JPH0833076B2 - Suspension scaffolding device for steel tower - Google Patents

Suspension scaffolding device for steel tower

Info

Publication number
JPH0833076B2
JPH0833076B2 JP4077095A JP7709592A JPH0833076B2 JP H0833076 B2 JPH0833076 B2 JP H0833076B2 JP 4077095 A JP4077095 A JP 4077095A JP 7709592 A JP7709592 A JP 7709592A JP H0833076 B2 JPH0833076 B2 JP H0833076B2
Authority
JP
Japan
Prior art keywords
scaffold
suspension
tower
power transmission
steel tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP4077095A
Other languages
Japanese (ja)
Other versions
JPH05280194A (en
Inventor
正則 清野
恵作 井畑
横山  稔
光男 三浦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumiden Transmission and Distribution Systems Products Corp
Tokyo Electric Power Co Holdings Inc
Original Assignee
Tokyo Electric Power Co Inc
Asahi Kinzoku Seiko Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc, Asahi Kinzoku Seiko Co Ltd filed Critical Tokyo Electric Power Co Inc
Priority to JP4077095A priority Critical patent/JPH0833076B2/en
Publication of JPH05280194A publication Critical patent/JPH05280194A/en
Publication of JPH0833076B2 publication Critical patent/JPH0833076B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/24Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/24Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
    • E04G3/243Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons following the outside contour of a building

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Movable Scaffolding (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、主に鋼管単柱送電用
鉄塔の塗装作業に使用される鋼管単柱送電用鉄塔の吊り
足場装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a suspension scaffolding apparatus for a steel pipe single pole power transmission steel tower, which is mainly used for painting a steel pipe single pole power transmission steel tower.

【0002】[0002]

【従来の技術】近年、おもに市街地に立つ送電用鉄塔に
は鋼管単柱送電用鉄塔が使用されているが、環境美化の
ために塗装される場合が多く、しかも、塗装は定期的に
行われている。
2. Description of the Related Art In recent years, steel pipe single-column power transmission towers have been used mainly for power transmission towers in urban areas, but they are often painted for environmental beautification, and furthermore, painting is done regularly. ing.

【0003】従来、この種の塗装作業は、鋼管単柱送電
用鉄塔の周囲に鋼管パイプやビティ足場などからなる組
立足場を地上より組み立て、この組立足場の上で行われ
ている。
Conventionally, this kind of coating work is carried out on the assembled scaffold from the ground by assembling an assembly scaffold consisting of steel pipes and bite scaffolds around a steel pipe single pole power transmission tower.

【0004】[0004]

【発明が解決しようとする課題】しかし、組立足場には
数多くの鋼管パイプやビティ足場を必要とし、また、そ
の組立および解体撤去に多くの手間・暇がかかるため、
仮設資材の搬入などにおいて管理が煩雑になり易くなる
ばかりでなく、塗装作業の長期化を免れないなどの課題
があった。
However, since many steel pipes and bite scaffolds are required for the assembly scaffold, and much time and effort are required for the assembly and disassembly and removal of the scaffold,
In addition to the complicated management of temporary materials being carried in, there is a problem that the coating work must be extended.

【0005】この発明は、以上の課題を解決するために
なされたもので、塗装作業などの補修作業をきわめて効
率的に行えるようにした鋼管単柱送電用鉄塔の吊り足場
装置を提供することを目的とする。
The present invention has been made to solve the above problems, and it is an object of the present invention to provide a suspension scaffolding apparatus for a steel pipe single pole power transmission steel tower, which enables repair work such as painting work to be performed very efficiently. To aim.

【0006】[0006]

【課題を解決するための手段】この発明に係る鋼管単柱
送電用鉄塔の吊り足場装置は、鋼管単柱送電用鉄塔の外
周および高さ方向の任意の位置に固定可能な複数部分に
ユニット化された組立解体可能な吊り足場と、この吊り
足場を吊るすリング状の把持部と、この把持部の両側に
水平に突設されたアーム部とからなる吊り治具と、前記
アーム部に滑車を介して取り付けられたワイヤーと、こ
のワイヤーを介して前記吊り足場を上げ下げするウイン
チとを備え、前記吊り足場の固定と上昇若しくは下降と
を交互に繰り返して前記吊り足場の位置を変えながら前
記鋼管単柱送電用鉄塔の補修を前記鋼管単柱送電用鉄塔
の腕金の下側位置まで行えるようにしてあるとともに、
前記腕金の下側位置に前記吊り足場を固定し、この吊り
足場の上に電気絶縁材又は電気絶縁処理を施した足場材
によって組立足場を組み立て、この組立足場の上で前記
腕金より上側部分の補修を行えるように構成されてい
る。
A suspension scaffolding device for a steel pipe single-column power transmission tower according to the present invention is unitized into a plurality of portions which can be fixed at the outer circumference of the steel pipe single-column power transmission tower and at arbitrary positions in the height direction. A suspension jig that can be assembled and disassembled, a ring-shaped gripping portion that suspends the suspension scaffolding, and a suspension jig that includes horizontally protruding arm portions on both sides of the gripping portion, and a pulley on the arm portion. A wire attached via the wire and a winch for raising and lowering the suspension scaffold via the wire, and fixing the suspension scaffold and raising or lowering the suspension scaffold alternately to change the position of the suspension scaffold, and the steel pipe single unit. It is possible to repair the steel tower for pole transmission up to the lower position of the arm of the steel tower for steel pole single pole transmission,
The suspension scaffold is fixed to a lower position of the arm, and an assembly scaffold is assembled on the suspension scaffold with an electric insulating material or a scaffold material subjected to an electric insulation treatment, and the assembly scaffold is above the arm. It is designed to be able to repair parts.

【0007】[0007]

【実施例】図1〜図4は、この発明に係る鋼管単柱送電
用鉄塔の吊り足場装置の一実施例を示し、図において、
符号1は鋼管単柱送電用鉄塔A(以下「鉄塔A」とい
う)のおもに塗装用作業足場として使用される吊り足
場、2と3は吊り足場1を鉄塔Aに吊るす吊り治具とワ
イヤー、そして、符号4は吊り足場1を鉄塔Aに沿って
上げ下げするウィンチである。
1 to 4 show an embodiment of a suspension scaffolding apparatus for a steel pipe single pole power transmission tower according to the present invention.
Reference numeral 1 is a suspension scaffold mainly used as a work scaffold for painting of a steel pipe single pole power transmission tower A (hereinafter referred to as "steel tower A"), and 2 and 3 are suspension jigs and wires for suspending the suspension scaffold 1 on the steel tower A, and Reference numeral 4 is a winch that raises and lowers the suspension scaffold 1 along the steel tower A.

【0008】吊り足場1はL形鋼又は鋼管などの軽量形
鋼からなる床軸組に床板5としてパンチングメタルなど
の鋼板を敷設し、かつ、周囲に手すり(図省略)を取り
付けることにより鉄塔Aの周囲に連続して構成されてい
る(図2参照)。
The suspension scaffold 1 is constructed by laying a steel plate such as punching metal as the floor plate 5 on a floor frame made of L-shaped steel or a light-gauge steel such as a steel pipe, and attaching a handrail (not shown) around the steel tower A. Are continuously formed around the periphery of the (see FIG. 2).

【0009】また、吊り足場1は複数部分に(実施例で
は4つ)分割してユニット化され、容易に組み立ておよ
び解体撤去がし易いように構成されている。
Further, the suspension scaffold 1 is divided into a plurality of parts (four in the embodiment) to be a unit, and is constructed so as to be easily assembled and disassembled.

【0010】このように構成された吊り足場1は吊り治
具2とワイヤー3とによって鉄塔Aの周囲に水平に吊る
せるように構成され、また、鉄塔Aの外周および高さ方
向の任意の位置に固定できるよに構成されている。
The suspension scaffolding 1 constructed in this way is constructed so as to be horizontally hung around the steel tower A by means of the suspension jig 2 and the wire 3, and the outer circumference of the steel tower A and any position in the height direction. It can be fixed to.

【0011】吊り治具2は鉄塔Aに巻き付けて取り付け
るられるようにリング状に構成された把握部2aと、この
把握部2aの両側に水平に突設された2本のアーム部2b,2
b とから構成されている(図3,4 参照)。
The hanging jig 2 has a ring-shaped grasping portion 2a so that the hanging jig 2 can be wound around the steel tower A, and two arm portions 2b, 2 protruding horizontally on both sides of the grasping portion 2a.
It is composed of b and b (see Figures 3 and 4).

【0012】把握部2aは鉄塔Aの外径に自由に対応でき
るように、鉄塔Aの外径に応じて径を変更できるように
構成され、また、アーム部2bの先端部に滑車6が取り付
けられ、この滑車6にウィンイチ4のドラムに巻き架け
られたワイヤー3が巻き架けられ、かつ、このワイヤー
3の端部に吊り足場1が吊られている。
The grasping portion 2a is constructed so that the diameter can be changed according to the outer diameter of the steel tower A so that it can freely correspond to the outer diameter of the steel tower A, and the pulley 6 is attached to the tip of the arm portion 2b. The wire 3 wound around the drum of the winch 4 is wound around the pulley 6, and the suspension scaffold 1 is hung at the end of the wire 3.

【0013】鉄塔Aの柱脚部にはH形鋼などの形鋼より
なるウィンチ台7が鉄塔Aを取り囲んで井桁状に組み立
てられ、このウィンチ台7の上に2台の動力式のウィン
チ4,4 が設置されている。そして、このウィンチ4を駆
動させることによって吊り足場1を鉄塔Aに沿って自由
に昇降できるようになっている。
On the column base of the tower A, a winch base 7 made of a shaped steel such as H-shaped steel is assembled in a cross girder shape surrounding the tower A, and two power winches 4 are mounted on the winch base 7. , 4 are installed. By driving the winch 4, the suspension scaffold 1 can be freely moved up and down along the steel tower A.

【0014】なお、吊り足場1には昇降がスムーズにな
されるように鉄塔Aの側面を滑走する複数個のガイドロ
ーラ(図省略)などが取り付けられている。
A plurality of guide rollers (not shown) that slide on the side surface of the tower A are attached to the suspension scaffold 1 so that the suspension scoops smoothly.

【0015】このような構成において、次に、この発明
に係る吊り足場による鉄塔Aの塗装作業を順をおって説
明する。
With such a structure, the coating operation of the steel tower A with the suspension scaffold according to the present invention will be described in order.

【0016】(1) 最初に、鉄塔Aの柱脚部にウィンチ台
7を組み立て、このウィンチ台7の上に2台のウィンチ
4を設置する(図5参照)。また、鉄塔Aの中間踊り場
Bのやや上側部分に吊り治具2を取り付け(図6参
照)、この吊り治具2の滑車6にウィンチ4,4 に巻き架
けられたワイヤー3を巻き架ける。さらに、吊り足場1
を組み立て、ワイヤー3に吊るす(図6参照)。なお、
これらの作業にはクレーンD(図1参照)を使用するも
のとする。
(1) First, the winch base 7 is assembled on the column base of the tower A, and the two winches 4 are installed on the winch base 7 (see FIG. 5). Further, the hanging jig 2 is attached to the upper part of the intermediate landing B of the tower A (see FIG. 6), and the wire 3 wound around the winches 4 and 4 is wound around the pulley 6 of the hanging jig 2. Furthermore, hanging scaffolding 1
And hang it on the wire 3 (see FIG. 6). In addition,
Crane D (see Fig. 1) shall be used for these operations.

【0017】(2) 次に、ウィンチ4,4 を駆動させ、吊り
足場1を中間踊り場Bの下側の直ぐ近くまで鉄塔Aに沿
って引き上げ、かつ、吊り足場1をその位置に固定す
る。
(2) Next, the winches 4 and 4 are driven so that the suspension scaffold 1 is pulled up along the steel tower A to a position immediately below the intermediate landing B, and the suspension scaffold 1 is fixed at that position.

【0018】そして、この吊り足場1を作業足場にして
中間踊り場Bを一時解体し、撤去する。中間踊り場Bの
撤去作業が完了したら、吊り足場1を鉄塔Aより解き離
し、ウィンチ4を駆動させて吊り足場1を地上まで下げ
ておく。
Then, the suspension scaffold 1 is used as a work scaffold to temporarily dismantle the intermediate landing B and remove it. After the removal work of the intermediate landing B is completed, the suspension scaffold 1 is released from the steel tower A, and the winch 4 is driven to lower the suspension scaffold 1 to the ground.

【0019】(3) 次に、送電線を架け渡すために鉄塔A
の側部に突設された最下段の腕金Cの上側に、吊り治具
2と全く同じように構成された吊り治具8を取り付け、
この吊り治具8の滑車6に吊り治具2のワイヤー3を付
け替える(図7参照)。
(3) Next, in order to bridge the transmission line, the tower A
The hanging jig 8 configured exactly the same as the hanging jig 2 is attached to the upper side of the lowermost arm C that is provided on the side of the
The wire 3 of the hanging jig 2 is replaced with the pulley 6 of the hanging jig 8 (see FIG. 7).

【0020】(4) 次に、再び、ウィンチ4を駆動させて
吊り足場1を吊り治具2の取付位置まで引き上げ、吊り
足場1を作業足場にして吊り治具2を取り外す。
(4) Next, the winch 4 is driven again to pull up the suspension scaffold 1 to the mounting position of the suspension jig 2, and the suspension scaffold 1 is used as a working scaffold to remove the suspension jig 2.

【0021】(5) 次に、再び、ウィンチ4を駆動させて
吊り足場1を最下段の腕金Cの下まで引き上げる。
(5) Next, the winch 4 is driven again to pull up the suspended scaffolding 1 to below the lowermost arm C.

【0022】(6) 次に、吊り足場1を鉄塔Aに対して固
定と開放および下降とを交互に行いながら、吊り足場1
から手の届く範囲で鉄塔Aの下塗り作業を腕金C部分か
ら地上まで順に行う。
(6) Next, while suspending the scaffolding 1 with respect to the steel tower A, alternately performing fixing, opening and lowering, the suspension scaffolding 1 is carried out.
Perform the undercoat work of the tower A from the arm C portion to the ground in order within reach.

【0023】(7) 腕金Cより下の部分の下塗りが地上ま
で完了したら、ウィンチ4を駆動させて吊り足場1を腕
金Cの下側部分まで引き上げ、その部分に固定する。
(7) When the undercoating of the portion below the armrest C is completed to the ground, the winch 4 is driven to pull up the hanging scaffold 1 to the lower portion of the armrest C and fix it to that portion.

【0024】(8) 次に、この吊り足場1の上に電気絶縁
材又は電気絶縁処理を施した足場材(例えば、FRP 製の
足場材) によって組立足場9を組み立て、この組立足場
9を作業足場にして腕金Cおよびこの腕金Cより上側部
分の塗装作業を行う(図8,9 参照)。この場合、鉄塔A
および腕金Cの塗装作業を左右片側ずつ前後して行え
ば、送電を全面的にストップさせないで塗装作業を行う
ことができる。
(8) Next, the assembly scaffold 9 is assembled on the suspended scaffold 1 with an electrically insulating material or a scaffold material subjected to an electrical insulation treatment (for example, scaffold material made of FRP), and the assembled scaffold 9 is worked. As a scaffold, the arm C and the part above the arm C are painted (see Figures 8 and 9). In this case, Tower A
By performing the coating work of the armrest C and the left and right sides back and forth, the painting work can be performed without completely stopping the power transmission.

【0025】また、組立足場9が電気絶縁材からなるの
で、緊急時には組立足場9を解体撤去しなくとも送電を
行うことができる。
Further, since the assembly scaffold 9 is made of an electric insulating material, power can be transmitted in an emergency without disassembling and removing the assembly scaffold 9.

【0026】(9) 腕金Cおよびこの腕金Cの上側部分の
塗装作業が全て終了したら、組立足場9を解体して地上
に降ろす。この作業にもクレーンDを利用する。
(9) When the coating work of the arm C and the upper part of the arm C is completed, the assembly scaffold 9 is disassembled and put down on the ground. The crane D is also used for this work.

【0027】(10)次に、吊り足場1を鉄塔Aより解き離
し、ウィンチ4を駆動させて吊り足場1の下降と固定と
を交互に行いながら中間踊り場Bの設置位置まで仕上げ
塗装を行い、中間踊り場Bの設置位置までの仕上げ塗装
作業が完了したら、この部分に吊り足場1を再び固定す
る。
(10) Next, the suspension scaffold 1 is released from the steel tower A, the winch 4 is driven, and the descent and the fixing of the suspension scaffold 1 are alternately performed, and finish coating is performed up to the installation position of the intermediate landing B. When the finishing painting work up to the installation position of the intermediate landing B is completed, the suspension scaffold 1 is fixed again to this portion.

【0028】そして、この吊り足場1を作業足場にして
中間踊り場Bを再び組み立てて設置する。
Then, the suspended scaffold 1 is used as a work scaffold to reassemble and install the intermediate landing site B.

【0029】また、中間踊り場Bの上側部分に吊り治具
2を再び取り付け、この吊り治具2の滑車6に吊り治具
8の滑車に架けられているワイヤー3を架け変える。こ
の場合、滑車6ごとワイヤー3を架け変えることもあ
る。
Further, the hanging jig 2 is attached to the upper part of the intermediate landing B again, and the pulley 6 of this hanging jig 2 is replaced with the wire 3 hung on the pulley of the hanging jig 8. In this case, the wire 3 may be replaced with the pulley 6.

【0030】(11)次に、吊り治具8を取り外す。(11) Next, the hanging jig 8 is removed.

【0031】(12)次に、ウィンチ4を駆動させて吊り足
場1の固定と下降とを交互に行って中間踊り場Bから地
上までの仕上げ塗装を行う。
(12) Next, the winch 4 is driven to alternately fix and lower the hanging scaffold 1, and finish coating from the intermediate landing B to the ground is performed.

【0032】最後に吊り治具2およびワイヤー3を取り
外し、続いてウィンチ4およびウィンチ台7を撤去す
る。この作業もクレーンDを使って行う。
Finally, the hanging jig 2 and the wire 3 are removed, and then the winch 4 and the winch base 7 are removed. This work is also performed using crane D.

【0033】なお、実施例では、腕金Cの下側部分の下
塗を先に行い、その後に腕金Cの上側部分の塗装を行っ
ているが、上側部分を先に行い、その後に下側部分をお
こなってもよく、状況に応じていずれかの方法を選択す
るものとする。
In the embodiment, the lower portion of the arm C is first coated, and then the upper portion of the arm C is coated. However, the upper portion is coated first, and then the lower portion is coated. Part may be performed, and either method shall be selected according to the situation.

【0034】また、中間踊り場Bの撤去および設置等に
際し、中間踊り場Bの上側部分に吊り治具2を取り付
け、この吊り治具2に吊り足場1を吊っているが、吊り
治具2を省略し、腕金Cの上側部分に当初より吊り金具
8を取り付け、この吊り治具8に吊り足場1を吊るよう
にしてもよい。
When removing or installing the intermediate landing B, the hanging jig 2 is attached to the upper part of the intermediate landing B, and the hanging scaffold 1 is hung on the hanging jig 2, but the hanging jig 2 is omitted. However, the hanging metal fitting 8 may be attached to the upper part of the arm C from the beginning, and the hanging scaffold 1 may be hung on the hanging jig 8.

【0035】[0035]

【発明の効果】この発明は、以上説明した構成からなる
ので、以下に記載するような効果を有する。
Since the present invention has the constitution described above, it has the following effects.

【0036】(1) 鉄塔に沿って地上より仮設足場を組み
立てる必要がないので、仮設資材としての鋼管パイプや
ビティ足場を大幅に減らすことができ、仮設資材の管理
が容易である。また、仮設足場の組立作業も無くなるた
め、塗装作業などの各種の補修作業を短期間のうちに行
うことができる。
(1) Since it is not necessary to assemble a temporary scaffold from the ground along the steel tower, the steel pipes and bite scaffolds as temporary materials can be significantly reduced, and the management of temporary materials is easy. Also, since the work of assembling the temporary scaffold is eliminated, various repair work such as painting work can be performed in a short period of time.

【0037】(2) 送電線を架け渡すための腕金より下側
部分の作業は、吊り足場の固定と上昇若しくは下降を交
互に繰り返しながら吊り足場を鉄塔に沿って移動し、こ
の吊り足場を作業足場として用い、腕金より上側部分の
作業は、吊り足場を腕金の下側部分に固定し、この吊り
足場の上に組立足場を組み立て、この組立足場を作業足
場として行うので、作業に無駄がなく作業性がきわめて
よい。
(2) For the work below the arm for bridging the power transmission line, the suspension scaffold is moved along the steel tower while alternately repeating fixing and lifting or lowering of the suspension scaffold, and It is used as a work scaffold.For the work above the arm, the suspending scaffold is fixed to the lower part of the arm, the assembly scaffold is assembled on this suspending scaffold, and this assembly scaffold is used as the work scaffold. There is no waste and workability is extremely good.

【0038】(3) 腕金より上側部分の組立足場には絶縁
材又は絶縁処理を施した足場材が使用されているので、
補修作業時の感電事故を未然に防止することができて作
業の安全性も図れる。
(3) Since an insulating material or a scaffold material subjected to an insulation treatment is used for the assembly scaffold above the armrest,
Electric shock accidents during repair work can be prevented and work safety can be improved.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明に係る鋼管単柱送電用鉄塔の吊り足場
装置の設置状態を示す鉄塔の正面図である。
FIG. 1 is a front view of a steel tower showing a state of installation of a suspension scaffolding device for a steel pipe single-column power transmission tower according to the present invention.

【図2】吊り足場の平面図である。FIG. 2 is a plan view of a suspended scaffold.

【図3】吊り治具の平面図である。FIG. 3 is a plan view of a hanging jig.

【図4】吊り治具の一部正面図である。FIG. 4 is a partial front view of a hanging jig.

【図5】ウィンチ台およびウィンチの設置状態を示す平
面図である。
FIG. 5 is a plan view showing an installed state of a winch base and a winch.

【図6】吊り足場の取付状態を示す鉄塔の一部正面図で
ある。
FIG. 6 is a partial front view of a steel tower showing a mounting state of suspension scaffolds.

【図7】吊り足場の取付状態を示す鉄塔の一部側面図で
ある。
FIG. 7 is a partial side view of a steel tower showing a mounting state of suspension scaffolds.

【図8】組立足場の組立状態を示す鉄塔の上部正面図で
ある。
FIG. 8 is a front view of the upper part of the steel tower showing the assembled state of the assembled scaffolds.

【図9】組立足場の組立状態を示す鉄塔の上部正面図で
ある。
FIG. 9 is a front view of the upper part of the steel tower showing the assembled state of the assembled scaffolds.

【符号の説明】[Explanation of symbols]

A…鉄塔(鋼管単柱送電用鉄塔)、B…中間踊り場、C
…腕金、1…吊り足場、2…吊り治具、3…ワイヤー、
4…ウィンチ、5…床板、6…滑車、7…ウィンチ台、
8…吊り治具、9…組立足場。
A: steel tower (steel pipe single pole power transmission steel tower), B: middle landing, C
… Arms, 1… Hanging scaffolding, 2… Hanging jigs, 3… Wires,
4 ... Winch, 5 ... Floor board, 6 ... Pulley, 7 ... Winch base,
8 ... Hanging jig, 9 ... Assembly scaffolding.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 井畑 恵作 兵庫県伊丹市北河原字当田20番地の2 朝 日金属精工株式会社内 (72)発明者 横山 稔 東京都中央区銀座6丁目2番10号 株式会 社巴組鐵工所内 (72)発明者 三浦 光男 東京都中央区銀座6丁目2番10号 株式会 社巴組鐵工所内 (56)参考文献 特開 昭63−93960(JP,A) 実開 昭63−117846(JP,U) 実開 昭61−1546(JP,U) ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Keisaku Ibata No. 20 Toda, Kitagawara, Itami City, Hyogo Prefecture 2 Asahi Metal Seiko Co., Ltd. (72) Inventor Minoru Yokoyama 6-2 Ginza, Chuo-ku, Tokyo No. 10 In stock company, Tomoeumi Steel Works (72) Inventor Mitsuo Miura 6-2-10 Ginza, Chuo-ku, Tokyo In stock company, Tomoeumi Works (56) Reference JP-A-63-93960 (JP) , A) Actually opened 63-117846 (JP, U) Actually opened 61-1546 (JP, U)

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 鋼管単柱送電用鉄塔の外周および高さ方
向の任意の位置に固定可能な複数部分にユニット化され
た組立解体可能な吊り足場と、この吊り足場を吊るすリ
ング状の把持部と、この把持部の両側に水平に突設され
たアーム部とからなる吊り治具と、前記アーム部に滑車
を介して取り付けられたワイヤーと、このワイヤーを介
して前記吊り足場を上げ下げするウインチとを備え、前
記吊り足場の固定と上昇若しくは下降とを交互に繰り返
して前記吊り足場の位置を変えながら前記鋼管単柱送電
用鉄塔の補修を前記鋼管単柱送電用鉄塔の腕金の下側位
置まで行えるようにしてあるとともに、前記腕金の下側
位置に前記吊り足場を固定し、この吊り足場の上に電気
絶縁材又は電気絶縁処理を施した足場材によって組立足
場を組み立て、この組立足場の上で前記腕金より上側部
分の補修を行えるようにしてあることを特徴とする鋼管
単柱送電用鉄塔の吊り足場装置。
1. A suspension scaffold that can be assembled and disassembled into a plurality of parts that can be fixed to the outer periphery of a steel pipe single-column power transmission tower and at arbitrary positions in the height direction, and a ring-shaped gripping part that suspends this suspension scaffold. And a hanging jig consisting of horizontally protruding arm portions on both sides of the grip portion, a wire attached to the arm portion via a pulley, and a winch for raising and lowering the hanging scaffolding through the wire. And fixing the suspension scaffold and alternately repeating ascending or descending to change the position of the suspension scaffold to repair the steel pipe single pole power transmission steel tower under the armor of the steel pipe single pole power transmission steel tower. The suspension scaffold is fixed to the lower position of the arm, and the assembly scaffold is assembled on the suspension scaffold with an electric insulating material or a scaffold material subjected to an electric insulation treatment. A suspension scaffolding device for a steel pipe single pole power transmission steel tower, characterized in that the upper part of the armature above the assembled scaffold can be repaired.
JP4077095A 1992-03-31 1992-03-31 Suspension scaffolding device for steel tower Expired - Fee Related JPH0833076B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4077095A JPH0833076B2 (en) 1992-03-31 1992-03-31 Suspension scaffolding device for steel tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4077095A JPH0833076B2 (en) 1992-03-31 1992-03-31 Suspension scaffolding device for steel tower

Publications (2)

Publication Number Publication Date
JPH05280194A JPH05280194A (en) 1993-10-26
JPH0833076B2 true JPH0833076B2 (en) 1996-03-29

Family

ID=13624228

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4077095A Expired - Fee Related JPH0833076B2 (en) 1992-03-31 1992-03-31 Suspension scaffolding device for steel tower

Country Status (1)

Country Link
JP (1) JPH0833076B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105625731A (en) * 2015-12-25 2016-06-01 安徽唐兴机械装备有限公司 Method for building steel structure building

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102704615B1 (en) * 2022-07-29 2024-09-11 한국전력공사 Modular pylon

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS611546U (en) * 1984-06-11 1986-01-08 徳直 鳴海 Gondola for working at heights
JPS6393960A (en) * 1986-10-06 1988-04-25 狩野 勝俊 Working apparatus of conical shape construction
JPH0443547Y2 (en) * 1987-01-19 1992-10-14

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105625731A (en) * 2015-12-25 2016-06-01 安徽唐兴机械装备有限公司 Method for building steel structure building

Also Published As

Publication number Publication date
JPH05280194A (en) 1993-10-26

Similar Documents

Publication Publication Date Title
JP2587684B2 (en) Construction wall construction equipment
JPH05295712A (en) Bridge mobile protection
JP5589183B2 (en) Cylindrical structure scaffolding apparatus and moving method thereof
JPH0833076B2 (en) Suspension scaffolding device for steel tower
JP2775201B2 (en) Lifting member positioning and mounting device for high lift crane
JP3028071B2 (en) Top removal method and scaffold for removal work of ultra-high tubular structure
JP2720339B2 (en) Cable laying method
JPH07150767A (en) Beam truss erection method in building with overhead traveling crane
JP2989969B2 (en) Exterior scaffolding and exterior construction method
JP3193334B2 (en) Gondola steady rest device
CN218621822U (en) Stores pylon assembled operation platform
JPH0755777B2 (en) Elevator installation method and installation work floor equipment
JPH0637159Y2 (en) Hanging scaffolding
CN222991125U (en) Steel construction horse way mounting structure
CN113789725B (en) Suspension bridge construction method and lifting device
JPH11349255A (en) How to replace elevator counterweights and counterrails
JPH0729138Y2 (en) Scaffold for dismantling tower-like structures
JP2003064864A (en) Circular gondola
JPH09310484A (en) Large space applicable suspended scaffold constructing system
JP2854389B2 (en) Steel construction method
JPH04237761A (en) Method for constructing high place facility
JPH1144093A (en) Exterior wall hanging tool
JPH021066B2 (en)
JP2876991B2 (en) Steel frame method for high-rise buildings
JP3035099B2 (en) Elevator main cable replacement method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313532

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees