JPH0821085A - Mountain retaining method using a wire mesh plate that does not need to be removed as the weir plate of the casting formwork - Google Patents
Mountain retaining method using a wire mesh plate that does not need to be removed as the weir plate of the casting formworkInfo
- Publication number
- JPH0821085A JPH0821085A JP6179601A JP17960194A JPH0821085A JP H0821085 A JPH0821085 A JP H0821085A JP 6179601 A JP6179601 A JP 6179601A JP 17960194 A JP17960194 A JP 17960194A JP H0821085 A JPH0821085 A JP H0821085A
- Authority
- JP
- Japan
- Prior art keywords
- plate
- wire mesh
- mesh plate
- mountain
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G9/00—Forming or shuttering elements for general use
- E04G9/02—Forming boards or similar elements
- E04G9/06—Forming boards or similar elements the form surface being of metal
- E04G9/065—Forming boards or similar elements the form surface being of metal the form surface being of wire mesh
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Retaining Walls (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、山等の土砂の崩壊防止
用に設ける山留めの施工方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a mountain cleat to prevent the collapse of soil such as mountains.
【0002】[0002]
【従来の技術】従来の山留めは、山側に沿って予め基礎
コンクリートを打設しておき、その基礎コンクリート部
分に、所定間隔(形成する山留めの幅に対応させた間
隔)離して相対して設けられた堰板からなる型枠に、コ
ンクリートを打設して形成されている。かかる型枠形成
時には、相対する堰板間は、セパレーターにより所定間
隔が保たれるようになっている。また、山側の堰板面
は、図4に示すように、山側との間に油圧調節可能なジ
ャッキ等を間に掛け渡して、打設したコンクリートが固
化するまで、型枠が倒れないように支えている。コンク
リート打設後は脱型し、山側との間を土砂で埋めて山留
めを完成させている。2. Description of the Related Art In the conventional mountain clasp, basic concrete is placed in advance along the mountain side, and is provided in the basic concrete portion at a predetermined interval (a gap corresponding to the width of the mountain clasp to be formed) facing each other. It is formed by pouring concrete on the form made of the dam plate. At the time of forming such a mold, a predetermined gap is kept between the opposing barrier plates by a separator. Also, as shown in FIG. 4, the weir plate surface on the mountain side has a hydraulically adjustable jack and the like on the mountain side so that the formwork does not fall until the placed concrete is solidified. Supporting. After pouring concrete, the mold is removed and the space between the mountain side and the mountain side is filled with earth and sand to complete the mountain retaining.
【0003】[0003]
【発明が解決しようとする課題】かかる従来の方法で
は、コンクリート打設後の脱型時には、ジャッキ等に支
えられた山側の堰板も外さなければならない。コンクリ
ート打設により山留めを一旦形成した後では、形成され
た山留めが却って邪魔になり、山側の斜面と山留めとの
間の狭い空間で、ジャッキと堰板を取外す作業は、大変
に手間がかかる面倒なものとなる。そのため、かかる作
業方法の改善及び省力化が以前から強く求められてい
た。また、本出願人は、以前に打設コンクリートの流出
防止が可能で、コンクリートの接続強度が上げられるコ
ンクリート打継ぎ用金網板を開発しており(実開平5−
3427号公報)、かかる金網板を堰板に使用すること
により、上記作業における省力化が図れるものと考え
た。In such a conventional method, it is also necessary to remove the weir plate on the mountain side supported by the jack or the like at the time of demolding after placing concrete. Once the mountain cleat has been formed by placing concrete, the cleat that has been formed will rather obstruct the work, and the work of removing the jack and the weir plate in the narrow space between the mountain side slope and the mountain clutter is extremely troublesome. It will be Therefore, improvement of such working method and labor saving have been strongly demanded for a long time. Further, the present applicant has previously developed a wire netting plate for concrete splicing which can prevent the outflow of the poured concrete and increase the connection strength of the concrete.
3427 gazette), it was thought that labor-saving in the said work can be achieved by using such a wire mesh plate for a dam plate.
【0004】そこで、本発明は、打設コンクリートの流
出防止が可能な網目形状を有する金網板を堰板に用いて
型枠形成を行なうことにより、脱型時の堰板撤去が不要
な山留め工法を提供することを目的とする。Therefore, the present invention uses a wire mesh plate having a mesh shape capable of preventing pouring concrete from flowing out as a dam plate to form a mold, thereby eliminating the need for removing the dam plate at the time of demolding. The purpose is to provide.
【0005】[0005]
【課題を解決するための手段】上記目的を達成するため
に、本発明は、土砂の崩壊防止用に山面等に沿ってコン
クリート製の山留めを構築する山留め工法において、山
留め形成用に所定間隔で堰板を相対させて型枠を形成
し、前記堰板のうち山側に面した堰板に、網目開口がコ
ンクリートの流出防止形状である金網板を使用するとと
もに、前記型枠へのコンクリート打設後の脱型時に、前
記金網板を撤去することなく土砂に埋めて山留めを構築
する。また、金網板は、金属板に多数の横方向の切込み
が入れられるとともに、縦方向に引伸ばされることによ
り切込み部が開口されている金網板であって、金属板に
おける多数の開口の上下間が全て同方向に傾斜され、か
つそれら傾斜部の外端が金属板の元の平面部側に折曲げ
られて、各開口の間が略く字形断面になっている金属板
とする。In order to achieve the above object, the present invention relates to a mountain retaining method for constructing a concrete mountain retaining along a mountain surface or the like to prevent the collapse of earth and sand, and a predetermined interval for forming the mountain retaining. To form a form by facing the weir plate with a wire mesh plate whose mesh opening is a concrete outflow preventing shape for the weir plate facing the mountain side of the weir plate, and concrete casting to the form At the time of demolding after construction, the wire mesh plate is buried in the sand without removing the wire mesh plate to construct a mountain retaining. Further, the wire mesh plate is a metal mesh plate in which a large number of transverse cuts are made in the metal plate and the cutouts are opened by stretching the metal plate in the vertical direction. Are all tilted in the same direction, and the outer ends of the tilted parts are bent toward the original flat surface side of the metal plate to form a metal plate having a substantially V-shaped cross section between the openings.
【0006】さらに、金網板は、山留め用基礎コンクリ
ートに所定間隔に起立させられたアングル部材と、これ
と格子状に交差するように横に複数設けられたアングル
部材との間に挟まれるとともに、アングル部材の交差す
る格子点部分で、両アングル部材と金網板とに連結部材
を抜け防止可能に挿通して、アングル部材に金網板を固
定する。Further, the wire mesh plate is sandwiched between angle members which are erected at a predetermined interval on the foundation concrete for mountain fastening and a plurality of angle members which are laterally provided so as to intersect with the angle members, and At the lattice points where the angle members intersect, the connecting members are inserted into the angle members and the wire mesh plate so as to prevent them from coming off, and the wire mesh plates are fixed to the angle members.
【0007】[0007]
【作用】本発明では、打設コンクリートの流出防止可能
な形状の網目を有した金網板を堰板として使用すること
により、コンクリート打設後に堰板を撤去せずにそのま
ま土砂に埋めて、山留めを形成する。また、形成された
山留め内部に金網板が内蔵されているので、従来よりも
強度的に強化されたものとなる。特に、金属板における
多数の開口の上下間が全て同方向に傾斜され、かつそれ
ら傾斜部の外端が金属板の元の平面部側に折曲げられ
て、各開口の間が略く字形断面になっているため、傾斜
部は外端に向かって直線的に開口面積を広くすることな
く外端近くで開口面積が狭められ、さらに金網板の基部
側に向くように傾斜部の外端が折曲げられているので、
このような網目開口を有する金網板を堰板に使用して
も、打設コンクリートの網目開口からの流出を防止する
ことができる。In the present invention, by using a wire mesh plate having a mesh having a shape capable of preventing the outflow of poured concrete as a weir plate, the weir plate is not removed after the concrete is poured, but is buried in the earth and sand as it is, and is piled up. To form. Further, since the wire mesh plate is built in the formed mountain clasp, the strength is strengthened as compared with the conventional one. In particular, the upper and lower sides of a large number of openings in a metal plate are all inclined in the same direction, and the outer ends of the inclined parts are bent toward the original flat surface side of the metal plate, resulting in a substantially V-shaped cross section between the openings. Therefore, the opening area of the inclined part is narrowed near the outer end without linearly increasing the opening area toward the outer end, and the outer end of the inclined part is directed toward the base side of the wire mesh plate. Because it is bent,
Even if the wire mesh plate having such mesh openings is used as the weir plate, the poured concrete can be prevented from flowing out from the mesh openings.
【0008】金網板の固定は、基礎コンクリートに所定
間隔で起立させた複数のアングル部材に金網板を載せ、
さらに、前記アングル部材と格子状に交差するように所
定間隔で横に渡したアングル部材を金網板に載せ、両ア
ングル部材の交差位置で金網板を挟むようにして固定す
る。特に、両アングル部材の交差位置では、両アングル
部材の側面及び金網板の網目開口に、両アングル部材の
間に金網板を挟んだ状態で連結部材が抜けないように挿
通することにより、金網板をアングル部材に固定するこ
とができる。The wire mesh plate is fixed by mounting the wire mesh plate on a plurality of angle members which are erected at a predetermined interval on the foundation concrete.
Further, the angle members laterally crossed at a predetermined interval so as to intersect the angle members in a grid pattern are placed on the wire mesh plate, and the wire mesh plate is sandwiched and fixed at the intersecting positions of both angle members. In particular, at the intersecting position of both angle members, the wire mesh plate is inserted into the side surface of both angle members and the mesh opening of the wire mesh plate so that the connecting member does not come off with the wire mesh plate sandwiched between the angle members. Can be fixed to the angle member.
【0009】[0009]
【実施例】本発明の実施例を図により説明する。本発明
の方法は、概略、図1(a)に示すように、先ず山留め
用基礎コンクリートAに所定間隔に起立させたアングル
部材10Aに、金網板20を載せるとともに、その金網
板20に上下方向に複数のアングル部材10Bを横に所
定間隔に渡して、上記起立したアングル部材10Aと横
に渡したアングル部材10Bとの間に金網板20を挟ん
で取付け、これを山側の堰板Bとして山留め用の打設型
枠Cを形成する。打設型枠C形成後、コンクリートを打
設し、図1(b)に示すように、脱型時に上記金網板2
0を撤去せずに、そのまま土砂に埋めて山留めを構築す
る施工方法である。Embodiments of the present invention will be described with reference to the drawings. In the method of the present invention, as shown in FIG. 1 (a), the wire mesh plate 20 is first placed on the angle members 10A standing on the foundation concrete A for mountain fastening at a predetermined interval, and the wire mesh plate 20 is vertically moved. A plurality of angle members 10B are laterally crossed at a predetermined interval, and a wire mesh plate 20 is sandwiched between the upright angle member 10A and the lateral angle member 10B. A casting form C for use is formed. After the casting form C has been formed, concrete is placed, and as shown in FIG.
It is a construction method in which 0 is not removed, but buried in the earth and sand to build a mountain retaining structure.
【0010】本実施例で使用する金網板20は、図2
(a)、(b)に示すように、金属板に横方向に切込み
が平行に、且つ一段ごとに1ピッチずらして多数設けら
れ、これを縦方向に引伸ばすことにより各切込みが開か
れた網目開口21が多数形成されている。また、この網
目開口21は、上下の切込間が同方向に約45度傾斜し
た傾斜部22に形成されている。これは、図2(c)に
示すように、金網板20に上記切込みを入れる際に、固
定刃と、内側が角形に突出して矢印方向に移動する移動
刃とが使用され、そのため切込みの内側が折り曲げら
れ、その後に前記のように引き伸ばされて、傾斜部22
が折り曲げ部23を有する断面く字形になるように形成
されるからである。かかる金網板20は、堰板Bとして
使用する際には、上記傾斜部22が堰板Bの外側に向く
ように(山側に向くように)取り付けることにより、コ
ンクリートが上記網目開口21から流出しないようにで
きる。The wire mesh plate 20 used in this embodiment is shown in FIG.
As shown in (a) and (b), a large number of cuts are provided in parallel in the horizontal direction on the metal plate and are shifted by one pitch for each step, and each cut is opened by stretching the cuts in the vertical direction. A large number of mesh openings 21 are formed. Further, the mesh opening 21 is formed in an inclined portion 22 in which the upper and lower cuts are inclined about 45 degrees in the same direction. As shown in FIG. 2 (c), a fixed blade and a moving blade that projects inward in a square shape and moves in the direction of the arrow are used when making the above incision in the wire mesh plate 20, so that the inside of the incision is Is bent and then stretched as described above, so that the sloping portion 22
Is formed so as to have a V-shaped cross section having the bent portion 23. When the wire mesh plate 20 is used as the dam plate B, the inclined portion 22 is attached to the outside of the dam plate B (toward the mountain side) so that concrete does not flow out from the mesh opening 21. You can
【0011】一方、本実施例で使用するアングル部材1
0A、10Bは、断面L字形に形成され、後記する連結
用に使用する差込開口11A、11Bがそれぞれ設けら
れている。差込開口11Aは、細長い矩形形状に形成さ
れ、その長手方向がアングル部材10Aの長手方向に直
交するようにして、複数所定間隔に設けられている。差
込開口11Bも細長い矩形形状に形成され、その長手方
向がアングル部材10Bの長手方向に沿って、複数所定
間隔で設けられている。また、アングル部材10A、1
0Bを、例えば、側面に設ける差込開口の形状を十文字
状に形成することにより同一形状にすることができる。
或は、差込開口を一本のアングル部材の両側面に設ける
ようにし、一方の側面には差込開口11Aのように設け
て、他方の側面には差込開口11Bのように設けるよう
にして10A及び10Bを同一形状にしても構わない。On the other hand, the angle member 1 used in this embodiment
0A and 10B are formed in an L-shaped cross section, and are provided with insertion openings 11A and 11B used for connection, which will be described later. The insertion openings 11A are formed in an elongated rectangular shape, and are provided at a plurality of predetermined intervals such that the longitudinal direction thereof is orthogonal to the longitudinal direction of the angle member 10A. The insertion openings 11B are also formed in an elongated rectangular shape, and the longitudinal direction thereof is provided at a plurality of predetermined intervals along the longitudinal direction of the angle member 10B. Also, the angle members 10A, 1
OB can be made the same shape by forming the shape of the insertion opening provided on the side surface in a cross shape.
Alternatively, the insertion openings may be provided on both side surfaces of one angle member, the insertion openings 11A may be provided on one side surface, and the insertion openings 11B may be provided on the other side surface. 10A and 10B may have the same shape.
【0012】上記構成のアングル部材10A及び10B
と、前記金網板20とを用いて、次のようにして、山留
めを形成する。先ず、図3(a)に示すように、矩形鉄
板をクランク状に曲げて作られた取付部材30の一端
を、山留め用基礎コンクリートA部分の山側に面した方
に、コンクリート釘31により取付ける。この取付部材
30の他端側を、前記金網板20の裾側部分20aを基
礎コンクリートA面上に接するようにしながら、金網板
20の網目開口21に挿通する。さらに、断面L字形で
側面の長手方向に所定間隔に差込開口11Aが設けられ
たアングル部材10Aの一端10aを山留め用の基礎コ
ンクリートA部分に起立させて接するように保持しなが
ら、前記差込開口11Aに前記取付部材30の他端30
aを挿通して、金網板20を取付部材30とアングル部
材10Aの間に挟む。この状態で、取付部材30の挿通
端側にクサビ部材40を打込んで、取付部材30から上
記アングル部材10A及び金網板20が抜けないように
固定する。尚、図3(a)では、金網板20及びその網
目開口21部分は、見やすいように略記した一部分のみ
示してある。The angle members 10A and 10B having the above structure
And the wire mesh plate 20 are used to form a mountain clasp as follows. First, as shown in FIG. 3 (a), one end of a mounting member 30 made by bending a rectangular iron plate into a crank shape is mounted with a concrete nail 31 on the side facing the mountain side of the foundation concrete A for mountain retaining. The other end of the mounting member 30 is inserted into the mesh opening 21 of the wire mesh plate 20 while the hem side portion 20a of the wire mesh plate 20 is in contact with the basic concrete A surface. Furthermore, while holding the one end 10a of the angle member 10A having an L-shaped cross section and provided with insertion openings 11A at predetermined intervals in the longitudinal direction of the side surface so as to stand and contact the foundation concrete A portion for mountain retaining, The other end 30 of the mounting member 30 is provided in the opening 11A.
The wire mesh plate 20 is sandwiched between the mounting member 30 and the angle member 10A by inserting a. In this state, the wedge member 40 is driven into the insertion end side of the mounting member 30 to fix the angle member 10A and the wire mesh plate 20 so as not to come off from the mounting member 30. Note that, in FIG. 3A, the wire mesh plate 20 and the mesh opening 21 portion thereof are shown only in abbreviated part for easy viewing.
【0013】このようにして金網板20の裾側部分20
aを起立したアングル部材10Aの下方部分に取付部材
30で固定するとともに、図3(b)に示すように、さ
らに金網板20の上方部分を次のようにして起立したア
ングル部材10Aに固定する。起立したアングル部材1
0Aの側面に所定間隔に設けた差込開口11Aに合わせ
て、金網板20を間に挟むようにして、複数の別のアン
グル部材10Bを格子状に横に渡す。その状態で、両ア
ングル部材10A、10Bの差込開口11A、11B及
び金網板20の網目開口21に、差込片50aと連結片
50bとからなる連結部材50の平板形状の差込片50
a側を挿通する。挿通状態のままで、金網板20を間に
挟んだ両アングル部材10A、10Bの側面部分に接す
るようにして、連結部材50の差込片50aの平面部分
に予め設けられた差込開口51にクサビ部材40を打ち
込み、金網板20を両アングル部材10A、10Bの交
差した格子点部分で挟んで固定する。In this way, the hem side portion 20 of the wire mesh plate 20
3A is fixed to the lower portion of the upright angle member 10A by the mounting member 30, and as shown in FIG. 3B, the upper portion of the wire mesh plate 20 is further fixed to the upright angle member 10A as follows. . Upright angle member 1
A plurality of other angle members 10B are laterally passed in a grid pattern so that the wire mesh plate 20 is sandwiched therebetween in accordance with the insertion openings 11A provided on the side surface of 0A at a predetermined interval. In that state, the flat plate-shaped insertion piece 50 of the connection member 50 including the insertion piece 50a and the connection piece 50b is inserted into the insertion openings 11A and 11B of both the angle members 10A and 10B and the mesh opening 21 of the wire mesh plate 20.
Insert the a side. With the insertion state maintained, the side surfaces of both angle members 10A and 10B sandwiching the wire netting plate 20 are brought into contact with the insertion opening 51 provided in advance in the plane portion of the insertion piece 50a of the connection member 50. The wedge member 40 is driven in, and the wire netting plate 20 is fixed by being sandwiched between the intersecting lattice points of the angle members 10A and 10B.
【0014】一方、連結部材50の連結片50bは断面
略U字形の半筒状に形成されるとともに、半筒の側面部
分が上記差込片50aと直交するように設けられ、この
連結片50bの断面U字形の溝部分に、平面部分に所定
間隔で複数の貫通孔60aを設けた矩形の間隔調整部材
60を差し込む。その際、連結片50bの半筒状の両側
面部分に設けた複数の貫通孔52と、間隔調整部材60
の貫通孔60aとを、間隔調整部材60と連結片50と
の連結長が所定長になるようにそれぞれの貫通孔52、
60aを選択して合わせる。この貫通孔52、60a
に、貫通孔52、60aの径に合わせた略円柱状のスト
ッパー70を差し込み、連結部材50と間隔調整部材6
0とを連結片50bを介して連結する。On the other hand, the connecting piece 50b of the connecting member 50 is formed in a semi-cylindrical shape having a substantially U-shaped cross section, and the side portion of the semi-cylindrical shape is provided so as to be orthogonal to the inserting piece 50a. A rectangular interval adjusting member 60 having a plurality of through holes 60a provided at a predetermined interval in a plane portion is inserted into the groove portion having a U-shaped cross section. At that time, the plurality of through holes 52 provided on both side surface portions of the semi-cylindrical shape of the connecting piece 50b and the space adjusting member 60.
Through hole 60a of each of the through holes 52 so that the connection length of the space adjusting member 60 and the connecting piece 50 becomes a predetermined length,
Select 60a and match. This through hole 52, 60a
A stopper 70 having a substantially cylindrical shape matching the diameters of the through holes 52 and 60a is inserted into the connecting member 50 and the space adjusting member 6
0 is connected via a connecting piece 50b.
【0015】一方、間隔調整部材60の他方を、上記金
網板20からなる堰板Bと相対する堰板D(図1(a)
に示した。)側に接続して所定間隔で堰板B、Dが相対
する打設型枠Cを形成する。本実施例では、メタルフォ
ームを堰板Dとして使用している。その後、打設型枠C
にコンクリートを打設し、コンクリートがある程度固化
したら脱型する。脱型時には、金網板20はそのまま残
し、金網板20の相対する堰板Dを撤去する。さらに、
山留めの金網板20側を土砂で埋めて山留めを構築す
る。On the other hand, the other of the space adjusting members 60 is a weir plate D facing the weir plate B formed of the wire mesh plate 20 (FIG. 1A).
It was shown to. ) Side to form a casting form C where the dam plates B and D face each other at a predetermined interval. In this embodiment, metal foam is used as the dam plate D. After that, the casting form C
Pour concrete into the mold and remove it when the concrete has solidified to some extent. At the time of demolding, the wire mesh plate 20 is left as it is, and the opposing dam plate D of the wire mesh plate 20 is removed. further,
The side of the wire mesh plate 20 of the mountain clasp is filled with earth and sand to construct the mountain clasp.
【0016】[0016]
【発明の効果】本発明により、コンクリートの流出防止
形状の網目開口を有した金網板を、堰板として使用する
とともに、そのまま脱型することなく土砂に埋めること
ができるため、従来のように脱型時の作業性を考慮にお
いた型枠施工や、脱型時の堰板の撤去作業が不要とな
り、施工工数の大幅な削減により省力化を強力に達成す
ることができる。さらに、本発明では、金網板はそのま
ま打設コンクリートとともに土砂に埋められて山留め内
部に残って補強材としての役目を果たすため、金網板の
ない山留めに比べて、山留めの内部強度の向上を図るこ
とができる。EFFECTS OF THE INVENTION According to the present invention, a wire mesh plate having a mesh opening for preventing concrete outflow can be used as a weir plate and can be buried in the earth and sand without demolding as it is. Form work considering the workability at the time of mold making and work of removing the weir plate at the time of demolding are not required, and labor saving can be strongly achieved by significantly reducing the number of construction steps. Further, in the present invention, the wire mesh plate is buried in the earth and sand together with the cast concrete as it is and remains inside the mountain cleat to serve as a reinforcing material, so that the internal strength of the mountain cleat is improved as compared with the mountain cleat without the wire mesh plate. be able to.
【図面の簡単な説明】[Brief description of drawings]
【図1】本発明における打設型枠の形成状況を示す断面
説明図(a)。コンクリート打設後に金網板をそのまま
埋めて構築した山留めの断面説明図(b)。FIG. 1 is an explanatory sectional view (a) showing a formation state of a casting form according to the present invention. Sectional explanatory drawing (b) of the mountain clasp constructed by burying the wire mesh plate as it is after pouring concrete.
【図2】金網板の平面説明図(a)と断面説明図
(b)。金網板の網目開口を形成する状況を示す部分説
明図(c)。FIG. 2 is a plan explanatory view (a) and a cross sectional explanatory view (b) of the wire netting plate. The partial explanatory view (c) which shows the situation which forms the mesh opening of a metal mesh plate.
【図3】取付部材を用いて金網板をアングル部材に固定
する状況を示した斜視図(a)。金網板をアングル部材
に挟んで、連結部材により固定する状況を示した斜視図
(b)。FIG. 3 is a perspective view (a) showing a state in which a wire mesh plate is fixed to an angle member using a mounting member. FIG. 6B is a perspective view showing a state in which the wire mesh plate is sandwiched between angle members and fixed by a connecting member.
【図4】従来の山留め用の打設型枠の形成状況示す断面
説明図。FIG. 4 is a cross-sectional explanatory view showing a formation state of a conventional pile-mounting formwork.
10A アングル部材 10B アングル部材 11A 差込開口 11B 差込開口 20 金網板 21 網目開口 30 取付部材 40 くさび部材 50 連結部材 50a 差込片 50b 連結片 60 間隔調整部材 A 基礎コンクリート B 堰板 C 打設型枠 D 堰板 10A Angle member 10B Angle member 11A Insert opening 11B Insert opening 20 Wire mesh plate 21 Mesh opening 30 Mounting member 40 Wedge member 50 Connecting member 50a Inserting piece 50b Connecting piece 60 Space adjusting member A Basic concrete B Weir board C Casting type Frame D Weir plate
Claims (3)
クリート製の山留めを構築する山留め工法において、山
留め形成用に所定間隔で堰板を相対させて型枠を形成
し、前記堰板のうち山側に面した堰板に、網目開口がコ
ンクリートの流出防止形状である金網板を使用するとと
もに、前記型枠へのコンクリート打設後の脱型時に、前
記金網板を撤去することなく土砂に埋めて山留めを構築
することを特徴とする撤去不要な金網板を打設用型枠の
堰板に使用した山留め工法。1. In a mountain retaining method for constructing a concrete mountain retaining along a mountain surface or the like to prevent the collapse of sediment, in the mountain retaining formation, weir plates are made to face each other at a predetermined interval to form a form, and the weir plate is formed. Among the weir plates facing the mountain side, a wire mesh plate with mesh openings having a concrete outflow preventing shape is used, and at the time of demolding after placing concrete on the formwork, without removing the wire mesh plate A mountain retaining method in which a wire mesh plate that does not need to be removed is used as a weir plate for a casting form, which is characterized by being buried in the structure to construct a mountain retaining structure.
みが入れられるとともに、縦方向に引伸ばされることに
より切込み部が開口されている金網板であって、金属板
における多数の開口の上下間が全て同方向に傾斜され、
かつそれら傾斜部の外端が金属板の元の平面部側に折曲
げられて、各開口の間が略く字形断面になっている金属
板であること特徴とする請求項1に記載の撤去不要な金
網板を打設用型枠の堰板に使用した山留め工法。2. The wire mesh plate is a metal mesh plate in which a large number of transverse cuts are made in a metal plate and the cuts are opened by stretching the metal plate in the vertical direction. The upper and lower parts of are all tilted in the same direction,
The removal according to claim 1, characterized in that the outer ends of the inclined portions are bent toward the original flat surface side of the metal plate, and the openings have a substantially V-shaped cross section. Mountain retaining method that uses unnecessary wire mesh plate as the dam plate of the casting form.
所定間隔に起立させられたアングル部材と、これと格子
状に交差するように横に複数設けられたアングル部材と
の間に挟まれるとともに、アングル部材の交差する格子
点部分で、両アングル部材と金網板とに連結部材を抜け
防止可能に挿通して、アングル部材に金網板を固定する
ことを特徴とする請求項1又は2に記載の撤去不要な金
網板を打設用型枠の堰板に使用した山留め工法。3. The wire mesh plate is sandwiched between an angle member that is erected at a predetermined interval on the mountain fastening base concrete and a plurality of angle members that are laterally provided so as to intersect with the angle member, and 3. The wire mesh plate is fixed to the angle member by inserting the connecting member between the angle members and the wire mesh plate so as to prevent the angle member from intersecting at the intersecting lattice points. A mountain retaining method that uses wire mesh plates that do not need to be removed as the weir plate of the casting formwork.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP6179601A JPH0821085A (en) | 1994-07-07 | 1994-07-07 | Mountain retaining method using a wire mesh plate that does not need to be removed as the weir plate of the casting formwork |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP6179601A JPH0821085A (en) | 1994-07-07 | 1994-07-07 | Mountain retaining method using a wire mesh plate that does not need to be removed as the weir plate of the casting formwork |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH0821085A true JPH0821085A (en) | 1996-01-23 |
Family
ID=16068602
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP6179601A Pending JPH0821085A (en) | 1994-07-07 | 1994-07-07 | Mountain retaining method using a wire mesh plate that does not need to be removed as the weir plate of the casting formwork |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0821085A (en) |
-
1994
- 1994-07-07 JP JP6179601A patent/JPH0821085A/en active Pending
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH0821088A (en) | Fixing structure of wire mesh plate for weir plate that does not need to be removed in concrete formwork | |
| KR200493864Y1 (en) | Blocking board | |
| JPS58143014A (en) | Concurrent construction of sheathing and underground outer wall | |
| JPH05133199A (en) | Installing method of waterstop | |
| JPH09279610A (en) | Retaining wall construction method and device | |
| JPH01271526A (en) | Construction method for foundation | |
| JP2000257078A (en) | Construction method of solid foundation using PC foundation beam member and PC support frame for PC foundation beam member | |
| JPH05340013A (en) | Concrete constructing method, runner for construction and construction structure | |
| JP2002194754A (en) | Stepped joint forming block | |
| JP2829242B2 (en) | Construction method of retaining wall | |
| JPH0362849B2 (en) | ||
| JP2745103B2 (en) | Slope protection frame and method of construction | |
| JPH10219894A (en) | Concrete formwork structure | |
| JPH02282570A (en) | Separator for continuous footing | |
| JPH067180Y2 (en) | Mortar support for concrete block structures | |
| JPH11343609A (en) | Backstay | |
| JP2700637B2 (en) | Slope stable structure | |
| JP3091180B2 (en) | Legal frame, frame used for legal frame, and legal frame construction method | |
| JPS6320980B2 (en) | ||
| JP2000160575A (en) | Reinforcement frame and formwork support for building foundation | |
| JPS62233341A (en) | Construction work of block foundation | |
| JPH07207686A (en) | Retaining wall construction method | |
| JP2001214461A (en) | Retaining wall | |
| JPH02190524A (en) | Assembling of reinforcing bar for underground beam | |
| JPH03260222A (en) | Construction of slope frame and block structure |