JPH0765371B2 - How to build a sloping roof by concrete - Google Patents

How to build a sloping roof by concrete

Info

Publication number
JPH0765371B2
JPH0765371B2 JP62201618A JP20161887A JPH0765371B2 JP H0765371 B2 JPH0765371 B2 JP H0765371B2 JP 62201618 A JP62201618 A JP 62201618A JP 20161887 A JP20161887 A JP 20161887A JP H0765371 B2 JPH0765371 B2 JP H0765371B2
Authority
JP
Japan
Prior art keywords
concrete
roof
ridge
height
wire rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP62201618A
Other languages
Japanese (ja)
Other versions
JPS6443654A (en
Inventor
三郎 桐山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP62201618A priority Critical patent/JPH0765371B2/en
Publication of JPS6443654A publication Critical patent/JPS6443654A/en
Publication of JPH0765371B2 publication Critical patent/JPH0765371B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

【発明の詳細な説明】 「産業上の利用分野」 この発明は、コンクリートによる勾配屋根の構築方法の
改良に関する。
TECHNICAL FIELD The present invention relates to an improvement in a method for constructing a pitched roof made of concrete.

「従来の技術」 従来、コンクリートで勾配屋根を構築する施工方法とし
ては、鉄筋コンクリート構造物上に勾配屋根の骨格とな
る配筋を行い、この配筋の周期にコンクリート用の型枠
を組んでコンクリートを打設し、コンクリートの硬化後
に型枠を取り外してコンクリート屋根を構築するという
方法が一般に実施されている。
“Conventional technology” Conventionally, as a construction method for constructing a pitched roof with concrete, reinforcing bars that are the skeleton of a pitched roof are laid on a reinforced concrete structure, and a concrete formwork is assembled in the cycle of this reinforcing bar. Is generally practiced, and after the concrete is hardened, the formwork is removed to construct a concrete roof.

この方法において、コンクリート屋根の上面高さ(型枠
からの厚み)を位置決めする手段としては、第3図に示
すように、縦横に配設された鉄筋1の上方に、この鉄筋
1を利用して補助筋等を溶接し、これにコンクリート屋
根の上面高さと等しい直線上に位置決め用のレベル筋
2、2、2…を等間隔で配設して、このレベル筋の高さ
までコンクリートCを打設するという手段が用いられて
いる。なお、符号3は型枠、符号4はコンクリートCの
はみ出し流れを防止するためのコンクリート流れ止めで
ある。
In this method, as a means for positioning the height of the top surface of the concrete roof (thickness from the formwork), as shown in FIG. 3, the reinforcing bar 1 is used above the reinforcing bars 1 arranged vertically and horizontally. Are welded with auxiliary reinforcements, etc., and positioning level reinforcements 2, 2, 2, ... Are arranged at equal intervals on a straight line equal to the height of the upper surface of the concrete roof, and concrete C is driven to the level reinforcements. The means of setting is used. Reference numeral 3 is a form, and reference numeral 4 is a concrete flow stop for preventing the overflow of the concrete C.

「発明が解決しようとする問題点」 ところが、上記施工方法によると、コンクリート打設時
にコンクリートを吐出させるためのポンプホース5を棟
部6(つまり棟部6のレベル筋2上)に載置するため、
棟部6のレベル筋2が下方に湾曲してしまうという問題
があった。また、棟部6以外でもコンクリートならし作
業を行うために作業員が配設された鉄筋1上に乗って、
色々な箇所で変形を生じさせてしまい、これに伴って各
レベル筋2の位置も変動してしまうという問題があっ
た。
[Problems to be Solved by the Invention] However, according to the above-mentioned construction method, the pump hose 5 for discharging concrete when placing concrete is placed on the ridge 6 (that is, on the level line 2 of the ridge 6). For,
There is a problem that the level muscle 2 of the ridge 6 is bent downward. In addition, riding on the rebar 1 where workers are placed to perform concrete leveling work outside the ridge 6,
There is a problem that deformation occurs at various places, and the position of each level muscle 2 also changes accordingly.

これらの問題のため、レベル筋2ではコンクリート屋根
の上面高さの位置決め精度を確保することが難しく、全
ての箇所を正確かつ平らに打設するのが不可能であっ
た。また、軒先の型枠3上にも作業員が乗って型枠3の
角度を下げてしまうことも上記の要因となっていた。
Due to these problems, it was difficult to secure the positioning accuracy of the height of the upper surface of the concrete roof with the level reinforcement 2, and it was impossible to drive all the parts accurately and flatly. In addition, the fact that a worker rides on the formwork 3 at the eaves side and lowers the angle of the formwork 3 has also been a factor.

さらに、レベル筋2がコンクリートから露出するためコ
ンクリート屋根の表面に錆が発生したり、レベル筋2と
コンクリートCとのわずかな隙間から漏水してしまうと
いう問題もあった。
Further, since the level reinforcement 2 is exposed from the concrete, there is a problem that rust is generated on the surface of the concrete roof and water leaks from a slight gap between the level reinforcement 2 and the concrete C.

以上の諸問題により、コンクリート屋根の再仕上げや漏
水防護の作業などコンクリート屋根の補修に余分な費用
や時間がかかり、コストの増加をもたらしていた。
Due to the above problems, additional costs and time are required for repairing the concrete roof such as refinishing of the concrete roof and work for water leakage protection, resulting in an increase in cost.

「問題点を解決するための手段」 この発明は、勾配屋根の配筋を行なってその周囲に型枠
を設けこの型枠内にコンクリートを打設して勾配屋根を
構築するコンクリートによる勾配屋根の構築方法であっ
て、勾配屋根の棟部から軒先部にかけてコンクリート屋
根の上面高さの基準にするためのラインを張設し、この
ライン高さに合わせてコンクリートを打設することを特
徴とするものである。
"Means for Solving Problems" The present invention is directed to arranging a pitched roof and providing a formwork around it to construct concrete by forming concrete in the formwork. The construction method is characterized in that a line is set up from the ridge part of the pitched roof to the eaves part as a standard for the height of the top surface of the concrete roof, and the concrete is placed according to this line height. It is a thing.

「作用」 勾配屋根の配筋を行なってその周囲に型枠を設け、さら
に勾配屋根の棟部から軒先部にかけてコンクリート屋根
の上面高さの基準にするためのラインを設け、このライ
ン高さに合わせてコンクリートを打設すれば、コンクリ
ート屋根の上面がラインに沿って平行となりかつ平面と
なる。また、ラインは張設するようにしているから、作
業員等によりたとえふまれても元に復帰し、または張り
直せるので、高さ基準が精度良く維持される。
"Action" The sloped roof is laid out and a formwork is installed around it, and a line is set up from the ridge to the eaves of the sloped roof to serve as the standard height of the concrete roof. If concrete is poured together, the top surface of the concrete roof becomes parallel and flat along the line. Further, since the line is stretched, it can be restored to its original state or re-stretched even if it is squeezed by an operator or the like, so that the height standard can be maintained accurately.

「実施例」 以下、この発明の実施例について図面を参照しながら説
明する。第1図および第2図はこの発明の一実施例であ
って、第3図の従来例と同一部材には同一符号を付して
ある。
[Examples] Examples of the present invention will be described below with reference to the drawings. 1 and 2 show an embodiment of the present invention, in which the same members as those in the conventional example of FIG. 3 are designated by the same reference numerals.

これらの図において、符号1は勾配屋根の骨格を形成す
る鉄筋であり、この鉄筋1は柱や梁で構成された建築構
造物の上方に形成されている。この鉄筋1の周囲には上
面を残して勾配屋根の外形を形成する型枠3が設けられ
ている。このうち軒先部7の型枠3は支柱(支保工)8
によって支えられている。また、鉄筋1の頂部には溶接
により補助筋9が一体に設けられており、補助筋9の先
端部には棟部6を形成する棟梁10(アングル材)が地面
に対して水平に渡して設けられている。そして、棟梁10
には等間隔にワイヤロープ(ライン)11の一端が着脱自
在に装着されている。
In these drawings, reference numeral 1 is a reinforcing bar that forms the skeleton of a pitched roof, and this reinforcing bar 1 is formed above a building structure composed of columns and beams. Around the rebar 1, there is provided a form 3 which forms the outer shape of a pitched roof while leaving the upper surface. Of these, the formwork 3 of the eaves part 7 is a support (supporting work) 8
Supported by. An auxiliary bar 9 is integrally provided on the top of the reinforcing bar 1 by welding, and a ridge beam 10 (an angle member) forming the ridge 6 is horizontally provided on the ground at the tip of the auxiliary bar 9. It is provided. And master beam 10
One end of a wire rope (line) 11 is detachably attached to the at equal intervals.

このワイヤロープ(ライン)11は型枠3内に打設するコ
ンクリートC高さの基準となるもので、コンクリート打
設時に棟部6から軒先部7にかけてワイヤロープ11を張
り、その先端部(他端部)をワイヤロープ11の張設具合
を調節するためのタンバックル12を介して支柱8等に掛
けるようにしたものである。
This wire rope (line) 11 serves as a standard for the height of the concrete C to be placed in the form 3, and the wire rope 11 is stretched from the ridge portion 6 to the eaves portion 7 at the time of placing concrete, and the tip portion (others) The end portion) is hung on the column 8 or the like via a tan buckle 12 for adjusting the tension of the wire rope 11.

なお、前記補助筋9の下端部には錆止めおよび漏水止め
のためにキャップ13が環着されている。
A cap 13 is attached to the lower end of the auxiliary muscle 9 to prevent rust and water leakage.

次にこのように構成されたコンクリートによる勾配屋根
の構築方法について、その作業手順を説明する。
Next, a work procedure of a method of constructing a pitched roof made of concrete configured as described above will be described.

まず、柱や梁で構成された構造建築物の上に勾配屋根の
骨格となる鉄筋1を組み、この鉄筋1の頂部ら補助筋9
を介して棟部6に棟梁10を水平に渡すとともに、鉄筋1
の上面を残して周囲に勾配屋根の外形となる型枠3を設
ける。このように配筋および型枠工事を終えたら、複数
本のワイヤロープ11の一端部をそれぞれ棟部6に等間隔
に装着して棟部6から軒先部7にかけて張設し、それぞ
れのワイヤロープ11の他端部を支柱8に掛ける。このと
きワイヤロープ11の張り具合は70%程度の抑えておく。
そして、ワイヤロープ11の高さに合わせてポンプホース
5によって棟部6から軒先部7にいたるまで第1図一点
鎖線で示すレベルまでコンクリートCをまんべんなく打
設する。ついで、ワイヤロープ11の張りを10%にし、こ
のワイヤロープ11の高さに合わせてコンクリートC上面
のならし作業を行う。最後にワイヤロープ11を取り外し
てコンクリート屋根が硬化した後に型枠3を外して仕上
げ作業を行い作業を完了する。
First, the reinforcing bar 1 that serves as the skeleton of a pitched roof is assembled on the structural building composed of columns and beams, and the reinforcing bar 9 from the top of the reinforcing bar 1
The ridge beam 10 is passed horizontally to the ridge section 6 via the
Forming 3 which becomes the outer shape of a pitched roof is provided around the upper surface of. After finishing the bar arrangement and the formwork work in this way, one end of each of the plurality of wire ropes 11 is attached to the ridge 6 at equal intervals and stretched from the ridge 6 to the eaves end 7, The other end of 11 is hung on the column 8. At this time, the tension of the wire rope 11 is suppressed to about 70%.
Then, in accordance with the height of the wire rope 11, concrete C is evenly poured from the ridge 6 to the eaves 7 by the pump hose 5 up to the level shown by the alternate long and short dash line in FIG. Then, the tension of the wire rope 11 is set to 10%, and the work for leveling the concrete C upper surface is performed according to the height of the wire rope 11. Finally, after removing the wire rope 11 and hardening the concrete roof, the formwork 3 is removed and finishing work is performed to complete the work.

この実施例によると棟部6に補助筋9を介して曲げ応力
の強い棟梁(アングル材)10を渡したので、棟梁10上に
ポンプホース5を載置したとしてもその重みで棟梁10が
変形したり下がったりすることがなく、この棟梁10から
軒先部7までワイヤロープ11を張設すれば、コンクリー
ト屋根の上面高さを簡単かつ確実に位置決めすることが
できる。しかも、万一作業員が鉄筋1上に乗って鉄筋1
の一部が変形したとしても、ワイヤロープ11の張りに影
響を及ぼさないので常にコンクリート屋根の上面高さ
(打設高さ)の精度が確保される。また、ワイヤロープ
11は着脱自在とされているので、その取り扱いが簡単で
ある。
According to this embodiment, since the ridge beam (angle member) 10 having a strong bending stress is passed to the ridge portion 6 via the auxiliary bar 9, even if the pump hose 5 is placed on the ridge beam 10, the ridge beam 10 is deformed due to its weight. If the wire rope 11 is stretched from the ridge beam 10 to the eaves end portion 7 without going down or down, the height of the upper surface of the concrete roof can be easily and reliably positioned. Moreover, in the unlikely event that the worker rides on the rebar 1, the rebar 1
Even if a part of it is deformed, it does not affect the tension of the wire rope 11, so that the accuracy of the upper surface height (punching height) of the concrete roof is always ensured. Also wire rope
The 11 is detachable, so its handling is easy.

なお、前記ラインとしては、ワイヤロープ11の替りに、
コンクリート打設作業中に作業員に踏まれても元のレベ
ルまで復帰が可能なように弾力性を有するゴム材を用い
ても良く、また、同じ効果を得るためにワイヤロープ11
の一部(前端部、後端部)に伸縮自在にゴム材を介させ
ても良い。
As the line, instead of the wire rope 11,
A rubber material having elasticity may be used so that it can be returned to the original level even if it is stepped on by a worker during concrete pouring work, and in order to obtain the same effect, the wire rope 11
A rubber material may be extensible in a part (front end portion, rear end portion) of the above.

「発明の効果」 以上詳細に説明したように、この発明によると勾配屋根
の棟部から軒先部にかけてコンクリート屋根の上面高さ
の基準にするためのラインを張設し、このライン高さに
合わせてコンクリートを打設するようにしたから、コン
クリート屋根の上面高さを極めて簡単かつ確実に位置決
めし得てコンクリートの打設作業や仕上げ作業をスムー
ズに実施することができる。しかも、屋根に沿って複数
本のラインを等間隔に張設すれば、屋根全体を正確かつ
平らに打設することができる。
[Effects of the Invention] As described in detail above, according to the present invention, a line is set up from the ridge part of the pitched roof to the eaves part as a reference for the height of the upper surface of the concrete roof, and adjusted to this line height. Since the concrete is placed by pouring, the height of the upper surface of the concrete roof can be positioned extremely easily and reliably, and the concrete placing work and the finishing work can be smoothly performed. Moreover, if a plurality of lines are stretched at equal intervals along the roof, the entire roof can be driven accurately and flatly.

また、コンクリート屋根内部には構造鉄筋のみが配され
ているので、従来のレベル筋の存在に起因する錆の発生
や漏水がなくなる。
Further, since only the structural reinforcing bars are arranged inside the concrete roof, the generation of rust and water leakage due to the existing level reinforcing bars are eliminated.

さらに、以上のことによりコンクリート屋根の上面高さ
不良による上面再仕上げや漏水防護作業などコンクリー
ト屋根の補修作業を行う必要がなくなるので、工期およ
び費用の削減を図ることができ、もってコストダウンの
実現を図ることができる。
Furthermore, as a result of the above, there is no need to perform repair work on the concrete roof such as refinishing the top surface of the concrete roof due to defective height of the top surface or water leakage protection work, so it is possible to reduce the construction period and cost, and thus realize cost reduction. Can be achieved.

【図面の簡単な説明】[Brief description of drawings]

第1図および第2図はこの発明の一実施例であって、第
1図は勾配屋根の断面図、第2図は勾配屋根の斜視図、
第3図はこの発明の従来例であって、勾配屋根の断面図
である。 3……型枠、6……棟部、7……軒先部、11……ライン
(ワイヤロープ)、C……コンクリート。
1 and 2 show an embodiment of the present invention, wherein FIG. 1 is a sectional view of a pitched roof, FIG. 2 is a perspective view of a pitched roof,
FIG. 3 is a sectional view of a pitched roof, which is a conventional example of the present invention. 3 ... Formwork, 6 ... Building, 7 ... Eaves, 11 ... Line (wire rope), C ... Concrete.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】勾配屋根の配筋を行なってその周囲に型枠
を設けこの型枠内にコンクリートを打設して勾配屋根を
構築するコンクリートによる勾配屋根の構築方法におい
て、勾配屋根の棟部から軒先部にかけてコンクリート屋
根の上面高さの基準にするためのラインを張設し、この
ライン高さに合わせてコンクリートを打設することを特
徴とするコンクリートによる勾配屋根の構築方法。
1. A method for constructing a pitched roof using concrete for constructing a pitched roof by arranging a pitched roof and providing a formwork around it to construct a pitched roof. A method for constructing a pitched roof made of concrete, in which a line is stretched from the toe to the eaves part to set the standard height of the upper surface of the concrete roof, and the concrete is placed according to this line height.
JP62201618A 1987-08-12 1987-08-12 How to build a sloping roof by concrete Expired - Lifetime JPH0765371B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62201618A JPH0765371B2 (en) 1987-08-12 1987-08-12 How to build a sloping roof by concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62201618A JPH0765371B2 (en) 1987-08-12 1987-08-12 How to build a sloping roof by concrete

Publications (2)

Publication Number Publication Date
JPS6443654A JPS6443654A (en) 1989-02-15
JPH0765371B2 true JPH0765371B2 (en) 1995-07-19

Family

ID=16444044

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62201618A Expired - Lifetime JPH0765371B2 (en) 1987-08-12 1987-08-12 How to build a sloping roof by concrete

Country Status (1)

Country Link
JP (1) JPH0765371B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104674999A (en) * 2013-11-27 2015-06-03 五冶集团上海有限公司 Spaced formwork supporting and concrete pouring method for pitched roof
CN104674998B (en) * 2013-11-27 2017-01-11 五冶集团上海有限公司 45-degree slope roof cast-in-place concrete construction method
CN107476567A (en) * 2017-07-20 2017-12-15 北京城建远东建设投资集团有限公司 It is a kind of to control the pitched roof gradient and the construction method and track-type facilities of thickness
CN107447903B (en) * 2017-09-03 2023-11-24 廊坊卓锐建材有限公司 Cast-in-situ building heat preservation integrated pitched roof structure and construction method
CN114961071B (en) * 2022-06-23 2025-09-09 中国二十二冶集团有限公司 Archaize roof structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6149850U (en) * 1984-09-03 1986-04-03

Also Published As

Publication number Publication date
JPS6443654A (en) 1989-02-15

Similar Documents

Publication Publication Date Title
CN106677069B (en) A kind of construction method of bridge pier integral formwork support one-shot forming structure
CN110206228B (en) Construction method of semi-fabricated cast-in-place concrete column
CN103410320B (en) The tower silo flexibility platform bitubular connects sliding construction method
CN114016610A (en) Self-climbing formwork and core barrel binding construction method
JPH0765371B2 (en) How to build a sloping roof by concrete
CN114277672B (en) Large-span prestressed concrete bent cap structure and construction method thereof
JPH05287901A (en) Construction of stairs
KR200233599Y1 (en) Installation structure for reinforcing rod of bent
CN117646390A (en) Method for bridge pier construction
JPH11158813A (en) How to build a concrete pier
CN210177369U (en) A prefabricated beam-slab auxiliary pouring platform
CN208858150U (en) A kind of close rib building roof mold
JP2821792B2 (en) Formwork equipment
CN206128635U (en) Transition stair can be dismantled to stair mold and flier
JPS5941530A (en) Installation of foundation bolt for apparatus setting
CN214362896U (en) Detachable pier stud template work platform
JPH08105059A (en) Concrete strip footing and forming method thereof
JPH09184286A (en) Construction method of formwork for concrete structure
CN215052169U (en) Bracket structure based on climb awl
CN112916771B (en) A one-piece tire frame for tying steel bars of assembled cover culvert wall
CN108979133A (en) A kind of close rib building roof mold and application method
JPH05230935A (en) Precast concrete beam formwork members
JP2891113B2 (en) Installation method of reinforced concrete shear walls
JP3102734U (en) Gondola temporary scaffold
JP3153468B2 (en) Construction method of concrete structure