JPH0874202A - Track track construction method and repair method - Google Patents

Track track construction method and repair method

Info

Publication number
JPH0874202A
JPH0874202A JP21454094A JP21454094A JPH0874202A JP H0874202 A JPH0874202 A JP H0874202A JP 21454094 A JP21454094 A JP 21454094A JP 21454094 A JP21454094 A JP 21454094A JP H0874202 A JPH0874202 A JP H0874202A
Authority
JP
Japan
Prior art keywords
roadbed
track
bag body
flexible bag
ballast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP21454094A
Other languages
Japanese (ja)
Other versions
JP3432302B2 (en
Inventor
Hisashi Tarumi
尚志 垂水
Masaru Tateyama
勝 舘山
Makoto Sunaga
誠 須長
Hiroshi Iwasa
弘 岩佐
Yoshitomo Kinoshita
吉友 木下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Railway Technical Research Institute
Raito Kogyo Co Ltd
Original Assignee
Railway Technical Research Institute
Raito Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Railway Technical Research Institute, Raito Kogyo Co Ltd filed Critical Railway Technical Research Institute
Priority to JP21454094A priority Critical patent/JP3432302B2/en
Publication of JPH0874202A publication Critical patent/JPH0874202A/en
Application granted granted Critical
Publication of JP3432302B2 publication Critical patent/JP3432302B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Railway Tracks (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

(57)【要約】 【目的】路盤の沈下およびバラストの緩み、供用後の列
車通過による繰り返し荷重や振動によるバラストの側方
移動および緩みなどに起因する軌道沈下を防止する。 【構成】路盤13上に道床バラスト8を敷き、その上に
枕木11およびレール10を敷設した有道床軌道の築造
に当り、前記枕木11と路盤13との間に、内部にバラ
スト、砂利、砕石等の中詰め材12が圧送充填された気
密性を有する可撓性袋体1を介在し、この可撓性袋体1
内にさらに中詰め材12を圧送充填し、この可撓性袋体
1の外圧により前記路盤13側を先行的に圧密沈下させ
る。
(57) [Summary] [Purpose] To prevent track subsidence due to subsidence of the roadbed and loosening of ballast, sideways movement and looseness of ballast due to repeated load and vibration due to passing trains after service, etc. [Structure] A roadbed ballast 8 is laid on the roadbed 13 and sleepers 11 and rails 10 are laid on the roadbed track to build a ballast, gravel, and crushed stone between the sleepers 11 and the roadbed 13. The flexible bag body 1 having airtightness filled with the filling material 12 such as
Further, the filling material 12 is pressure-filled therein, and the roadbed 13 side is preliminarily compacted and settled by the external pressure of the flexible bag 1.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、軌道沈下の少ない線路
軌道の築造方法および線路軌道への改修方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a railroad track with less subsidence and a method for repairing a railroad track.

【0002】[0002]

【従来の技術】従来より、線路軌道の構造としては、バ
ラスト道床軌道、スラブ軌道、舗装軌道、鋼橋直結軌
道、コンクリート直結軌道等があり、この内、レールを
枕木に締結装置を用いて緊結し、枕木を道床バラストで
支持するバラスト道床軌道が最も多く採用されている。
バラストを道床に使用する利点としては、建設費が安
い、配線変更が簡単である、バラストの噛み合い効果に
より内部摩擦角が高く荷重に対する強度が高い、変形に
対する追従性が高い、さらに、列車荷重を分散して路盤
や盛土に伝えるなどの種々の効果を有するが、同時に路
盤または地盤の沈下、列車の繰り返し荷重や振動、レー
ル自身の温度伸縮などにより道床部が経時的に変形し、
レールの高低や通りに狂いが生じ、それがある一定値以
上になると列車の乗り心地や安定走行に支障をきたすよ
うになる。そのため、軌道の保守点検を定期的に行い、
軌道に沈下があった場合には、その道床部にバラストを
補充し突き固め軌道ズレを修復するなどの補修作業を行
い、軌道ズレが常に一定基準内になるように管理してい
る。
2. Description of the Related Art Conventionally, track track structures include ballast track tracks, slab tracks, pavement tracks, steel bridge direct tracks, concrete direct tracks, etc. However, the ballast ballast track, which supports the sleepers with ballast ballast, is most often adopted.
The advantages of using ballast on the roadbed are low construction cost, easy wiring change, high internal friction angle due to ballast meshing effect, high strength against load, high followability to deformation, and train load. It has various effects such as distributed to the roadbed or embankment, but at the same time the roadbed is deformed over time due to subsidence of the roadbed or ground, repeated load and vibration of the train, temperature expansion and contraction of the rail itself, etc.
If the rails rise or fall or the road gets out of order, and if it exceeds a certain value, it will hinder the ride comfort and stable running of the train. Therefore, maintenance and inspection of the track is regularly performed,
When there is a subsidence on the track, repair work such as refilling ballast to the roadbed to tamper and repair the track deviation is managed so that the track deviation is always within a certain standard.

【0003】また、近年、省力化軌道と称して、初めか
らバラストを無くしたスラブ軌道が提案されている。こ
のスラブ軌道は、枕木に比べて受圧面積の大きいスラブ
版や大版枕木により列車荷重を分散して路盤に荷重を伝
える構造であり、地盤が強固であれば、または路盤の圧
密が列車の通過により完了している場合には、その後の
軌道ズレが少ないため、保守の省力化に大きく貢献する
ものとなっている。
In recent years, a slab track without ballast has been proposed from the beginning, which is called a labor-saving track. This slab track is a structure in which the train load is distributed to the subbase by distributing the train load with a slab plate or large-sized sleeper that has a larger pressure receiving area than the sleepers.If the ground is strong or the roadbed is compacted, it will pass through the train. If it has been completed by, there is little orbital deviation after that, which greatly contributes to labor saving in maintenance.

【0004】[0004]

【発明が解決しようとする課題】前述のように、道床に
バラストを使用した有道床軌道の場合、列車荷重を分散
して路盤や盛土に伝えることができるとしても、開線当
初の初期の段階では、路盤や盛土の締固めが不十分であ
るなどの理由により、路盤や盛土の圧密が完了するまで
に急激な沈下が生ずるとともに、列車通過による振動に
よりバラストの間隙が密となってバラスト粒子の配置が
最終的に安定化するまで沈下が生じる。これらに原因す
る沈下は比較的その量も大きく、開線当初の保守管理が
非常に大変なものとなっている。また、これらの沈下が
安定したとしても、列車による繰り返し荷重や振動によ
る道床バラストの緩みに起因した変形や、道床バラスト
と路盤との境界面において生じるバラスト粒子のめり込
みなどによる軌道沈下は、経時的にもさほど減少せず進
行するため、依然として大きな問題となっており、保線
作業の省力化が望まれている。
As described above, in the case of a ballasted track using ballast for the roadbed, even if the train load can be distributed and transmitted to the roadbed or embankment, the initial stage at the beginning of the line opening However, due to insufficient compaction of the roadbed and the embankment, rapid subsidence occurs until the consolidation of the roadbed and the embankment is completed, and the vibration of the train passage causes the ballast gap to become dense and the ballast particles. Subsidence occurs until the placement of the is finally stabilized. The amount of subsidence caused by these is relatively large, and maintenance at the beginning of the opening of the line is extremely difficult. Even if these subsidences are stable, the deformation due to the looseness of the ballast ballast due to the repeated load and vibration from the train, and the subsidence of the track due to the ballast particles getting into the boundary surface between the roadbed ballast and the roadbed, etc. Since it does not decrease so much and progresses, it is still a big problem, and labor saving of track maintenance work is desired.

【0005】また、前記無道床軌道構造の場合には、バ
ラストが存在しないためバラストの緩みやめり込みなど
のバラスト自身に起因した問題は生じない。しかし、特
に新設線の場合には、同様に路盤や地盤の締固めが不十
分であるなどの原因により、開線当初の段階において、
路盤や地盤の圧密沈下が大きいものとなっている。この
場合、有道床軌道の営業線を道床の無いスラブ軌道に改
修すれば、路盤の圧密現象が完了しており、軌道沈下の
少ない良好な軌道になるとも考えられるが、現実問題と
してはスラブ軌道への変更は極めて困難である。
In addition, in the case of the above-mentioned ballastless track structure, since there is no ballast, problems caused by the ballast itself such as loosening or sinking of the ballast do not occur. However, especially in the case of newly installed lines, due to reasons such as insufficient compaction of the roadbed and ground, at the initial stage of opening the line,
The consolidation settlement of the roadbed and ground is large. In this case, if the sales line of the trackbed track is modified to a slab track without a trackbed, the consolidation phenomenon of the roadbed will be completed, and it is considered that the track will be a good track with less settlement, but the actual problem is the slab track. Change to is extremely difficult.

【0006】そこで、本発明の主たる課題は、路盤や地
盤等の沈下およびバラストの緩みなどに起因する比較的
初期の段階の軌道沈下を防止するとともに、供用後の列
車通過による繰り返し荷重や振動によるバラストの側方
移動および緩みに起因した軌道沈下を防止し、保守管理
に手間の掛からない省力化された線路軌道の築造方法お
よび省力化線路軌道への改修方法を提供することにあ
る。
Therefore, the main object of the present invention is to prevent the track subsidence at a relatively early stage due to the subsidence of the roadbed or the ground and the looseness of the ballast, and to prevent the repeated load and vibration due to passing the train after the service. (EN) Provided are a method for constructing a labor-saving railroad track and a method for repairing a labor-saving railroad track, which prevents railroad subsidence due to lateral movement and loosening of ballasts and saves maintenance work.

【0007】[0007]

【課題を解決するための手段】前記課題を解決するめ
に、本発明は、路盤上に道床バラストを敷き、その上に
枕木およびレールを敷設した有道床軌道の築造に当り、
前記枕木と路盤との間に、内部に砕・粒状物および/ま
たは粉状物からなる中詰め材が圧送充填された気密性を
有する可撓性袋体を介在して設け、この可撓性袋体内に
さらに中詰め材の圧送充填または空気のみの圧送を行
い、この可撓性袋体の外圧により前記路盤を先行的に圧
密沈下させることを特徴とする。
Means for Solving the Problems To solve the above problems, the present invention relates to the construction of a ballasted track in which a ballast ballast is laid on a roadbed and sleepers and rails are laid on the ballasted ballast.
Between the sleepers and the roadbed, there is provided an airtight flexible bag body in which a filling material made of crushed / granular material and / or powder material is pumped and filled, It is characterized in that the filling material is further pressure-fed and filled into the bag body or only air is pressure-fed, and the roadbed is preliminarily compacted and settled by the external pressure of the flexible bag body.

【0008】また、路盤上にスラブ版を敷設し、このス
ラブ版の上にレールを敷設した無道床軌道の築造に当
り、前記スラブ版と路盤との間に、内部に砕・粒状物お
よび/または粉状物からなる中詰め材が圧送充填された
気密性を有する可撓性袋体を介在して設け、この可撓性
袋体内にさらに中詰め材の圧送充填または空気のみの圧
送を行い、この可撓性袋体の外圧により前記路盤を先行
的に圧密沈下させることを特徴とする。
Further, when a slab slab is laid on the roadbed and rails are laid on the slab slab to construct a ballastless track, crushed / granular particles and / Alternatively, a flexible bag body having airtightness in which a filling material made of powder is filled by pressure is provided, and the filling material or the air alone is further fed into the flexible bag body. The roadbed is preliminarily compacted and settled by the external pressure of the flexible bag body.

【0009】他方、路盤上に道床バラストを敷き、その
上に枕木およびレールを敷設した既設の有道床軌道の改
修に当っては、枕木の直下の道床バラストを掘削し、枕
木の直下にかつその長手方向に沿って路盤上に気密性を
有する可撓性袋体を配置し、この可撓性袋体の内部に砕
・粒状物および/または粉状物からなる中詰め材を圧送
充填して膨らませた後、可撓性袋体周囲に道床バラスト
の埋め戻しを行い、次いでこの可撓性袋体内にさらに中
詰め材の圧送充填または空気のみの圧送を行い、この可
撓性袋体の外圧により前記路盤を先行的に圧密沈下させ
ることを特徴とするものである。
On the other hand, when repairing an existing roadbed track in which a ballast ballast is laid on the roadbed and sleepers and rails are laid on it, the ballast ballast immediately under the sleepers is excavated and directly under the sleepers. A flexible bag having airtightness is arranged on the roadbed along the longitudinal direction, and a filling material made of crushed / granular and / or powdery material is pressure-fed and filled into the inside of the flexible bag. After inflating, the ballast ballast is backfilled around the flexible bag body, and then the flexible bag body is further pumped and filled with the filling material or the air only, and the external pressure of the flexible bag body is increased. Is characterized in that the roadbed is preliminarily consolidated and subsided.

【0010】[0010]

【作用】本発明に係る路線軌道の築造方法においては、
枕木またはスラブ版と路盤との間に、内部に砕・粒状物
および/または粉状物からなる中詰め材が圧送充填され
た気密性を有する可撓性袋体を介在して設け、この可撓
性袋体内にさらに中詰め材を圧送充填等を行い、この可
撓性袋体の外圧により前記路盤を先行的に圧密沈下させ
る。土は、一般的にそれまでに経験した応力履歴以内の
荷重が作用する場合にはほとんど変形せず、応力履歴以
上の荷重が作用した場合には大きく変形する特性を有す
る。したがって、特に新設軌道の場合には、路盤の締固
めが不十分である場合には、営業開始の初期の段階で、
列車通過により路盤が大きく沈下することとなる。
[Operation] In the method of constructing a track according to the present invention,
Between the sleepers or slabs and the roadbed, an airtight flexible bag body filled with pressure-filled filling material made of crushed / granular material and / or powder is provided, The flexible bag body is further filled with a filling material by pressure and the like, and the roadbed is preliminarily compacted and settled by the external pressure of the flexible bag body. Soil generally has a characteristic that it hardly deforms when a load within a stress history experienced up to that time acts, and largely deforms when a load exceeding a stress history acts. Therefore, especially in the case of new track, if the roadbed is not sufficiently compacted,
The passage of the train will cause the roadbed to sink significantly.

【0011】そのために、本発明においては、可撓性袋
体に中詰め材を圧送充填することにより、路盤に外圧、
好ましくは列車荷重相当以上の外圧を与えることによ
り、過圧密の路盤とする。したがって、その後に列車荷
重が加わっても、路盤の沈下量が著しく減少する。ま
た、この際、圧力は可撓性袋体を通じて路盤に平均的に
加えられるため、従来のように、局部的に過大な圧力に
よってバラストが直接路盤にめり込むこともない。
Therefore, in the present invention, by filling the flexible bag body with the filling material by pressure, an external pressure is applied to the roadbed.
An over-consolidated roadbed is preferably provided by applying an external pressure equal to or higher than the train load. Therefore, even if the train load is applied thereafter, the subsidence amount of the roadbed is significantly reduced. Further, at this time, since the pressure is applied to the roadbed evenly through the flexible bag, the ballast does not directly go into the roadbed due to locally excessive pressure as in the conventional case.

【0012】また、可撓性袋体は、中詰め材の圧送充填
が完了した後は、収縮しようとするため、圧送充填され
た中詰め材が締め付けられ密な状態となるとともに、可
撓性袋体によりその配置が拘束されるために、列車荷重
による繰り返し荷重や振動を受けても、緩みが生じない
し側方移動もなくなる。さらに、可撓性袋体による拘束
効果により、中詰め材の強度特性も向上し、道床バネ値
も改善されることとなる。したがって、供用後の軌道沈
下も著しく少ないものとなり、保守管理が容易となり保
線作業が省力化される。
Further, since the flexible bag body tries to shrink after the filling and filling of the filling material is completed, the filling material filled with the feeding material is tightened to be in a dense state, and the flexible bag body is flexible. Since the bag is constrained in its arrangement, it does not loosen or move laterally even when subjected to repeated load or vibration due to train load. Further, due to the restraining effect of the flexible bag, the strength characteristics of the filling material are improved and the roadbed spring value is also improved. Therefore, track subsidence after service is significantly reduced, maintenance is facilitated, and track maintenance work is saved.

【0013】また、本発明においては、前記路盤の圧密
沈下の際に、レール上に列車車両を搭載することによ
り、レールの盛り上がりを防止することができるととも
に、可撓性袋体が列車自重を反力として路盤側を押圧す
ることができる。さらに、前記路盤の圧密沈下の完了後
に、可撓性袋体内より空気の強制的抜気を行うことによ
り、可撓性袋体の収縮力により、締固めと同様の効果、
すなわち内部の中詰め材をより密実な状態とすることが
でき、その後に中詰め材の緩みや側方移動を確実に抑
え、軌道が沈下するのを防止することができる。
Further, in the present invention, when the roadbed is compacted and subsided, by mounting the train car on the rail, the rail can be prevented from rising, and the flexible bag body can reduce the weight of the train. The roadbed side can be pressed as a reaction force. Furthermore, after completion of the consolidation settlement of the roadbed, by forcibly deaerating air from the flexible bag body, due to the contracting force of the flexible bag body, the same effect as compaction,
That is, it is possible to make the inner filling material in a more compact state, and thereafter to reliably suppress loosening and lateral movement of the filling material and prevent the track from sinking.

【0014】他方、供用後の保線工事において、軌道沈
下が生じた際、前記可撓性袋体内にさらに中詰め材を補
充的に充填して、その沈下分を補償することもできる
し、可撓性袋体内より中詰め材を吸引回収することによ
り、枕木直下に空間を形成し、当該枕木の交換を行うこ
ともできる。
On the other hand, when track subsidence occurs in the track maintenance work after service, the flexible bag body may be supplementarily filled with a filling material to compensate for the subsidence. By sucking and collecting the filling material from the flexible bag body, a space can be formed directly under the sleepers and the sleepers can be replaced.

【0015】ところで、本発明においては、中詰め材と
して、砕・粒状物および/または粉状物を用いる。これ
らの材料は、変形に対する追随性が高く、圧送した後で
も変形の進行に合わせて再圧送が可能である。また、空
隙のほとんどは空気であり、空気を排出するだけで瞬間
的に密実な状態で袋詰めすることが可能となる。これに
対して、たとえばセメントミルクなどの固化材を用いる
場合には、注入後に固化するため再注入が難しくなる。
また、粘土や泥水などの固化しない粘性体若しくは流体
の場合には、脱水のために多くの時間を要するととも
に、枕木やスラブ版の固定度も小さいものとなる。
By the way, in the present invention, a crushed / granular material and / or a powdery material is used as the filling material. These materials have high followability to deformation, and can be re-pressurized according to the progress of deformation even after being pressure-fed. Moreover, most of the voids are air, and it is possible to instantaneously pack the bag in a solid state simply by discharging the air. On the other hand, when a solidifying material such as cement milk is used, it is hard to re-inject because it solidifies after the injection.
Further, in the case of a viscous material or fluid such as clay or muddy water which does not solidify, it takes a lot of time for dehydration and the degree of fixing of sleepers and slabs becomes small.

【0016】[0016]

【実施例】以下、本発明を図面を参照しながらさらに詳
述する。 〔実施例1〕実施例1においては、本発明法により既設
軌道の改修工事を行った場合について説明する。図1
は、本発明に係る第1の可撓性袋体を示したもので、可
撓性袋体1は、気密性を有し、たとえばゴム、布とゴム
との複合材などの伸縮性の高い有機質材料が好適に使用
される。その形状は、本実施例1の場合は、好ましくは
円筒状とされ、均一に半径方向に伸長し、逆に長手方向
に伸びないように、袋体の端部を強化したりすることも
できる。この場合、直径は一様であることに限定され
ず、長手方向の途中が一部括れているものであってもよ
い。また、袋体1の伸縮性については、材料特性として
素材自体に伸縮性がなくても、蛇腹構造により構造的に
伸縮性を与えることでもよい。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described in more detail below with reference to the drawings. [Embodiment 1] In Embodiment 1, the case where the existing track is refurbished by the method of the present invention will be described. FIG.
Shows a first flexible bag body according to the present invention, in which the flexible bag body 1 is airtight and has high elasticity such as rubber or a composite material of cloth and rubber. Organic materials are preferably used. In the case of the first embodiment, the shape thereof is preferably cylindrical, and the end portion of the bag body can be strengthened so that it uniformly extends in the radial direction and does not extend in the longitudinal direction. . In this case, the diameter is not limited to be uniform, and the diameter may be partially constricted in the middle. Regarding the stretchability of the bag body 1, the material itself may have no stretchability, but the bellows structure may impart structural stretchability.

【0017】前記可撓性袋体1は、供給口2と排気口3
とを備え、それぞれの通路に開閉バルブ4、7が設けら
れている。供給口2には中詰め材供給用の作業車両から
延長された接続自在の中詰め材供給パイプ5が接続さ
れ、バラスト、豆砂利、砂、プラスチックビーズ、スラ
グ粉粒体などの砕・粒状体および/または粉体の中詰め
材12が圧送供給されるようになっている。また、排気
口3にはフィルター6が内装されており、圧送用空気の
みが外部に排出され中詰め材12が外に排出されないよ
うになっている。なお、圧送に伴う可撓性袋体1内の圧
力は、圧送する際の圧縮空気圧力およびフィルター6の
粗密程度や排気口3の開閉バルブ7の開度によって調整
される。
The flexible bag 1 has a supply port 2 and an exhaust port 3
And opening / closing valves 4 and 7 are provided in the respective passages. Connected to the supply port 2 is a freely connectable filling material supply pipe 5 extending from a work vehicle for supplying filling material, and crushed / granular bodies such as ballast, bean gravel, sand, plastic beads, and slag powder granules. And / or the filling material 12 of the powder is fed by pressure. Further, the exhaust port 3 is internally provided with a filter 6 so that only the pressure-feeding air is discharged to the outside and the filling material 12 is not discharged to the outside. The pressure in the flexible bag 1 accompanying the pressure feeding is adjusted by the compressed air pressure at the time of pressure feeding, the degree of coarseness and fineness of the filter 6, and the opening degree of the opening / closing valve 7 of the exhaust port 3.

【0018】前記可撓性袋体1を用いて既設軌道の改修
工事を行うに当たっては、図2(A)〜(D) に示される手
順により行う。先ず、図2(A) に示されるように、枕木
11直下部分の道床バラスト8を下層の路盤13が露出
するまで掘削し、路盤13上に可撓性袋体1(以下、単
に袋体という。)を配置する。次いで、袋体1の供給口
2に中詰め材供給パイプ5を接続して、バラスト、豆砂
利、砂、プラスチックビーズ、スラグ粉粒体などの砕・
粒状体もしくは粉体等の中詰め材12を圧搾空気と共に
圧送し(以下、便宜上「一次圧送」と定義する。)、袋
体1内に充填し、袋体1の上部が枕木11の下面に接触
する程度まで膨らました後、図2(B) に示されるよう
に、袋体1の周囲に掘削した道床バラスト8を初期の状
態まで埋め戻す。なお、改修後は、列車が通過する際に
枕木11からの伝わる荷重は、袋体1によって支持され
ることになるため、埋め戻しした道床バラスト8は、袋
体1が側方に膨張するのを拘束する機能のみを有すれば
充分であり、特に締め固めの必要はない。また、圧送さ
え可能であれば、良質なバラストである必要もないの
で、現場で発生した不良バラストを中詰め材12として
使用することもできる。
When the existing track is repaired using the flexible bag body 1, the procedure shown in FIGS. 2 (A) to 2 (D) is performed. First, as shown in FIG. 2 (A), the roadbed ballast 8 directly below the sleepers 11 is excavated until the lower roadbed 13 is exposed, and the flexible bag 1 (hereinafter simply referred to as a bag) is placed on the roadbed 13. .) Is placed. Next, the filling material supply pipe 5 is connected to the supply port 2 of the bag body 1 to crush ballast, bean gravel, sand, plastic beads, slag powder, etc.
The filling material 12 such as granules or powder is pressure-fed together with compressed air (hereinafter, referred to as "primary pressure feed" for convenience) and filled in the bag body 1, and the upper portion of the bag body 1 is placed on the lower surface of the sleeper 11. After swelling to the extent of contact, the ballast ballast 8 excavated around the bag body 1 is backfilled to the initial state as shown in FIG. 2 (B). After the repair, since the load transmitted from the sleepers 11 when the train passes is supported by the bag body 1, the backfilled ballast ballast 8 has the bag body 1 inflating sideways. It suffices to have only the function of restraining, and there is no particular need for compaction. Further, since it is not necessary that the ballast has a good quality as long as it can be pressure-fed, a defective ballast generated on site can be used as the filling material 12.

【0019】続いて、図2(C) に示されるように、袋体
1内の圧力が、好ましくは列車荷重による路盤反力と同
程度以上となるように、すなわち、列車荷重による圧力
以上の力を先行圧密荷重として路盤に与えるために、さ
らに前記中詰め材12を圧送充填し(以下、便宜上「二
次圧送」と定義する。)、路盤13を押圧する。この二
次圧送状態の横断面図を図3に示す。この場合、二次圧
送の際に、袋体1の反力点は枕木11となるが、袋体1
の膨張により枕木11とともにレール10を上方に押し
上げてしまう場合もあるため、作業車両を対象箇所に停
車させておくのが望ましい。
Then, as shown in FIG. 2 (C), the pressure in the bag 1 is preferably equal to or higher than the roadbed reaction force due to the train load, that is, higher than the pressure due to the train load. In order to apply a force to the roadbed as a pre-consolidation load, the filling material 12 is further pressure-fed (hereinafter referred to as “secondary pressure feeding” for convenience), and the roadbed 13 is pressed. A cross-sectional view of this secondary pressure-feeding state is shown in FIG. In this case, at the time of secondary pressure feeding, the reaction point of the bag body 1 becomes the sleeper 11, but the bag body 1
In some cases, the rail 10 may be pushed upward together with the sleepers 11 due to the expansion of No. 1, so it is desirable to stop the work vehicle at the target location.

【0020】以上の工程を、各枕木11、11…毎に繰
り返して行い、図2(D) に示されるように、対象とする
区間に設置されているすべての枕木11の下に袋体1を
配置し、本発明に係る路線軌道の改修工事を完了する。
なお、一次圧送および二次圧送の際に、中詰め材12と
ともに圧送した圧搾空気は、排気口3より外部に排出さ
れるが、二次圧送が完了した時点で、排気口3より真空
ポンプなどにより袋体1内の空気を強制的に吸引するこ
とにより、前記袋体1内の中詰め材12を密実な状態に
することもできる。
The above steps are repeated for each sleeper 11, 11 ..., As shown in FIG. 2D, the bag 1 is placed under all the sleepers 11 installed in the target section. Is completed, and the repair work for the route track according to the present invention is completed.
The compressed air sent together with the filling material 12 at the time of the primary pressure feeding and the secondary pressure feeding is discharged to the outside from the exhaust port 3, but when the secondary pressure feeding is completed, a vacuum pump or the like is discharged from the exhaust port 3. By forcibly sucking the air in the bag body 1, the filling material 12 in the bag body 1 can be brought into a solid state.

【0021】また、将来的にレール10に沈下が生じた
場合には、前記二次圧送と同様の要領により、中詰め材
12を袋体1内に補充的に充填することにより、その沈
下分を補償することができる。また、枕木11を新規の
木製枕木やコンクリート製枕木に交換する場合には、袋
体1の中の中詰め材を吸引回収することにより、枕木1
1の直下に空間を形成することができ、容易に当該枕木
の交換を行うことができる。
When the rail 10 sinks in the future, the filling material 12 is replenished in the bag 1 in the same manner as the secondary pressure feeding, and the sinking amount is reduced. Can be compensated. When replacing the sleepers 11 with new wooden sleepers or sleepers made of concrete, the sleepers 1 can be collected by suctioning and collecting the filling material in the bag 1.
A space can be formed immediately below the sleeper 1, and the sleepers can be easily replaced.

【0022】ところで、本実施例1においては、既設の
線路軌道の改修工事について説明したが、新設路線の軌
道に対しても同様に適用することができる。
By the way, in the first embodiment, the repair work of the existing track has been described, but the present invention can be similarly applied to the track of the new track.

【0023】〔実施例2〕次に、実施例2として、本発
明を道床バラストを有せず新設盛土上に設置されるスラ
ブ軌道に適用した場合について詳述する。図4は、本実
施例2で使用するスラブ版17の斜視図であり、下面両
側部に下方に突出する側部突片18、18が形成されて
おり、この側部突片18、18より内方側のスラブ底面
に直方体状の蛇腹袋体21が貼設して一体的に設けられ
ている。前記蛇腹袋体21は、ほぼスラブ版17の底面
積に相当する平面寸法とされ、供給口20と排出口19
とを備え、これらはスラブ版17を貫いて上面側まで延
長して設けられている。また、これらの口部には開閉バ
ルブ29、28がそれぞれ設けられている。
[Second Embodiment] Next, as a second embodiment, a case where the present invention is applied to a slab track installed on a new embankment without a ballast ballast will be described in detail. FIG. 4 is a perspective view of the slab 17 used in the second embodiment, in which side projections 18, 18 projecting downward are formed on both sides of the lower surface. A rectangular parallelepiped bellows bag body 21 is attached and integrally provided on the bottom surface of the inner slab. The bellows bag body 21 has a plane size substantially corresponding to the bottom area of the slab 17 and has a supply port 20 and a discharge port 19.
And are provided so as to extend through the slab 17 to the upper surface side. Further, opening / closing valves 29 and 28 are provided at these ports, respectively.

【0024】前記スラブ版17により新設軌道を築造す
るには、図5(A)(B)に示される手順により行う。先ず、
路盤13上に、スラブ版17を配置し、レール10を取
り付けた後に、中詰め材12を材料供給車より中詰め材
供給パイプ5により一次圧送し、蛇腹袋体21を膨らま
す。前記一次圧送は、蛇腹袋体21に大きな内圧が生じ
ない程度とし、スラブ版17の底面と路盤13との間隙
部分が極力なくなるまで中詰め材12の充填を行う。そ
の後、図5(B) に示されるように、作業車両24を対象
スラブ版17の直上に乗せ、さらに中詰め材12を二次
圧送し蛇腹袋体21を膨らまし、スラブ版17と作業車
両24とを反力部材として路盤13を押圧する。この二
次圧送の際、蛇腹袋体21内の内圧により、スラブ版1
7直下の路盤13がこの圧力を受けて凹状に変形するが
中詰め材12が変形に合わせて蛇腹袋体21内に詰め込
まれるため、スラブ版17が沈下することはない。ま
た、蛇腹袋体21内の圧力の管理が難しい場合には、排
気口の開閉バルブ28を閉め、所定値の圧力を作用させ
ることもできる。ただし、この場合には中詰め材12の
供給ができないため、路盤13が蛇腹袋体21からの圧
力により変形し、落ち着いた後で供給口20の開閉バル
ブ29を閉めて、作業車両24を当該スラブ版17から
移動させ、その後、双方の開閉バルブ28、29を開け
て空隙部分に中詰め材12を再充填する。これらの工程
をスラブ版17毎に行い、蛇腹袋体21によって連続的
に支えられたスラブ軌道の敷設を完了する。
In order to construct a new track by the slab plate 17, the procedure shown in FIGS. 5 (A) and 5 (B) is performed. First,
After placing the slab 17 on the roadbed 13 and mounting the rails 10, the filling material 12 is first pressure-fed by the filling material supply pipe 5 from the material feeding vehicle to inflate the bellows bag body 21. The primary pressure feeding is performed to such an extent that a large internal pressure is not generated in the bellows bag body 21, and the filling material 12 is filled until the gap between the bottom surface of the slab 17 and the roadbed 13 is reduced as much as possible. After that, as shown in FIG. 5 (B), the work vehicle 24 is placed directly on the target slab plate 17, and the filling material 12 is secondarily fed to inflate the bellows bag body 21 to inflate the slab plate 17 and the work vehicle 24. The roadbed 13 is pressed by using and as reaction members. At the time of this secondary pressure feeding, the slab plate 1 is produced by the internal pressure in the bellows bag body 21.
The roadbed 13 immediately below 7 is deformed into a concave shape by receiving this pressure, but since the filling material 12 is packed in the bellows bag body 21 according to the deformation, the slab 17 does not sink. Further, when it is difficult to control the pressure inside the bellows bag 21, the opening / closing valve 28 of the exhaust port can be closed to apply a predetermined pressure. However, in this case, since the filling material 12 cannot be supplied, the roadbed 13 is deformed by the pressure from the bellows bag body 21 and, after it has settled down, the opening / closing valve 29 of the supply port 20 is closed to close the work vehicle 24. After moving from the slab 17 and opening and closing valves 28 and 29 on both sides, the space 12 is refilled with the filling material 12. These steps are performed for each slab 17 to complete the laying of the slab track continuously supported by the bellows bag body 21.

【0025】ところで、鉄道開通後に、レール10に沈
下が生じた場合には、前述した二次圧送と同様の要領に
より蛇腹袋体21に中詰め材12を再充填して、その分
の沈下を補償することができる。
By the way, when the rail 10 is sunk after the railway is opened, the bellows bag body 21 is refilled with the filling material 12 in the same manner as the above-described secondary pressure feeding, and the subsidence is caused. Can be compensated.

【0026】[0026]

【発明の効果】以上詳説のとおり、本発明によれば、先
ず第1に、路盤や地盤等の沈下およびバラストの緩みな
どに起因する比較的初期の段階の軌道沈下を防止するこ
とができる。また、第2に供用後の列車通過による繰り
返し荷重や振動によるバラストの側方移動および緩みに
起因した軌道沈下を防止することができ、保守管理に手
間の掛からない省力化された線路軌道を得ることができ
る。
As described above in detail, according to the present invention, firstly, it is possible to prevent the subsidence of the roadbed or the ground or the like, and the subsidence of the track at a relatively early stage due to the loosening of the ballast or the like. Secondly, it is possible to prevent track subsidence due to lateral movement and looseness of ballast due to repeated load and vibration due to passing trains after service, and to obtain a labor-saving track that does not require maintenance. be able to.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る袋体の側面図である。FIG. 1 is a side view of a bag according to the present invention.

【図2】実施例1における既設線路軌道の改修手順図で
ある。
FIG. 2 is a procedure diagram for rehabilitating an existing track in Example 1.

【図3】実施例1における路盤押圧状態の横断面図であ
る。
FIG. 3 is a cross-sectional view of the roadbed pressing state in the first embodiment.

【図4】実施例2におけるスラブ版の斜視図である。FIG. 4 is a perspective view of a slab plate according to a second embodiment.

【図5】実施例2における新設スラブ軌道の築造手順図
である。
FIG. 5 is a construction procedure diagram of a new slab track in the second embodiment.

【符号の説明】[Explanation of symbols]

1…袋体、2・20…供給口、3・19…排気口、4・
28・29…開閉バルブ、5…中詰め材供給パイプ、6
…フィルター、8…道床バラスト、10…レール、11
…枕木、12…中詰め材、13…路盤、17…スラブ
版、21…蛇腹袋体
1 ... Bag, 2/20 ... Supply port, 3/19 ... Exhaust port, 4 ...
28 ・ 29 ... Open / close valve, 5 ... Filling material supply pipe, 6
... filter, 8 ... ballast ballast, 10 ... rail, 11
… Sleepers, 12… Filling materials, 13… Roadbed, 17… Slab version, 21… Bellows bag

フロントページの続き (72)発明者 須長 誠 東京都国分寺市光町二丁目8番地38 財団 法人鉄道総合技術研究所内 (72)発明者 岩佐 弘 東京都千代田区九段北4丁目2番35号 ラ イト工業株式会社内 (72)発明者 木下 吉友 東京都千代田区九段北4丁目2番35号 ラ イト工業株式会社内Front page continuation (72) Inventor Makoto Sunaga 38-8, Hikarimachi, Kokubunji, Tokyo 38 Railroad Research Institute of Japan (72) Hiroshi Iwasa 4-35 Kudankita 4-chome, Chiyoda-ku, Tokyo Light Industrial Co., Ltd. (72) Inventor Yoshitomo Kinoshita 4-35, Kudankita 4-chome, Chiyoda-ku, Tokyo Inside Light Industrial Co., Ltd.

Claims (8)

【特許請求の範囲】[Claims] 【請求項1】路盤上に道床バラストを敷き、その上に枕
木およびレールを敷設した有道床軌道の築造に当り、 前記枕木と路盤との間に、内部に砕・粒状物および/ま
たは粉状物からなる中詰め材が圧送充填された気密性を
有する可撓性袋体を介在して設け、この可撓性袋体内に
さらに中詰め材の圧送充填または空気のみの圧送を行
い、この可撓性袋体の外圧により前記路盤を先行的に圧
密沈下させることを特徴とする線路軌道の築造方法。
1. When constructing a roadbed track in which a ballast ballast is laid on a roadbed and sleepers and rails are laid on the ballast, a crushed / granular material and / or a powdery substance is internally formed between the sleeper and the roadbed. An airtight flexible bag body filled with a filling material made of material is provided, and the filling material or the air alone is further fed into the flexible bag body. A method for constructing a railway track, wherein the roadbed is preliminarily compacted and settled by the external pressure of the flexible bag body.
【請求項2】路盤上にスラブ版を敷設し、このスラブ版
の上にレールを敷設した無道床軌道の築造に当り、 前記スラブ版と路盤との間に、内部に砕・粒状物および
/または粉状物からなる中詰め材が圧送充填された気密
性を有する可撓性袋体を介在して設け、この可撓性袋体
内にさらに中詰め材の圧送充填または空気のみの圧送を
行い、この可撓性袋体の外圧により前記路盤を先行的に
圧密沈下させることを特徴とする線路軌道の築造方法。
2. A slab slab is laid on a roadbed and a railbed is laid on the slab slab to construct a ballastless track. Alternatively, a flexible bag body having airtightness in which a filling material made of powder is filled by pressure is provided, and the filling material or the air alone is further fed into the flexible bag body. A method for constructing a railway track, wherein the roadbed is preliminarily compacted and settled by an external pressure of the flexible bag body.
【請求項3】路盤上に道床バラストを敷き、その上に枕
木およびレールを敷設した既設の有道床軌道の改修に当
り、 枕木の直下の道床バラストを掘削し、枕木の直下にかつ
その長手方向に沿って路盤上に気密性を有する可撓性袋
体を配置し、この可撓性袋体の内部に砕・粒状物および
/または粉状物からなる中詰め材を圧送充填して膨らま
せた後、可撓性袋体周囲に道床バラストの埋め戻しを行
い、次いでこの可撓性袋体内にさらに中詰め材の圧送充
填または空気のみの圧送を行い、この可撓性袋体の外圧
により前記路盤を先行的に圧密沈下させることを特徴と
する線路軌道の改修方法。
3. A roadbed ballast is laid on the roadbed, and an existing roadbed track with sleepers and rails laid on the roadbed is repaired. A flexible bag body having airtightness is arranged on the roadbed along with, and a filling material made of crushed / granular material and / or powder material is pressure-filled and inflated inside the flexible bag body. After that, the ballast ballast is backfilled around the flexible bag body, and then the filling material or the air alone is further fed into the flexible bag body by the external pressure of the flexible bag body. A method for rehabilitating a railroad track, characterized by precipitating the roadbed to settle.
【請求項4】前記路盤の圧密沈下の際、可撓性袋体の外
圧を路盤が受ける列車荷重以上の圧力とする請求項1〜
3記載の線路軌道の築造または改修方法。
4. The pressure outside the flexible bag is set to a pressure equal to or higher than a train load received by the roadbed when the roadbed is subsided.
The method of constructing or rehabilitating the track described in 3.
【請求項5】前記路盤の圧密沈下の際、レール上に列車
車両を搭載し、レールの盛り上がりを防止する請求項1
〜4記載の線路軌道の築造方法または改修方法。
5. A railcar is mounted on the rail to prevent the rail from rising when the roadbed is consolidated.
~ The method of constructing or rehabilitating the track described in 4.
【請求項6】前記路盤の圧密沈下の完了後に、可撓性袋
体より空気の強制的抜気を行う請求項1〜5記載の線路
軌道の築造方法または改修方法。
6. The method for constructing or rehabilitating a track according to claim 1, wherein the air is forced out of the flexible bag after the consolidation and settlement of the roadbed is completed.
【請求項7】請求項1〜6記載の方法によって築造また
は改修された線路軌道において、軌道沈下が生じた際、
前記可撓性袋体内にさらに中詰め材を補充的に充填し
て、その沈下分を補償する線路軌道の改修方法。
7. A railroad track constructed or refurbished by the method according to any one of claims 1 to 6, when subsidence occurs,
A method of rehabilitating a railroad track, wherein the flexible bag body is supplementarily filled with a filling material to compensate for the subsidence.
【請求項8】請求項1、3〜6記載の方法によって築造
または改修された線路軌道において、可撓性袋体内より
中詰め材を吸引回収することにより、枕木直下に空間を
形成し、当該枕木の交換を行う線路軌道の改修方法。
8. A line track constructed or renovated by the method according to any one of claims 1 to 3 to 6, by suctioning and collecting the filling material from the flexible bag body to form a space directly below the sleepers, A method of rehabilitating railroad tracks to replace sleepers.
JP21454094A 1994-09-08 1994-09-08 Construction method and repair method of track Expired - Fee Related JP3432302B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21454094A JP3432302B2 (en) 1994-09-08 1994-09-08 Construction method and repair method of track

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21454094A JP3432302B2 (en) 1994-09-08 1994-09-08 Construction method and repair method of track

Publications (2)

Publication Number Publication Date
JPH0874202A true JPH0874202A (en) 1996-03-19
JP3432302B2 JP3432302B2 (en) 2003-08-04

Family

ID=16657437

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21454094A Expired - Fee Related JP3432302B2 (en) 1994-09-08 1994-09-08 Construction method and repair method of track

Country Status (1)

Country Link
JP (1) JP3432302B2 (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007070891A (en) * 2005-09-07 2007-03-22 Railway Technical Res Inst Ground improvement material, track structure and ground repair method
KR100709099B1 (en) * 2005-12-27 2007-04-19 한국철도기술연구원 Construction method and structure of asphalt pavement track
JP2008095413A (en) * 2006-10-13 2008-04-24 Hokkaido Railway Co Ballast repairing method for ballasted track
JP2011006866A (en) * 2009-06-24 2011-01-13 Railway Technical Res Inst Mud-pumping preventing structure in track
JP2011017169A (en) * 2009-07-08 2011-01-27 Taisei Corp Saddle type monorail girder and construction method for the saddle type monorail girder
KR101012603B1 (en) * 2008-07-30 2011-02-10 이형준 Spacing Filler for Railbed
JP2014111897A (en) * 2014-03-28 2014-06-19 Railway Technical Research Institute Vibration control device
WO2015129996A1 (en) * 2014-02-25 2015-09-03 한국철도기술연구원 Rail tie having embedded automatic differential settlement compensation apparatus using oil pressure for railroad tracks
CN110593018A (en) * 2019-06-28 2019-12-20 吉林大学 Method for predicting settlement of high-speed railway subgrade
CN111535090A (en) * 2020-05-12 2020-08-14 湖北木之君工程材料有限公司 Bag filling method lifting rapid repairing method for ballastless track settlement
CN113818292A (en) * 2021-10-11 2021-12-21 国能黄大铁路有限责任公司 Sand filling device for railway gravel bed
JP2022163782A (en) * 2021-04-15 2022-10-27 東日本旅客鉄道株式会社 Repair method for filler layer of concrete slab track
KR20240024668A (en) * 2022-08-17 2024-02-26 (주)동명기술공단종합건축사사무소 Control method that can prevent railway derailment and respond to ground subsidence using a control device
KR20240024664A (en) * 2022-08-17 2024-02-26 (주)동명기술공단종합건축사사무소 Control device capable of preventing railway derailment and responding to ground subsidence

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007070891A (en) * 2005-09-07 2007-03-22 Railway Technical Res Inst Ground improvement material, track structure and ground repair method
KR100709099B1 (en) * 2005-12-27 2007-04-19 한국철도기술연구원 Construction method and structure of asphalt pavement track
JP2008095413A (en) * 2006-10-13 2008-04-24 Hokkaido Railway Co Ballast repairing method for ballasted track
KR101012603B1 (en) * 2008-07-30 2011-02-10 이형준 Spacing Filler for Railbed
JP2011006866A (en) * 2009-06-24 2011-01-13 Railway Technical Res Inst Mud-pumping preventing structure in track
JP2011017169A (en) * 2009-07-08 2011-01-27 Taisei Corp Saddle type monorail girder and construction method for the saddle type monorail girder
EP3112533A4 (en) * 2014-02-25 2017-10-18 Korea Railroad Research Institute Rail tie having embedded automatic differential settlement compensation apparatus using oil pressure for railroad tracks
WO2015129996A1 (en) * 2014-02-25 2015-09-03 한국철도기술연구원 Rail tie having embedded automatic differential settlement compensation apparatus using oil pressure for railroad tracks
US10138604B2 (en) 2014-02-25 2018-11-27 Korea Railroad Research Institute Rail tie having embedded automatic differential settlement compensation apparatus using oil pressure for railroad tracks
JP2014111897A (en) * 2014-03-28 2014-06-19 Railway Technical Research Institute Vibration control device
CN110593018A (en) * 2019-06-28 2019-12-20 吉林大学 Method for predicting settlement of high-speed railway subgrade
CN111535090A (en) * 2020-05-12 2020-08-14 湖北木之君工程材料有限公司 Bag filling method lifting rapid repairing method for ballastless track settlement
JP2022163782A (en) * 2021-04-15 2022-10-27 東日本旅客鉄道株式会社 Repair method for filler layer of concrete slab track
CN113818292A (en) * 2021-10-11 2021-12-21 国能黄大铁路有限责任公司 Sand filling device for railway gravel bed
CN113818292B (en) * 2021-10-11 2022-12-13 国能黄大铁路有限责任公司 Sand filling device for railway gravel bed
KR20240024668A (en) * 2022-08-17 2024-02-26 (주)동명기술공단종합건축사사무소 Control method that can prevent railway derailment and respond to ground subsidence using a control device
KR20240024664A (en) * 2022-08-17 2024-02-26 (주)동명기술공단종합건축사사무소 Control device capable of preventing railway derailment and responding to ground subsidence

Also Published As

Publication number Publication date
JP3432302B2 (en) 2003-08-04

Similar Documents

Publication Publication Date Title
JP3432302B2 (en) Construction method and repair method of track
CN109763397B (en) Asphalt pavement with embedded structure and construction method
CN103518019B (en) rail track sleeper support body
CN100547165C (en) Altitude Correction Method for Fixed Track Road and Fixed Track Road
JP3473998B2 (en) Improvement method of track ground
CN117026700B (en) Construction method for reconstructing existing line CRTSI type double-block ballastless track sleeper
KR101076029B1 (en) Replacing Method of Old Train Track using Twin-Block Type Train Track
CN102102315B (en) Method for constructing sleeper bolted elastic crossing
US4911360A (en) Precast railway crossing slab
CN105274912B (en) Construction method for hardening monolithic track bed of tramcar
KR100901753B1 (en) Crane continuous block unit structure for crane rail support for container and cargo yard equipment and method for adjusting horizontal level of vertically displaced rail continuous PC continuous block
CN206298785U (en) A kind of board-like binding type Ballast track of pillow wide
EP0105560A1 (en) Railway track structure, and a method of building such structure
RU2004129299A (en) RAIL BEDROOM AND BALLAST-FREE DESIGN OF RAILWAYS
CN108103923A (en) A kind of anti-bumping at bridge-head device of bridge
CN104947565A (en) Construction technology for forming railway crossing by pouring of concrete
KR102249391B1 (en) Method for constructing Precast Concrete Driving Road Block with Rubber Wheel AGT
WO1979000031A1 (en) Rail support with provision for ballast
CN210482091U (en) Culvert and road culvert transition structure
JPH0827701A (en) Reinforced construction and ballast replacing method for ballast track bed
CN117188212B (en) A technology and method for the construction of railway subgrade closure
RU2297488C1 (en) Railroad crossing and method for rubber-and-ferroconcrete platform production for railroad crossing erection
US4280657A (en) Concrete railroad track
CN121519365B (en) Ballastless track structure suitable for large deformation of foundation and construction method thereof
KR102319784B1 (en) Traffic Control Reduction Rapid Packaging Method Due to Ground Deposition on Roads

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 6

Free format text: PAYMENT UNTIL: 20090523

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 7

Free format text: PAYMENT UNTIL: 20100523

LAPS Cancellation because of no payment of annual fees