JPH08177228A - Joint pin for scaffolding jambs - Google Patents
Joint pin for scaffolding jambsInfo
- Publication number
- JPH08177228A JPH08177228A JP32465094A JP32465094A JPH08177228A JP H08177228 A JPH08177228 A JP H08177228A JP 32465094 A JP32465094 A JP 32465094A JP 32465094 A JP32465094 A JP 32465094A JP H08177228 A JPH08177228 A JP H08177228A
- Authority
- JP
- Japan
- Prior art keywords
- pin
- scaffolding
- frame
- hole
- lock pin
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000002184 metal Substances 0.000 claims description 18
- 229910052751 metal Inorganic materials 0.000 claims description 18
- 238000010276 construction Methods 0.000 claims description 11
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 8
- 239000000463 material Substances 0.000 description 7
- 238000005452 bending Methods 0.000 description 4
- 238000003780 insertion Methods 0.000 description 4
- 230000037431 insertion Effects 0.000 description 4
- 229910052742 iron Inorganic materials 0.000 description 4
- 238000004519 manufacturing process Methods 0.000 description 3
- 238000003825 pressing Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 230000000717 retained effect Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- Mutual Connection Of Rods And Tubes (AREA)
Abstract
Description
【0001】本発明は、順次上方に組み立てていくのに
適した仮設用足場建枠の連結ピンに関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a connecting pin for a scaffolding construction frame for temporary construction, which is suitable for sequentially assembling upwards.
【0002】[0002]
【従来の技術】建物の建築現場において、足場建枠を順
次組み立てていくには、当然に上下に対向する足場建枠
を互いに連結するための連結手段を必要とする。2. Description of the Related Art In order to sequentially assemble scaffold building frames at a building construction site, it is naturally necessary to provide a connecting means for connecting the vertically facing scaffold building frames to each other.
【0003】従来では、この連結手段として下方側の足
場建枠の左右上端部に連結ピンを突設し、これに上方側
の足場建枠の左右下端部を差し込み、しかる後、両者間
にわたって略弓状の抜け止め用ロックーアームをその側
面より係止して両者を互いに連結するタイプのものや、
例えば実開平1−131753号公報に示すように上下
の足場建枠間に連結ピンを遊嵌し、この連結ピンを所要
角度回転操作することによって足場建枠と連結ピンとに
設けた凹凸部を互いに係合させて上下の足場建枠を互い
に連結するタイプのものが提案されている。[0003] Conventionally, as this connecting means, connecting pins are provided at the upper and left upper end portions of the lower scaffolding construction frame, and the lower left and right end portions of the upper scaffolding construction frame are inserted into the connecting pins, and thereafter, approximately between them. A type that locks the arch-shaped lockout arm from the side surface to connect both,
For example, as shown in Japanese Utility Model Laid-Open No. 1-131753, a connecting pin is loosely fitted between upper and lower scaffold building frames, and the connecting pin is rotated by a required angle so that the uneven portions provided on the scaffold building frame and the connecting pin are mutually separated. There has been proposed a type in which the upper and lower scaffold building frames are connected to each other by being engaged with each other.
【0004】[0004]
【発明が解決しようとする課題】上記のような従来技術
にあっては、いずれも下方側の足場建枠の連結ピンに上
方側の足場建枠を差し込む作業とは別個に、これらの上
下の足場建枠を保持しながら両者間の左右のロックアー
ムを係止する作業や、両者間の左右の連結ピンを回転操
作する作業が必要となり、そのため連結作業を行うのに
少なくとも二人の作業者を必要としたり、連結作業が面
倒で能率的でないという問題があった。In the prior art as described above, both the upper and lower scaffold building frames are separated from the work of inserting the upper scaffold building frame into the connecting pins of the lower scaffold building frame. It is necessary to lock the left and right lock arms between the two while holding the scaffolding frame, and to rotate the left and right connecting pins between the two. Therefore, at least two workers must perform the connecting work. However, there was a problem that the connection work was troublesome and inefficient.
【0005】本発明は、これの難点を払拭することを解
決課題とする。An object of the present invention is to eliminate this difficulty.
【0006】[0006]
【課題を解決するための手段】本発明の請求項1に係る
足場建枠用連結ピン15は、管状等の中空状のピン本体
16に、その内側面で支持される支点部20を中心に揺
動可能なロックピン18であって、その一端部の係合突
起21がピン本体16の上段側透孔22aより突出して
足場建枠aに係合すると共にその透孔22a内に退入自
在であり且つ他端部の突出軸部23がピン本体16の下
段側透孔22bから常時突出するロックピン18と、該
ロックピン18をその係合突起21が上段側透孔22a
から突出するように付勢するばね24とを内蔵し、前記
突出軸部23の外端部には、ロックピン18をばね付勢
力に抗して揺動させて前記係合突起21をその透孔22
a内に退入させるように該突出軸部23を引張操作する
ための解除レバー25を設けてなるものである。A scaffolding frame connecting pin 15 according to claim 1 of the present invention is centered around a fulcrum portion 20 supported by an inner side surface of a hollow pin body 16 such as a tube. It is a rockable lock pin 18, and an engaging projection 21 at one end thereof projects from an upper stage side through hole 22a of the pin main body 16 to engage with the scaffolding building frame a and is retractable into the through hole 22a. And the protruding shaft portion 23 at the other end always projects from the lower side through hole 22b of the pin body 16, and the engaging projection 21 of the lock pin 18 has the upper side through hole 22a.
A spring 24 for urging the locking pin 18 so as to project therefrom, and the locking pin 18 is swung against the spring urging force at the outer end portion of the projecting shaft portion 23 so that the engaging projection 21 is transparent. Hole 22
A release lever 25 for pulling the protruding shaft portion 23 so as to retract into the inside of a is provided.
【0007】本発明の請求項2は、請求項1に記載の足
場建枠用連結ピン15において、ロックピン18の係合
突起21にはその先端部に、下り傾斜状の滑り面26が
形成されてなるものである。According to a second aspect of the present invention, in the scaffolding frame connecting pin 15 according to the first aspect, the engaging projection 21 of the lock pin 18 has a downwardly inclined sliding surface 26 formed at the tip thereof. It has been done.
【0008】本発明の請求項3は、請求項1または2に
記載の足場建枠用連結ピン15において、解除レバー2
5は、背板部30aと両側板部30b,30bとでコ字
状に形成された枠片30と、前記背板部30aの一端か
ら一体に突設された把手31とからなり、前記コ字状枠
片30を、その両側板部30b,30bの先端面がピン
本体16の外側面に当接すると共に前記把手31が該枠
片30の真上に位置する状態で、ピン本体16の下段側
透孔22bから突出するロックピン18の突出軸部23
に嵌合して、該突出軸部23を両側板部30b,30b
にピン32で枢着し、前記把手31を介して前記コ字状
枠片30を下向きに回動することによって、突出軸部2
3を引張するようにしたものである。According to a third aspect of the present invention, the release lever 2 is provided in the scaffolding frame connecting pin 15 according to the first or second aspect.
