって形成する。
On the other hand, holding plates 4 are detachably inserted into the holding groove 3c at both ends of the holding pipe 2 and fixed. Then, by inserting the holding plate 4 into the holding groove 3c from the lateral direction in a slidable manner, both ends of the holding pipe 2 are fixed to both frame members.
As a result, the two frame bodies 1 and 1 are held in a state of being opposed to each other with a predetermined gap (length of the holding pipe 2) therebetween. Therefore, the holding pipe 2 is formed to have a length that is substantially the same as the width of the digging slot.

枠体1の上辺両端部の角部には、土留枠a同士を上下に
積み重ねた際の上方に位置する土留枠aの枠体1の下辺
両端部を係止するための係止ガイド5,5を各々突設して
ある。
At the corners of both ends of the upper side of the frame body 1, locking guides 5 for locking both ends of the lower side of the frame body 1 of the soil retaining frame a located above when the soil retaining frames a are vertically stacked, 5 are projected.

係止ガイド5は、第2図及び第4図にて示すように、枠
体1上辺の表面側に宛てられる板5aと枠体1側面側に宛
てられる板5bとで断面L字形に形成され、その表面側に
面する板5aには挿入孔5cを開穿してある。
As shown in FIGS. 2 and 4, the locking guide 5 is formed in an L-shaped cross section by a plate 5a directed to the surface side of the upper side of the frame 1 and a plate 5b directed to the side surface of the frame 1. An insertion hole 5c is opened in the plate 5a facing the front surface side.

また、枠体1の下辺両端部、即ち、左右両側辺の角形鋼
管1bの下部の表面側には、枠体1同士を上下に積み重ね
た際に下方に位置する枠体1の係止ガイド5における上
記挿通孔5cに連通する鍵孔状の係止孔7を開穿してあ
る。
Further, at both end portions of the lower side of the frame body 1, that is, on the lower surface sides of the rectangular steel pipes 1b on both the left and right sides, the locking guides 5 of the frame body 1 positioned below when the frame bodies 1 are vertically stacked. A keyhole-shaped locking hole 7 communicating with the insertion hole 5c is opened.

上記挿通孔5c及び係止孔7は土留枠a同士を上下に積み
重ねた際に連通し、両孔5a,7に係止ピン6を貫通するこ
とにより上下の土留枠a同士の連結状態を一層確実なも
のとする。
The insertion hole 5c and the locking hole 7 communicate with each other when the soil retaining frames a are stacked vertically, and the locking pin 6 is penetrated through both holes 5a, 7 to further connect the upper and lower soil retaining frames a. Make sure.

係止ピン6は第3図の如く丸棒の周面一側に係止片6aを
長さ方向の一直線上に2枚突設して側面視略凹状に構成
し、枠体1を上下に積み重ねた際に、その係止ピン6を
下方に位置する枠体1における前記係止ガイド5の挿入
孔5c内及び上方に位置する枠体1における角形鋼管1bの
係止孔7に挿入した後、回転して一つの係止片6aを係止
孔7の周囲に掛止できるように構成されている。
As shown in FIG. 3, the locking pin 6 has two locking pieces 6a on one side of the circumferential surface of the round bar so as to project in a straight line in the length direction to form a substantially concave shape in a side view. After stacking the locking pins 6 into the insertion holes 5c of the locking guides 5 in the frame body 1 located below and into the locking holes 7 of the rectangular steel pipes 1b in the frame body 1 located above It is configured so that one locking piece 6a can be rotated and locked around the locking hole 7.

而して、土留枠aは、2枚の枠体1,1の各両側辺部に設
けた保持部3の保持溝3cに対して保持パイプ2両端の保
持板4を横方向からスライド状に挿入して係止すること
により、両枠体1,1が所定の間隔、即ち掘削溝孔の幅と
略同じ間隔を置いて対向した状態で組立られる。
Thus, the soil retaining frame a slides the holding plates 4 at both ends of the holding pipe 2 from the lateral direction with respect to the holding grooves 3c of the holding portions 3 provided on both sides of the two frame bodies 1 and 1. By inserting and locking, both frames 1, 1 are assembled in a state of facing each other at a predetermined interval, that is, at an interval substantially the same as the width of the excavation groove hole.

この土留枠aの組立は地上にて行ない、組み立てた土留
枠aを掘削した溝孔の中に納めて設置する。土留枠aを
掘削した溝穴内に設置すると、対向する枠体1,1によっ
て掘削溝の壁面が内側から支えられ、崩壊が防止され
る。
The soil retaining frame a is assembled on the ground, and the assembled soil retaining frame a is installed in the excavated slot. When the soil retaining frame a is installed in the excavated slot, the wall surfaces of the excavation groove are supported from the inside by the opposing frame bodies 1 and 1, and collapse is prevented.

また、掘削溝孔が深くなる場合には、溝穴内に設置した
土留枠aの上に別の土留枠aを載せる。その際、下方の
土留枠aの枠体1における係止ガイド5の内側に対して
上方の土留枠aにおける枠体1の下辺両端部をはめ込ん
で上方の土留枠aを適正位置にガイドして積み重ねる。
更に、係止ピン6を係止ガイド5に開設した挿入孔5c内
に挿入し、該係止ピン6を回転させ、係止片6aを係止孔
7に係止させれば、土留枠aは二段に積み重ねられ且つ
適正に位置決めされた状態で確実に連結される。
When the excavation slot becomes deep, another soil retaining frame a is placed on the soil retaining frame a installed in the slot. At that time, the both ends of the lower side of the frame 1 of the upper soil retaining frame a are fitted to the inside of the locking guide 5 of the frame 1 of the lower soil retaining frame a to guide the upper soil retaining frame a to a proper position. Stack up.
Further, by inserting the locking pin 6 into the insertion hole 5c formed in the locking guide 5, rotating the locking pin 6 and locking the locking piece 6a in the locking hole 7, the retaining frame a Are stacked in two stages and are securely connected in a properly positioned state.

また、掘削溝穴が延長される場合は、複数の土留枠a同
士を掘削溝孔内において隣合わせに設置することにより
掘削溝の長さに合わせて土留枠aを自由に延長すること
ができる。
Further, when the excavation slot is extended, the soil retaining frames a can be freely extended in accordance with the length of the excavation groove by installing the soil retaining frames a adjacent to each other in the excavation slot.

(考案の効果) 本考案は以上のように構成したものであるから、以下に
列記することき効果を奏する。
(Effects of the Invention) Since the present invention is configured as described above, the following effects are achieved.

個々の土留枠を地上にて組立ることが可能であるか
ら、溝穴を掘削しながら該溝穴内に土留枠を順次設置す
ることが可能であり、また、掘削する溝穴の深さに対応
させて、土留枠同士を適正に位置決めされながら上下方
向に積み重ねて組むことができるので、従来と比較する
と設置作業が大変簡単になり、作業効率を向上させるこ
とができる。
Since each soil retaining frame can be assembled on the ground, it is possible to sequentially install the soil retaining frame in the slot while excavating the slot, and also corresponding to the depth of the slot to be excavated. By doing so, the soil retaining frames can be vertically stacked and assembled while being properly positioned, so that the installation work becomes much simpler and the work efficiency can be improved compared to the conventional case.

したがって、土留枠を設置する際に作業者が溝穴の中に
入る必要がなくなるので、土留枠の設置作業を安全に進
行することができる。
Therefore, when installing the soil retaining frame, it is not necessary for the worker to enter the slot, and thus the installation work of the soil retaining frame can be safely proceeded.

請求項2の土留枠によれば、上下方向に積み重ねた土
留枠同士が互いにずれる心配がなく、両者の連結状態を
一層確実なものとすることができる。
According to the soil retaining frame of the second aspect, there is no concern that the soil retaining frames stacked in the vertical direction are displaced from each other, and the connected state of the both can be made more reliable.

請求項3の土留枠によれば、保持パイプによる両枠体
の保持を容易に行なうことができる。
According to the soil retaining frame of the third aspect, both frame bodies can be easily held by the holding pipe.

請求項4の土留枠によれば、枠体を軽量化し、作業性
及び土留効果を向上させることができる。
According to the soil retaining frame of the fourth aspect, it is possible to reduce the weight of the frame body and improve workability and soil retaining effect.

【図面の簡単な説明】[Brief description of drawings]

第1図は本考案の土留枠を示す正面図、第2図は保持パ
イプで対向保持した土留枠を示す斜視図、第3図(a)
は係止ピンの断面図、第3図(b)は同係止ピンの側面
図、第4図は積重ねた枠体同士の連結部分を示す拡大正
面図、第5図(a)は保持体を示す正面図、第5図
(b)は同保持体の側面図である。 図中 a……土留枠 1……枠体 2……保持パイプ 3……保持部 3c……保持溝 5……係止ガイド 5c……挿入孔 6……係止ピン 7……係止孔 1e……デッキプレート
FIG. 1 is a front view showing the soil retaining frame of the present invention, FIG. 2 is a perspective view showing the soil retaining frame opposed by a retaining pipe, and FIG. 3 (a).
Is a cross-sectional view of the locking pin, FIG. 3 (b) is a side view of the locking pin, FIG. 4 is an enlarged front view showing a connecting portion between stacked frame bodies, and FIG. 5 (a) is a holding body. And FIG. 5 (b) is a side view of the holder. In the figure a …… Soil retaining frame 1 …… Frame 2 …… Holding pipe 3 …… Holding part 3c …… Holding groove 5 …… Locking guide 5c …… Insertion hole 6 …… Locking pin 7 …… Locking hole 1e …… Deck plate

Claims (4)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】枠体を、略四角形状のパネル状に形成する
と共に、その上辺両端部の角部における枠体表面側と側
面側とにわたり、枠体同士を上下に積み重ねた際の上方
に位置する枠体下辺両端部を係止するための係止ガイド
を突設して枠体下辺両端部と係止ガイドの表面側とを連
結可能に構成し、且つ、2枚の上記枠体の表面側を互い
に対向させ、その枠体同士の両側辺部間にわたって保持
パイプを着脱自在に架設することにより両枠体を所定の
間隔を置いて保持してなる土留枠。
1. A frame body is formed in a substantially quadrangular panel shape, and extends over the frame body surface side and side surface side at the corners of the upper side both ends thereof when the frame bodies are stacked vertically. Locking guides for locking both ends of the lower side of the frame body are provided so as to connect the both ends of the lower side of the frame body to the front surface side of the locking guide, and An earth retaining frame in which both front and back sides are opposed to each other and holding pipes are detachably installed over both side portions of the respective frame bodies to hold the both frame bodies at a predetermined interval.
【請求項2】係止ガイドの表面側の側面に挿通孔を開穿
すると共に枠体の下辺両端部の表面側に、枠体同士を上
下に積み重ねた際に下方に位置する枠体の上記挿通孔に
連通する係止孔を開穿し、枠体同士を上下に積み重ねた
際、上記挿通孔と係止孔とに係止ピンを貫通して両枠体
を連結してなる請求項(1)記載の土留枠。
2. An insertion hole is opened in a side surface of a front surface side of the locking guide, and the frame body positioned below the frame bodies is vertically stacked on the surface sides of both end portions of the lower side of the frame body. A method in which both the frame bodies are connected by penetrating a locking pin into the insertion hole and the locking hole when the locking holes communicating with the insertion hole are opened and the frame bodies are stacked vertically. 1) The earth retaining frame described.
【請求項3】枠体表面側における両側辺部の略中央部
に、保持パイプの端部を横方向からスライド自在に挿入
する保持溝を有する保持部を設け、保持パイプ端部を該
保持部の保持溝に係合させることにより保持パイプを対
向する枠体間に着脱自在に架設してなる請求項(1)又
は(2)記載の土留枠。
3. A holding portion having a holding groove into which the end portion of the holding pipe is slidably inserted in the lateral direction is provided at substantially central portions of both side portions on the front surface side of the frame body, and the holding pipe end portion is provided with the holding portion. The soil retaining frame according to claim 1 or 2, wherein the retaining pipe is detachably installed between the opposing frame bodies by engaging with the retaining groove.
【請求項4】枠体は、両側辺を角形鋼管で構成し、上下
辺を溝形鋼で構成すると共に、上下左右辺間の隙間部分
にデッキプレートをはめ込んでなる請求項(1)又は
(2)又は(3)記載の土留枠。
4. The frame body, wherein both sides are made of rectangular steel pipes, upper and lower sides are made of grooved steel, and a deck plate is fitted in a gap between the upper, lower, left and right sides (1) or ( Earth retaining frame described in 2) or (3).
JP13851388U 1988-10-24 1988-10-24 Earth retaining frame Expired - Fee Related JPH0730748Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13851388U JPH0730748Y2 (en) 1988-10-24 1988-10-24 Earth retaining frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13851388U JPH0730748Y2 (en) 1988-10-24 1988-10-24 Earth retaining frame

Publications (2)

Publication Number Publication Date
JPH0262926U JPH0262926U (en) 1990-05-10
JPH0730748Y2 true JPH0730748Y2 (en) 1995-07-19

Family

ID=31400920

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13851388U Expired - Fee Related JPH0730748Y2 (en) 1988-10-24 1988-10-24 Earth retaining frame

Country Status (1)

Country Link
JP (1) JPH0730748Y2 (en)

Also Published As

Publication number Publication date
JPH0262926U (en) 1990-05-10

Similar Documents

Publication Publication Date Title
KR100977206B1 (en) A retaining wall structure for using slide rail and installation method
KR101094827B1 (en) Variable Simple Earth Block Structure
WO2017048056A1 (en) Water barrier-type earth blocking structure for temporary facility and method of constructing same
US3727413A (en) Trench shoring, shuttering and sheeting system
US5669738A (en) Modular trench box sheeting
US5158398A (en) Method and apparatus for an excavation support system for trenches
GB2054692A (en) Fencing system
JP2006070437A (en) Digging earth retaining method and apparatus
KR101219445B1 (en) Construction method for underground wall
KR20230136576A (en) Combined guide unit for sheet pile construction and construction method of sheet pile using it.
JP5976976B1 (en) Slide rail method built-in simple earth retaining method
JP6804034B2 (en) How to build a retaining wall structure
JPH0634423Y2 (en) Guide rail for earth retaining device for excavation trench
JPH0593423A (en) Guide wall constructing pc slab and construction method of guide wall
JPS5849250Y2 (en) Earth retention shoring device for excavated trenches
JPS5847086Y2 (en) Earth retention shoring device for excavated trenches
CN217692583U (en) Installation tool for cable channel firewall
JPS6088725A (en) Sheathing work of excavated trench
JP3587896B2 (en) Foldable sheet pile, belly raising material and installation method of sheet pile
JP4751125B2 (en) Building floor construction method
JPS5910192Y2 (en) Earth retaining piles and iron sheet piles
JPH0637065Y2 (en) Earth retaining device for excavation trench
JPS5840122Y2 (en) Earth retention shoring device for excavated trenches
JPH0711649A (en) Earth retaining method and earth retaining box
JPS5852056B2 (en) Earth retaining device for cloth excavation work

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees