JPH08105122A - Simultaneous construction method for underground structure - Google Patents

Simultaneous construction method for underground structure

Info

Publication number
JPH08105122A
JPH08105122A JP6241110A JP24111094A JPH08105122A JP H08105122 A JPH08105122 A JP H08105122A JP 6241110 A JP6241110 A JP 6241110A JP 24111094 A JP24111094 A JP 24111094A JP H08105122 A JPH08105122 A JP H08105122A
Authority
JP
Japan
Prior art keywords
underground
ground
construction
retaining wall
truss beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6241110A
Other languages
Japanese (ja)
Inventor
Eiji Tajima
英治 田島
Masahiro Takeno
雅博 竹野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP6241110A priority Critical patent/JPH08105122A/en
Publication of JPH08105122A publication Critical patent/JPH08105122A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

(57)【要約】 【目的】山留め壁1の施工直後に、地上躯体A部分と地
下躯体B部分との同時施工を開始できるようにした顕著
な工期短縮が図れる構築物の地下・地上同時施工方法を
提供する。 【構成】初めに地中連続壁の山留め壁1を構築し、次
に、山留め壁1に連結してトラス梁3を地上に建て込
み、以後、トラス梁3上に地上部躯体Aを構築する地上
工事と、山留め壁1内の地下掘削及び地下部躯体Bを構
築する地下工事とを独立に並行して施工し、最終的に地
上部躯体Aと地下部躯体Bとを一体に結合せしめる。
(57) [Abstract] [Purpose] Immediately after the construction of the retaining wall 1, the simultaneous construction of the above-ground structure A part and the below-ground structure B part can be started simultaneously. I will provide a. [Structure] First, the earth retaining wall 1 which is an underground continuous wall is constructed, and then the truss beam 3 is erected on the ground by connecting to the earth retaining wall 1, and thereafter, the above-ground structure A is constructed on the truss beam 3. The above-ground construction and the underground excavation in the retaining wall 1 and the underground construction for constructing the underground skeleton B are independently performed in parallel, and finally the above-ground skeleton A and the underground skeleton B are integrally combined.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、構築物の施工方法に係
り、特に、地上工事と地下工事を分離して同時に並行し
て進めることにより工期短縮を図る構築物の地下地上同
時施工方法の改良に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a structure, and more particularly, to an improvement of a method of constructing a structure underground and underground by simultaneously separating the aboveground work and the underground work and proceeding in parallel at the same time. .

【0002】[0002]

【従来の技術】従来の構築物の地下地上同時施工方法と
しては、逆打ち工法と一階床先行工法とがある。逆打ち
工法は、地下の根切り工事と平行して、一階の梁及び床
等の本設躯体を構築し、これを山留め支保工としながら
地下一階,地下二階へと下階に向かって順次根切りと躯
体の構築を繰り返していく工法である。
2. Description of the Related Art Conventional methods for constructing underground structures above ground include a reverse construction method and a first-floor preceding construction method. In the reverse construction method, in parallel with the underground root cutting work, a permanent building structure such as beams and floors on the first floor is constructed, and this is used as mountain retaining support to the lower floors to the first basement floor and the second basement floor. It is a construction method in which root cutting and construction of the body are repeated in sequence.

【0003】一階床先行工法は、地下の根切り工事に先
行して、一階床を構築する工法である。上記のいずれの
工法も、一階の床梁,場所打ち杭.構真柱を建て込んで
から、地下掘削、地下躯体の構築を行い、その後に地上
の鉄骨建方に取り掛かる。
The first-floor preceding construction method is a method of constructing a first-floor floor prior to underground root cutting work. All of the above construction methods are floor beams and cast-in-place piles on the first floor. After erection of a true pillar, underground excavation and construction of an underground structure will be performed, and then the above-mentioned steel erection will be started.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、このよ
うに、初めに一階の床梁,杭,構真柱を建て込んだ後
に、地下掘削、地下躯体構築、地上の鉄骨建方に取り掛
かる従来工法では、工期短縮に関してそれ程効果的では
ないという問題点がある。そこで本発明は、このような
従来の問題点を改善すべくなされたものであり、山留め
壁(地中連続壁)の施工直後に地上部分と地下部分との
施工を開始できるようにした、顕著な工期短縮が図れる
構築物の地下・地上同時施工方法を提供することを目的
としている。
However, after the floor beams, piles, and structural columns of the first floor are first built in this way, the conventional method of undertaking underground excavation, underground structure construction, and steel erection on the ground is started. Then, there is a problem that it is not so effective in shortening the construction period. Therefore, the present invention has been made to improve such conventional problems, and enables the construction of the above-ground portion and the underground portion to be started immediately after the construction of the retaining wall (underground continuous wall). The purpose is to provide a simultaneous underground and above-ground construction method for structures that can shorten the construction period.

【0005】[0005]

【課題を解決するための手段】上記の目的を達成する本
発明は、構築物の地下地上同時施工方法に係り、初めに
地中連続壁の山留め壁を構築し、次に、該山留め壁に連
結してトラス梁を地上に建て込み、以後、前記トラス梁
上に地上部躯体を構築する地上工事と、前記山留め壁内
の地下掘削及び地下部躯体を構築する地下工事とを独立
に並行して施工し、最終的に前記地上部躯体と地下部躯
体とを一体に結合せしめることを特徴とするものであ
る。
SUMMARY OF THE INVENTION The present invention for achieving the above object relates to a method for simultaneously constructing a subterranean ground of a structure, firstly constructing an earth retaining wall of a continuous underground wall and then connecting it to the earth retaining wall. After that, the truss beam is built on the ground, and thereafter, the above-ground work for constructing the above-ground structure on the truss beam and the underground work for constructing the underground excavation and underground structure inside the retaining wall are performed independently in parallel. The construction is carried out, and finally the above-mentioned skeleton and the below-ground skeleton are integrally connected.

【0006】[0006]

【作用】山留め壁(地中連続壁)の施工終了直後に、以
降の地上部と地下部の工事を分離して施工を開始できる
ように、地上でトラス梁等を設けて工期を短縮する。ト
ラス組み立ては、山留め壁工事の終了直後に行う。また
は、山留め壁施工中に、予め別の場所で組み立ててお
き、山留め壁工事の終了後に定位置にスライドさせて設
置する。
[Operation] A truss beam or the like is provided on the ground to shorten the construction period so that the construction of the above-ground portion and the underground portion can be separated and the construction can be started immediately after the construction of the retaining wall (underground continuous wall) is completed. Assemble the truss immediately after the construction of the retaining wall. Alternatively, during the construction of the retaining wall, it is assembled in another place in advance, and after the completion of the retaining wall construction, it is slid into a fixed position for installation.

【0007】地下工事と地上部の工事とは分離して施工
し、最終工事段階でドッキングさせる。施工中は、地上
部の力をトラス→連壁→支持地盤の順序に流す。最終的
には、地下と地上はドッキングし、地上→地下→支持地
盤の順序で力を流す。
The underground construction and the above-ground construction are carried out separately and docked at the final construction stage. During construction, the force from the ground is applied in the order of truss->wall-> support ground. Eventually, the underground and the ground will be docked, and the power will flow in the order of ground, underground, and supporting ground.

【0008】[0008]

【実施例】以下、本発明の実施例の工事手順を図面を参
照して説明する。 第1工程:山留め壁打設及び地下一次掘削(図1)。 この工程で、先ず、地中連続壁工法により山留め壁1を
打設する。これは、単位の壁体であるパネルを順次構築
し、これらを連結して連続した地中壁とするものであ
る。施工方法は、壁構築区画毎にエレメント溝を掘削
し、掘削したエレメントの溝内に鉄筋かごを挿入し、溝
底からコンクリートを打設していく。こうして構築され
たパネル同士を継ぎ手で一体に結合される。構築された
山留め壁1は、地下外壁となる。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT A construction procedure of an embodiment of the present invention will be described below with reference to the drawings. First step: Placing a retaining wall and excavating underground (Fig. 1). In this step, first, the retaining wall 1 is placed by the underground continuous wall method. This is to construct panels, which are the walls of the units, in sequence and connect them to form a continuous underground wall. The construction method is to excavate an element groove for each wall construction section, insert a reinforcing steel cage into the excavated element groove, and place concrete from the groove bottom. The panels thus constructed are joined together by a joint. The constructed retaining wall 1 serves as an underground outer wall.

【0009】山留め壁1の構築後に、これに囲まれた地
下区画2内を比較的浅く一次掘削する。 第2工程:ト
ラス梁の組立(図2)。 トラス梁3を、構築された上記山留め壁1の上に取り付
ける。トラス梁3は、図3に示すように、大梁4,トラ
ス5を組み立ててなる枠体である。トラス梁3は、山留
め壁1の工事の終了直後に、その上に現場で組み立てな
がら取り付けてもよく、または、山留め壁1の工事の終
了以前に予め別の場所で組み立てておいたものを、山留
め壁1の工事の終了後にその上に横滑りさせて載せ取り
付けるようにしても良い。
After the construction of the retaining wall 1, the underground section 2 surrounded by the retaining wall 1 is excavated relatively shallowly. Second step: truss beam assembly (Fig. 2). The truss beam 3 is mounted on the constructed retaining wall 1. The truss beam 3 is a frame body formed by assembling the large beam 4 and the truss 5, as shown in FIG. The truss beam 3 may be mounted on the ground retaining wall 1 immediately after the construction of the mountain retaining wall 1 while assembling it, or the truss beam 3 that has been assembled in another place before the construction of the mountain retaining wall 1 in advance, After the construction of the mountain retaining wall 1 is completed, the mountain retaining wall 1 may be slid on and mounted thereon.

【0010】次いで、そのトラス梁3が構築された一階
床部分に、一階床コンクリート6を打設する。トラス梁
3の二階床部分は、図2及び図4に示すように、地上躯
体を構築しない区画部分に必要に応じてブレース8を取
り付ける。その後、前記ブレース8を取り付けた区画を
除いて二階床コンクリート9を打設する。しかし、最終
的にトラス両端が必要な場合(1F床面積>基準階床面
積のとき)には、一階コンクリート打設後、2階も同様
にコンクリート打設を行う。
Next, the first-floor concrete 6 is poured into the first-floor portion where the truss beam 3 is constructed. As shown in FIG. 2 and FIG. 4, the brace 8 is attached to the second floor portion of the truss beam 3 in a partition portion that does not construct a ground frame, as necessary. After that, the second-floor concrete 9 is placed except for the section where the brace 8 is attached. However, if both ends of the truss are finally required (1F floor area> standard floor area), after the first floor concrete is placed, the second floor is also similarly placed.

【0011】第3工程:地上部躯体建方、地下部掘削
(図5)。 地上部は、前工程で地上に架設したトラス梁3の上に、
二階,三階と順次に上階に向けて地上部躯体Aの躯体建
方を行う。同時に、平行して、地下部は地下区画2内の
掘削を所要の深さまで行う。 第4工程:地上部躯体建方、地下部躯体建方(図6)。
Third step: erection of the skeleton on the ground and excavation of the underground (Fig. 5). The above-ground part is on the truss beam 3 installed on the ground in the previous process,
The erection of the skeleton of the above-ground structure A is performed on the second and third floors in order toward the upper floor. At the same time, in parallel, the underground section excavates the underground section 2 to a required depth. 4th step: above-ground building structure, underground building structure (Fig. 6).

【0012】地上部は、第3工程に引き続いて地上部躯
体Aの上階部分の躯体建方を行う。一方、所定深さ迄の
掘削を終了した地下部(図では地下二階迄)では、杭1
0の現場打ち工事(図6a)、またはマットスラブ施工
(図6b)後、構真柱11(本設鉄骨柱である)の建て
込み等を含む地下部躯体Bの躯体建方を行う。以上の第
2工程から第4工程に到る間は、構築された地上部躯体
Aによる負荷は、トラス梁3から山留め壁1を経て支持
地盤に順に伝わり受け止められる。
Following the third step, the above-ground portion carries out the erection of the upper floor of the above-ground structure A. On the other hand, in the underground part (up to the second basement in the figure) where the excavation to the predetermined depth has been completed, piles 1
After the in-situ construction work (Fig. 6a) of No. 0 (Fig. 6a) or the mat slab construction work (Fig. 6b), the skeleton erection of the underground skeleton B including the construction of the true column 11 (which is the main steel column) is performed. During the steps from the second step to the fourth step described above, the load by the constructed above-ground structure A is transmitted in order from the truss beam 3 through the mountain retaining wall 1 to the supporting ground and received.

【0013】第5工程:地下躯体と地上躯体のドッキン
グ、及び不要な場合に限りトラス部の一部の部材の撤去
(図7)。 地下部躯体Bの構真柱11と地上部躯体Aの鉄骨柱12
とが接続されて一体になる。続いて、設計上不要な場合
に限り、トラス梁3(図7)が撤去される。これ以後の
躯体による負荷は、地上,地下,支持地盤の順に伝わり
受け止められることになる。かくして、この実施例によ
れば、従来のように一階の梁,杭,構真柱を建て込んで
から地下掘削、地上の鉄骨建方の工法のように、地上と
地下工事が互いに影響し合うことがなく、それぞれの工
事は独立しており、同時に平行して行うことができる。
Fifth step: docking of the underground structure and the above-ground structure, and removal of some members of the truss part only when unnecessary (FIG. 7). Structural column 11 of underground structure B and steel column 12 of aboveground structure A
And are connected and become one. Subsequently, the truss beam 3 (FIG. 7) is removed only when it is unnecessary in the design. Subsequent loads from the skeleton will be transmitted and received in the order of ground, underground, and supporting ground. Thus, according to this embodiment, as in the conventional method of constructing beams, piles, and structural columns on the first floor and then excavating underground, or constructing a steel frame on the ground, the above-ground and underground works influence each other. There is no match and each work is independent and can be done in parallel at the same time.

【0014】[0014]

【発明の効果】以上、説明したように、本発明の構築物
の地下地上同時施工方法によれば、地中連続壁の山留め
壁を構築後、その山留め壁を利用してトラス梁を地上に
建て込み、以後は、そのトラス梁を介して加重を支持地
盤に受け流しながら、トラス梁上に地上部躯体を構築し
つつ、山留め壁内の掘削・地下部躯体の構築を地上工事
と独立に並行して施工し、最終的に前記地上部躯体と地
下部躯体とを一体に結合せしめるものであるから、建築
工期の大幅な短縮が実現できるという効果を奏する。
As described above, according to the method for simultaneously constructing underground structures above ground according to the present invention, after building the earth retaining wall of the underground continuous wall, the truss beam is built on the ground using the earth retaining wall. After that, while constructing the above-ground structure on the truss beam while unloading the weight to the supporting ground through the truss beam, excavation inside the mountain retaining wall and construction of the underground structure are performed in parallel with the ground work independently. Since the above-mentioned structure and the underground structure are finally integrally combined, the construction period can be significantly shortened.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の第1工程の説明図である。FIG. 1 is an explanatory diagram of a first step of the present invention.

【図2】本発明の第2工程の説明図である。FIG. 2 is an explanatory diagram of a second step of the present invention.

【図3】本発明のトラス梁の一階部分の平面図である。FIG. 3 is a plan view of the first floor portion of the truss beam of the present invention.

【図4】本発明のトラス梁の二階部分の平面図である。FIG. 4 is a plan view of the second floor portion of the truss beam of the present invention.

【図5】本発明の第3工程の説明図である。FIG. 5 is an explanatory diagram of a third step of the present invention.

【図6】本発明の第4工程の説明図である。(a)は杭
打ち込みの場合、(b)はマットスラブ施工の場合を示
す。
FIG. 6 is an explanatory diagram of a fourth step of the present invention. (A) shows the case of pile driving, (b) shows the case of mat slab construction.

【図7】本発明の第5工程の説明図である。FIG. 7 is an explanatory diagram of a fifth step of the present invention.

【符号の説明】[Explanation of symbols]

1 山留め壁 3 トラス梁 10 杭 10A マットスラブ 11 構真柱 A 地上部躯体 B 地下部躯体 1 Mountain retaining wall 3 Truss beam 10 Pile 10A Mat slab 11 Structural true pillar A Aboveground structure B Underground structure

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 地中連続壁の山留め壁を構築後、該山留
め壁に連結してトラス梁を地上に建て込み、以後、前記
トラス梁上の地上部躯体の構築と、前記山留め壁内の地
下掘削及び地下部躯体の構築とを独立に並行して施工
し、最終的に前記地上部躯体と地下部躯体とを一体に結
合せしめることを特徴とする構築物の地下地上同時施工
方法。
1. After constructing the earth retaining wall of the underground continuous wall, the truss beam is connected to the earth retaining wall and the truss beam is built on the ground, and thereafter, the construction of the above-ground part frame on the truss beam and the inside of the earth retaining wall. Underground simultaneous construction method for a structure, characterized in that underground excavation and construction of an underground structure are independently and concurrently performed, and finally the above-ground structure and the underground structure are integrally connected.
JP6241110A 1994-10-05 1994-10-05 Simultaneous construction method for underground structure Pending JPH08105122A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6241110A JPH08105122A (en) 1994-10-05 1994-10-05 Simultaneous construction method for underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6241110A JPH08105122A (en) 1994-10-05 1994-10-05 Simultaneous construction method for underground structure

Publications (1)

Publication Number Publication Date
JPH08105122A true JPH08105122A (en) 1996-04-23

Family

ID=17069438

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6241110A Pending JPH08105122A (en) 1994-10-05 1994-10-05 Simultaneous construction method for underground structure

Country Status (1)

Country Link
JP (1) JPH08105122A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20150013630A (en) 2012-06-04 2015-02-05 미쯔비시 레이온 가부시끼가이샤 Resin composition for anti-fouling coating material, anti-fouling coating material, and anti-fouling film
JP2017128951A (en) * 2016-01-21 2017-07-27 株式会社大林組 Reverse strike method
JP2020070701A (en) * 2018-11-03 2020-05-07 大成建設株式会社 Underground structure, building and method for constructing underground structure
JP2023077832A (en) * 2021-11-25 2023-06-06 清水建設株式会社 Construction method of underground structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20150013630A (en) 2012-06-04 2015-02-05 미쯔비시 레이온 가부시끼가이샤 Resin composition for anti-fouling coating material, anti-fouling coating material, and anti-fouling film
JP2017128951A (en) * 2016-01-21 2017-07-27 株式会社大林組 Reverse strike method
JP2020070701A (en) * 2018-11-03 2020-05-07 大成建設株式会社 Underground structure, building and method for constructing underground structure
JP2023104993A (en) * 2018-11-03 2023-07-28 大成建設株式会社 Foundation construction method of underground structure
JP2023077832A (en) * 2021-11-25 2023-06-06 清水建設株式会社 Construction method of underground structure

Similar Documents

Publication Publication Date Title
JP4558145B2 (en) Seismic isolation method for existing buildings
JPH0220767A (en) Earthquake-proofing method for existing building
JPH08105122A (en) Simultaneous construction method for underground structure
JP2001271497A (en) Temporary receiving method for existing buildings
JPH0684690B2 (en) Building basement extension method
JP2003003690A (en) Seismic isolation method for seismically isolated buildings and existing buildings
JP2757026B2 (en) Reverse construction method of basement structure
JP2768178B2 (en) How to build underground structures
JPH0721196B2 (en) Reverse construction method of underground structure
JPH05141004A (en) Two-step placing construction
JPH09228398A (en) Construction method of high-rise building supported by piles
JPH07119465B2 (en) Underground excavation construction method
JP2894217B2 (en) Building structural frame
JPH08291526A (en) How to build an underground structure
JPH1130053A (en) Construction method of seismic isolation building
JPH0742179A (en) Modified inversion placing construction method
JPH06146308A (en) How to build an underground structure
JPH07103583B2 (en) Construction method for large span underground structure
JPH0657769A (en) Underground structure and its construction method
JPH07173847A (en) Large scale and large depth conformable independent open-cut method
JPH10140588A (en) Reconstruction method of underground structure
JPH08291529A (en) Basement floor construction method
JP2001011874A (en) Construction method for structural stud using precast pile
JP2565457B2 (en) Structure pillar construction method
JPH0765313B2 (en) Underground construction method