JPH0747846B2 - Pile construction method and its members on soft ground - Google Patents

Pile construction method and its members on soft ground

Info

Publication number
JPH0747846B2
JPH0747846B2 JP16264886A JP16264886A JPH0747846B2 JP H0747846 B2 JPH0747846 B2 JP H0747846B2 JP 16264886 A JP16264886 A JP 16264886A JP 16264886 A JP16264886 A JP 16264886A JP H0747846 B2 JPH0747846 B2 JP H0747846B2
Authority
JP
Japan
Prior art keywords
pile
vertical
tubular body
pile hole
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP16264886A
Other languages
Japanese (ja)
Other versions
JPS6319325A (en
Inventor
洋 高森
裕治 野田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui House Ltd
Original Assignee
Sekisui House Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui House Ltd filed Critical Sekisui House Ltd
Priority to JP16264886A priority Critical patent/JPH0747846B2/en
Publication of JPS6319325A publication Critical patent/JPS6319325A/en
Publication of JPH0747846B2 publication Critical patent/JPH0747846B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Piles And Underground Anchors (AREA)

Description

【発明の詳細な説明】 産業上の利用分野 この発明は、軟弱地盤における杭築造方法並びにその部
材に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing piles on soft ground and members thereof.

従来の技術 軟弱地盤における基礎地業には、いわゆる杭基礎が採用
されることが多い。
Conventional technology So-called pile foundations are often used for basic ground work on soft ground.

この種の杭基礎としては、支持層に打ち込んだ支持杭に
よって上部構造体の荷重を支持するのが一般的である。
しかし、そのような支持杭による杭基礎では、特に広域
地盤沈下地域において、いわゆる抜け上がりの現象があ
るため、最近では地盤中に設置したRC摩擦杭等の既成コ
ンクリート杭体に働く摩擦力を利用する摩擦杭によるも
のが多くなっている。
As a pile foundation of this type, it is general that the load of the upper structure is supported by a support pile driven into the support layer.
However, in the case of pile foundations with such support piles, there is a phenomenon of so-called slip-out, especially in wide-area ground subsidence areas, so recently, the friction force acting on existing concrete piles such as RC friction piles installed in the ground is used. The friction piles are often used.

発明が解決しようとする問題点 しかしながら、上記既成コンクリート杭体の施工には大
型の作業機械を必要とし、しかも上記杭体の施工現場へ
の搬入のために大型トラックを必要とする等、施工コス
トが高くなるのみならず、施工場所によっては実施でき
ない場合があり、汎用性に乏しいという難点がある。更
には、杭体自体による自重が大きいため、それによって
支持力が低下するという問題点がある。
Problems to be Solved by the Invention However, the construction cost of the existing concrete pile body requires a large work machine, and a large truck is required to bring the pile body to the construction site. Not only becomes high, but it may not be possible depending on the construction site, and there is a drawback that it is not versatile. Furthermore, since the weight of the pile itself is large, there is a problem in that the supporting force is reduced.

この発明は、このような問題点に鑑みて、現場施工によ
っても、安価に施工でき、しかも支持力の強い杭を得る
ことを目的として成されたものである。
In view of such a problem, the present invention has been made for the purpose of obtaining a pile that can be constructed at low cost and has a strong supporting force even by on-site construction.

問題点を解決するための手段 すなわち、この発明では、上記目的を達成するために、
地盤に予め杭孔を形成した後、上下方向の中間部分に側
方に突出する複数の節状突出部を有する網状筒体を挿入
して据え付け、しかる後に土材を上記網状筒体の内側に
投入して突き固めるようにしている。
Means for Solving the Problems That is, in the present invention, in order to achieve the above object,
After forming a pile hole in the ground in advance, insert and install a mesh cylinder having a plurality of laterally protruding nodular protrusions in the intermediate portion in the vertical direction, and then install the earth material inside the mesh cylinder. I try to throw it in and tamper with it.

実施例 以下、この発明の好適な実施例を図面を参照して説明す
る。
Embodiments Preferred embodiments of the present invention will be described below with reference to the drawings.

第1図は、この実施例において使用する網状筒体(1)
の一例を示している。この網状筒体(1)は、上下間隔
をおいて略水平面内に配置され、かつ上下方向の複数の
縦筋(2)(2)……によって互いに結合された多数の
フープ筋(3)(3)……と、同じく上下間隔をおいて
略水平面内に配置され、かつ上下方向の複数の縦筋
(4)(4)……によって互いに結合された多数のフー
プ筋(5)(5)……とによって構成されている。略同
一面内において環状に配置された左右一対のフープ筋
(3)(5)は、一端側のヒンジ部(6)を介して互い
に連結されている。両フープ筋(3)(5)の他端側
は、一方のフープ筋(3)を内側にし、他方のフープ筋
(5)を外側にして互いにオーバーラップしている。外
側のフープ筋(5)の先端部分には、内方へ屈曲する係
合部(5a)が設けられている。すなわち、この網状筒体
(1)は、略同一面内に配置されたフープ筋(3)
(5)同士を両者間のヒンジ部(6)を支点として水平
方向に回動させることにより、他端側のオーバーラップ
部分の長さが変化して、両フープ筋(3)(5)によっ
て形成される環状部分が半径方向に拡張するようになっ
ている。
FIG. 1 shows a mesh cylinder (1) used in this embodiment.
Shows an example. This reticulated tubular body (1) is arranged in a substantially horizontal plane at a vertical interval and is connected to each other by a plurality of vertical streaks (2) (2). 3) ..., and a large number of hoop muscles (5) (5), which are also arranged in a substantially horizontal plane at vertical intervals and are connected to each other by a plurality of vertical stripes (4) (4). ...... is composed of and. The pair of left and right hoop muscles (3) and (5), which are annularly arranged in substantially the same plane, are connected to each other via a hinge portion (6) on one end side. The other end sides of both hoop muscles (3) and (5) overlap each other with one hoop muscle (3) inside and the other hoop muscle (5) outside. An engaging portion (5a) that bends inward is provided at the tip of the outer hoop muscle (5). That is, the reticulated tubular body (1) has hoop muscles (3) arranged substantially in the same plane.
(5) By horizontally rotating the hinges (6) between them as a fulcrum, the length of the overlapping portion on the other end side is changed, and both hoop muscles (3) (5) The annular portion formed is adapted to expand radially.

また、この網状筒体(1)では、上下方向の中間部分に
おける適当な一対のフープ筋(3)(5)を、ほかのも
のよりも一回り大きくして同心円状に設けることによ
り、側方に突出する節状突出部(7)を設けている。こ
のような節状突出部(7)(7)…が、上下方向に適宜
間隔をおいて設けられている。なお、この網状筒体
(1)は、樹脂製としてもよく、あるいは鉄線を網状に
形成したものでもよい。
In addition, in this reticulated cylindrical body (1), a pair of suitable hoop muscles (3) and (5) in the middle part in the vertical direction are provided one by one larger than the other ones so as to form concentric circles. A nodular protrusion (7) is provided to protrude to the. Such nodal protrusions (7) (7) ... Are provided at appropriate intervals in the vertical direction. The reticulated tubular body (1) may be made of resin, or may be a reticulated iron wire.

次に、この発明の施工手順を、第2図(A)〜(D)を
参照して説明する。
Next, a construction procedure of the present invention will be described with reference to FIGS. 2 (A) to (D).

まず、オーガー(8)等を用いて地盤(9)を掘削し、
所定の位置に適当な深さの杭孔(10)を形成する(第1
図(A)参照)。
First, excavate the ground (9) using an auger (8),
Form a pile hole (10) of appropriate depth at a predetermined position (first
See FIG.

次いで、そのようにして予め削孔した杭孔(10)の内部
に、前記の網状筒体(1)を挿入して据え付ける(第1
図(B)参照)。その際、網状筒体(1)は、第3図に
示すように、各ヒンジ部(6)(6)……を支点として
内側へ丸め込み、全体に差し渡しを小さくした状態で上
記の杭孔(10)に挿入する。このように、網状筒体
(1)を構成する一対のフープ筋(3)(5)をヒンジ
部(6)を介して各々連結したことにより、網状筒体
(1)の差し渡しを簡単に変更することができ、それに
よって杭孔(10)への挿入を容易に行なえることができ
ることになる。
Then, the reticulated cylindrical body (1) is inserted into the inside of the pile hole (10) thus preliminarily drilled and installed (first).
See FIG. At that time, as shown in FIG. 3, the mesh tube body (1) is rolled inward with each hinge part (6) (6) ... as a fulcrum, and the pile hole ( Insert into 10). In this way, by connecting the pair of hoop muscles (3) and (5) constituting the reticulated tubular body (1) via the hinge portion (6), the delivery of the reticulated tubular body (1) can be easily changed. Therefore, the insertion into the pile hole (10) can be easily performed.

しかる後に、網状筒体(1)上端の開口部分から適量の
土材(11)を投入する。この土材(11)としては、固化
剤を添加した土、切込み砂利、クラッシャーラン等を用
いる。そして、その土材(11)表面を突棒(12)等によ
って繰り返し打撃することによって充分に突き固める
(第2図(C)参照)。そうすると、土材(11)が打撃
力によって締め固められると同時に、打撃部分に近いと
ころの網状筒体(1)には、土材(11)を介して側方へ
の拡張力が作用する。したがって、当該部分の網状筒体
(1)においては、第4図に示すように、フープ筋
(3)(5)同士がオーバーラップ部分が少なくなるこ
とによって半径外方向に拡がり、それによって差し渡し
が大きくなって杭孔(10)壁面に密着する。その際、地
盤条件にもよるが、一回り外径の大きい節状突出部
(7)は杭孔(10)壁面に食い込むことになる。なお、
フープ筋(3)(5)同士は、一方のフープ筋(5)に
設けた前記の係合部(5a)が、他方のフープ筋(3)と
一体となった1本の縦筋(2)に係合することにより、
互いに分離することがない。
After that, an appropriate amount of earth material (11) is put in through the opening at the upper end of the mesh cylinder (1). As the soil material (11), soil to which a solidifying agent is added, cut gravel, crusher run, or the like is used. Then, the surface of the soil material (11) is struck sufficiently with the projecting rod (12) and the like to be sufficiently struck (see FIG. 2 (C)). Then, the soil material (11) is compacted by the striking force, and at the same time, a lateral expansive force acts on the reticulated tubular body (1) near the striking portion via the soil material (11). Therefore, in the net-like tubular body (1) of the relevant portion, as shown in FIG. 4, the hoop streaks (3) and (5) expand outward in the radial direction due to the reduced overlapping portion, and thereby the hand-over is performed. It grows and sticks to the wall of the pile hole (10). At that time, although depending on the ground conditions, the nodular protrusions (7) having a slightly larger outer diameter bite into the wall surface of the pile hole (10). In addition,
As for the hoop muscles (3) and (5), the one engaging portion (5a) provided on one hoop muscle (5) is integrated with the other hoop muscle (3) to form a single longitudinal muscle (2). ) By engaging
Never separate from each other.

そして、上記のような作業、すなわち土材(11)を投入
しては突き固めるという作業を繰り返すことにより、深
さ方向において側方に突出する突起(13)(13)……を
有する土杭(14)が築造される(第2図(D)参照)。
Then, by repeating the above work, that is, the work of charging the soil material (11) and solidifying it, the soil pile having the projections (13) (13) ... Which project laterally in the depth direction. (14) is built (see Fig. 2 (D)).

そうして、例えば第5図に示すように、上記の手順で施
工した複数の土杭(14)(14)……上部にフーチング
(15)(15)……が設置され、そのフーチング(15)
(15)……上部に上部構造体(16)が建築されることに
なる。その場合に、上記の各土杭(14)の周壁部分に
は、網状筒体(1)の節状突出部(7)(7)……によ
る突起(13)(13)……が、上下方向に複数個節状に形
成されているから、それらの突起(13)(13)……が抵
抗となって摩擦力が大きくなり、前記のフーチング(1
5)を介して作用する上部構造体(16)の荷重を確実に
支持することができる。
Then, as shown in FIG. 5, for example, a plurality of earth piles (14) (14) constructed by the above-mentioned procedure are installed on the upper part of the footings (15) (15). )
(15) …… The upper structure (16) will be built on top. In that case, the protrusions (13) (13) by the nodular protrusions (7) (7) of the reticulated tubular body (1) are vertically arranged on the peripheral wall of each earth pile (14). Since a plurality of nodules are formed in the direction, the protrusions (13) (13) ...
The load of the upper structure (16) acting via 5) can be reliably supported.

発明の効果 以上のように、この発明では、予め削孔した杭孔に網状
筒体を挿入し、しかる後に土材を網状筒体の内側に投入
して杭を築造するため、杭孔壁面の崩壊が防止されて、
目的に応じた形状の土杭を得ることができる。また、網
状筒体に設けた節状突出部により、側方に突出する突起
が確実に形成されるため、それらの突起が抵抗となって
杭孔壁面と土杭との間に大きな摩擦力が生じ、それによ
って支持力が増強されるという効果がある。しかも、前
記の突起による抵抗によって支持力が大きくなるから、
全長を長くする必要がなくなり、ハンドオーガーやトラ
ックオーガー等のように中小型の作業機器で削孔作業を
行なうことができ、汎用的に実施することが可能とな
る。更には、この発明では土材によって杭体を形成する
ため、従来のような既成コンクリート製摩擦杭と異なり
工事費用が低減されだけでなく、杭体自体の自重が少な
くて済むから、超軟弱地盤にも実施することができる。
Effects of the Invention As described above, in the present invention, the mesh cylinder is inserted into the preliminarily drilled pile hole, and then the earth material is put inside the mesh cylinder to build the pile, so that the pile hole wall surface Is prevented from collapsing,
It is possible to obtain a clay pile having a shape according to the purpose. In addition, the nodular protrusions provided on the net-like tubular body reliably form the protrusions projecting laterally, and these protrusions act as a resistance to generate a large frictional force between the pile hole wall surface and the earth pile. This has the effect of increasing the bearing capacity. Moreover, since the supporting force increases due to the resistance of the protrusions,
It is not necessary to lengthen the entire length, and it is possible to perform drilling work with a small-to-medium-sized working device such as a hand auger or a truck auger, and it becomes possible to carry out a general-purpose work. Further, in the present invention, since the pile body is formed by the soil material, unlike the conventional concrete concrete friction pile, not only the construction cost is reduced, but also the self-weight of the pile body itself is small, so that the super soft ground Can also be implemented.

【図面の簡単な説明】[Brief description of drawings]

第1図は、この発明において使用する網状筒体の一例を
示す全体斜視図、第2図(A)から(D)は、この発明
の施工手順を示す概略断面図、第3図は、第2図(B)
において、杭孔に網状筒体を挿入した状態を示す横断面
図、第4図は、同じく第2図(C)において、網状筒体
が拡大した状態を示す横断面図、第5図は、この発明を
実施した地盤上に上部構造体を構築した状態を示す概略
図である。 (1)……網状筒体、(2)(4)……縦筋、(3)
(5)……フープ筋、(7)……節状突出部、(9)…
…地盤、(10)……杭孔、(11)……土材。
FIG. 1 is an overall perspective view showing an example of a mesh cylinder used in the present invention, FIGS. 2 (A) to (D) are schematic cross-sectional views showing a construction procedure of the present invention, and FIG. Figure 2 (B)
In Fig. 4, a cross-sectional view showing a state in which the net-like tubular body is inserted into the pile hole, Fig. 4 is a cross-sectional view showing a state in which the net-like tubular body is enlarged in Fig. 2 (C), and Fig. 5 is It is the schematic which shows the state which built the upper structure on the ground which implemented this invention. (1) ... Mesh tube, (2) (4) ... Vertical streaks, (3)
(5) …… Hoop streak, (7) …… Nodular protrusion, (9)…
… Ground, (10) …… Pile hole, (11) …… Soil material.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】地盤に予め杭孔を形成した後、上下方向の
中間部分に側方に突出する複数の節状突出部を有する網
状筒体を上記の杭孔に挿入して据え付け、しかる後に土
材を上記網状筒体の内側に投入して突き固めることを特
徴とする軟弱地盤における杭築造方法。
1. After preliminarily forming a pile hole in the ground, a net-like tubular body having a plurality of laterally projecting nodular protrusions at an intermediate portion in the up-down direction is inserted into the pile hole and installed, after which A method of constructing a pile in soft ground, which comprises pouring earth material into the mesh tubular body and solidifying it.
【請求項2】杭孔に挿入して据え付けるものであって、
上下間隔をおいて略水平面内に配置され、かつ上下方向
の縦筋によって互いに連結された複数のフープ筋と、同
じく上下間隔をおいて略水平面内に配置され、かつ上下
方向の縦筋によって互いに連結された複数のフープ筋と
を、半径方向に拡張可能な状態で概略中空円筒形状に連
結するとともに、上下方向の中間部分には、側方に突出
する複数の節状突出部を適宜間隔をおいて設けたことを
特徴とする網状筒体。
2. A device for inserting and installing in a pile hole,
A plurality of hoops arranged in a substantially horizontal plane with a vertical spacing and connected to each other by vertical streaks, and a plurality of hoops also arranged in a substantially horizontal plane with a vertical spacing, and with each other by vertical vertical streaks The plurality of connected hoop muscles are connected to each other in a substantially hollow cylindrical shape in a state in which they can be expanded in the radial direction, and a plurality of laterally projecting nodal projections are provided at appropriate intervals in the vertical middle portion. A reticulated tubular body characterized by being provided in advance.
JP16264886A 1986-07-09 1986-07-09 Pile construction method and its members on soft ground Expired - Fee Related JPH0747846B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16264886A JPH0747846B2 (en) 1986-07-09 1986-07-09 Pile construction method and its members on soft ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16264886A JPH0747846B2 (en) 1986-07-09 1986-07-09 Pile construction method and its members on soft ground

Publications (2)

Publication Number Publication Date
JPS6319325A JPS6319325A (en) 1988-01-27
JPH0747846B2 true JPH0747846B2 (en) 1995-05-24

Family

ID=15758615

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16264886A Expired - Fee Related JPH0747846B2 (en) 1986-07-09 1986-07-09 Pile construction method and its members on soft ground

Country Status (1)

Country Link
JP (1) JPH0747846B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6010311B2 (en) * 2012-03-07 2016-10-19 ケンテック株式会社 Foundation reinforcement structure
CN109707345B (en) * 2018-12-27 2023-09-22 中国水利水电科学研究院 Wall protection net structure to prevent borehole wall collapse and its installation tools and methods

Also Published As

Publication number Publication date
JPS6319325A (en) 1988-01-27

Similar Documents

Publication Publication Date Title
US5039256A (en) Pinned foundation system
JP2010031647A (en) Internal excavation method through pile, and foundation pile structure
US4293242A (en) Piles
EP3178994B1 (en) Methods and apparatuses for compacting soil and granular materials
US4790689A (en) Method and apparatus for producing a support element in the ground
JP3506350B2 (en) Construction method of foundation pile
JPH11280067A5 (en)
JP7007691B1 (en) Casting method for spring spacers, reinforcing bar cages and underground piles
JP3129676B2 (en) Piling columns in building structures using piles as pillars
JPH0747846B2 (en) Pile construction method and its members on soft ground
KR101951684B1 (en) Expandable cast-in-place pile construction method
JP3561228B2 (en) Construction method of steel pipe for concrete composite pile and steel pipe concrete composite pile
JP3858157B2 (en) Construction method of underground structure
JPH0280710A (en) Preparing cast-in-place concrete pile
KR20180082749A (en) Embankment support pile construction method with tube type pile and embankment support pile therewith
JPS61109822A (en) Construction work of pile
JP2017223018A (en) Installation method of foundation pile, foundation pile structure, and double precast pile
JPS61254716A (en) Setting of in-place concrete pile
JP7557911B1 (en) Pole structure and method for installing the same
JPS62268423A (en) Construction work of underground pile used in common for earth anchor
JPH03275806A (en) Method of making knotting pile
JPH01102125A (en) How to drive cast-in-place concrete piles
JPH0359222A (en) Steep slope banking
JP2811436B2 (en) Construction method of earth retaining or fence and concrete block used in the method
JPH04309617A (en) Method for improving foundation ground and device therefor

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees