JPH08209678A - Ground improvement method and construction method of pile or underground wall - Google Patents

Ground improvement method and construction method of pile or underground wall

Info

Publication number
JPH08209678A
JPH08209678A JP2066195A JP2066195A JPH08209678A JP H08209678 A JPH08209678 A JP H08209678A JP 2066195 A JP2066195 A JP 2066195A JP 2066195 A JP2066195 A JP 2066195A JP H08209678 A JPH08209678 A JP H08209678A
Authority
JP
Japan
Prior art keywords
auger
earth
pile
sand
soil mortar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2066195A
Other languages
Japanese (ja)
Inventor
Tetsuo Kesen
哲夫 気仙
Masaaki Ishihara
公明 石原
Yuetsu Kikuchi
祐悦 菊地
Kaoru Hirose
馨 弘瀬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BAUAA JAPAN KK
Daiyou Kiko Kogyo Kk
Hazama Ando Corp
Original Assignee
BAUAA JAPAN KK
Daiyou Kiko Kogyo Kk
Hazama Gumi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BAUAA JAPAN KK, Daiyou Kiko Kogyo Kk, Hazama Gumi Ltd filed Critical BAUAA JAPAN KK
Priority to JP2066195A priority Critical patent/JPH08209678A/en
Publication of JPH08209678A publication Critical patent/JPH08209678A/en
Pending legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

(57)【要約】 【目的】 削孔時の土砂や泥水を廃棄処分する必要が無
く、安定した材料を供給できるので杭や地盤改良の品質
を容易に向上することができ、さらに、止水性が良好な
柱列壁を構築することができる地盤改良方法、および杭
または地中壁の構築方法を提供すること 【構成】 本発明の地盤改良方法及び杭の構築方法は、
土砂を地上に排出しながら所定深度までオーガー11を掘
進し、地上に排出された土砂でソイルモルタルを製造
し、オーガー11を引き上げながらオーガー先端からソイ
ルモルタル32を削孔内に注入することを特徴とする。ま
た本発明の地中壁35,36の構築方法は、土砂を地上に排
出しながら所定深度までオーガー11を掘進し、地上に排
出された土砂でソイルモルタルを製造し、オーガー11を
引き上げながらオーガー先端からソイルモルタルを削孔
内に注入して杭を構築し、同様の工程で複数の杭33を連
設して構築することを特徴とする。
(57) [Summary] [Purpose] It is not necessary to dispose of earth and sand or muddy water at the time of drilling, and stable materials can be supplied, so the quality of piles and ground improvement can be easily improved, To provide a ground improvement method capable of constructing a good column row wall, and a method of constructing a pile or an underground wall [Configuration] A ground improvement method and a pile construction method of the present invention,
It is characterized by excavating auger 11 to a predetermined depth while discharging earth and sand, manufacturing soil mortar from the earth and sand discharged on the ground, and injecting soil mortar 32 from the tip of the auger into the drilling hole while pulling up auger 11. And Further, the method of constructing the underground walls 35, 36 of the present invention is to excavate the auger 11 to a predetermined depth while discharging the earth and sand, to manufacture soil mortar with the earth and sand discharged to the ground, and to lift the auger 11 while the auger is being pulled up. It is characterized in that soil mortar is injected into the drilled hole from the tip to construct a pile, and a plurality of piles 33 are consecutively constructed in the same process.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、地盤改良方法、および
杭または地中壁の構築方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a ground improvement method and a pile or underground wall construction method.

【0002】[0002]

【従来の技術】現在、杭または地中壁の構築方法とし
て、CFA(Continuous Flight Auger)工法が提案され
ている。この工法は、大口径のオーガー(杭削孔機)で
所定深度まで削孔して土砂を排出し、このオーガーを引
き上げながら先端からコンクリートやモルタルを注入
し、その後、芯材となる鉄筋や型鋼をコンクリートやモ
ルタルの中に挿入して場所打ち杭や柱列壁を構築する方
法である。すなわち、CFA工法では、削孔時に孔壁に
かかる土圧をオーガーで支持しながら、土砂を、コンク
リートやモルタルによって削孔内で完全に置換して杭や
柱列壁を構築し、排出された土砂は廃棄する。
2. Description of the Related Art At present, a CFA (Continuous Flight Auger) method is proposed as a method for constructing a pile or an underground wall. This method uses a large-diameter auger (pile drilling machine) to drill holes to a specified depth to discharge the earth and sand, and while pulling up the auger, inject concrete and mortar from the tip, and then rebar or shaped steel that becomes the core material. Is a method of constructing cast-in-place piles and column walls by inserting into concrete or mortar. That is, in the CFA method, the earth pressure applied to the hole wall at the time of drilling was supported by the auger, and the earth and sand were completely replaced in the drilled hole by concrete or mortar to construct the piles and column walls, which were then discharged. Discard the earth and sand.

【0003】また、これ以外に、掘削された溝や孔の埋
め戻し等に用いられる工法として、施工現場で地上に排
出した土砂にセメントや水等を加えてソイルモルタルと
して利用する方法がある。この工法は、ベントナイト泥
水等の安定液で孔壁の崩壊を防ぎながらバケット、アー
スドリル等で溝や孔を掘削し、この溝や孔内に前記ソイ
ルモルタルを打設して、ベントナイト泥水等とソイルモ
ルタルとを置換する方法である。
In addition to this, as a construction method used for backfilling of excavated trenches and holes, there is a method of adding cement, water or the like to the earth and sand discharged to the ground at a construction site and using it as a soil mortar. In this method, a bucket or earth drill is used to excavate grooves or holes while preventing the collapse of the hole wall with a stable liquid such as bentonite mud, and the soil mortar is placed in the grooves or holes to produce bentonite mud or the like. This is a method of replacing soil mortar.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、上記従
来のCFA工法では、排出された土砂を廃棄処分しなけ
ればならず、そのため施工コストが上昇するという問題
点がある。また、杭を連設して形成する柱列壁のような
場合、先に打設したコンクリートやモルタルが硬化する
と、これを切削することは困難で、隣接する杭と杭との
間の止水性を確実に打ち継ぐことができないという問題
点がある。さらに、コンクリートの打設にブーム付きコ
ンクリートポンプ車を用いることから比較的広い施工ス
ペースが必要となりコストも上昇するという問題点があ
る。
However, in the above-mentioned conventional CFA method, the discharged earth and sand have to be discarded, which causes a problem that the construction cost increases. In addition, in the case of a pillar row wall formed by connecting piles in series, it is difficult to cut the concrete or mortar that has been placed first, and it is difficult to cut it, and the waterproofing between adjacent piles However, there is a problem in that Furthermore, since a concrete pump car with a boom is used for placing concrete, a relatively large construction space is required, and the cost is increased.

【0005】また、上記従来のソイルモルタルを利用す
る工法では、作泥プラントや泥水処理プラント、トレミ
ー管やコンクリート打設高さ測定装置、およびトレミー
管の建込みや引き抜きのためのクレーン等の設備が必要
となり施工コストが上昇する。さらに、ソイルモルタル
打設はベントナイト泥水中にて行なうため、打設や泥水
管理に高度の技術を必要とし、品質管理が難しいという
問題点がある。更にまた、膨大な量のベントナイト泥水
を廃液処理しなければならないという問題もある。
In the conventional method using soil mortar, a mud making plant, a mud water treatment plant, a tremie pipe or a concrete pouring height measuring device, and a crane or the like for building or pulling out the tremie pipe are installed. Will be required and the construction cost will increase. Further, since the soil mortar is cast in bentonite muddy water, there is a problem in that quality control is difficult because of the high technology required for casting and muddy water management. Furthermore, there is also a problem that a huge amount of bentonite mud must be treated as a waste liquid.

【0006】そこで、本発明は係る課題に着目してなさ
れたもので、その目的は、削孔時に生じる土砂や泥水の
ほとんどを廃棄処分する必要が無く、また、安定した材
料を供給できるので杭や地盤改良の品質を容易に向上す
ることができ、さらに、柱列壁を構築する場合には止水
性が良好な打ち継ぎ目を得ることができる地盤改良方
法、および杭または地中壁の構築方法を提供することに
ある。
Therefore, the present invention has been made in view of the above-mentioned problems, and its purpose is to eliminate the need to discard most of the earth and sand and mud water generated during drilling and to supply a stable material, so that the piles And a ground improvement method, which can easily improve the quality of ground improvement, and can obtain a seam with good waterproofness when constructing a column wall, and a method for constructing a pile or an underground wall. To provide.

【0007】[0007]

【課題を解決するための手段】本発明は、上記目的に鑑
みてなされたもので、その要旨は、土砂を地上に排出し
ながら所定深度までオーガーを掘進し、地上に排出され
た土砂でソイルモルタルを製造し、前記オーガーを引き
上げながらオーガー先端から前記ソイルモルタルを削孔
内に注入することを特徴とする地盤改良方法および杭の
構築方法にある。 また、本発明の別の要旨は、土砂を
地上に排出しながら所定深度までオーガーを掘進し、地
上に排出された土砂でソイルモルタルを製造し、前記オ
ーガーを引き上げながらオーガー先端から前記ソイルモ
ルタルを削孔内に注入して杭を構築し、同様の工程で複
数の杭を連設して構築することを特徴とする地中壁の構
築方法にある。
The present invention has been made in view of the above object, and its gist is to excavate an auger to a predetermined depth while discharging earth and sand to the ground, and to remove soil with the earth and sand discharged to the ground. It is a method for ground improvement and a method for constructing piles, which comprises producing mortar and injecting the soil mortar into the drilling hole from the tip of the auger while pulling up the auger. Further, another gist of the present invention is to excavate an auger to a predetermined depth while discharging earth and sand to the ground, to manufacture a soil mortar with the earth and sand discharged to the ground, and while pulling up the auger, the soil mortar from the tip of the auger. It is a method of constructing an underground wall, which is characterized in that it is injected into a drilled hole to construct a pile, and a plurality of piles are consecutively constructed in the same process.

【0008】[0008]

【作用】本発明の杭の構築方法では、最初に掘削機のオ
ーガーで所定深度まで削孔する。この時、削孔内の孔壁
は、フライト間に土砂が詰まったオーガーによって崩壊
しないように維持される。次に、オーガーを引き上げな
がら、前工程にて発生した土砂を使用して製造されたソ
イルモルタルを、パイプやオーガー内を介してポンプで
圧送し、オーガー先端から削孔内に注入する。この時、
削孔内の孔壁は、オーガー及び注入されたソイルモルタ
ルにより崩壊しないように維持される。ここで、オーガ
ーを引き上げる際に土砂が掻き落とされて、搬送手段に
よってストックヤードに設けられたソイルモルタル調合
プラントまで搬送される。この搬送された土砂は、所定
量のセメント及び水、あるいは場合によってベントナイ
ト等と混合されて、ソイルモルタルとして調合される。
かようにして製造されたソイルモルタルは、搬送手段に
よって掘削機のポンプに供給される。削孔内にソイルモ
ルタルが充満されたら、この孔内に芯材としての鉄筋籠
や型鋼等を挿入して杭が構築される。また、地中壁を構
築する場合には、複数の杭を上述の工程によって形成し
て連設すれば良い。さらに、地盤改良を行なう場合に
も、所定の敷地内に上述の工程によって複数の杭を構築
すれば、安定した地盤に改良することができる。
In the method of constructing a pile according to the present invention, first, an auger of an excavator is drilled to a predetermined depth. At this time, the hole wall in the drill hole is maintained so as not to be collapsed by the auger filled with earth and sand during the flight. Next, while pulling up the auger, the soil mortar produced by using the earth and sand generated in the previous step is pumped by a pump through the pipe and the inside of the auger, and is injected into the drilled hole from the tip of the auger. This time,
The hole wall in the drilled hole is maintained so as not to be collapsed by the auger and the poured soil mortar. Here, the earth and sand are scraped off when the auger is pulled up, and transported by the transporting means to the soil mortar blending plant provided in the stockyard. The transported earth and sand is mixed with a predetermined amount of cement and water, or if necessary, bentonite or the like, and mixed as soil mortar.
The soil mortar thus produced is supplied to the pump of the excavator by the conveying means. After the soil mortar is filled in the drilled hole, a reinforcing rod cage or shaped steel as a core material is inserted into the hole to construct a pile. Moreover, when constructing an underground wall, it is sufficient to form a plurality of piles by the above-mentioned steps and to connect them in series. Further, even when the ground is improved, it is possible to improve the ground to be stable by constructing a plurality of piles in the predetermined site by the above-described process.

【0009】[0009]

【実施例】以下に、本発明の実施例を添付図面に基づい
て詳細に説明する。図1は本発明の地盤改良方法、およ
び杭または地中壁の構築方法に使用する装置の側面図で
ある。図1において、掘削機1は、例えば大口径の管体
に螺旋状に刃(フライト)が形成されたオーガー11
(外径500〜1200mm程度)と、これを立設して支持する
ブーム14と、このブーム14を支持したり、掘削機1
全体を移動するベースマシン15と、オーガー11の上
端に設けられ、オーガー11を回転しながら地中に圧入
する回転圧入装置10と、ブーム14の下部に設けら
れ、オーガー11の昇降時の左右方向の振れ止めや、オ
ーガー11を引き上げるときに土砂を掻き落としたりす
るオーガーガイド12とを備える。さらに、掘削機1に
は、オーガー11の中にホース13を介してソイルソイ
ルモルタルを圧送するための圧送手段としてのポンプ1
7と、ホース13の巻き出し巻き取り装置16とを備え
る。また、本発明の工法においては、オーガーガイド1
2によって掻き落とした土砂を搬送するためのベルトコ
ンベア等の残土搬送機20を削孔口に配置する。
Embodiments of the present invention will be described in detail below with reference to the accompanying drawings. FIG. 1 is a side view of an apparatus used for the ground improvement method and the pile or underground wall construction method of the present invention. In FIG. 1, an excavator 1 includes, for example, an auger 11 in which a blade (flight) is spirally formed on a large-diameter pipe body.
(Outer diameter of about 500 to 1200 mm), a boom 14 that erects and supports the boom 14, supports the boom 14, and the excavator 1
A base machine 15 that moves the whole body, a rotary press-fitting device 10 that is provided on the upper end of the auger 11 and press-fits into the ground while rotating the auger 11, and a lower part of the boom 14, and the left-right direction when the auger 11 is moved up and down. And an auger guide 12 that scrapes off the earth and sand when pulling up the auger 11. Further, the excavator 1 has a pump 1 as a pumping means for pumping soil soil mortar into the auger 11 via a hose 13.
7 and an unwinding and winding device 16 for the hose 13. In the construction method of the present invention, the auger guide 1
A residual soil carrier 20 such as a belt conveyor for transporting the soil scraped off by 2 is arranged at the drilling port.

【0010】次に、図2を参照して本発明の杭の構築方
法について説明する。図2に示したように、最初に施
工現場における杭形成予定地点に、掘削機1のオーガー
11先端を位置合わせして、オーガー11の周りに残土
搬送機20を設置する。
Next, the method of constructing a pile according to the present invention will be described with reference to FIG. As shown in FIG. 2, first, the tip of the auger 11 of the excavator 1 is aligned with the planned pile formation point on the construction site, and the residual soil carrier 20 is installed around the auger 11.

【0011】次に、図2に示したように、回転圧入装
置10によってオーガー11を回転しながら所定深度ま
で圧入する。この時、削孔内の孔壁は、フライト間に土
砂が詰まった大口径のオーガー11によって崩壊しない
ように維持される。
Next, as shown in FIG. 2, the auger 11 is pressed into a predetermined depth while being rotated by the rotary press-fitting device 10. At this time, the hole wall in the drilled hole is maintained so as not to be collapsed by the large-diameter auger 11 filled with earth and sand during the flight.

【0012】そして、図2に示したように、オーガー
11を引き上げながら、ポンプ17に供給されたソイル
モルタルをホース13やオーガー11内を介して圧送
し、オーガー11先端から削孔内31に注入する。この
時、削孔内の孔壁は、オーガー11及び注入されたソイ
ルモルタル32により崩壊しないように維持される。こ
こで、注入されたソイルモルタルは、前工程にて発生し
た土砂を使用して製造される。また、このオーガー11
を引き上げる際に、フライト間に挟まった土砂はオーガ
ーガイド12によって掻き落とされて、図1に示した残
土搬送機20で施工現場内あるいは施工現場外のストッ
クヤードに設けられたソイルモルタル調合プラント(図
示せず)まで搬送される。なお、これ以外に、残土の搬
送は、施工現場の広さに応じて残土搬送機20からダン
プに積載して行なったり、あるいは残土搬送機20を使
用せずにバックホウで直接行なうこともできる。ソイル
モルタル調合プラントまで搬送された土砂は、粒度、シ
ルトの含量および含水率等が計測されると共に、計量さ
れて撹拌器(図示せず)に投入される。また同時に、前
記計測値に応じて所定量のセメント及び水、あるいは場
合によってベントナイト等を調合したセメントミルクを
撹拌器に投入する。撹拌器では、投入された土砂やセメ
ントミルクを撹拌してソイルモルタルを調合し、貯蔵タ
ンクに蓄える。かようにして製造されたソイルモルタル
は、ポンプあるいは生コン車両等によって、掘削機1の
ポンプ17に供給される。
Then, as shown in FIG. 2, while pulling up the auger 11, the soil mortar supplied to the pump 17 is pressure-fed through the hose 13 and the inside of the auger 11, and injected into the drilled hole 31 from the tip of the auger 11. To do. At this time, the hole wall in the drilled hole is maintained by the auger 11 and the poured soil mortar 32 so as not to collapse. Here, the poured soil mortar is manufactured by using the earth and sand generated in the previous step. Also, this auger 11
When pulling up, the soil sandwiched between the flights is scraped off by the auger guide 12, and the soil mortar blending plant (in the stockyard inside or outside the construction site with the residual soil carrier 20 shown in FIG. (Not shown). In addition to this, the residual soil can be transferred from the residual soil carrier 20 by loading it on a dump according to the size of the construction site, or directly using the backhoe without using the residual soil carrier 20. The earth and sand transported to the soil mortar blending plant are measured for particle size, silt content, water content, etc., and are weighed and put into an agitator (not shown). At the same time, a predetermined amount of cement and water, or cement milk in which bentonite or the like is mixed depending on the measured value is added to the stirrer. The stirrer mixes the soil and cement milk that have been put in, mixes the soil mortar, and stores it in a storage tank. The soil mortar thus manufactured is supplied to the pump 17 of the excavator 1 by a pump, a ready-mixed concrete vehicle or the like.

【0013】削孔内31にソイルモルタルを充満させ
て、この孔内に芯材となる鉄筋籠や型鋼(図示せず)を
挿入すると、場所打ち杭が構築される。
By filling the inside of the drilled hole 31 with soil mortar and inserting a rebar cage or shaped steel (not shown) as a core material into this hole, a cast-in-place pile is constructed.

【0014】また、地中壁を構築する場合には、例え
ば、図3及びの平面図に示したような配置で、複数
の場所打ち杭33を上述の工程によって形成して連設す
れば良い。本発明の杭は、ソイルモルタルによって形成
されているため、それぞれ先行して構築された杭に接す
る位置に杭を構築する際、オーガー11で先行杭の外周
部分を容易に切削しながら削孔することができ、この削
孔内にソイルモルタルを充填すると、先行杭との一体性
が良好で止水性良好な柱列壁35や36、あるいはこれ
以外の配列の柱列壁を形成することができる。
In the case of constructing an underground wall, a plurality of cast-in-place piles 33 may be formed and connected in series by the above-described process, for example, in the arrangement shown in the plan views of FIGS. . Since the pile of the present invention is formed of soil mortar, when constructing the pile at a position in contact with the pile constructed in advance, the auger 11 makes a hole while easily cutting the outer peripheral portion of the preceding pile. By filling the hole with soil mortar, it is possible to form the column row walls 35 and 36 having good integration with the preceding piles and good water blocking property, or column row walls of other arrangements. .

【0015】さらに、地盤改良を行なう場合にも、所定
の敷地内に上述の工程によって複数の杭を構築すれば、
安定した地盤に改良することができる。
Further, even when the ground is improved, if a plurality of piles are constructed in the predetermined site by the above process,
It can be improved to a stable ground.

【0016】[0016]

【発明の効果】本発明の地盤改良方法および杭の構築方
法は、オーガーで削孔し、このオーガーにより地上に排
出された土砂でソイルモルタルを製造し、このソイルモ
ルタルをオーガーを引き抜きながら先端から削孔内に注
入するので、削孔内の孔壁はオーガーまたは/及びソイ
ルモルタルによって常に支持される。そのため、孔壁の
崩壊を防止するためにベントナイト泥水等を削孔内に充
填する必要が無く、したがって、このベントナイト泥水
のための作泥プラントや泥水処理プラント、コンクリー
ト等の打設のためのトレミー管や打設高さ測定装置、お
よびトレミー管の建込みや引き抜きのためのクレーン等
の設備が不要になり、これら設備設置のためのスペース
や設備コストを大幅に削減することができる。
INDUSTRIAL APPLICABILITY The ground improvement method and pile construction method of the present invention are drilled with an auger, a soil mortar is produced from the earth and sand discharged by the auger, and the soil mortar is pulled out from the tip while pulling out the auger. Pouring into the drill hole, the hole wall in the drill hole is always supported by the auger or / and soil mortar. Therefore, it is not necessary to fill the drill hole with bentonite mud or the like in order to prevent the collapse of the hole wall. Therefore, a tremy for pouring mud plant or mud treatment plant for this bentonite mud, concrete, etc. It is not necessary to use a pipe, a driving height measuring device, and a crane or the like for installing and extracting a tremie pipe, and it is possible to significantly reduce the space and the facility cost for installing these facilities.

【0017】また、削孔時に生じる土砂を用いて、地上
のプラントでソイルモルタルを製造するので、高品質の
ソイルモルタルを製造することができて、さらに、ベン
トナイト泥水等の液体が無い削孔内に、このソイルモル
タルを直接注入するので、地盤改良および杭の品質を向
上することができる。さらに、廃棄処分にする土砂も大
幅に減少させることができて、全排出土砂の20〜30
%程度を廃棄処分にするだけで良い。
Further, since soil mortar is produced in a plant on the ground by using the earth and sand produced during drilling, it is possible to produce high quality soil mortar, and further, in the drilling where there is no liquid such as bentonite muddy water. Since the soil mortar is directly injected into the ground, the ground can be improved and the quality of the pile can be improved. Furthermore, the amount of earth and sand to be disposed of can be greatly reduced, and the total amount of earth and sand discharged is 20 to 30
It is enough to dispose about%.

【0018】更にまた、柱列壁等によって地中壁を構築
する場合には、各杭をソイルモルタルで構築するので、
オーガーで先行杭の外周部分を容易に切削しながら削孔
することができ、この削孔内にソイルモルタルを充填す
ると、打継ぎ目の一体性が良好で止水性良好な柱列壁を
形成することができる。
Furthermore, when constructing an underground wall by means of a column wall, etc., since each pile is constructed with soil mortar,
You can easily drill the outer peripheral part of the leading pile with an auger and fill the hole with soil mortar to form a column wall that has good seam integrity and good waterproofness. You can

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の地盤改良方法、および杭または地中壁
の構築方法に使用する装置の側面図である。
FIG. 1 is a side view of an apparatus used in the ground improvement method and the pile or underground wall construction method of the present invention.

【図2】本発明の地盤改良、および杭または地中壁の構
築工程を説明するための側面図である。
FIG. 2 is a side view for explaining the ground improvement of the present invention and the steps of constructing a pile or an underground wall.

【図3】本発明の構築方法によって形成された地中壁の
平面図である。
FIG. 3 is a plan view of an underground wall formed by the construction method of the present invention.

【符号の説明】[Explanation of symbols]

1 掘削機 11 オーガー 32 ソイルモルタル 33 杭 35,36 柱列壁(地中壁) 1 Excavator 11 Auger 32 Soil mortar 33 Pile 35, 36 Column wall (underground wall)

───────────────────────────────────────────────────── フロントページの続き (72)発明者 石原 公明 東京都港区北青山2−5−8 株式会社間 組内 (72)発明者 菊地 祐悦 東京都港区北青山2−5−8 株式会社間 組内 (72)発明者 弘瀬 馨 高知市塩田町1−6 ─────────────────────────────────────────────────── ─── Continuation of front page (72) Inventor Kimiaki Ishihara 2-5-8 Kita-Aoyama, Minato-ku, Tokyo In-group (72) Inventor Yuetsu Kikuchi 2-5-8 Kita-Aoyama, Minato-ku, Tokyo (72) Inventor Kaoru Hirose 1-6 Shioda-cho, Kochi City

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 土砂を地上に排出しながら所定深度まで
オーガーを掘進し、地上に排出された土砂でソイルモル
タルを製造し、前記オーガーを引き上げながらオーガー
先端から前記ソイルモルタルを削孔内に注入することを
特徴とする地盤改良方法および杭の構築方法。
1. A soil mortar is excavated to a predetermined depth while being discharged to the ground, a soil mortar is manufactured from the soil discharged to the ground, and the soil mortar is injected into a drilling hole from the tip of the auger while pulling up the auger. A method for improving the ground and a method for constructing a pile.
【請求項2】 土砂を地上に排出しながら所定深度まで
オーガーを掘進し、地上に排出された土砂でソイルモル
タルを製造し、前記オーガーを引き上げながらオーガー
先端から前記ソイルモルタルを削孔内に注入して杭を構
築し、同様の工程で複数の杭を連設して構築することを
特徴とする地中壁の構築方法。
2. An auger is excavated to a predetermined depth while discharging the earth and sand, and a soil mortar is manufactured from the earth and sand discharged on the ground, and the soil mortar is injected into a drilling hole from the tip of the auger while pulling up the auger. Then, a pile is constructed, and a plurality of piles are consecutively constructed in the same process to construct the underground wall.
JP2066195A 1995-02-08 1995-02-08 Ground improvement method and construction method of pile or underground wall Pending JPH08209678A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2066195A JPH08209678A (en) 1995-02-08 1995-02-08 Ground improvement method and construction method of pile or underground wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2066195A JPH08209678A (en) 1995-02-08 1995-02-08 Ground improvement method and construction method of pile or underground wall

Publications (1)

Publication Number Publication Date
JPH08209678A true JPH08209678A (en) 1996-08-13

Family

ID=12033398

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2066195A Pending JPH08209678A (en) 1995-02-08 1995-02-08 Ground improvement method and construction method of pile or underground wall

Country Status (1)

Country Link
JP (1) JPH08209678A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111305758A (en) * 2020-03-30 2020-06-19 华北水利水电大学 A kind of building construction punching pile driver pile hammer
CN113529720A (en) * 2021-07-06 2021-10-22 上海市基础工程集团有限公司 Wall forming and slurry parameter control method for milling equal-thickness cement-soil continuous steel wall on thick sand layer

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111305758A (en) * 2020-03-30 2020-06-19 华北水利水电大学 A kind of building construction punching pile driver pile hammer
CN113529720A (en) * 2021-07-06 2021-10-22 上海市基础工程集团有限公司 Wall forming and slurry parameter control method for milling equal-thickness cement-soil continuous steel wall on thick sand layer

Similar Documents

Publication Publication Date Title
JP7104536B2 (en) How to build an impermeable wall
JP2000073354A (en) Preparating method of ground improving body and preparating method of continuous walls
JP7430103B2 (en) Ground improvement method for pile extraction holes
JP4200237B2 (en) Construction method of foundation pile
JP4020858B2 (en) Manufacturing method for underground structures
JP4313070B2 (en) Sludge treatment method in ready-made pile construction and ground reinforcement structure obtained by the treatment method
JPH07103550B2 (en) Pile or continuous wall and its construction method
JPH0280710A (en) Preparing cast-in-place concrete pile
JPH11269874A (en) Pile construction method for foundation pile
KR100521888B1 (en) Method for constructing soil cement a stake
JP2937766B2 (en) Continuous underground wall construction method
JPH06341140A (en) Construction method by which column-wall holes are bored within approximate line by 10-700mm from boundary by intermittent work and continuous wall, connection wall, butt-joint wall, superposed wall, and cut-off wall are erected by use of the hole, and these walls
JPH0449314A (en) Execution method of soil cement method
JP2698768B2 (en) Method of forming underground continuous wall
JP4031967B2 (en) Box-type buckets used in the construction method of underground underground walls, and impermeable wall construction methods for waste landfills
JPS63197717A (en) Construction work of in-situ pile
JP2783525B2 (en) Ground improvement method
JPS63223215A (en) In-situ concrete piling work
JP2006138091A (en) Construction method for burying tank and the like
JPS63197718A (en) Construction work of in-situ pile
JPH01131717A (en) Construction of in-situ pile
JP2698772B2 (en) Slag graft system underground wall construction method
JP3904294B2 (en) Underground excavation method and underground structure construction method using this method
JP2023171016A (en) Existing pile extraction method
JPH0757947B2 (en) Cast-in-place pile construction method