JPH0754351Y2 - Abandoned formwork used in the temporary construction method - Google Patents
Abandoned formwork used in the temporary construction methodInfo
- Publication number
- JPH0754351Y2 JPH0754351Y2 JP7096691U JP7096691U JPH0754351Y2 JP H0754351 Y2 JPH0754351 Y2 JP H0754351Y2 JP 7096691 U JP7096691 U JP 7096691U JP 7096691 U JP7096691 U JP 7096691U JP H0754351 Y2 JPH0754351 Y2 JP H0754351Y2
- Authority
- JP
- Japan
- Prior art keywords
- temporary
- concrete
- holding member
- scrap frame
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000010276 construction Methods 0.000 title claims description 33
- 238000009415 formwork Methods 0.000 title claims description 12
- 239000011162 core material Substances 0.000 claims description 13
- 238000005452 bending Methods 0.000 description 13
- 238000000034 method Methods 0.000 description 13
- 229910000831 Steel Inorganic materials 0.000 description 11
- 239000010959 steel Substances 0.000 description 11
- 239000000470 constituent Substances 0.000 description 8
- 239000000463 material Substances 0.000 description 6
- 239000002699 waste material Substances 0.000 description 6
- 239000004568 cement Substances 0.000 description 3
- 238000000465 moulding Methods 0.000 description 3
- 230000000149 penetrating effect Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 239000011120 plywood Substances 0.000 description 2
- 230000001105 regulatory effect Effects 0.000 description 2
- 238000007789 sealing Methods 0.000 description 2
- 230000001065 anti-restriction Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 239000004745 nonwoven fabric Substances 0.000 description 1
- 229920000642 polymer Polymers 0.000 description 1
- 238000004080 punching Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 229920003002 synthetic resin Polymers 0.000 description 1
- 239000000057 synthetic resin Substances 0.000 description 1
- 239000002759 woven fabric Substances 0.000 description 1
Description
【0001】[0001]
【産業上の利用分野】本考案は、地下階を有する、例え
ばコンクリート系建築物の建築工事等において、この地
下階の工事をその期間中、地上から行うための仮設地上
床を支持するH型鋼等の仮設杭で代表される仮設部材の
周囲にコンクリートスラブで代表されるコンクリート部
を構築する場合等の仮設工法で用いられる捨型枠で、そ
の全体を板状に一体成形することで、保管又は運搬の省
スペース化が達成でき、しかも取扱いが簡易に行える捨
型枠に関する。[Industrial application] The present invention is an H-shaped steel for supporting a temporary above-ground floor for performing construction of this basement from the ground during the construction of a concrete building having a basement, for example. It is a formwork used in the temporary construction method such as when constructing a concrete part typified by concrete slabs around temporary members typified by temporary piles, etc. Alternatively, the present invention relates to a waste frame that can achieve space saving in transportation and can be easily handled.
【0002】[0002]
【従来の技術】従来、地下階を有する、例えばコンクリ
ート系建築物の地下階建築工事は、次に示すようにして
行われている。先ず、図1に示すように建築予定箇所の
周囲にシートパイル1を打込んで土留め壁2を構築す
る。次に、地上から、例えばH型鋼を用いた仮設杭3を
所要の間隔をあけて打込む。そして、地上に仮設杭3に
保持される状態で仮設地上床4を設ける。この後、仮設
地上床4上に置いたバックホー等の堀削機5を利用して
所要の深度まで堀削する。次に、コンクリートスラブ6
を構築する。この一連の工事が終了すれば、仮設杭3を
引抜いて撤去する。そして、コンクリートスラブ6に形
成された仮設杭3の撤去跡の貫通口又は凹部をコンクリ
ートで埋戻し処理したりする。2. Description of the Related Art Conventionally, for example, a basement floor construction work of a concrete building having a basement floor is performed as follows. First, as shown in FIG. 1, a sheet pile 1 is driven around the planned construction site to construct an earth retaining wall 2. Next, from the ground, the temporary piles 3 made of, for example, H-shaped steel are driven at a required interval. Then, the temporary ground floor 4 is provided on the ground while being held by the temporary pile 3. After this, the excavator 5 such as a backhoe placed on the temporary ground floor 4 is used to excavate to a required depth. Next, concrete slab 6
To build. When this series of construction work is completed, the temporary pile 3 is pulled out and removed. Then, the through holes or recesses of the removal marks of the temporary piles 3 formed on the concrete slab 6 are backfilled with concrete.
【0003】このような地下階の建築工事において、一
連の工事の終了後、仮設杭3の引抜き撤去を行うため、
例えば特開昭59−8838号公報では、仮設杭3のコ
ンクリートスラブ6に対応する貫通部分又は埋込部分の
外側に、図20に示すような発泡合成樹脂体又はゴムか
ら作成され、対の二つ割りの構成部分7、7に分割した
離型部材8を配設させることが開示されている。In the construction work of such a basement floor, in order to remove the temporary pile 3 after the completion of a series of works,
For example, in Japanese Patent Laid-Open No. 59-8838, a pair of halves is formed from a foamed synthetic resin body or rubber as shown in FIG. 20 on the outside of a through portion or an embedded portion corresponding to the concrete slab 6 of the temporary pile 3. It is disclosed that the release member 8 divided into the constituent parts 7, 7 is arranged.
【0004】[0004]
【考案が解決しようとする課題】ところが、こうした離
型部材8は、対の二つ割りの構成部分8、8に分割され
ているとは言っても、仮設抗3の断面の外形状と断面が
ほぼ同一形状で、しかもその外側に配設されるものであ
るから、嵩張って、保管又は運搬にスペースを多く必要
とする。又、形状が複雑であるから取扱いも面倒であ
る。更に、この離型部材8は変形しやすい素材から形成
されているため、工事期間中、仮設地上床4上を重量の
大きなバックポー等の切削機5が縦横に移動した場合、
仮設抗3が離型部材8の厚みの所要の範囲内で撓んで、
これに保持されている仮設地上床4が縦横に揺動して、
地上での作業に支障を生じることがある。こうしたこと
から、通常、コンクリートの打設後、離型部材8の所要
部分を上方からかき取り、このかき取り部分を利用し
て、仮設抗3と打設コンクリートの間に上方からクサビ
を打込む必要がある。又、仮設抗3が複数層のコンクリ
ートスラブ6を貫通している場合、この撤去に先立って
離型部材8を撤去する必要がある。更に、廃材の発生も
問題である。そして、コンクリートスラブ6に仮設抗3
が上下に貫通する状態で立設されている箇所において、
仮設抗3の撤去後、これの撤去跡に形成された貫通口を
コンクリートで埋戻し処理する場合には、コンクリート
スラブ6の貫通口の下方に型枠をサポートを介して配設
する必要がある。However, even though the release member 8 is divided into the pair of component parts 8 and 8, the external shape and the cross section of the temporary anti-resistance member 3 are almost the same. Since they have the same shape and are arranged on the outer side, they are bulky and require a lot of space for storage or transportation. Moreover, since the shape is complicated, it is difficult to handle. Further, since the release member 8 is formed of a material that is easily deformed, when the heavy cutting machine 5 such as a backpo moves vertically and horizontally on the temporary ground floor 4 during the construction period,
The temporary resistance 3 bends within the required range of the thickness of the release member 8,
The temporary ground floor 4 held by this swings vertically and horizontally,
This may hinder work on the ground. For this reason, normally, after pouring concrete, a required portion of the release member 8 is scraped from above, and by using this scraped portion, wedges are driven from above between the temporary resistance 3 and the poured concrete. There is a need. Further, when the temporary anti-removal 3 penetrates through the concrete slab 6 of multiple layers, it is necessary to remove the release member 8 prior to this removal. Furthermore, the generation of waste materials is also a problem. Then, the concrete slab 6 has a temporary anti-3
At the place where is erected up and down,
After the temporary anti-removal 3 is removed, when the through hole formed in the removed trace is backfilled with concrete, it is necessary to dispose the formwork through the support below the through hole of the concrete slab 6. .
【0005】こうした従来の問題点に鑑みて考案された
のが本考案に係る仮設工法で用いられる捨型枠で、地下
階を有する、例えばコンクリート系建築物の建築工事等
において、この地下階の工事をその期間中、地上から行
うための仮設地上床を支持するH型鋼等の仮設杭で代表
される仮設部材の周囲にコンクリートスラブで代表され
るコンクリート部を構築する場合等の仮設工法で用いら
れる捨型枠で、その全体を板状に一体成形することで、
保管又は運搬の省スペース化が達成でき、しかも取扱い
が簡易に行えることを目的とする。In view of the above conventional problems, a scrap frame used in the temporary construction method according to the present invention was devised. For example, in the construction work of a concrete building having a basement, Used in the temporary construction method when constructing a concrete part represented by a concrete slab around a temporary member represented by a temporary pile such as an H-shaped steel that supports a temporary ground floor for performing construction from the ground during the period. It is a scrap frame that is formed by integrally molding the whole in a plate shape.
The objective is to save space for storage or transportation and to facilitate handling.
【0006】[0006]
【課題を解決するための手段】こうした目的を達成する
ため、本考案の請求項1では、仮設部材の外側面との間
に間隔があく大きさで、仮設部材の断面の外形状と断面
がほぼ同一形状の筒状になるように、その連接角度とな
る折曲部を幅方向に横断的に設けるとともに、外側面に
対応する面にはアンカー部が、又内側面に対応する面に
は係止部がそれぞれ形成されるように構成して、セメン
トを主体に長さ方向に芯材を内装させて板状に一体成形
した仮設工法で用いられる捨型枠を構成した。又、請求
項2では、芯材を折曲部では折曲外側に位置させて内装
させるとともに、折曲部の折曲内側の両側縁には相対向
させて斜め状に切欠した切欠縁部を設けることを、又請
求項3では、内側面の下方に対応する部分から上方に対
応する部分に沿わせてその下方に対応する部分から折返
し可能に埋戻し処理するコンクリートの保持部材を設け
ることをそれぞれ例示した。更に、請求項4では、請求
項3において、保持部材を金網から形成することを例示
した。In order to achieve such an object, according to claim 1 of the present invention, the outer shape and the cross section of the temporary member have a size such that there is a space between the outer surface of the temporary member. In order to have a cylindrical shape of almost the same shape, a bent portion at the connecting angle is provided transversely in the width direction, and the anchor portion is provided on the surface corresponding to the outer surface and the bent portion is provided on the surface corresponding to the inner surface. By constructing the locking portions respectively, a waste form frame used in the temporary construction method was constructed in which the core material was mainly composed of cement and the core material was embedded in the length direction and integrally molded into a plate shape. Further, in the second aspect, the core material is positioned inside the bent portion so as to be placed inside the bent portion, and both side edges on the inner side of the bent portion of the bent portion are provided with notched edge portions that are diagonally cut and face each other. In addition, according to claim 3, a concrete holding member for backfilling is provided so that it can be folded back from the portion corresponding to the lower portion of the inner side surface to the portion corresponding to the upper portion thereof. Each is illustrated. Furthermore, in claim 4, in claim 3, the holding member is formed of a wire mesh.
【0007】[0007]
【作用】而して、こうした捨型枠を用いて、仮設部材の
周囲にコンクリート部を構築するには、次のようにす
る。先ず、例えば鉛直方向に設けられた仮設部材の水平
方向に向けられるコンクリート部に対応する貫通部分又
は埋込部分の直下に合板パネル等のスラブ型枠をサポー
トを介して配設する。この後、仮設部材の外側に間隔を
あけてその外側面周囲を囲むように折曲部で折曲げて立
体形状に組立てた捨型枠を置き、仮設部材の撓みを防止
するために仮設部材の外側面と捨型枠の内側面間に間隔
保持部材を上方から落とし込んで捨型枠の係止部に係止
させる。この状態でコンクリートを捨型枠の外側面周囲
に打設する。このようにすることで、仮設部材に保持さ
せた仮設地上床に大きな移動荷重が負荷された場合で
も、仮設部材の撓みが規制されて、地上での作業に支障
を生じることが少なくなるのである。そして、そのコン
クリートが硬化した後、仮設部材を撤去させるときに
は、先ず間隔保持部材を撤去し、次にこれを引抜き撤去
する。この後、コンクリート部に仮設部材が貫通する状
態で立設されている箇所において、仮設部材の撤去後、
これの撤去跡の捨型枠内に形成された貫通口をコンクリ
ートで埋戻し処理する場合には、捨型枠の内側面に設け
た保持部材を貫通口を閉止する方向に折返して、この上
方から作業を行うのである。又、捨型枠内に形成された
凹部についても、コンクリートで埋戻し処理するときに
は、そのままこの上方から作業を行う。この他、このコ
ンクリート部の貫通口又は凹部に各種構造部材の一部を
貫通又は埋設させる場合もある。The construction of the concrete portion around the temporary member using such a scrap frame is as follows. First, for example, a slab formwork such as a plywood panel is arranged via a support immediately below a through-hole or an embedding part corresponding to a horizontally oriented concrete part of a temporary member provided in the vertical direction. After this, a temporary frame is placed outside the temporary member with a space provided between the temporary member and the bending frame so as to surround the outer surface of the temporary member, and the waste frame is assembled in a three-dimensional shape to prevent the temporary member from bending. A space holding member is dropped from above between the outer side surface and the inner side surface of the scrap frame to be locked to the locking portion of the scrap frame. In this state, concrete is cast around the outer surface of the scrap frame. By doing so, even when a large moving load is applied to the temporary ground floor held by the temporary member, the bending of the temporary member is regulated, and the work on the ground is less likely to be hindered. . Then, when the temporary member is to be removed after the concrete has hardened, the spacing member is first removed, and then this is pulled out. After this, at the place where the temporary member is erected in a state of penetrating the concrete part, after removing the temporary member,
When backfilling the through hole formed in the scrap frame of this removal trace with concrete, fold back the holding member provided on the inner surface of the scrap frame in the direction to close the through hole, Work from. In addition, the recess formed in the scrap frame is also worked from above when backfilling with concrete. In addition, a part of various structural members may be penetrated or embedded in the through hole or the recess of the concrete portion.
【0008】[0008]
【実施例】本考案に係る仮設工法で用いられる捨型枠の
詳細を更に添付の図面に基づき説明する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The details of the scrap frame used in the temporary construction method according to the present invention will be further described with reference to the accompanying drawings.
【0009】ここでは、図1に示すような地下階を有す
る、例えばコンクリート系建築物の地下階建築工事のコ
ンクリートスラブを構築する場合に用いるのを例示して
説明する。Here, an explanation will be given by exemplifying the case where it is used in the case of constructing a concrete slab having a basement floor as shown in FIG. 1, for example, in a basement floor construction work of a concrete building.
【0010】この捨型枠10は、二つの板状に一体成形さ
れたものを立体形状に組立てて、対の二つ割りの構成部
分13、13を形成して構成されるもので、これらを組合せ
たときには、H型鋼を用いた仮設抗3の外側面との間に
間隔があく大きさで、仮設杭3の断面の外形状と断面が
ほぼ同一形状のH字形を形取った筒状に形成されるとと
もに、外側面にアンカー部11、内側面に間隔保持部材の
係止部12をそれぞれ有するものとなる。そして、この外
側面のアンカー部11と内側面の係止部12は、図2、図
3、図4、図5で示すように予め厚みの全体をほぼ同一
に形成するとともに、立体形状に組立てて、構成部分1
3、13を形成したとき、外側面と内側面がともに上面側
より下面側を絞ったテーパー面になるように構成するこ
とで設けられる。又、外側面に対応する面の上下水平方
向に三条設けた凹所は、補助アンカー部14を構成するた
めのものである。そして、この捨型枠10は前記したよう
に対の二つ割りに分割した構成部分13がそれぞれ図6、
図7、図8に示すように成形時には板状に形成されるの
であるが、それは幅方向に横断的に設けた連接角部を構
成する折曲部15で折曲げて、図2、図3、図4、図5に
示す形状になるようにしたものである。こうした折曲げ
を可能とするため、この構成部分13にはその長さ方向全
体に両側部を残して、図8に示すように金網から形成さ
れた芯材16を折曲部15では折曲外側に位置させて内装さ
せるとともに、折曲部15の折曲内側の両側縁には相対向
させて斜め状に切欠した切欠縁部17が設けられている。
この切欠縁部17を設けることで、成形型には突条が形成
され、これによって芯材16がこの部分では、折曲外側に
位置することになる。尚、図中18は構成部分13、13の内
側面下方に対応する部分の各折曲部15、15間に図9、図
10に示すように芯材16の端縁から外部に延設させて七つ
の内側面に対応する面の全てに設けた後述する埋戻し処
理するコンクリートの保持部材である。又、図中19は芯
材16とは別に一端を構成部分13に内装させるとともに、
他端を外部に延設させて二つの内側面に対応する面にだ
け設けた同じく埋戻し処理するコンクリートの補助保持
部材である。そして、この保持部材18、補助保持部材19
は、仮設抗3の撤去後、これの撤去跡の捨型枠10内に形
成された貫通口をコンクリートで埋戻し処理するまで
は、図9、図10に示すように構成部分13、13の内側面下
方に対応する部分から上方に対応する部分に向けてこの
内側面に沿わせて、これが一連の作業の支障にならない
ようにすることが望まれる。又、これら保持部材18、補
助保持部材19はこの仮設抗3の撤去跡の貫通口を閉止す
る方向に折返すのであるが、このとき隣接した面又は相
対面した面にあるもの同士は少なくともその先端側同士
が重合する程度の長さ関係に形成することが考慮され
る。The scrap frame 10 is constructed by integrally assembling two plate-like ones into a three-dimensional shape to form a pair of divided parts 13 and 13, which are combined. Occasionally, the temporary pile 3 is formed into a cylindrical shape having an H-shape having a cross-section that is substantially the same as the outer shape of the cross section of the temporary pile 3. In addition, the outer surface has an anchor portion 11, and the inner surface has a locking portion 12 of the spacing member. The anchor portion 11 on the outer side surface and the locking portion 12 on the inner side surface are preliminarily formed to have substantially the same thickness as shown in FIGS. 2, 3, 4, and 5, and are assembled into a three-dimensional shape. Component 1
When 3 and 13 are formed, both the outer side surface and the inner side surface are provided so as to be tapered surfaces with the lower surface side narrowed from the upper surface side. Further, the three recesses provided in the upper and lower horizontal directions of the surface corresponding to the outer side surface are for forming the auxiliary anchor portion 14. Further, as described above, the scrap frame 10 has the constituent parts 13 which are divided into two pairs as shown in FIG.
As shown in FIG. 7 and FIG. 8, it is formed into a plate shape at the time of molding, but it is bent at a bending portion 15 which forms a connecting angle portion provided transversely in the width direction, The shapes are shown in FIGS. 4 and 5. In order to enable such bending, both sides of the component 13 are left in the entire length direction thereof, and the core material 16 formed of the wire mesh is bent outside at the bending portion 15 as shown in FIG. Notches 17 are provided on both sides of the bent portion 15 on the inner side of the bent portion so as to face each other and are obliquely cut.
By providing the cut-out edge portion 17, a ridge is formed on the molding die, whereby the core material 16 is located outside the bent portion in this portion. In the figure, 18 is a portion corresponding to the lower part of the inner side surface of the constituent parts 13, 13 between the bent parts 15, 15.
As shown in 10, it is a holding member for concrete to be backfilled, which will be described later, which is extended from the edge of the core material 16 to the outside and is provided on all of the surfaces corresponding to the seven inner surfaces. In addition, in the figure, 19 is one end separate from the core material 16 and is incorporated in the constituent portion 13,
It is a concrete auxiliary holding member for backfilling, which has the other end extended to the outside and is provided only on the surfaces corresponding to the two inner surfaces. Then, the holding member 18 and the auxiliary holding member 19
After removing the temporary anti-removal 3, until the through-hole formed in the scrap frame 10 of the removal trace is backfilled with concrete, as shown in FIG. 9 and FIG. It is desired that the inner side surface be provided along the inner side surface from the portion corresponding to the lower side to the portion corresponding to the upper side so that this does not hinder a series of operations. Further, the holding member 18 and the auxiliary holding member 19 are folded back in the direction of closing the through hole of the removal trace of the temporary anti-resistance 3. At this time, at least those on the adjacent surfaces or the surfaces facing each other are at least the same. It is considered to form the length relationship such that the tip sides overlap each other.
【0011】この芯材16並びに保持部材18、補助保持部
材19を構成する金網は素材の線径が0.7〜1.5m
m、好ましくは0.9〜1.1mm、又素材の間隔は1
〜10mm、好ましくは3〜7mmの範囲内のものが好
適である。The wire mesh of the core material 16, the holding member 18, and the auxiliary holding member 19 has a wire diameter of 0.7 to 1.5 m.
m, preferably 0.9 to 1.1 mm, and the distance between the materials is 1
Those in the range of 10 to 10 mm, preferably 3 to 7 mm are suitable.
【0012】又、この捨型枠10は打設したコンクリート
中に残す必要性から、セメントを主体に作成されてい
る。そして、セメントを主体にした素材の内でも、ポリ
マーを含浸させたものを利用するのが、厚みを、例えば
1cm程度に成形でき、更には形状を自由に設定できるこ
とから好ましいと言える。又、硬化する前には流動性が
良好で、硬化後には剛性が大きくなるものが好適であ
る。Further, the scrap frame 10 is made mainly of cement because it is necessary to leave it in the cast concrete. Among the materials mainly composed of cement, it is preferable to use a material impregnated with a polymer because the thickness can be molded to, for example, about 1 cm and the shape can be freely set. Further, it is preferable that the fluidity is good before curing and the rigidity becomes large after curing.
【0013】ところで、本考案に係る捨型枠を用いて、
仮設抗3の周囲にコンクリートスラブ6を設ける場合で
も、建築予定箇所の周囲にシートパイル1を打込んで土
留め壁2を構築した後、地上からH型鋼を用いた仮設杭
3を所要の間隔をあけて打込み、そして地上に仮設杭3
に保持される状態で仮設地上床4を設け、この仮設地上
床4上に置いたバックホー等の堀削機5を利用して所要
の深度まで堀削する工程までは従来と同様である。By the way, using the scrap frame according to the present invention,
Even when the concrete slab 6 is provided around the temporary building 3, after constructing the earth retaining wall 2 by driving the sheet pile 1 around the planned construction site, the temporary piles 3 made of H-shaped steel are provided at the required intervals from the ground. Open and drive in, and temporarily stake 3 on the ground
The temporary ground floor 4 is provided in a state of being held at, and the process of excavating to a required depth using the excavator 5 such as a backhoe placed on the temporary ground floor 4 is the same as the conventional process.
【0014】次に、仮設杭3のコンクリートスラブ6に
対応する貫通部分又は埋込部分の直下に合板パネル等の
スラブ型枠20を図示しないサポートを介して配設する。
この後、図11に示すように仮設杭3の外側に間隔をあけ
てその側方から折曲部15で折曲げて立体形状に組立てた
対の構成部分13、13から構成される捨型枠10を置き、次
に図12に示すように捨型枠10の上面にシール部材21を貼
り着ける。更に、仮設杭3の撓みを防止するために図1
3、14に示すように仮設抗3の外側面と内側面間にクサ
ビ状に形成した間隔保持部材22を上方から落とし込んで
捨型枠10の係止部12に係止させるものである。そして、
この状態で図15に示すようにコンクリートを捨型枠10の
外側面周囲に上面がシール部材21上面とほぼ面一になる
ように打設する。このようにすることで、仮設抗3の撓
みが規制されて、地上での作業に支障を生じることが少
なくなるのである。次に、図16に示すようにスラブ型枠
20を取外す。そして、そのコンクリートが硬化した後、
仮設抗3を撤去させるときには、先ず間隔保持部材22を
撤去し、次にこれを引抜き撤去する。この仮設抗3とコ
ンクリートスラブ6とは間に捨型枠10をはさんで対面し
ているから、仮設抗3の撤去時にコンクリートスラブ6
に損壊を与えるおそれが少なくなる。この後、コンクリ
ートスラブ6に仮設抗3が貫通する状態で立設されてい
る箇所において、仮設抗3の撤去後、これの撤去跡の捨
型枠10内に形成された貫通口をコンクリートで埋戻し処
理する場合には、捨型枠10に設けた保持部材18、図示し
ていないが補助保持部材19を図17、図18に示すように貫
通口を閉止する方向に折返して、この上方から作業を行
うのである。この保持部材18を折返したとき、隣接した
面又は相対した面にあるもの同士の間で少なくとも先端
側同士が重合していない箇所がある場合、又は保持部材
18を構成する素材の剛性が小さい場合、金網から形成さ
れた閉止部材を上方から落とし込むことが考慮される。
そして、捨型枠10の上面に貼り着けたシール部材21を取
外し、この捨型枠10の上面にもこの周囲と面一になるよ
うにコンクリートを埋戻し処理する。捨型枠10の保持部
材18下方は適宜、コンクリート又はモルタルを埋戻し処
理してもよい。このようにして、コンクリートスラブ6
の仮設抗3の撤去跡に形成された貫通口をコンクリート
で埋戻し処理すれば、貫通口の下方に型枠をサポートを
介して配設する作業が不要になる。又、捨型枠10内に形
成された凹部についても、コンクリートで埋戻し処理す
るときには、この捨型枠10に保持部材18、補助保持部材
19が設けられていても、これを凹部を閉止する方向に折
返すことなく、そのまま上方から作業を行う。Next, a slab formwork 20 such as a plywood panel is arranged directly below the penetrating or embedding part of the temporary pile 3 corresponding to the concrete slab 6 via a support (not shown).
After this, as shown in FIG. 11, a scrap frame composed of a pair of constituent parts 13 and 13 assembled at a three-dimensional shape by folding the temporary pile 3 at a space outside the temporary pile 3 at a bending portion 15 from its side. Then, the seal member 21 is attached to the upper surface of the scrap frame 10 as shown in FIG. Furthermore, in order to prevent the bending of the temporary pile 3,
As shown by 3 and 14, a wedge-shaped spacing member 22 formed between the outer side surface and the inner side surface of the temporary protection 3 is dropped from above and locked to the locking portion 12 of the scrap frame 10. And
In this state, as shown in FIG. 15, concrete is cast around the outer surface of the scrap frame 10 such that the upper surface is substantially flush with the upper surface of the seal member 21. By doing so, the bending of the temporary anti-restriction 3 is regulated, and the work on the ground is less likely to be hindered. Next, as shown in Figure 16, slab formwork
Remove 20. And after the concrete hardens,
When removing the temporary anti-removal member 3, first, the spacing member 22 is removed, and then this is pulled out and removed. Since the temporary formwork 3 and the concrete slab 6 face each other with a scrap frame 10 interposed therebetween, the concrete slab 6 is removed when the temporary formwork 3 is removed.
It reduces the risk of damage to. After this, at the location where the temporary proof 3 is erected in the concrete slab 6 in a penetrating state, after removing the temporary proof 3, the through hole formed in the scrap frame 10 of the removal trace is filled with concrete. When performing the returning process, the holding member 18 provided on the scrap frame 10, the auxiliary holding member 19 (not shown) are folded back in the direction of closing the through-hole as shown in FIGS. Do the work. When this holding member 18 is folded back, if there is a portion where at least the tip ends do not overlap with each other between those on the adjacent surface or the facing surface, or the holding member
When the material forming the member 18 has low rigidity, it is considered to drop the closing member formed of the wire mesh from above.
Then, the sealing member 21 attached to the upper surface of the scrap frame 10 is removed, and the upper surface of the scrap frame 10 is also backfilled with concrete so as to be flush with the surroundings. Below the holding member 18 of the scrap frame 10, concrete or mortar may be appropriately backfilled. In this way, concrete slab 6
If the through hole formed in the removal mark of the temporary anti-removal 3 is backfilled with concrete, the work of disposing the formwork below the through hole via the support becomes unnecessary. Further, regarding the recess formed in the scrap frame 10, when the backfilling process with concrete is performed, the scrap frame 10 is provided with a holding member 18 and an auxiliary holding member.
Even if 19 is provided, work is performed from above without folding back this in the direction of closing the recess.
【0015】この捨型枠10において、芯材16、保持部材
18、補助保持部材19は金網以外の網状物、又は各種パン
チングシート、又は各種織物、編物、不織布等を用いる
ことができる。又、芯材16は針金等の条体をその長さ方
向に平行に間隔をあけて配設して設けることも可能であ
る。更に、折曲部15は折曲可能であるなら、種々の態様
のものが利用できる。In the scrap frame 10, the core material 16 and the holding member
As the auxiliary holding member 19, a net-like material other than a wire net, various punching sheets, various woven fabrics, knitted fabrics, non-woven fabrics and the like can be used. Further, the core material 16 can also be provided by arranging strips of wire or the like in parallel with each other in parallel with the length direction thereof. Further, if the bending portion 15 is bendable, various forms can be used.
【0016】又、捨型枠10に設ける保持部材18、補助保
持部材19は図示した配列に限定されるものではなく、更
にこれらを配筋作業に利用することも適宜考慮される。
しかし、捨型枠10には必ずしも保持部材18、補助保持部
材19を設ける必要はなく、これらがないものも利用可能
である。Further, the holding member 18 and the auxiliary holding member 19 provided on the scrap frame 10 are not limited to the arrangements shown in the drawings, and it may be considered to utilize them for the rebar work.
However, the scrap frame 10 does not necessarily need to be provided with the holding member 18 and the auxiliary holding member 19, and those without them can be used.
【0017】更に、外側面に設けるアンカー部11や内側
面に設ける係止部12についても、図示した実施例の他、
突条様に形成したり、又は突部を点在させて設けること
が適宜考慮される。Further, the anchor portion 11 provided on the outer side surface and the locking portion 12 provided on the inner side surface, in addition to the illustrated embodiment,
It is appropriately considered to form the protrusions or provide the protrusions in a scattered manner.
【0018】又、捨型枠10は対の二つ割りに分割した構
成部分13、13に形成することなく、それ以外の二つ割り
以上に分割することもできる。Further, the discarding frame 10 may be divided into other two or more parts without being formed into the component parts 13 and 13 which are divided into two parts.
【0019】更に、こうした捨型枠10は折曲部15で折曲
げて立体形状に組立てたとき、一つの完全なものになる
ように形成することも可能である。Further, it is also possible to form such a scrap frame 10 so that when it is bent at the bending portion 15 and assembled into a three-dimensional shape, it becomes one complete product.
【0020】図示した実施例にかかわらず、仮設杭3で
代表される仮設部材としては、H型鋼の他、L型鋼、C
型鋼又は中空丸鋼、中空角鋼、更には中実の各種棒鋼等
が利用できる。Regardless of the illustrated embodiment, the temporary members represented by the temporary pile 3 include H-shaped steel, L-shaped steel, and C-shaped steel.
Shaped steel, hollow round steel, hollow square steel, and various solid steel bars can be used.
【0021】図示した実施例では、本考案に係る捨型枠
を、地下階を有するコンクリート系建築物の地下階建築
工事のコンクリートスラブを構築する場合に用いるのを
例示したが、この捨型枠ではこの他、床や壁等のコンク
リート部に対して管類等の各種構造部材を貫通する状態
又はその一部が埋込まれる状態で支持させるために貫通
口又は凹部を形成する場合に採用することも可能であ
る。又、ベランダの手摺用支柱や道路の中央分離帯、カ
ードレール等の支柱を、その下端部が埋込まれる状態で
支持させる凹部を形成する場合にも採用できる。In the illustrated embodiment, the scrap frame according to the present invention is used in the case of constructing a concrete slab for a basement floor construction work of a concrete building having a basement floor. Also, in addition to this, it should be used when forming a through hole or a recess to support various structural members such as pipes in a concrete part such as a floor or a wall in a state of being penetrated or a part of which is embedded. Is also possible. It can also be used when forming a recess for supporting a handrail support on a veranda, a median strip of a road, a support such as a card rail, in a state where its lower end is embedded.
【0022】[0022]
【考案の効果】以上のような本考案に係る仮設工法で用
いられる捨型枠は、その全体を板状に一体成形すること
で、保管又は運搬の省スペース化が達成でき、しかも取
扱いが簡易に行えるのである。又、仮設部材の外側に配
設した後、仮設部材の外側面とこれの間に間隔保持部材
を、例えば上方から嵌込むだけで、これの正確な位置決
めができ、しかも仮設部材の撓みが規制できる。更に、
内側面にコンクリートの保持部材を設けた場合、コンク
リート部に仮設部材が上下に貫通する状態で立設されて
いる箇所において、仮設部材の撤去後、これの撤去跡に
形成された貫通口をコンクリートで埋戻し処理するとき
には、保持部材を貫通口を閉止する方向に折返すだけ
で、貫通口の下方に型枠をサポートを介して配設しなく
ても作業が行える。又、これはコンクリートを打設した
後では、コンクリート部に残るから、廃材の発生も少な
くなる。[Effects of the Invention] The scrap frame used in the temporary construction method according to the present invention as described above is integrally molded into a plate shape, so that space saving for storage or transportation can be achieved and the handling is easy. It can be done. Further, after arranging on the outer side of the temporary member, it is possible to accurately position the outer surface of the temporary member and the space holding member between the outer member and the space holding member, for example, from above, and to restrict the bending of the temporary member. it can. Furthermore,
When a concrete holding member is provided on the inner surface, at the place where the temporary member is erected vertically in the concrete part, after removing the temporary member, the through hole formed in the removal trace When the backfilling process is performed by, the holding member is simply folded back in the direction of closing the through hole, and the work can be performed without disposing the formwork below the through hole through the support. Further, since this remains in the concrete portion after the concrete is placed, the generation of waste materials is reduced.
【図1】地下階を有する、例えばコンクリート系建築物
の地下階建築工事の概略を示す縦断面説明図FIG. 1 is an explanatory vertical sectional view showing an outline of a basement floor construction work of a concrete building having a basement floor, for example.
【図2】本考案に係る捨型枠の対の二つ割りに分割した
構成部分を組立て状態を示す斜視図FIG. 2 is a perspective view showing an assembled state of constituent parts of a pair of scrap frames according to the present invention divided into two parts.
【図3】組立てた状態の外側面を示す正面図FIG. 3 is a front view showing an outer side surface in an assembled state.
【図4】同じく平面図FIG. 4 is a plan view of the same.
【図5】同じく内側面を示す正面図FIG. 5 is a front view showing an inner surface of the same.
【図6】展開状態の外側面を示す正面図FIG. 6 is a front view showing an outer side surface in a deployed state.
【図7】同じく平面図FIG. 7 is a plan view of the same.
【図8】同じく内側面を示す正面図FIG. 8 is a front view showing the inner surface of the same.
【図9】図8中のA−A拡大端面図9 is an enlarged end view taken along the line AA in FIG.
【図10】図8中のB−B拡大端面図FIG. 10 is an enlarged end view of BB in FIG.
【図11】本考案に係る捨型枠を用いたコンクリート系建
築物の構築工程順序を示す縦断面説明図FIG. 11 is a vertical cross-sectional explanatory view showing the construction process sequence of the concrete building using the scrap frame according to the present invention.
【図12】本考案に係る捨型枠を用いたコンクリート系建
築物の構築工程順序を示す縦断面説明図FIG. 12 is a vertical cross-sectional explanatory view showing the construction process sequence of the concrete building using the scrap frame according to the present invention.
【図13】本考案に係る捨型枠を用いたコンクリート系建
築物の構築工程順序を示す縦断面説明図FIG. 13 is a vertical cross-sectional explanatory view showing the construction process sequence of a concrete building using a scrap frame according to the present invention.
【図14】本考案に係る捨型枠を用いたコンクリート系建
築物の構築工程順序を示す横断面説明図FIG. 14 is an explanatory cross-sectional view showing the order of steps for constructing a concrete building using the scrap frame according to the present invention.
【図15】本考案に係る捨型枠を用いたコンクリート系建
築物の構築工程順序を示す縦断面説明図FIG. 15 is a vertical cross-sectional explanatory view showing the construction process sequence of the concrete building using the scrap frame according to the present invention.
【図16】本考案に係る捨型枠を用いたコンクリート系建
築物の構築工程順序を示す縦断面説明図FIG. 16 is a vertical cross-sectional explanatory diagram showing the construction process sequence of the concrete building using the scrap frame according to the present invention.
【図17】本考案に係る捨型枠を用いたコンクリート系建
築物の構築工程順序を示す縦断面説明図FIG. 17 is a vertical cross-sectional explanatory diagram showing the construction process sequence of the concrete building using the scrap frame according to the present invention.
【図18】本考案に係る捨型枠を用いたコンクリート系建
築物の構築工程順序を示す縦断面説明図FIG. 18 is an explanatory vertical cross-sectional view showing the construction process sequence of the concrete building using the scrap frame according to the present invention.
【図19】本考案に係る捨型枠を用いたコンクリート系建
築物の構築工程順序を示す縦断面説明図FIG. 19 is a vertical cross-sectional explanatory view showing the construction process sequence of the concrete building using the scrap frame according to the present invention.
【図20】従来の離型部材を示す斜視図FIG. 20 is a perspective view showing a conventional release member.
1 シートパイル 2 土留め壁 3 仮設杭 4 仮設地上床 5 堀削機 6 コンクリートスラブ 7 構成部分 8 離型部材 10 捨型枠 11 アンカー部 12 係止部 13 構成部分 14 補助アンカー部 15 折曲部 16 芯材 17 切欠縁部 18 保持部材 19 補助保持部材 20 スラブ型枠 21 シール部材 22 間隔保持部材 1 Sheet pile 2 Earth retaining wall 3 Temporary pile 4 Temporary ground floor 5 Excavator 6 Concrete slab 7 Constituent part 8 Releasing member 10 Waste form frame 11 Anchor part 12 Locking part 13 Constituent part 14 Auxiliary anchor part 15 Bending part 16 Core material 17 Notched edge 18 Holding member 19 Auxiliary holding member 20 Slab formwork 21 Sealing member 22 Interval holding member
───────────────────────────────────────────────────── フロントページの続き (72)考案者 桑原 茂 徳島県麻植郡川島町大字三ツ島字新田179 番地の1 日本フネン株式会社内 (72)考案者 伊藤 浩 徳島県麻植郡川島町大字三ツ島字新田179 番地の1 日本フネン株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Shigeru Kuwahara, Shita, Kawashima-cho, Asa-gun, Tokushima Prefecture, Nitta, Mitsushima, No. 179, No. 1 Nippon Funen Co., Ltd. No. 179 No. 1 Inside Nippon Funen Co., Ltd.
Claims (4)
きさで、仮設部材の断面の外形状と断面がほぼ同一形状
の筒状になるように、その連接角度となる折曲部を幅方
向に横断的に設けるとともに、外側面に対応する面には
アンカー部が、又内側面に対応する面には係止部がそれ
ぞれ形成されるように構成して、セメントを主体に長さ
方向に芯材を内装させて板状に一体成形した仮設工法で
用いられる捨型枠。1. A bent portion having a size such that there is a gap between the outer surface of the temporary member and the connecting angle of the temporary member so that the outer shape of the cross section of the temporary member is substantially the same as the cross section. Are provided transversely in the width direction, the anchor part is formed on the surface corresponding to the outer surface, and the locking part is formed on the surface corresponding to the inner surface. A scrap frame used in the temporary construction method in which a core material is internally installed in the vertical direction and integrally molded into a plate shape.
内装させるとともに、折曲部の折曲内側の両側縁には相
対向させて斜め状に切欠した切欠縁部を設けた請求項1
記載の仮設工法で用いられる捨型枠。2. The core member is positioned inside the bent portion at the outside of the bent portion to be internally mounted, and both side edges on the inside of the bent portion of the bent portion are provided with notched edge portions which are diagonally cut to face each other. Claim 1
A scrap frame used in the described temporary construction method.
対応する部分に沿わせてその下方に対応する部分から折
返し可能に埋戻し処理するコンクリートの保持部材を設
けた請求項1又は2記載の仮設工法で用いられる捨型
枠。3. The concrete holding member according to claim 1 or 2, wherein a concrete holding member is provided along the portion corresponding to the upper portion of the inner side surface to the portion corresponding to the upper portion, and the portion corresponding to the lower portion is backfilled so that it can be folded back. A formwork used in the temporary construction method of.
載の仮設工法で用いられる捨型枠。4. The scrap frame used in the temporary construction method according to claim 3, wherein the holding member is formed of wire mesh.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP7096691U JPH0754351Y2 (en) | 1991-08-09 | 1991-08-09 | Abandoned formwork used in the temporary construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP7096691U JPH0754351Y2 (en) | 1991-08-09 | 1991-08-09 | Abandoned formwork used in the temporary construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH064153U JPH064153U (en) | 1994-01-18 |
| JPH0754351Y2 true JPH0754351Y2 (en) | 1995-12-18 |
Family
ID=13446777
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP7096691U Expired - Lifetime JPH0754351Y2 (en) | 1991-08-09 | 1991-08-09 | Abandoned formwork used in the temporary construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0754351Y2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH072486U (en) * | 1993-06-21 | 1995-01-13 | 奥村メリヤス株式会社 | Weft knitted products with special knitting structure |
-
1991
- 1991-08-09 JP JP7096691U patent/JPH0754351Y2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH064153U (en) | 1994-01-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR101173045B1 (en) | Earth retaining-cum-retaining wall, and construction method thereof | |
| KR101041274B1 (en) | Synthetic Grouting Fixture Structure and Construction Method | |
| JPH0754351Y2 (en) | Abandoned formwork used in the temporary construction method | |
| JP3251698B2 (en) | Tunnel lining element and tunnel construction method using the same | |
| JP2004285613A (en) | Construction method for building foundation | |
| JP2979117B2 (en) | Building foundation method | |
| JPH05112948A (en) | Permanent form and foundation execution method using it | |
| JPH11190024A (en) | Earth retaining work | |
| JPH10102514A (en) | Construction structure for retaining wall | |
| JPH084033A (en) | Construction method of the pressure barrier against the outer perimeter of the building | |
| JPH07119470B2 (en) | Construction method of concrete structure and scrap frame used in it | |
| JP3025766B2 (en) | Non-demoldable concrete foundation for buildings, etc. | |
| JPS63280153A (en) | Reverse construction method for underground framework | |
| JP2001164559A (en) | Construction method of continuous underground wall guide wall making use of l-type precast member | |
| JPH07119469B2 (en) | Construction method of concrete structure and scrap frame used in it | |
| JP2002030674A (en) | Polystyrene resin foam plate assembly, lightweight ground construction method, foundation construction method, and lightweight embankment construction method | |
| JPH0739666B2 (en) | Permeable temporary earth retaining material, permeable frame structure and concrete wall construction method | |
| JPS5853321Y2 (en) | Element for mountain retainer | |
| JP2006161272A (en) | Formwork device for fabric foundation | |
| EP1964978B1 (en) | Method for erecting a wharfage and wharfage | |
| JPH03180613A (en) | Underground continuous wall | |
| JP2584682Y2 (en) | Work frame for excavation work | |
| JPH02266016A (en) | Structural process of underground concrete body of building | |
| JP2007009640A (en) | Shore strut for supporting retaining wall and its construction method | |
| JPH0352822Y2 (en) |