The reference numeral 5 includes a frame piece 30 formed in a U shape by the back plate portion 30a and both side plate portions 30b, 30b, and a handle 31 integrally projecting from one end of the back plate portion 30a. The bottom portion of the pin body 16 of the character-shaped frame piece 30 with the front end surfaces of both side plate portions 30b, 30b abutting the outer surface of the pin body 16 and the handle 31 being positioned directly above the frame piece 30. The protruding shaft portion 23 of the lock pin 18 protruding from the side through hole 22b
By fitting the protruding shaft portion 23 to both side plate portions 30b, 30b.
The protrusion shaft portion 2 is pivotally attached to the protruding shaft portion 2 by a pin 32, and the U-shaped frame piece 30 is rotated downward via the handle 31.
3 is pulled.
【0009】本発明の請求項4は、請求項1〜3のいず
れかに記載の足場建枠用連結ピン15において、ロック
ピン18は、所要長さに切断した所要径を有する金属線
材の中間所要部に弯曲部18aを形成してその突端部を
支点部20とすると共に、該金属線材の両端部をそれぞ
れ前記弯曲部18aの突出方向と同一方向に屈曲して、
その一方の屈曲部18bに係合突起21を形成し、他方
の屈曲部18cに突出軸部23を形成してなるものであ
る。According to a fourth aspect of the present invention, in the scaffolding construction frame connecting pin 15 according to any one of the first to third aspects, the lock pin 18 is a metal wire rod having a required diameter cut into a required length. A curved portion 18a is formed at a required portion and its projecting end portion is used as a fulcrum portion 20, and both ends of the metal wire are bent in the same direction as the projecting direction of the curved portion 18a,
An engaging protrusion 21 is formed on one of the bent portions 18b, and a protruding shaft portion 23 is formed on the other bent portion 18c.
【0010】[0010]
【作用】本発明の請求項1に係る連結ピン15にあって
は、ピン本体16の下端部側を下方側足場建枠bの縦パ
イプ10上端部に取付けた後、ロックピン18の係合突
起21をピン本体16の上段側透孔22a内に退入させ
た状態で、上方側足場建枠aの縦パイプ10をピン本体
16の本体上部16aに差し込む。この差し込み途上で
は、係合突起21がばね24の付勢力によって縦パイプ
10の内側面に弾接している。しかして、上方側足場建
枠aの縦パイプ10がピン本体16への差し込み終了位
置まで達したとき、係合突起21が縦パイプ10の係合
孔14に係合してロック状態となり、この係合突起21
によってピン本体16と上方側足場建枠aの縦パイプ1
0とが連結され、これによって上下の足場建枠a,bが
互いに連結される。In the connecting pin 15 according to the first aspect of the present invention, after the lower end portion of the pin body 16 is attached to the upper end portion of the vertical pipe 10 of the lower scaffolding building frame b, the lock pin 18 is engaged. The vertical pipe 10 of the upper scaffolding frame a is inserted into the main body upper portion 16a of the pin body 16 with the protrusion 21 retracted into the upper-side through hole 22a of the pin body 16. During this insertion, the engaging projection 21 is elastically contacted with the inner surface of the vertical pipe 10 by the urging force of the spring 24. Then, when the vertical pipe 10 of the upper side scaffolding frame a reaches the insertion end position into the pin body 16, the engaging projection 21 engages with the engaging hole 14 of the vertical pipe 10 and becomes in the locked state. Engagement protrusion 21
The vertical pipe 1 of the pin body 16 and the upper side scaffolding frame a
0 and 0 are connected, and thereby the upper and lower scaffold building frames a and b are connected to each other.
【0011】また、上方側足場建枠aを下方側足場建枠
bから取り外すときは、解除レバー25をピン本体16
の外側面に近づく方向に手で押動することにより、ロッ
クピン18がばね付勢力に抗し揺動して、係合突起21
が透孔22a内に退入し、ロック解除の状態となる。し
かして、この状態で上方側足場建枠aの縦パイプ10を
引き抜くことにより、上方側足場建枠aを下方側足場建
枠bから容易に取り外すことができる。When removing the upper scaffolding frame a from the lower scaffolding frame b, the release lever 25 is moved to the pin body 16
When the lock pin 18 swings against the spring biasing force by being manually pushed in a direction approaching the outer side surface of the engaging projection 21.
Moves into the through hole 22a and is unlocked. By pulling out the vertical pipe 10 of the upper scaffolding frame a in this state, the upper scaffolding frame a can be easily removed from the lower scaffolding frame b.
【0012】請求項2に係る連結ピン15にあっては、
上方側足場建枠aの縦パイプ10をピン本体16の本体
上部16aに差し込むことにより、その差し込み途上に
おいてピン本体16の上段側透孔22aから突出してい
る係合突起21の下り傾斜状滑り面26に当接し、これ
により係合突起21がばね付勢力に抗してピン本体16
の内部側へ押動されるような負荷を受けて、係合突起2
1がその透孔22a内に退入し、しかして上記縦パイプ
10の下端がピン本体16の所定位置まで来たとき、係
合突起21が縦パイプ10の係合孔14に係合してロッ
ク状態となる。従って、上方側足場建枠aの縦パイプ1
0をピン本体16に差し込むだけで、上下両足場建枠
a,bが自動的に連結される。In the connecting pin 15 according to claim 2,
By inserting the vertical pipe 10 of the upper scaffold building frame a into the main body upper portion 16a of the pin main body 16, the downward sloped sliding surface of the engaging projection 21 protruding from the upper-stage through hole 22a of the pin main body 16 during the insertion. 26, whereby the engagement protrusion 21 resists the spring biasing force and the pin body 16
The engaging projection 2 receives a load that is pushed toward the inside of the
When the lower end of the vertical pipe 10 reaches the predetermined position of the pin body 16, the engaging projection 21 engages with the engaging hole 14 of the vertical pipe 10. It will be locked. Therefore, the vertical pipe 1 of the upper side scaffolding frame a
Only by inserting 0 into the pin body 16, the upper and lower scaffold building frames a and b are automatically connected.
【0013】請求項3に係る連結ピン15にあっては、
上方側足場建枠aを下方側足場建枠bから取り外すにあ
たり、解除レバー25の把手31を引き下げると、コ字
状枠片30がピン本体16外側面に当接している両側板
部30b,30bの下端部を中心に回動し、これに伴い
ピン本体16の下段側透孔22bから突出している突出
軸部23が外側へ引張され、それによりロックピン18
は支点部20を中心に係合突起21が上段側透孔22a
内に退入する方向に揺動する。しかして、コ字状枠片3
0を更に回動して該枠片30の下端面30dをピン本体
16外側面に当接支持させるようにすることにより、係
合突起21が上段側透孔22a内に退入してロック解除
されると共に、ロックピン18がそのロック解除位置に
保持される。このロック解除状態で、上方側足場建枠a
をピン本体16の本体上部16aから引き抜くことによ
り、上方側足場建枠aを下方側足場建枠bから容易に取
り外すことができる。In the connecting pin 15 according to claim 3,
When removing the upper side scaffolding frame a from the lower side scaffolding frame b, when the handle 31 of the release lever 25 is pulled down, the U-shaped frame piece 30 is in contact with the outer side surface of the pin body 16, both side plate portions 30b, 30b. Of the lock pin 18 is rotated about the lower end portion of the lock pin 18, and accordingly, the protruding shaft portion 23 protruding from the lower-stage through hole 22b of the pin body 16 is pulled outward.
The engaging projection 21 is centered on the fulcrum portion 20 and the upper side through hole 22a is formed.
It swings in the direction of moving in and out. Then, the U-shaped frame piece 3
0 is further rotated so that the lower end surface 30d of the frame piece 30 is brought into contact with and supported by the outer surface of the pin body 16, so that the engaging projection 21 retracts into the upper through hole 22a and unlocks. At the same time, the lock pin 18 is held in its unlocked position. In this unlocked state, the upper scaffolding frame a
The upper side scaffolding building frame a can be easily removed from the lower side scaffolding building frame b by pulling out from the upper body 16a of the pin body 16.
【0014】請求項4に係る連結ピン15にあっては、
ロックピン18を金属線材を使用して、プレス加工等に
より形成することによって、金属板材や角材で形成する
場合に比べ、製作が簡単容易となる上に、ロックピン1
8の機械的強度、特に、ピン本体16と上方側足場建枠
aの縦パイプ10とを連結する係合突起21部分の曲げ
強度を十分に大きくすることができて、使用上の安全性
を十分確保できると共に、耐用寿命を延ばすことができ
る。In the connecting pin 15 according to claim 4,
By forming the lock pin 18 by using a metal wire rod by press working or the like, the manufacturing becomes easier and easier than the case of forming the lock pin 18 by a metal plate material or a square material, and the lock pin 1
8, the bending strength of the engaging projections 21 connecting the pin body 16 and the vertical pipe 10 of the upper side scaffolding building frame a can be sufficiently increased, and the safety in use is improved. It can be ensured sufficiently and the service life can be extended.
【0015】[0015]
【実施例】図1は、上方側の足場建枠aと下方側の足場
建枠bとの連結前の状態を示し、各足場建枠は、左右一
対の縦パイプ10,10と、両縦パイプ10,10の上
端部同士ををつなぐ横パイプ11,11と、縦横パイプ
10,11にわたって取付けられた補強桟12,12と
からなるもので、横パイプ11に足場板13がその掛合
爪13aを掛合させることにより懸架されるようになっ
ている。そして、縦パイプ10の下端部には足場板13
側に面して係合孔14が設けられており、上下の縦パイ
プ10,10の間に本発明に係る連結ピン15が差し込
まれることになる。EXAMPLE FIG. 1 shows a state before the scaffold building frame a on the upper side and the scaffold building frame b on the lower side are connected to each other. Each scaffold building frame is composed of a pair of left and right vertical pipes 10, 10, and both vertical pipes. The horizontal pipes 11 and 11 connect the upper ends of the pipes 10 and 10 and the reinforcing bars 12 and 12 mounted over the vertical and horizontal pipes 10 and 11, and the scaffolding plate 13 is attached to the horizontal pipes 11a. It is designed to be suspended by engaging with. The scaffolding plate 13 is provided at the lower end of the vertical pipe 10.
The engaging hole 14 is provided facing the side, and the connecting pin 15 according to the present invention is inserted between the upper and lower vertical pipes 10, 10.
【0016】図2は、上下の縦パイプ10,10の間に
差し込まれた連結ピン15を示したもので、この連結ピ
ン15は、上下に貫通した円管状のピン本体16を有す
る。このピン本体16は、中央部の肉厚部17を隔てて
その上下両側に本体上部16aと本体下部16bとを形
成し、本体上部16aに上方側足場建枠aの縦パイプ1
0が差し込まれ、そのパイプ10下端面が肉厚部17の
上端面17aに当接して位置決めされ、また本体下部1
6bに下方側足場建枠bの縦パイプ10が差し込まれ
て、そのパイプ10上端面が肉厚部17の下端面17b
に当接して位置決めされる。しかして、上下の縦パイプ
10,10は、ピン本体16の本体上部16a及び本体
下部16bにそれぞれ差し込まれて位置決めされた状態
で、本発明に係る連結ピン15の一部を構成するロック
ピン18と、従来より知られている連結用突起19によ
ってよりピン本体16に連結される。FIG. 2 shows a connecting pin 15 inserted between the upper and lower vertical pipes 10, 10. The connecting pin 15 has a cylindrical pin body 16 that penetrates vertically. The pin main body 16 has a main body upper portion 16a and a main body lower portion 16b formed on both upper and lower sides thereof with a thick portion 17 in the center portion therebetween, and the vertical pipe 1 of the upper side scaffolding frame a is formed on the main body upper portion 16a.
0 is inserted, the lower end surface of the pipe 10 is brought into contact with the upper end surface 17a of the thick portion 17 and positioned, and
The vertical pipe 10 of the lower scaffolding building frame b is inserted into 6b, and the upper end surface of the pipe 10 is the lower end surface 17b of the thick portion 17.
Is abutted against and positioned. Then, the upper and lower vertical pipes 10, 10 are inserted into the upper body 16a and the lower body 16b of the pin body 16 respectively and positioned, and the lock pin 18 constituting a part of the connecting pin 15 according to the present invention. Then, it is more connected to the pin body 16 by the conventionally known connecting projection 19.
【0017】ロックピン18は、図2(A)に示すよう
に、上記円管状ピン本体16に内蔵されて、その内側面
所要部で支持される支点部20を中心に揺動可能であっ
て、その一端部の係合突起21が、ピン本体16の本体
上部16aに穿設された上段側透孔22aより突出して
上方側足場建枠aの縦パイプ10の係合孔14に係合す
ると共にその透孔22a内に退入自在であり、他端部の
突出軸部23がピン本体16の肉厚部17に穿設された
下段側透孔22bから常時突出している。また、ピン本
体16には、ロックピン18をその係合突起21が上段
側透孔22aから突出するように付勢するための板ばね
24が内蔵されており、そしてロックピン18を板ばね
24の付勢力に抗して揺動させて係合突起21を上段側
透孔22a内に退入させるように前記突出軸部23を引
張操作するための解除レバー25が設けられている。As shown in FIG. 2A, the lock pin 18 is built in the circular tubular pin body 16 and is swingable around a fulcrum portion 20 supported by a required portion on the inner surface thereof. , The engaging projection 21 at one end thereof protrudes from the upper stage side through hole 22a formed in the upper body portion 16a of the pin body 16 and engages with the engaging hole 14 of the vertical pipe 10 of the upper side scaffolding building frame a. At the same time, it is freely retractable into the through hole 22a, and the protruding shaft portion 23 at the other end always projects from the lower through hole 22b formed in the thick portion 17 of the pin body 16. Further, the pin body 16 has a built-in leaf spring 24 for urging the lock pin 18 such that the engaging projection 21 thereof projects from the upper through hole 22a. There is provided a release lever 25 for pulling the projecting shaft portion 23 so as to swing the engaging projection 21 into the upper through hole 22a against the urging force of the projecting shaft portion 22a.
【0018】上記ロックピン18は、例えば直径9mm
の鉄線材(金属線材)を所要長さに切断し、そしてプレ
ス加工等により、この鉄線材の中間所要部に湾曲部18
aを形成してその突端部を支点部20とすると共に、そ
の鉄線材の両端部をそれぞれ上記湾曲部18aの突出方
向と同一方向に屈曲して、その一方の屈曲部18bを係
合突起21とし、他方の屈曲部18cを突出軸部23と
することによって形成することができる。この場合、係
合突起21の外径が9mmとなるため、この係合突起2
1が突入係合可能なピン本体16の上段側透孔22a及
び縦パイプ10の係合孔14のそれぞれの内径は、例え
ば10mmとされる。また、下段側透孔22bの内径も
同じ程度とされる。因みに、ピン本体16の外径は、4
1.9mm、縦パイプ10の外径は48.6である。The lock pin 18 has a diameter of 9 mm, for example.
The iron wire rod (metal wire rod) is cut into a required length, and by pressing or the like, the curved portion 18 is formed in the intermediate required portion of the iron wire rod.
a is formed and the projecting end portion is used as the fulcrum portion 20, and both ends of the iron wire are bent in the same direction as the projecting direction of the bending portion 18a, and one of the bent portions 18b is engaged with the engaging projection 21. And the other bent portion 18c is used as the protruding shaft portion 23. In this case, since the outer diameter of the engaging protrusion 21 is 9 mm, the engaging protrusion 2
The inner diameters of the upper-stage through hole 22a of the pin body 16 and the engagement hole 14 of the vertical pipe 10 into which 1 can be inserted and engaged are, for example, 10 mm. Further, the inner diameter of the lower through hole 22b is set to the same level. Incidentally, the outer diameter of the pin body 16 is 4
The vertical pipe 10 has an outer diameter of 48.6 mm.
【0019】このロックピン18は、金属板材を切断加
工したり、金属角材をプレス加工することによっても形
成できるが、縦パイプ10の係合孔14が丸孔であり、
しかもその内径をあまり大きくできないことから、金属
板材や角材の場合には、係合突起21部分の断面が矩形
状となり、従って例えば断面が正方形の金属角材を使用
してロックピン18を形成するものとすれば、内径が1
0mmの係合孔14に係合可能な係合突起21の断面正
方形の一辺の長さは、6.5mm程度となる。この場
合、その係合突起21部分の断面二次モーメントを求め
ると、約149mm4 となる。これに対し、前記のよう
に直径9mmの鉄線を使用してロックピン18を形成し
た場合、係合突起21部分の断面は円形で、その直径は
9mmであるから、この場合の係合突起21部分の断面
二次モーメントは、約322mm4となる。従って、両
者を比較して明らかなように、金属線材による場合は、
その係合突起21部分の断面二次モーメントが金属角材
による場合のそれよりもはるかに大きくなり、十分な曲
げ強度が得られる。また、金属線材によってロックピン
18を形成する場合は、金属板材や角材の場合よりもロ
ックピン18の製作が容易となる。The lock pin 18 can be formed by cutting a metal plate material or pressing a metal square material, but the engaging hole 14 of the vertical pipe 10 is a round hole,
Moreover, since the inner diameter cannot be made too large, in the case of a metal plate material or a square member, the engaging projection 21 portion has a rectangular cross section, and therefore the lock pin 18 is formed by using a metal square material having a square cross section, for example. If so, the inner diameter is 1
The length of one side of the square section of the engaging protrusion 21 that can be engaged with the 0 mm engaging hole 14 is about 6.5 mm. In this case, the geometrical moment of inertia of the engaging projection 21 is about 149 mm 4 . On the other hand, when the lock pin 18 is formed by using the iron wire having the diameter of 9 mm as described above, the engaging projection 21 has a circular cross section and the diameter is 9 mm. The second moment of area of the part is about 322 mm 4 . Therefore, as is clear by comparing the two, when using a metal wire,
The second moment of area of the engaging projection 21 is much larger than that of the case of using a metal square bar, and sufficient bending strength can be obtained. Further, when the lock pin 18 is formed of a metal wire rod, the lock pin 18 is easier to manufacture than when the lock pin 18 is formed of a metal plate material or a square bar.
【0020】図2(A)その他の図面に示されるよう
に、上記ロックピン18の係合突起21にはその先端部
に、下り傾斜状の滑り面26が形成されている。しかし
て、ピン本体16の本体上部16aに上方側足場建枠a
の縦パイプ10を差し込むときに、この縦パイプ10の
下端が上段側透孔22aから突出した係合突起21の滑
り面26に当接し、これによって係合突起21は、板ば
ね24の付勢力に抗してピン本体16の内部側へ押動さ
れるような負荷を受けて、その透孔22a内に退入する
ようになっている。As shown in FIG. 2A and other drawings, the engaging projection 21 of the lock pin 18 is formed with a downwardly inclined sliding surface 26 at the tip thereof. Then, the upper side scaffolding frame a on the upper body 16a of the pin body 16
When the vertical pipe 10 is inserted, the lower end of the vertical pipe 10 comes into contact with the sliding surface 26 of the engaging projection 21 protruding from the upper through hole 22a, whereby the engaging projection 21 is urged by the leaf spring 24. Against this, a load that pushes the pin body 16 toward the inside thereof is received, and the pin body 16 retreats into the through hole 22a.
【0021】板ばね24は、図2(A)及び(B)に示
すように、山形状に形成されていて、その頂部24a
が、ロックピン18の係合突起21寄りの側面部にビス
27で取付けられ、その両端部24b,24bが、ピン
本体16の透孔22a22bとは反対側の内側面に弾接
される。この板ばね24をロックピン18に取付けるに
は、上記のようにビス27によって固着せずに、同図の
(C)に示すように、ロックピン18の側面部に突起2
8を突設し、この突起28が嵌合可能な凹部29を板ば
ね24の頂部24aに設けておいて、その凹部29を突
起28に嵌合させるようにしてもよい。As shown in FIGS. 2A and 2B, the leaf spring 24 is formed in a mountain shape and has a top portion 24a.
Is attached to a side surface portion of the lock pin 18 near the engaging projection 21 with a screw 27, and both end portions 24b, 24b thereof are elastically contacted with the inner side surface of the pin body 16 opposite to the through holes 22a22b. In order to attach the leaf spring 24 to the lock pin 18, the protrusion 2 is attached to the side surface of the lock pin 18 as shown in FIG.
It is also possible to project 8 and provide a recess 29 into which the projection 28 can be fitted, on the top portion 24a of the leaf spring 24, and to fit the recess 29 into the projection 28.
【0022】解除レバー25は、鋼板等の金属板によっ
て、背板部30a及び両側板部30b,30bからなる
コ字状の枠片30と、背板部30aの一端から突設され
た把手31とを一体に形成してなるもので、図2の
(A)に示すように、コ字状枠片30を、その両側板部
30b,30bの先端面がピン本体16の外側面に当接
すると共に前記把手31がコ字状枠片30の真上に位置
する状態で、ピン本体16の下段側透孔22bから突出
するロックピン18の突出軸部23に嵌合させて、該突
出軸部23を両側板部30b,30bにピン32により
枢着している。上記コ字状枠片30には両側板部30
b,30bの先端面下端部に回動案内面30cを有す
る。また、この場合、上記ピン32から両側板部30
b,30bの下端面30cまでの距離は、同ピン32か
ら両側板部30b,30bの先端面までの距離よりも長
くなっている。The release lever 25 is made of a metal plate such as a steel plate and has a U-shaped frame piece 30 including a back plate portion 30a and both side plate portions 30b and 30b, and a handle 31 protruding from one end of the back plate portion 30a. 2 is integrally formed, and as shown in FIG. 2 (A), the U-shaped frame piece 30 has a tip end surface of both side plate portions 30b, 30b contacting an outer surface of the pin body 16. Along with the handle 31 positioned right above the U-shaped frame piece 30, the handle 31 is fitted into the protruding shaft portion 23 of the lock pin 18 protruding from the lower-stage side through hole 22b of the pin body 16, and the protruding shaft portion 23 is pivotally attached to both side plate portions 30b, 30b by a pin 32. The U-shaped frame piece 30 has both side plate portions 30.
Rotation guide surfaces 30c are provided at the lower end portions of the front end surfaces of b and 30b. Further, in this case, the pin 32 is connected to the both side plate portions 30.
The distance from the pin 32 to the lower end surfaces 30c of the b and 30b is longer than the distance from the pin 32 to the tip surfaces of the side plate portions 30b and 30b.
【0023】しかして、前記把手31を、図2(A)の
矢印方向に引くと、コ字状枠片30がピン本体16外側
面に当接している両側板部30b,30bの先端面下端
部を中心にその回動案内面30cを介して回動し、これ
に伴いピン本体16の下段側透孔22bから突出してい
る突出軸部23が外側へ引張され、それによりロックピ
ン18は板ばね24の付勢力に抗して支点部20を中心
に係合突起21が上段側透孔22a内に退入する方向に
揺動する。しかして、コ字状枠片30を更に回動して該
枠片30の下端面30dをピン本体16外側面に当接支
持させるようにすることにより、係合突起21が上段側
透孔22a内に退入してロック解除されると共に、ロッ
クピン18がそのロック解除位置に保持される(図4参
照)。When the handle 31 is pulled in the direction of the arrow in FIG. 2 (A), the U-shaped frame piece 30 is in contact with the outer surface of the pin body 16, and the lower ends of the front end surfaces of the side plate portions 30b, 30b. The pin is pivoted around its pivotal guide surface 30c, and along with this, the projecting shaft portion 23 projecting from the lower-stage through hole 22b of the pin body 16 is pulled outward, whereby the lock pin 18 becomes a plate. The engaging projection 21 swings around the fulcrum portion 20 in the direction of retracting into the upper through hole 22a against the biasing force of the spring 24. Then, the U-shaped frame piece 30 is further rotated so that the lower end surface 30d of the frame piece 30 is brought into contact with and supported by the outer surface of the pin body 16, so that the engaging projection 21 is brought into contact with the upper through hole 22a. The lock pin 18 is retained in its unlocked position while retracting inside and being unlocked (see FIG. 4).
【0024】また、連結ピン15を下方側足場建枠bに
連結するための連結用突起19は、周知構造のもので、
図2の(A)に示すように、左右一対設けられ、両連結
用突起19,19は、断面略U字状の板ばね33の両端
部にそれぞれ取付けてあって、前記連結ピン15の本体
下部16b下端部に穿設された両透孔34,34から上
記板ばね33の付勢力により常時突出している。従っ
て、使用にあたっては、上記両透孔34,34から突出
している両連結用突起19,19を、板ばね33付勢力
に抗して連結ピン15の内部に退入せしめた状態で、下
方側足場建枠bの縦パイプ10の上端部に差し込み、両
連結用突起19,19を縦パイプ10の連結孔35,3
5に係合させる。これによって、連結ピン15は下方側
足場建枠bの縦パイプ10の上端部に取付けられ、一旦
取付けた後は不使用時でも取り外す必要はない。The connecting projection 19 for connecting the connecting pin 15 to the lower scaffold building frame b has a well-known structure.
As shown in FIG. 2A, a pair of left and right connecting projections 19 and 19 are attached to both ends of a leaf spring 33 having a substantially U-shaped cross section, and the connecting pin 15 has a main body. The through holes 34, 34 formed at the lower end of the lower portion 16b are constantly projected by the urging force of the leaf spring 33. Therefore, in use, the connecting projections 19, 19 projecting from the through holes 34, 34 are retracted into the connecting pin 15 against the urging force of the leaf spring 33, and the lower side Insert it into the upper end of the vertical pipe 10 of the scaffolding frame b, and connect both projections 19, 19 to the connecting holes 35, 3 of the vertical pipe 10.
5 is engaged. As a result, the connecting pin 15 is attached to the upper end of the vertical pipe 10 of the lower scaffold building frame b, and once attached, it is not necessary to remove it even when it is not used.
【0025】次に、上記のようにして下方側足場建枠b
に取付けた連結ピン15を介して、この下方側足場建枠
bに上方側足場建枠aを連結するには、図3の(A)に
示すように、上方側足場建枠aの縦パイプ10をピン本
体16の本体上部16aに差し込むことにより、その差
し込み途上においてピン本体16の上段側透孔22aか
ら突出している係合突起21の下り傾斜状滑り面26に
当接し、これにより係合突起21は板ばね24の付勢力
に抗してピン本体16の内部側へ押動されるような負荷
を受け、しかしてロックピン18は支点部20を中心に
同図面に関し時計回りに揺動し、同図の仮想線図示のよ
うに係合突起21が上段側透孔22a内に退入し、同時
に突出軸部23が下段側透孔22bから更に突出する状
態となる。このとき、解除レバー25は例えば同図の仮
想線図示のような状態となる。Next, the lower scaffolding frame b as described above.
To connect the upper scaffolding frame a to the lower scaffolding frame b via the connecting pin 15 attached to the vertical scaffolding frame of the upper scaffolding frame a as shown in FIG. By inserting 10 into the main body upper portion 16a of the pin main body 16, it abuts on the descending inclined sliding surface 26 of the engaging projection 21 projecting from the upper-stage through hole 22a of the pin main body 16 in the process of insertion, thereby engaging. The protrusion 21 receives a load that pushes it toward the inside of the pin body 16 against the urging force of the leaf spring 24, so that the lock pin 18 swings around the fulcrum portion 20 in the clockwise direction in the drawing. Then, as shown by the phantom line in the figure, the engaging projection 21 retracts into the upper through hole 22a, and at the same time, the protruding shaft portion 23 further projects from the lower through hole 22b. At this time, the release lever 25 is in a state as shown by the phantom line in the figure, for example.
【0026】しかして、図3の(B)に示すように、上
記縦パイプ10の下端面がピン本体16の肉厚部17の
上端面17aに当接したとき、縦パイプ10の係合孔1
4がピン本体16の上段側透孔22aと合致する状態と
なり、これにより係合突起21に対する退入付勢力が解
放されて、この係合突起21が板ばね24の付勢力によ
り上記透孔22aから縦パイプ10の係合孔14に係合
し、この係合突起21によってピン本体16と上方側足
場建枠aの縦パイプ10とが連結され、これによって上
下の足場建枠a,bが互いに連結されることになる。As shown in FIG. 3B, when the lower end surface of the vertical pipe 10 comes into contact with the upper end surface 17a of the thick portion 17 of the pin body 16, the engaging hole of the vertical pipe 10 is formed. 1
4 is brought into a state of matching with the upper side through hole 22a of the pin body 16, whereby the retracting biasing force with respect to the engaging projection 21 is released, and the engaging projection 21 is pushed through the through hole 22a by the biasing force of the leaf spring 24. To the engaging hole 14 of the vertical pipe 10, and the engaging projection 21 connects the pin body 16 to the vertical pipe 10 of the upper scaffolding frame a, whereby the upper and lower scaffolding frames a and b are connected. Will be connected to each other.
【0027】上記のように、上方側足場建枠aの縦パイ
プ10下端部を、下方側足場建枠bの縦パイプ10に取
付けたピン本体16の本体上部16aに差し込むだけ
で、上下両足場建枠a,bが自動的に連結されることに
なり、従って連結作業を一人の作業者できわめて簡単容
易に行うことができる。尚、上方側足場建枠aの縦パイ
プ10の差し込み途上でロックピン18の突出軸部23
が下段側透孔22bから更に突出するとき、解除レバー
25は、図3(A)の仮想線図示のように、コ字状枠片
30がピン本体16外側面に当接している側板部30b
の上端部を中心に時計回りに回動することになる。As described above, by simply inserting the lower end of the vertical pipe 10 of the upper scaffolding building frame a into the upper body 16a of the pin body 16 attached to the vertical pipe 10 of the lower scaffolding building frame b, both upper and lower scaffolding scaffolds can be inserted. Since the building frames a and b are automatically connected, the connecting work can be performed by one operator extremely easily. Incidentally, the protruding shaft portion 23 of the lock pin 18 is inserted in the middle of inserting the vertical pipe 10 of the upper side scaffold building frame a.
Is further projected from the lower through hole 22b, the release lever 25 has a side plate portion 30b in which the U-shaped frame piece 30 is in contact with the outer surface of the pin body 16 as shown by the phantom line in FIG.
It will rotate clockwise around the upper end of the.
【0028】尚、この実施例では、ロックピン18の係
合突起21先端部に下り傾斜状の滑り面26を設けて、
上記のように上方側足場建枠aの縦パイプ10を、ピン
本体16の本体上部16aに差し込むだけで、上下両足
場建枠a,bが自動的に連結できるようにしているが、
ロックピン18の係合突起21先端部に滑り面26を設
けない場合には、上方側足場建枠aの縦パイプ10をピ
ン本体16の本体上部16aに差し込むにあたり、作業
者が、ピン本体16の上段側透孔22aから突出してい
る係合突起21の先端部を、板ばね24の付勢力に抗し
ピン本体16内部側へ押動して、手動で上段側透孔22
a内に退入させるようにすればよく、この場合の作業も
一人の作業者で容易に行うことができる。In this embodiment, a downwardly inclined sliding surface 26 is provided at the tip of the engaging projection 21 of the lock pin 18.
As described above, by simply inserting the vertical pipe 10 of the upper scaffolding frame a into the upper body 16a of the pin body 16, the upper and lower scaffolding frames a and b can be automatically connected.
When the sliding surface 26 is not provided at the tip of the engaging projection 21 of the lock pin 18, the worker inserts the vertical pipe 10 of the upper scaffolding building frame a into the upper body 16 a of the pin body 16 by an operator. The tip end portion of the engaging projection 21 protruding from the upper side through hole 22a is pushed to the inside of the pin body 16 against the urging force of the leaf spring 24, and the upper side through hole 22 is manually operated.
It suffices to allow the operator to retreat into the inside of a, and the work in this case can be easily performed by one operator.
【0029】一方、上方側足場建枠aを下方側足場建枠
bから取り外す場合には、図4に示すように、解除レバ
ー25の把手31を、同図の矢印方向に引くと、コ字状
枠片30がピン本体16外側面に当接している両側板部
30b,30bの先端面下端部を中心にその回動案内面
30cを介して回動し、これに伴いピン本体16の下段
側透孔22bから突出している突出軸部23が外方へ引
張され、それによりロックピン18は、板ばね24の付
勢力に抗して支点部20を中心に係合突起21が上段側
透孔22a内に退入する方向に揺動する。しかして、コ
字状枠片30を更に回動させ、図4の仮想線で示すよう
にようにコ字状枠片30の下端面30dをピン本体16
外側面に当接支持させることにより、同図の仮想線図示
のように係合突起21が上段側透孔22a内に完全に退
入してロック解除されると共に、ロックピン18はこの
ロック解除位置に保持される(図4参照)。従って、こ
のように係合突起21がその透孔22a内に退入したロ
ック解除の状態で、上方側足場建枠aをピン本体16の
本体上部16aから引き抜けばよい。このとき、解除レ
バー25によってロックピン18がロック解除位置に保
持されるため、上方側足場建枠aの引き抜き作業が非常
に楽になる。上方側足場建枠aの引き抜き後は、解除レ
バー25の把手31を図4の仮想線図示の位置から上方
へ引き上げて同図の実線図示の位置に戻せば、ロックピ
ン18は元の状態、即ち係合突起21がピン本体16の
上段側透孔22aから突出したロック状態に復帰するこ
とができる。On the other hand, when removing the upper scaffolding frame a from the lower scaffolding frame b, as shown in FIG. 4, if the handle 31 of the release lever 25 is pulled in the direction of the arrow in FIG. -Shaped frame piece 30 rotates about the lower end portions of the front end surfaces of both side plate portions 30b, 30b that are in contact with the outer surface of pin body 16, via its rotation guide surface 30c, and accordingly, the lower stage of pin body 16 The projecting shaft portion 23 projecting from the side through hole 22b is pulled outward, whereby the lock pin 18 resists the biasing force of the leaf spring 24 and the engaging projection 21 is centered on the fulcrum portion 20 and the upper projection side. It swings in the direction in which it retreats into the hole 22a. Then, the U-shaped frame piece 30 is further rotated, and the lower end surface 30d of the U-shaped frame piece 30 is moved to the pin body 16 as shown by the phantom line in FIG.
By engaging and supporting the outer side surface, the engaging projection 21 is completely retracted and unlocked in the upper through hole 22a as shown in the phantom line in the figure, and the lock pin 18 is unlocked. Held in position (see FIG. 4). Therefore, the upper side scaffolding frame a may be pulled out from the main body upper portion 16a of the pin main body 16 in the unlocked state in which the engagement projection 21 is retracted into the through hole 22a in this manner. At this time, since the lock pin 18 is held at the lock release position by the release lever 25, the work of pulling out the upper side scaffolding building frame a becomes very easy. After pulling out the upper side scaffolding frame a, if the handle 31 of the release lever 25 is pulled upward from the position shown by the phantom line in FIG. 4 and returned to the position shown by the solid line in FIG. 4, the lock pin 18 is in its original state. That is, the engagement projection 21 can be returned to the locked state in which the engagement projection 21 projects from the upper-stage through hole 22a of the pin body 16.
【0030】上記のように、上方側足場建枠aを下方側
足場建枠bから取り外すときは、解除レバー25の把手
31をピン本体16の外側面に近づく方向に手で押動す
るだけで、ロック解除できるから、その取外し作業も一
人の作業者で非常に簡単に行うことができるものであ
る。As described above, when the upper scaffolding frame a is removed from the lower scaffolding frame b, the handle 31 of the release lever 25 is simply pushed by hand in a direction approaching the outer surface of the pin body 16. Since it can be unlocked, the removal work can be performed very easily by one operator.
【0031】[0031]
【発明の効果】本発明の請求項1に係る連結ピンによれ
ば、下方側足場建枠の縦パイプに取付けたピン本体に内
蔵されたロックピンの係合突起をピン本体の上段側透孔
内に退入させた状態で、このピン本体に上方側足場建枠
の縦パイプを差し込むことによって、ピン本体と上方側
足場建枠の縦パイプとを連結して、上下の足場建枠を互
いに連結することができるから、その連結作業を作業者
一人で容易に行うことができる。また、上方側足場建枠
を下方側足場建枠から取り外すときは、解除レバーをピ
ン本体の外側面に近づく方向に手で押動するだけで、ロ
ック解除の状態となるから、この取外し作業も簡単容易
に行うことができる。従って、足場建枠の連結及び取外
し作業を能率良く行うことができる。According to the connecting pin of the first aspect of the present invention, the engaging projection of the lock pin built in the pin body attached to the vertical pipe of the lower scaffolding construction frame has the through hole of the upper stage side of the pin body. By inserting the vertical pipe of the upper scaffolding frame into this pin body while retracting inside, the pin body and the vertical pipe of the upper scaffolding frame are connected, and the upper and lower scaffolding frames are connected to each other. Since they can be connected, the connecting work can be easily performed by one worker. Also, when removing the upper side scaffolding frame from the lower side scaffolding frame, the lock is released by simply pushing the release lever by hand in the direction toward the outer surface of the pin body. It can be done easily and easily. Therefore, the work of connecting and removing the scaffolding frame can be efficiently performed.
【0032】請求項2に係る連結ピンによれば、上方側
足場建枠の縦パイプをピン本体に差し込むだけで、上下
両足場建枠を自動的に連結できるから、上方側足場建枠
と下方側足場建枠との連結作業をきわめて簡単容易に行
うことができる。According to the connecting pin of the second aspect, the upper and lower scaffolding frames can be automatically connected by simply inserting the vertical pipe of the upper side scaffolding frame into the pin body. The connection work with the side scaffolding frame can be performed very easily and easily.
【0033】請求項3に係る連結ピンによれば、把手を
引き下げるだけで、ロックピンの係合突起によるピン本
体と上方側足場建枠とのロックを解除できると共に、そ
のロック解除位置に保持できるため、解除操作が簡単容
易となり、足場建枠取外し作業の能率向上を図ることが
できる。According to the connecting pin of the third aspect, the lock between the pin body and the upper scaffolding construction frame by the engaging projection of the lock pin can be released and held at the unlocked position only by pulling down the handle. Therefore, the releasing operation becomes easy and easy, and the efficiency of the scaffolding frame removal work can be improved.
【0034】請求項4に係る連結ピンによれば、ロック
ピンを金属線材で形成することによって、金属板材や角
材で形成する場合に比べ、製作が簡単容易となる上に、
ロックピンの機械的強度、特に、ピン本体と上方側足場
建枠の縦パイプとを連結する係合突起部分の曲げ強度を
十分に大きくすることができて、使用上の安全性を十分
確保でき、耐用寿命を延ばすことができる。According to the connecting pin of the fourth aspect, since the lock pin is made of a metal wire rod, the manufacturing is simpler and easier than the case of being made of a metal plate or a square rod.
The mechanical strength of the lock pin, especially the bending strength of the engaging protrusion that connects the pin body and the vertical pipe of the upper scaffolding frame, can be sufficiently increased to ensure sufficient safety in use. , The service life can be extended.
【図1】 本発明に係る連結ピンの使用状態を示す全体
斜視図である。FIG. 1 is an overall perspective view showing a use state of a connecting pin according to the present invention.
【図2】 (A)は、本発明に係る連結ピンの一実施例
を示す縦断面側面図、(B)は、(A)のX−X線断面
図、(C)は、板ばねをロックピンに取付ける他の例を
示す側面図である。2A is a vertical cross-sectional side view showing an embodiment of a connecting pin according to the present invention, FIG. 2B is a cross-sectional view taken along line XX of FIG. 2A, and FIG. It is a side view which shows the other example attached to a lock pin.
【図3】 (A)は、上方側足場建枠を下方側足場建
枠に連結するときのロックピンの作動状態を示す縦断面
側面図、(B)は、ロックピンによってピン本体と上方
側足場建枠とが連結された状態を示す縦断面側面図であ
る。3A is a vertical cross-sectional side view showing an operating state of a lock pin when the upper scaffolding frame is connected to the lower scaffolding frame, and FIG. 3B is a pin body and an upper side by the lock pin. It is a longitudinal section side view showing the state where the scaffolding construction frame was connected.
【図4】 解除レバーを操作して上方側足場建枠を下方
側足場建枠から取り外すときのロックピンの作動状態を
示す縦断面側面図である。FIG. 4 is a vertical cross-sectional side view showing an operating state of the lock pin when the release lever is operated to remove the upper scaffold building frame from the lower scaffold building frame.
a 上方側足場建枠 b 下方側足場建枠 10 縦パイプ 14 縦パイプの係合孔 15 連結ピン 16 ピン本体 18 ロックピン 20 支点部 21 係合突起 22a 上段側透孔 22b 下段側透孔 23 突出軸部 24 板ばね(ばね) 25 解除レバー 26 滑り面 30 コ字状枠片 30a 背板部 30b 側板部 31 把手 32 ピン a Upper side scaffolding frame b Lower side scaffolding frame 10 Vertical pipe 14 Vertical pipe engaging hole 15 Connecting pin 16 Pin body 18 Lock pin 20 Support point 21 Engagement protrusion 22a Upper stage through hole 22b Lower stage through hole 23 Projection Shaft part 24 Leaf spring (spring) 25 Release lever 26 Sliding surface 30 U-shaped frame piece 30a Back plate part 30b Side plate part 31 Handle 32 pin
Claims (4)
面で支持される支点部を中心に揺動可能なロックピンで
あって、その一端部の係合突起がピン本体の上段側透孔
より突出して足場建枠に係合すると共にその透孔内に退
入自在であり且つ他端部の突出軸部がピン本体の下段側
透孔から常時突出するロックピンと、該ロックピンをそ
の係合突起が上段側透孔から突出するように付勢するば
ねとを内蔵し、前記突出軸部の外端部には、ロックピン
をばね付勢力に抗して揺動させて前記係合突起をその透
孔内に退入させるように該突出軸部を引張操作するため
の解除レバーを設けてなる足場建枠用連結ピン。1. A lock pin, which is swingable around a fulcrum portion supported by an inner surface of a hollow pin body such as a tubular body, the engagement protrusion of one end of which is on the upper side of the pin body. A lock pin that protrudes from the through hole, engages with the scaffolding building frame, is retractable into the through hole, and the protruding shaft portion of the other end always protrudes from the lower through hole of the pin body; A spring for urging the engaging projection so as to project from the upper through hole is built in, and the lock pin is rocked against the spring urging force at the outer end portion of the projecting shaft portion. A scaffolding construction frame connecting pin provided with a release lever for pulling the protruding shaft portion so as to retract the fitting protrusion into the through hole.
部に、下り傾斜状の滑り面が形成されてなる請求項1に
記載の足場建枠用連結ピン。2. The connecting pin for a scaffolding construction frame according to claim 1, wherein the engaging projection of the lock pin has a downwardly inclined sliding surface formed at the tip thereof.
でコ字状に形成された枠片と、背板部の一端から一体に
突設された把手とからなり、前記コ字状枠片を、その両
側板部の先端面がピン本体の外側面に当接すると共に前
記把手が該枠片の真上に位置する状態で、ピン本体の下
段側透孔から突出するロックピンの突出軸部に嵌合し
て、該突出軸部を両側板部にピンで枢着し、前記把手に
より前記コ字状枠片を下向きに回動して該枠片の下端面
をピン本体外側面に当接支持させることによって、突出
軸部を引張してその位置に保持するようにした請求項1
または2に記載の足場建枠用連結ピン。3. The release lever comprises a frame piece formed in a U shape by a back plate portion and both side plate portions, and a handle integrally projecting from one end of the back plate portion. Of the lock pin protruding from the lower-stage through hole of the pin body in a state in which the front end surfaces of both side plate portions of the frame member are in contact with the outer side surfaces of the pin body and the handle is located right above the frame member. It is fitted to the protruding shaft portion, and the protruding shaft portion is pivotally attached to both side plate portions by pins, and the U-shaped frame piece is rotated downward by the handle so that the lower end surface of the frame piece is outside the pin body. 3. The protruding shaft portion is pulled and held at that position by supporting the side surface in abutment.
Alternatively, the scaffolding frame connecting pin according to 2.
金属線材の中間所要部に弯曲部を形成してその突端部を
支点部とすると共に、該金属線材の両端部をそれぞれ前
記弯曲部の突出方向と同一方向に屈曲して、その一方の
屈曲部に係合突起を形成し、他方の屈曲部に突出軸部を
形成してなる請求項1〜3のいずれかに記載の足場建枠
用連結ピン。4. The lock pin has a curved portion formed at an intermediate required portion of a metal wire rod cut into a required length so that a projecting end portion thereof serves as a fulcrum portion, and both end portions of the metal wire rod are respectively curved portions. The scaffold construction according to any one of claims 1 to 3, wherein the scaffold is bent in the same direction as the protruding direction of, and the engaging protrusion is formed on one of the bent portions, and the protruding shaft portion is formed on the other bent portion. Frame connection pin.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP32465094A JP3642592B2 (en) | 1994-12-27 | 1994-12-27 | Connecting pin for scaffolding frame |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP32465094A JP3642592B2 (en) | 1994-12-27 | 1994-12-27 | Connecting pin for scaffolding frame |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH08177228A true JPH08177228A (en) | 1996-07-09 |
| JP3642592B2 JP3642592B2 (en) | 2005-04-27 |
Family
ID=18168198
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP32465094A Expired - Fee Related JP3642592B2 (en) | 1994-12-27 | 1994-12-27 | Connecting pin for scaffolding frame |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3642592B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2021006678A (en) * | 2019-06-28 | 2021-01-21 | アルインコ株式会社 | Connecting joints in temporary scaffolding |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CH716839A1 (en) * | 2019-11-25 | 2021-05-31 | Vitra Patente Ag | Pipe connection structure and furniture kit. |
-
1994
- 1994-12-27 JP JP32465094A patent/JP3642592B2/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2021006678A (en) * | 2019-06-28 | 2021-01-21 | アルインコ株式会社 | Connecting joints in temporary scaffolding |
Also Published As
| Publication number | Publication date |
|---|---|
| JP3642592B2 (en) | 2005-04-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US6273381B1 (en) | Load actuated lock | |
| KR102255702B1 (en) | Construction safety scaffolding and ladder hook and connection structure | |
| JPH0520541B2 (en) | ||
| US4630956A (en) | Scaffolding connection and retention device and method | |
| JPH08177228A (en) | Joint pin for scaffolding jambs | |
| US20030102186A1 (en) | Mobile utility scaffold having a platform locking and securing device | |
| KR200487459Y1 (en) | System scaffolding diagonal brace locker | |
| US20030102187A1 (en) | Locking and securing device | |
| KR200487460Y1 (en) | System scaffolding diagonal brace locker | |
| JP4108075B2 (en) | Wife side skirting board for scaffolding board | |
| JPH07292958A (en) | Joint of scaffolding frame | |
| JPH0724521Y2 (en) | Pipe joint | |
| KR100342141B1 (en) | Support Metallic Tool for Timbering | |
| FI75311C (en) | ANORDNING FOER LOESTAGBAR FASTSAETTNING AV EN STOLPE VID ETT LASTFLAK OCH EN LAEM ELLER LIKNANDE VID STOLPEN. | |
| JPH0913661A (en) | Pipe joint | |
| JPH07150761A (en) | Connecting pin for scaffold erecting frame | |
| JPS5849323Y2 (en) | locking device | |
| JPH11241502A (en) | Construction scaffold | |
| JP6057861B2 (en) | Joining structure and joining method | |
| JP3784053B2 (en) | Scaffolding board | |
| JPH0738423U (en) | Building frame holder for handrail frame for temporary scaffolding | |
| JP2500345Y2 (en) | Pipe fittings | |
| JP3001737U (en) | Connecting pin | |
| JP2718870B2 (en) | Work ladder | |
| JP2004052493A (en) | Toe plate fitting device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040910 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20041027 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050107 |
|
| A61 | First payment of annual fees (during grant procedure) |
Effective date: 20050125 Free format text: JAPANESE INTERMEDIATE CODE: A61 |
|
| R150 | Certificate of patent (=grant) or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 4 Free format text: PAYMENT UNTIL: 20090204 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100204 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 6 Free format text: PAYMENT UNTIL: 20110204 |
|
| LAPS | Cancellation because of no payment of annual fees |