JPH0749681B2 - Steel frame / reinforced concrete composite construction method - Google Patents

Steel frame / reinforced concrete composite construction method

Info

Publication number
JPH0749681B2
JPH0749681B2 JP11648288A JP11648288A JPH0749681B2 JP H0749681 B2 JPH0749681 B2 JP H0749681B2 JP 11648288 A JP11648288 A JP 11648288A JP 11648288 A JP11648288 A JP 11648288A JP H0749681 B2 JPH0749681 B2 JP H0749681B2
Authority
JP
Japan
Prior art keywords
reinforced concrete
concrete
column
steel frame
pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP11648288A
Other languages
Japanese (ja)
Other versions
JPH01287336A (en
Inventor
義則 村井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP11648288A priority Critical patent/JPH0749681B2/en
Publication of JPH01287336A publication Critical patent/JPH01287336A/en
Publication of JPH0749681B2 publication Critical patent/JPH0749681B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)
  • Joining Of Building Structures In Genera (AREA)

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明は、粱を鉄骨で構成し、柱を鉄筋コンクリートで
構成する鉄骨・鉄筋コンクリート複合構造の建築物を施
工するための構法に関する。
TECHNICAL FIELD The present invention relates to a construction method for constructing a building of a composite structure of steel frame and reinforced concrete, in which the grits are made of steel and the columns are made of reinforced concrete.

「従来の技術」 この種の複合構造の建築物を施工するための構法として
は、現場において柱となる鉄筋を組み立て、さらに、こ
の鉄筋に梁となる鉄骨を固定して組み付けるとともに、
前記鉄筋や仕口部(柱と梁の接合部)の周りに型枠を設
けた後、該型枠の内部にコンクリートを打設することに
より柱と仕口部を形成して建築物の躯体を構築する、と
いうものが従来一般的である。
"Conventional technology" As a construction method for constructing a building of this type of composite structure, assembling a reinforcing bar to be a pillar on the site, and further fixing a steel frame to be a beam to this reinforcing bar and assembling,
After forming a mold around the reinforcing bars and the joint (joint between the column and the beam), the pillar and the joint are formed by placing concrete inside the mold to form the structure of the building. It is common practice to build a.

「発明が解決しようとする課題」 ところが、上記のように構法にあっては、鉄筋や鉄骨を
組み立てた後、コンクリートを打設する部分に型枠を組
み立て、ついで、その型枠の内部にコンクリートを打設
するようにしたものであるので、現場において型枠を組
み立てるための足場や、コンクリートを打設するために
の場所及び設備が必要であるとともに、型枠組み立てや
コンクリート打設のための作業員が多数必要であるこ
と、そのため工期遅延や工費増大の原因となっているこ
と、また、現場においてコンクリートを打設するために
気象条件やその他の諸条件等によって打設コンクリート
の品質のむらができること等の問題点があった。
"Problems to be solved by the invention" However, in the construction method as described above, after assembling the reinforcing bars and the steel frames, the formwork is assembled at the portion where the concrete is placed, and then the concrete is placed inside the formwork. Since it is designed to cast concrete, it is necessary to have a scaffold for assembling the formwork at the site, a place and equipment for placing concrete, as well as for assembling formwork and concrete. The large number of workers is required, which causes the delay in construction period and the increase in construction cost. Moreover, the unevenness of the quality of the placed concrete due to the weather conditions and other various conditions for placing the concrete on site. There was a problem such as what could be done.

本発明は前記問題点の鑑みてなされたもので、鉄骨・鉄
筋コンクリート複合構造の建築物を構築するに当たり、
現場での作業を省力化し得るとともに現場での作業空間
の無駄をなくし、工期短縮や工費低減を図ることがで
き、かつまたコンクリート品質を向上させて構造耐力の
向上を図ることができる有効な構法を提供することを目
的としている。
The present invention has been made in view of the above problems, in constructing a building of a steel frame / reinforced concrete composite structure,
An effective construction method that can save labor on site, eliminate waste of work space on site, shorten construction period and construction cost, and also improve concrete strength to improve structural strength. Is intended to provide.

「課題を解決するための手段」 上記目的を達成するために、本発明は、鉄骨梁を仕口部
材を介して鉄筋コンクリート柱に対して接合することが
躯体が構築される鉄骨・鉄筋コンクリート複合構造の建
築物を施工するための構法であって、前記鉄筋コンクリ
ート柱を、その上下に柱主筋が突出しているプレキャス
トコンクリート部材として予め工場製作しておくととも
に、前記仕口部材を、前記鉄骨梁が接続される梁取付部
材と、該梁取付部材と一体とされて前記鉄筋コンクリー
ト柱の上部に連設されるコンクリート部を有するととと
もに、該コンクリート部には前記鉄筋コンクリート柱の
柱主筋を挿通させる貫通孔が形成されてなぬものとし
て、この仕口部材をプレキャストコンクリート部材とし
て予め工場製作しておき、それから鉄筋コンクリート柱
および仕口部材をそれぞれ現場に搬入し、前記鉄筋コン
クリート柱を立設した後、その上部に突出している柱主
筋を前記貫通孔に挿通させることによって該鉄筋コンク
リート柱の上部に前記仕口部材を載置固定し、該仕口部
材の梁取付部材に前記鉄骨梁を接続することで躯体を構
築することを特徴とするものである。
"Means for Solving the Problem" In order to achieve the above-mentioned object, the present invention is directed to joining a steel beam to a reinforced concrete column via a connection member, and a structure of a steel frame-reinforced concrete composite structure in which a frame is constructed. A construction method for constructing a building, wherein the reinforced concrete column is pre-manufactured in advance as a precast concrete member having column main bars protruding above and below it, and the joint member is connected to the steel beam. A beam mounting member, and a concrete part which is integrated with the beam mounting member and is continuously provided above the reinforced concrete column, and a through hole for inserting a column main bar of the reinforced concrete column is formed in the concrete part. As a matter of course, this joint member was prefabricated in advance as a precast concrete member, and then The cleat column and the joint member are respectively carried into the site, and after the reinforced concrete column is erected, the column main bar protruding above is inserted into the through hole so that the joint member is above the reinforced concrete column. It is characterized by constructing a skeleton by mounting and fixing and connecting the steel beam to the beam attachment member of the connection member.

「作用」 本発明では、プレキャストコンクリート部材として予め
工場製作した鉄筋コンクリート柱を現場に搬入して所定
位置に立設し、その上部に、同じくプレキャストコンク
リート部材として予め製作した仕口部材を載置固定して
一体化い、その仕口部材に対して鉄骨梁を接続すること
で躯体を構築するものであり、したがって現場での型枠
組立作業やコンクリート打設作業が最小限に止まる。
"Operation" In the present invention, a reinforced concrete column manufactured in advance as a precast concrete member is carried into the site and erected at a predetermined position, and a joint member also manufactured in advance as a precast concrete member is placed and fixed on the upper part thereof. The structure is constructed by connecting steel beams to the connection member, and therefore the formwork assembling work and concrete placing work on site can be minimized.

本構法において用いる仕口部材は、鉄骨梁が直接的に接
続される梁取付部材と、その梁取付部材と一体化してい
るコンクリート部を有しており、そのコンクリート部に
形成されている貫通孔に柱主筋が挿通されることで仕口
部材が鉄筋コンクリート柱に対して固定され、したがっ
て、この仕口部材を介して鉄骨梁と鉄筋コンクリート柱
とが構造的に強固に一体化される。
The joint member used in this construction method has a beam attachment member to which a steel beam is directly connected, and a concrete portion integrated with the beam attachment member, and a through hole formed in the concrete portion. The connection member is fixed to the reinforced concrete column by inserting the column main bar into, and therefore, the steel beam and the reinforced concrete column are structurally and firmly integrated through this connection member.

「実施例」 以下、第1図ないし第3図を参照して本発明の実施例を
説明する。第1図は本実施例の構法により構築された鉄
骨・鉄筋コンクリート複合構造の建築物の躯体Aの特に
仕口部の部分を示す側面図、第2図はその平面図であ
る。
[Embodiment] An embodiment of the present invention will be described below with reference to FIGS. 1 to 3. FIG. 1 is a side view showing a portion of a skeleton A of a building having a composite structure of a steel frame and a reinforced concrete constructed by the construction method of this embodiment, particularly a portion thereof, and FIG. 2 is a plan view thereof.

この躯体Aは、内部び主筋1及びこれを補給する帯筋
(図示せず)等が配設された状態で予め工場製作された
プレキャストコンクリート(PC)製の柱2と、その柱2
の主筋1に挿通された状態でその上部に取り付けられた
仕口部材3とから構成されている。
This skeleton A is a column 2 made of precast concrete (PC) which is pre-manufactured in advance in a state in which an inner portion and a main rod 1 and a band (not shown) for supplying the same are arranged, and the column 2.
The connecting member 3 is attached to the upper part of the main bar 1 while being inserted into the main bar 1.

前記柱2は主筋1が柱本体の上下両端から突出するよう
に設けられ、柱2の上部突出す主筋1は、仕口部材3を
貫通してその僅か上方で接続部材(スリーブ継手)4に
よって、上階層の柱2に突出している主筋1と接続され
るようになっており、接続部分の主筋1の周りには、帯
筋5が設けられている。
The pillars 2 are provided so that the main bars 1 project from the upper and lower ends of the pillar body. , Is connected to the main bar 1 projecting to the pillar 2 of the upper layer, and a band 5 is provided around the main bar 1 of the connecting portion.

また、前記仕口部材3は、第2図に示すように、H型鋼
を十字形に組み合わせることにより製作された梁取付部
材7と、この梁取付部材7の側部に取り付けられて、前
記柱2の断面形状と同型状に形成された鋼製の粋体8
と、この粋体8の内部にコンクリートが打設充填される
ことで形成されてたコンクリート部9とからなり、コン
クリート部9には、この仕口部材3を主筋1に取り付け
るための貫通孔10が予め形成されている。そして、上記
の梁取付部材7に、その梁取付部材7と同一断面形状の
H形鋼からなる梁6が補強板11を介してボルト12により
締結されて接続されるようになっている。
Further, as shown in FIG. 2, the connection member 3 is attached to the beam attachment member 7 made by combining H-shaped steels in a cross shape and the side portion of the beam attachment member 7, and the column attachment member 3 is attached. Steel smart body 8 formed in the same shape as the cross-sectional shape of 2
And a concrete portion 9 formed by pouring and filling the inside of the smart body 8 with a through hole 10 for attaching the joint member 3 to the main bar 1. Are formed in advance. A beam 6 made of H-shaped steel having the same cross-sectional shape as the beam mounting member 7 is fastened and connected to the beam mounting member 7 with a bolt 12 via a reinforcing plate 11.

なお、図中符号13はスラブを形成するための型枠を兼ね
た床板である。また、柱2と仕口部材3のコンクリート
部9との接続部14にはグラウト材が充填されるよういな
っている。
Reference numeral 13 in the figure is a floor plate that also serves as a mold for forming a slab. Further, the connection portion 14 between the pillar 2 and the concrete portion 9 of the connection member 3 is filled with grout material.

次に、上記建築物の躯体Aを構築するための作業手順に
ついて説明する。
Next, a work procedure for constructing the building body A of the building will be described.

*まず、工場において柱2及び仕口部材3を予め製作す
る。
* First, the pillar 2 and the connection member 3 are manufactured in advance in the factory.

柱2は、帯筋等によって所定の形状に組まれた主筋1を
その両端部が突出するように型枠(図示せず)内に配置
した後、その型枠の内部にコンクリートを打設すること
によって、PC部材として製作する。
The pillar 2 is arranged in a form (not shown) so that both ends of the main bar 1 assembled into a predetermined shape by a band or the like are arranged, and then concrete is placed inside the form. By doing so, it will be manufactured as a PC member.

また、仕口部材3は、H型鋼を十字形に組み立てて梁取
付部材7とし、この梁取付部材7の外側に梁せいと同じ
高さでかつ柱2の断面形状と同形状に形成された鋼製の
梁体8を固定し、その粋体8の内部にコンクリートを打
設充填してコンクリート部9を形成することで、製作す
る。
Further, the connection member 3 is formed by assembling a H-shaped steel into a cross shape to form a beam attachment member 7, and is formed outside the beam attachment member 7 at the same height as the beam and in the same shape as the cross-sectional shape of the column 2. It is manufactured by fixing the steel beam body 8 and pouring and filling the inside of the smart body 8 to form the concrete portion 9.

なお、柱2や仕口部材3を構成するコンクリートとして
高強度コンクリートや繊維補強コンクリート等を使用す
ることにより、柱2や仕口部材の構造耐力の向上を図る
ことは勿論、前記粋体8内の敵宜の位置に鉄筋を配筋し
たりすることは任意である。
In addition, by using high-strength concrete, fiber reinforced concrete, or the like as the concrete constituting the pillar 2 or the connecting member 3, it is of course possible to improve the structural strength of the pillar 2 or the connecting member, and of course the inside of the smart body 8 It is optional to arrange the reinforcing bar in the position of the enemy.

*上記に柱2および仕口部材3を現場に搬入し、柱2を
所定位置に立設した後、第3図に示すように、その柱2
の上部に突出している主筋1を仕口部材3の貫通孔10に
挿通させることにより、仕口部材3を柱2の上部に取り
付ける。そして、仕口部材3の梁取付部材7に対して梁
6を接合する。
* After the pillar 2 and the connecting member 3 are carried into the site and the pillar 2 is erected at a predetermined position, as shown in FIG.
The connecting member 3 is attached to the upper portion of the pillar 2 by inserting the main bar 1 protruding to the upper part of the into the through hole 10 of the connecting member 3. Then, the beam 6 is joined to the beam attachment member 7 of the connection member 3.

*上記で取り付けられた仕口部材3の上部に突出してい
る主筋1に接続部材4を介して上階の柱2の下側に突出
している主筋1を接続してその柱2を建て込む。なお、
接続部分の主筋1の周囲には帯筋5を設ける(第1図参
照)。
* The main bar 1 protruding above the connecting member 3 attached above is connected to the main bar 1 protruding below the pillar 2 on the upper floor via the connecting member 4, and the pillar 2 is built. In addition,
A stirrup 5 is provided around the main bar 1 at the connecting portion (see FIG. 1).

*以下、前述した工程を繰り返すことにより、建築物を
構築していく。
* The building will be constructed by repeating the above steps.

なお、柱2の接続部には、従来のように周囲に型粋を設
け、その内部にコンクリートを打設するとともに、柱2
と仕口部材3との間にはグラウト材を注入することによ
り、柱2と仕口部材3のコンクリートどうし、および仕
口部材3のコンクリート部9と主筋1との間の間僚を埋
めてこれらの密着性を向上させる。
In addition, the connection part of the pillar 2 is provided with a stencil around the periphery as in the conventional case, concrete is placed therein, and
By injecting grout material between the connection member and the connection member 3, the concrete between the pillar 2 and the connection member 3 and the intermediary between the concrete portion 9 of the connection member 3 and the main bar 1 are buried. Improve the adhesion of these.

上記の構法によれば、工場において予めPC部材として製
作された柱2と仕口部材3とを現場において組み立てて
いくようにしているため、現場においては型粋を組み立
てるための足場や、コンクリートを打設するための場所
および設備が不要となるとともに、型粋組み立てやコン
クリート打設のための作業員の消滅を図ることができ、
その結果、工期の短縮や工費の消滅を実現することがで
きる。また、柱2や仕口部材3を工場において製作する
ため、現場で多量のコンクリートを打設する場合のうよ
うに気象条件その他の諸条件に影響を受けることが少な
く、工場内において緻密な品質管理を行うことができ、
良質なPC部材を製作することができ、その結果、それら
を用いて構築される躯体Aの構造耐力の向上をも図るこ
とができる。
According to the above construction method, the pillars 2 and the connection members 3 which are preliminarily manufactured as PC members in the factory are assembled on site, so scaffolding for assembling molds and concrete are assembled on site. A place and equipment for pouring are unnecessary, and it is possible to eliminate workers for stencil assembly and concrete pouring,
As a result, it is possible to shorten the construction period and eliminate the construction cost. In addition, since the pillars 2 and the connection members 3 are manufactured in the factory, they are less affected by weather conditions and other various conditions as in the case where a large amount of concrete is placed on site, and the quality is precise in the factory. Can manage
It is possible to manufacture high-quality PC members, and as a result, it is also possible to improve the structural yield strength of the skeleton A constructed using them.

「発明の効果」 以上説明したように、本発明の構造によれば、鉄筋コン
クリート柱および仕口部材を予めプレキャストコンクリ
ート部材として工場製作し、それから現場に搬入して組
み立ててるとともに、その仕口部材に鉄骨梁を接続する
ことで躯体を構築するようにしているので、現場での型
枠組み立てや足場組み立て、コンクリート打設等の作業
を省力化することができるとともに、これからの作業に
伴って現場で必要となる設備や作業空間を少なくするこ
とができ、工期短縮や工費消滅を実現することができ
る。また、鉄筋コンクリート柱や仕口部材を工場におい
て製作するために、コンクリートの品質を向上させて構
造耐力を向上させることができる。
"Effects of the Invention" As described above, according to the structure of the present invention, a reinforced concrete column and a joint member are manufactured in advance as a precast concrete member in a factory, and then carried into the site and assembled, and the joint member is Since the frame is constructed by connecting steel beams, it is possible to save labor such as on-site formwork assembly, scaffolding assembly, concrete placement, etc. The required equipment and working space can be reduced, and the construction period can be shortened and the construction cost can be eliminated. In addition, since reinforced concrete columns and connection members are manufactured in a factory, it is possible to improve the quality of concrete and structural strength.

【図面の簡単な説明】[Brief description of drawings]

第1図ないし第3図は本発明の一実施例を示すものであ
り、第1図は本実施例の鉄骨・鉄筋コンクリート複合構
造によって構築された建築物の躯体の仕口部付近の側面
図、第2図はその平面図、第3図は柱の上部に仕口部材
を取り付ける状況を示す説明図である。 A……躯体、1……主筋(柱主筋)、2……柱(鉄筋コ
ンクリート柱)、3……仕口部材、6……梁(鉄骨
梁)、7……梁取付部材、9……コンクリート部、10…
…貫通孔。
FIGS. 1 to 3 show an embodiment of the present invention, and FIG. 1 is a side view in the vicinity of a joint portion of a skeleton of a building constructed by a composite structure of steel frame and reinforced concrete of this embodiment, FIG. 2 is a plan view thereof, and FIG. 3 is an explanatory view showing a situation in which a connecting member is attached to the upper part of a pillar. A: frame, 1 ... main bar (column main bar), 2 ... column (reinforced concrete column), 3 ... connection member, 6 ... beam (steel beam), 7 ... beam mounting member, 9 ... concrete Department, 10 ...
… Through holes.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】鉄骨粱が仕口部材を介して鉄筋コンクリー
ト柱に対して接合されることにより躯体が構築される鉄
骨・鉄筋コンクリート複合構造の建築物を施工するに際
し、 前記鉄筋コンクリート柱を、その上下に柱主筋が突出し
ているプレキャストコンクリート部材として予め工場製
作しておくとともに、 前記仕口部材を、前記鉄骨粱が接続される粱取付部材
と、該粱取付部材と一体とされて前記鉄筋コンクリート
柱の上部に連設されるコンクリート部を有するととも
に、該コンクリート部には前記鉄筋コンクリート柱の柱
主筋を挿通させる貫通孔が形成されてなるものとして、
この仕口部材をプレキャストコンクリート部材として予
め工場製作しておき、 それら鉄筋コンクリート柱および仕口部材をそれぞれ現
場に搬入し、 前記鉄筋コンクリート柱を立設した後、その上部に突出
している柱主筋を前記貫通孔に挿通させることによって
該鉄筋コンクリート柱の上部に前記仕口部材を載置固定
し、該仕口部材の粱取付部材に前記鉄骨粱を接続するこ
とで躯体を構築することを特徴とする鉄骨・鉄筋コンク
リート複合構法。
1. When constructing a building of a composite structure of steel frame and reinforced concrete in which a frame is constructed by joining steel slag to a reinforced concrete column through a connecting member, the reinforced concrete column is arranged above and below the reinforced concrete column. While pre-manufacturing in advance as a precast concrete member with pillar main bars protruding, the joint member is a grout mounting member to which the steel frame is connected, and an upper part of the reinforced concrete pillar that is integrated with the gruel mounting member. While having a concrete portion continuously connected to, as the through hole is formed in the concrete portion through which the column main bar of the reinforced concrete column is inserted,
This joint member was prefabricated as a precast concrete member in advance, and each of these reinforced concrete columns and joint members were brought into the site, and after the reinforced concrete columns were erected, the column main bars protruding above were penetrated. A steel frame characterized by constructing a skeleton by connecting and fixing the joint member on the upper part of the reinforced concrete column by inserting it through a hole, and connecting the steel frame to the leech mounting member of the joint member. Reinforced concrete composite construction method.
JP11648288A 1988-05-13 1988-05-13 Steel frame / reinforced concrete composite construction method Expired - Fee Related JPH0749681B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11648288A JPH0749681B2 (en) 1988-05-13 1988-05-13 Steel frame / reinforced concrete composite construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11648288A JPH0749681B2 (en) 1988-05-13 1988-05-13 Steel frame / reinforced concrete composite construction method

Publications (2)

Publication Number Publication Date
JPH01287336A JPH01287336A (en) 1989-11-20
JPH0749681B2 true JPH0749681B2 (en) 1995-05-31

Family

ID=14688204

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11648288A Expired - Fee Related JPH0749681B2 (en) 1988-05-13 1988-05-13 Steel frame / reinforced concrete composite construction method

Country Status (1)

Country Link
JP (1) JPH0749681B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08144425A (en) * 1994-11-18 1996-06-04 Ohbayashi Corp Prefabricated member of mixed structure and construction method of mixed structure

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02136444A (en) * 1988-11-15 1990-05-25 Fujita Corp Construction of composite structure consisting of precast reinforced concrete column and steel structural beam
JPH0578706U (en) * 1992-03-31 1993-10-26 東急建設株式会社 PC column joint reinforcement structure
JP6424075B2 (en) * 2014-11-23 2018-11-14 株式会社安藤・間 REINFORCED CONCRETE COLUMN STEEL BEAM JOINTING MEMBER, ITS MANUFACTURING METHOD, AND BUILDING CONSTRUCTION METHOD

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08144425A (en) * 1994-11-18 1996-06-04 Ohbayashi Corp Prefabricated member of mixed structure and construction method of mixed structure

Also Published As

Publication number Publication date
JPH01287336A (en) 1989-11-20

Similar Documents

Publication Publication Date Title
JPH02136444A (en) Construction of composite structure consisting of precast reinforced concrete column and steel structural beam
JP2999126B2 (en) Foundation base for installation of various machines
JPH08144425A (en) Prefabricated member of mixed structure and construction method of mixed structure
JPH0790933A (en) Construction method of structure
JPH066818B2 (en) Reinforced steel composite column
JPH0480444A (en) Connection unit of reinforced concrete pole and steel framed beam
JPH02300439A (en) Prefabricating method
JP2716510B2 (en) Column and beam joining method
JPH01287336A (en) Steel frame reinforced concrete lamination construction
JP2635872B2 (en) How to build a composite structure
JPH01203537A (en) Src precast beam and junction structure of column and beam
JPH0726440B2 (en) Method of joining steel-reinforced bar precast concrete columns and steel beams
JPH02236325A (en) Construction method for super-highrise building
JP2763488B2 (en) Prefabricated pillar and inverted ramen prefabricated construction method
JP2967452B2 (en) Building construction methods and lightweight floor slabs
JPH07103620B2 (en) Construction method for steel structure
JPH01137032A (en) Method of lap joint construction of main reinforcement in post and beam joining section
JPH0830360B2 (en) Connection method for columns and beams
JPH1181694A (en) Seismic retrofitting of structures
JP2758203B2 (en) Connection method between columns and steel beams
JPH09256631A (en) Construction method of reinforced concrete wall
JPS62280435A (en) Construction method of body
JPH02282538A (en) Construction method of reinforced concrete-made building frame
JPH04161628A (en) Building method using reinforced concrete column and steel beam
JPH0749680B2 (en) Construction method of precast steel reinforced concrete structure

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees