JPH09281268A - Nuclear power plant turbine building construction method - Google Patents
Nuclear power plant turbine building construction methodInfo
- Publication number
- JPH09281268A JPH09281268A JP8094953A JP9495396A JPH09281268A JP H09281268 A JPH09281268 A JP H09281268A JP 8094953 A JP8094953 A JP 8094953A JP 9495396 A JP9495396 A JP 9495396A JP H09281268 A JPH09281268 A JP H09281268A
- Authority
- JP
- Japan
- Prior art keywords
- turbine building
- construction
- turbine
- power plant
- nuclear power
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
- Y02E30/30—Nuclear fission reactors
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、原子力発電所内に
構築される原子力発電所タービン建屋の建設工法に関す
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for a turbine building of a nuclear power plant constructed in a nuclear power plant.
【0002】[0002]
【従来の技術】図7および図8(a)〜(c)により従
来から施工している原子力発電所タービン建屋の建設工
法を説明する。図7は従来の原子力発電所のタービン建
屋の建設工法の一例を説明するための月数と主要工程の
建設工事と機電工事との関係を示す工程図である。図8
は従来の原子力発電所のタービン建屋の建設工法を各段
階に分けて説明するための概略断面図で、(a)は地面
(G.L)の掘削からマット工事および初期の建築工事
の状態、(b)は大型揚重機による機械・電気設備搬入
の状態、(c)は天井クレーン稼働後のタービン建屋内
の状態を示している。2. Description of the Related Art A conventional construction method for a turbine building of a nuclear power plant will be described with reference to FIGS. 7 and 8A to 8C. FIG. 7 is a process diagram showing the relationship between the number of months and the construction work of the main process and the electrical work for explaining an example of the conventional construction method of the turbine building of the nuclear power plant. FIG.
Is a schematic cross-sectional view for explaining the conventional construction method of a turbine building of a nuclear power plant by dividing it into stages, and (a) is a state of excavation of the ground (GL) to mat construction and initial construction work, (B) shows the state of the mechanical / electrical equipment carried in by the large lifting machine, and (c) shows the state of the turbine building after the operation of the overhead crane.
【0003】図7に示すように原子力発電所のタービン
建屋を建設するためには大別して建築工事と機電工事と
がある。建築工事は地面G.Lの掘削から岩検,マット
工事から始り各種の建屋工事がある。機電工事は機械・
電気工事,復水器組立,タービン・発電機組立,調整な
どがある。As shown in FIG. 7, in order to construct a turbine building of a nuclear power plant, it is roughly classified into a construction work and a mechanical work. Construction work is on the ground G. There are various building works starting from excavation of L, rock inspection, mat construction. Mechanical work is mechanical
Electrical work, condenser assembly, turbine / generator assembly, adjustment, etc.
【0004】機電工事は建築工事の進捗状況に応じて工
事が行われるが、例えばタービン発電機(T/G)ペデ
スタルの工事から並列作業が行われる。タービン,発電
機の組立は天井クレーンを使用して主タービンベースに
据付ける。タービン発電機組立・調整後は原子炉建屋内
の原子炉に燃料が装荷され、原子力発電プラントは運転
開始(運開)となる。The mechanoelectric work is carried out according to the progress of the construction work, and for example, the parallel work is carried out from the work of the turbine generator (T / G) pedestal. The turbine and generator are assembled on the main turbine base using an overhead crane. After assembling and adjusting the turbine generator, fuel is loaded into the reactor inside the reactor building, and the nuclear power plant starts operation (starts operation).
【0005】つぎに図8(a)〜(c)により従来のタ
ービン建屋の建設工法を具体的に説明する。まず、図8
(a)に示すように一般に地面(G.L)を掘削して岩
盤検査(岩検)を行った後、岩検岩盤2をタービン建屋
の基礎として構築する場合と、岩盤2が深いところにあ
る場合にはその岩盤2の上に、コンクリートによる人工
的な岩盤(Man Made Rock ;以下MMRと記す)3を打
設して、MMR3をタービン建屋1の基礎として構築す
る場合と、タービン建屋1の建設地点の岩盤2の状況に
よりこれらを組み合わせた方法で構築する場合とがあ
る。Next, a conventional turbine building construction method will be specifically described with reference to FIGS. 8 (a) to 8 (c). First, FIG.
As shown in (a), generally, after excavating the ground (GL) and performing rock mass inspection (rock mass inspection), the rock mass rock mass 2 is constructed as the foundation of the turbine building, and when the rock mass 2 is deep. In some cases, an artificial rock bed (Man Made Rock; hereinafter referred to as MMR) 3 made of concrete is placed on the rock bed 2 to build the MMR 3 as the foundation of the turbine building 1 and the turbine building 1 Depending on the condition of the bedrock 2 at the construction point, there is a case where they are constructed by a method combining these.
【0006】いずれの場合も岩盤2上にコンクリートを
打設するマット4の工事完了後、図8(b)に示すよう
に最下階部分から各々主柱5,主梁6が立ち上げられ、
その周辺および内部の壁、床の建築工事が進められター
ビン建屋1が順次に構築されていく。In either case, after the construction of the mat 4 for placing concrete on the bedrock 2 is completed, the main pillars 5 and the main beams 6 are respectively raised from the lowest floor portion as shown in FIG. 8 (b).
Turbine building 1 will be constructed sequentially by the construction work of the surrounding and internal walls and floors.
【0007】一方、タービン建屋1内に設置される搬入
機器・配管等7の設備に関しては、一部、タンクや熱交
換機および配管等をまだタービン建屋建築工事が終了し
てない据付場所、またはその近傍に搬入するという先行
搬入を行う方法もあるが、一般的には原則として建築工
事がある程度終了した時点で据付場所へ搬入し、据付を
開始する方法を採っている。On the other hand, with regard to the equipment such as the carry-in equipment / pipes 7 installed in the turbine building 1, some of the tanks, heat exchangers, pipes, etc. are installed at a place where the turbine building construction work has not been completed yet, or Although there is a method of carrying in before, such as carrying in to the vicinity, in general, the method of carrying in to the installation site and starting the installation when the construction work is completed to some extent is generally adopted.
【0008】従来の建築工法においては、下層階から上
層階へ順次タービン建屋が構築されていく過程で各階の
床,壁がある程度組み立てられ、機電工事ができる状態
になった時点で図7に示したように機電工事を開始す
る。In the conventional construction method, the floors and walls of each floor are assembled to some extent in the process of constructing the turbine building from the lower floors to the upper floors one after another, as shown in FIG. As you can see, start the electrical work.
【0009】この機電工事におけるタービン建屋内への
機器・配管等の設備の搬入・据付は、全体工期の確保、
重量物が多いこと、搬入エリアが広いこと等から図8
(b)に示すらタワークレーン8及びやクローラークレ
ーン9を搬入用として使用している。また、このような
タワークレーン8やクローラークレーン9は大型揚重機
であり、その能力や作業旋回半径の限界のため、タービ
ン建屋への寄り付け用として構台10を設置している。In carrying in and installing equipment such as equipment and pipes into the turbine building in this electrical and electrical work, it is necessary to secure the entire construction period.
As there are many heavy items and the loading area is large,
As shown in (b), the tower crane 8 and the crawler crane 9 are used for loading. Further, such a tower crane 8 and a crawler crane 9 are large-sized hoisting machines, and a gantry 10 is installed for leaning to the turbine building because of its capacity and the limit of the working turning radius.
【0010】一方、タービン建屋の外周面が順次構築さ
ていくなかで、タービン建屋中央部では独立したタービ
ン・発電機基礎台(以下T/Gペデスタルと記す)11が
立ち上げられて完成し、機電側に明け渡されると復水器
12の組立工事、タービン・発電機13の据付工事へと進み
燃料装荷までにタービン建屋の工事を完了させる。On the other hand, while the outer peripheral surface of the turbine building was being constructed in sequence, an independent turbine / generator foundation (hereinafter referred to as T / G pedestal) 11 was started up and completed in the central part of the turbine building. Condenser when surrendered to the side
Proceed to 12 assembly work and turbine / generator 13 installation work to complete the construction of the turbine building before loading the fuel.
【0011】このようにして建設されたタービン建屋内
には天井走行クレーン14が走行レール(図示せず)が搭
載されるが、この天井走行クレーン14はタービン発電機
据付床面(オペレーティングフロア;以下オペフロと記
す)15が構築され、このオぺフロ15より上方の壁、屋根
等16の工事が完了した後、搭載され、主にタービン、発
電機の組立用として稼働開始する。A traveling rail (not shown) for an overhead traveling crane 14 is installed in the turbine building constructed in this way. The overhead traveling crane 14 is installed on the floor surface of the turbine generator (operating floor; 15) will be built, and after the construction of the wall, roof, etc. 16 above the operation floor 15 is completed, it will be installed and will start operation mainly for assembling turbines and generators.
【0012】[0012]
【発明が解決しようとする課題】しかしながら、従来の
建設工法の場合、以下に挙げるような課題がある。従来
の原子力発電所のタービン建屋の建設工法において、天
井走行クレーン14は、原子力発電所建設工期の後半に搭
載,稼働するので、全体工期の確保のため、天井走行ク
レーン14の稼働前には、屋外に機械設備搬入用としてタ
ワークレーン8およびクローラクレーン9などの大型揚
重機を準備する必要がある。However, the conventional construction method has the following problems. In the conventional construction method of the turbine building of the nuclear power plant, the overhead traveling crane 14 is installed and operated in the latter half of the nuclear power plant construction period, so in order to secure the entire construction period, before operation of the overhead traveling crane 14, It is necessary to prepare a large crane such as a tower crane 8 and a crawler crane 9 for carrying mechanical equipment outdoors.
【0013】また、大型揚重機設置の場合には、その組
立,解体のための作業スペースが必要となる。大型揚重
機組立時は、大型揚重機設置場所周辺に構築物が少ない
ことから、比較的組立スペースを確保しやすいが、解体
時には、工事の進捗に伴って建物等が構築されるため、
このような構築物があっては邪魔となり、解体できなく
なる恐れがある。In addition, when a large-sized lifting machine is installed, a work space for assembling and disassembling it is required. When assembling a large-sized lifting machine, it is relatively easy to secure an assembly space because there are few structures around the large-sized lifting machine installation location, but at the time of dismantling, a building etc. will be built as the construction progresses.
Such a structure would be an obstacle and could not be dismantled.
【0014】また、機械設備搬入時には、大型揚重機設
置場所の地耐圧が揚重機自重,吊荷カウンターウエイト
等の分増加するため、構台上で実施の場合にはその補強
が必要となる。Further, when the mechanical equipment is carried in, the ground pressure at the installation location of the large hoisting machine increases due to the self-weight of the hoisting machine, the hanging counterweight, etc., so that it is necessary to reinforce it when it is carried out on the gantry.
【0015】一般に大型揚重機は、タービン建屋建築用
のものと機電設備工事用のものとが用意される。この場
合、双方の揚重機の干渉が生じる場合があるため、その
調整が必要となる。さらに、大型揚重機は屋外に設置さ
れるため、天候の影響を大きく受ける。特に強風時に
は、その使用が不可能となる場合がある。また、先行搬
入物等の機電設備は、その多くがタービン建屋完成前の
搬入となるため、搬入後の雨,風等に対する養生が必要
となる。Generally, large-sized hoisting machines are prepared for construction of turbine buildings and for construction of electric / electrical equipment. In this case, since there is a possibility that interference between the two lifting machines may occur, the adjustment is necessary. Further, since the large-sized lifting machine is installed outdoors, it is greatly affected by the weather. Especially in strong winds, its use may not be possible. In addition, since most of the mechanic equipment such as preceding cargo is carried in before the completion of the turbine building, it is necessary to protect it against rain, wind, etc. after carrying it in.
【0016】本発明は、上記課題を解決するためになさ
れたもので、タービン建屋を構成する主柱や主梁となる
鉄骨をタービン建屋を構成する床や壁よりも先行して組
立て、天井走行クレーンを早期に搭載,稼働することに
より、大型揚重機の設置を不要とし、また、タービン建
屋の外壁部を採光性シートまたはパネル等で覆設するこ
とにより天候に左右されずにタービン建屋の機械設備を
据付ることができる原子力発電所のタービン建屋の建設
工法を提供することにある。The present invention has been made in order to solve the above problems, and an iron frame as a main pillar or a main beam constituting a turbine building is assembled prior to a floor or a wall constituting the turbine building, and an overhead traveling crane is constructed. By installing and operating the turbine early, it is not necessary to install a large lifting machine, and by covering the outer wall of the turbine building with a daylighting sheet or panel, the mechanical equipment of the turbine building is not affected by the weather. It is to provide a construction method for a turbine building of a nuclear power plant that can be installed.
【0017】[0017]
【課題を解決するための手段】本発明は原子力発電所の
タービン建屋を構成する主柱や主梁となる鉄骨および屋
根を、タービン建屋を構成する床や壁よりも先行して組
み立てるとともに、前記タービン建屋建設の初期段階か
ら天井走行クレーンを走行レールに搭載し稼働させるこ
とを特徴とする。SUMMARY OF THE INVENTION According to the present invention, a steel frame and a roof serving as main columns and main beams constituting a turbine building of a nuclear power plant are assembled prior to a floor and walls constituting the turbine building, and the turbine is The feature is that an overhead traveling crane is mounted on a traveling rail and operated from the initial stage of building construction.
【0018】本発明は前記タービン建屋の床や壁等の構
築物の建設およびタービン建屋に設置されるタービンや
タービン発電機および付属設備などの据付工事に、ター
ビン建屋建設の初期段階から天井走行クレーンを使用す
ることを特徴とする。The present invention uses an overhead traveling crane from the initial stage of turbine building construction for the construction of structures such as the floors and walls of the turbine building and for the installation work of turbines, turbine generators and auxiliary equipment installed in the turbine building. It is characterized by doing.
【0019】本発明は前記タービン建屋建設の初期段階
から搭載した天井走行クレーンの走行レールをタービン
建屋の外部に延長し、荷取りエリアをタービン建屋外部
に設置することを特徴とする。The present invention is characterized in that the traveling rail of the overhead traveling crane installed from the initial stage of the construction of the turbine building is extended to the outside of the turbine building, and the loading area is installed outside the turbine building.
【0020】本発明は前記構築された主柱や主梁となる
鉄骨を利用して、天井走行クレーンの稼働範囲内に車両
が乗込みできる床を本設または仮設し、荷取りエリアを
タービン建屋内部に設置することを特徴とする。According to the present invention, the steel frame serving as the main pillars and main beams constructed as described above is used to permanently or temporarily install a floor on which a vehicle can be loaded within an operating range of an overhead traveling crane, and a loading area is a turbine building. It is characterized by being installed inside.
【0021】本発明は前記構築された主柱や主梁となる
鉄骨を使用して、タービン建屋外壁部を覆うことを特徴
とする。本発明は前記タービン建屋の外壁部を採光性シ
ートまたはパネルで覆うことを特徴とする。The present invention is characterized in that the outer wall of the turbine building is covered by using the steel frame which is the main pillar or the main beam constructed as described above. The present invention is characterized in that the outer wall of the turbine building is covered with a daylighting sheet or panel.
【0022】原子力発電所のタービン建屋を構成する主
柱や主梁となる鉄骨,屋根をタービン建屋を構成する床
や壁よりも先行して組み立てて、タービン建屋天井走行
クレーンを早期に搭載,稼働することにより従来の建設
工法で使用されていた大型揚重機を設置する必要がな
く、これにより大型揚重機に関わる前記課題を解消でき
る。The main pillars and the main beams that form the turbine building of the nuclear power plant, the roof, and the roof are assembled prior to the floor and the walls that form the turbine building, and the turbine building overhead traveling crane is installed and operated early. As a result, it is not necessary to install a large-sized hoisting machine used in the conventional construction method, and thus the above-mentioned problems relating to the large-sized hoisting machine can be solved.
【0023】一方、搬入物の荷取り(または荷受け、荷
捌き)のためには、天井走行クレーンの走行レールを荷
取り可能な位置まで延長し、荷取り(または荷受け、荷
捌き)エリアをタービン建屋外部に設置するか、また
は、タービン建屋を構成する主柱,主枠となる鉄骨を利
用して、天井走行クレーン稼働範囲内に早期により車両
等の乗り込みのできる床を本設あるいは仮設にて構築
し、荷取り(または荷受け、荷捌き)エリアをタービン
建屋内部に設置することにより前記課題を解消できる。On the other hand, in order to unload (or receive and handle) the carried-in goods, the traveling rail of the overhead traveling crane is extended to a position where the unloading is possible, and the unloading (or receiving and unloading) area is set to the turbine. Installed outside the building, or by using the main pillars and the main frame that make up the turbine building, the floor that allows the early loading of vehicles, etc., within the operating range of the overhead traveling crane can be installed permanently or temporarily. The above problem can be solved by constructing and installing the load (or load receiving / loading) area inside the turbine building.
【0024】さらに、雨,風等の天候の影響に関わる課
題については、タービン建屋を構成する主柱,主梁を利
用して、タービン建屋外壁部を採光性の良いシートまた
はパネル等で覆設することにより外気の影響を低減でき
る。Further, regarding the problems related to the influence of weather such as rain and wind, the main pillars and the main beams constituting the turbine building are used to cover the outdoor wall portion of the turbine building with a sheet or panel having good lighting. By doing so, the influence of outside air can be reduced.
【0025】[0025]
【発明の実施の形態】図1から図4を参照しながら本発
明に係る原子力発電所タービン建屋の建設工法の第1の
実施の形態を説明する。図1は本実施の形態に係る建設
工法を説明するための工程図で、図8と対応して示して
いる。図1が図8と異なる点は岩検前に全天候鉄骨建方
を行い、岩検時に天井走行クレーンを搭載,稼働すると
同時にマット工事を行うことにある。また、マット工事
と同時に機器,配管を先行搬入し、床,壁,建屋工事と
T/Gペデスタル設置工事を並行作業する。さらに、復
水器組立とタービン・発電機組立・調整工程に移行する
が機器・配管先行搬入の途中から機械電気工事を並行し
て行うことにある。BEST MODE FOR CARRYING OUT THE INVENTION A first embodiment of a construction method for a nuclear power plant turbine building according to the present invention will be described with reference to FIGS. 1 to 4. FIG. 1 is a process diagram for explaining the construction method according to the present embodiment, which is shown corresponding to FIG. 8. The difference between Fig. 1 and Fig. 8 is that the all-weather steel erection is performed before the rock inspection, and the overhead traveling crane is installed and operated at the time of the rock inspection, and at the same time, the mat construction is performed. At the same time as the mat work, equipment and piping will be loaded in advance, and floor, wall, building work and T / G pedestal installation work will be performed in parallel. In addition, the condenser and the turbine / generator assembly / adjustment process will be carried out, but the mechanical and electrical work will be carried out in parallel with the preceding loading of equipment and piping.
【0026】図2は図1の工程により構築される建設中
のタービン建屋を示し、図3(a),(b)と図4
(a),(b)は図1のタービン建屋建設工程に沿って
説明するためのもので、図3(a)は鉄骨建方完了後の
状態、図3(b)は天井走行クレーン搭載完了後の状
態、図4(a)は機電設備搬入および機電工事開始の状
態、図4(b)はタービン・発電機据付完了後の状態を
それぞれ示す概略断面図である。なお、図2から図4に
おいて図9と同一部分には同一符号を付している。FIG. 2 shows a turbine building under construction constructed by the process of FIG. 1, and is shown in FIGS. 3 (a), 3 (b) and FIG.
(A) and (b) are for explaining along with the turbine building construction process of FIG. 1, FIG. 3 (a) is a state after the steel frame construction is completed, and FIG. 3 (b) is an overhead traveling crane installation completion FIG. 4A is a schematic cross-sectional view showing a state after the completion of the installation of the mechanical and electrical equipment and a state after the completion of the mechanical and electrical work, and FIG. 2 to 4, the same parts as those in FIG. 9 are designated by the same reference numerals.
【0027】図2中、符号1は建設中のタービン建屋、
2は岩盤で3は岩盤2上に打設するMMRで岩盤2と一
体に示している。MMR3にはマット4が敷設されてい
る。5は主柱、6は主梁、7は搬入機器配管等、11はT
/Gペデスタル、14は天井走行クレーン、16は屋根、17
は採光性シートまたはパネル、18は走行レール、19はタ
ービン建屋1に隣接した荷取りエリア、20は荷取りエリ
アの仮設壁,屋根である。In FIG. 2, reference numeral 1 is a turbine building under construction,
Reference numeral 2 is a bedrock, and 3 is an MMR placed on the bedrock 2, which is shown integrally with the bedrock 2. A mat 4 is laid on the MMR 3. 5 is a main pillar, 6 is a main beam, 7 is a pipe for carrying-in equipment, 11 is a T
/ G pedestal, 14 is an overhead traveling crane, 16 is a roof, 17
Is a lighting sheet or panel, 18 is a traveling rail, 19 is a unloading area adjacent to the turbine building 1, 20 is a temporary wall and roof of the unloading area.
【0028】本実施の形態は図3(a)に示すようにタ
ービン建屋1の工事着工後、直ちにタービン建屋を構成
する主柱5,主梁6となる鉄骨の建方および屋根16の施
工が行われるとともに荷取りエリア19も隣接される。こ
の時、主柱5,主梁6となる鉄骨は鉄筋コンクリート製
のものでもよい。また、タービン建屋1の外壁部に主柱
5,主梁6を利用して採光性シートまたはパネル17を覆
設する。In this embodiment, as shown in FIG. 3 (a), immediately after the construction of the turbine building 1 is started, the construction of the steel frame to be the main pillars 5 and the main beams 6 constituting the turbine building and the construction of the roof 16 are performed. As it is done, the pickup area 19 is also adjacent. At this time, the steel frames to be the main columns 5 and the main beams 6 may be made of reinforced concrete. Further, a daylighting sheet or panel 17 is provided on the outer wall portion of the turbine building 1 using the main pillars 5 and the main beams 6.
【0029】一方、タービン建屋マット4の工事はター
ビン建屋1を構成する主柱5,主梁6となる鉄骨の建方
完了後、あるいは完了前に適時行われる。なお、図1お
よび図2においては、鉄骨建方完了後にマット4を打設
した例を示している。この時、岩検は完了しており、タ
ービン建屋の基礎となる岩盤2は前述の従来の工法で述
べたように、人工的な岩盤(MMR)3を打設する場合
もある。On the other hand, the construction of the turbine building mat 4 is performed after the completion of the erection of the steel frames to be the main pillars 5 and the main beams 6 constituting the turbine building 1, or before completion. 1 and 2, an example in which the mat 4 is placed after the steel frame construction is completed is shown. At this time, the rock inspection has been completed, and the bedrock 2 that forms the basis of the turbine building may be placed with the artificial bedrock (MMR) 3 as described in the conventional construction method.
【0030】つぎに図3(b)に示すようにタービン建
屋を構成する主柱5,社梁6および屋根16が完成すると
走行レール18が設置され、この走行レール18に天井走行
クレーン14が搭載され、稼働する。この時、天井走行ク
レーン14の走行レール18はタービン建屋1の外部に設置
された荷取り(荷受けまたは荷捌き)エリア19まで延長
される。また、この荷取りエリア19は、雨,風等の天候
の影響を防ぐため、荷取りエリアの仮設壁,屋根20等で
覆設され、必要に応じて採光性シートまたはパネル17を
覆設する。Next, as shown in FIG. 3 (b), when the main pillar 5, the company beam 6 and the roof 16 constituting the turbine building are completed, a traveling rail 18 is installed, and an overhead traveling crane 14 is mounted on the traveling rail 18. Is up and running. At this time, the traveling rails 18 of the overhead traveling crane 14 are extended to the load-collecting (load-receiving or handling) area 19 installed outside the turbine building 1. In addition, in order to prevent the influence of weather such as rain and wind, the loading area 19 is covered with a temporary wall in the loading area, the roof 20, etc., and a lighting sheet or panel 17 is covered as necessary. .
【0031】一方、天井走行クレーンが稼働すると、図
4(a)に示すように天井走行クレーン14はタービン建
屋1の床や壁等の構築物の建築工事およびタービン建屋
1に設置される搬入機器・配管等7の機電工事の搬入,
据付工事に使用される。またこの時、図1に示すように
機電設備の搬入の形態は、タービン建屋内部の各エリア
において床,壁建築工事が開始する時期ということで、
主に機器・配管先行搬入の形態がとられる。On the other hand, when the overhead traveling crane operates, the overhead traveling crane 14, as shown in FIG. 4A, is used for the construction work of the structure such as the floor or wall of the turbine building 1 and the carrying-in equipment / pipes installed in the turbine building 1. Carrying in 7 mechanics, etc.,
Used for installation work. In addition, at this time, as shown in FIG. 1, the form of carrying in the mechanical and electrical equipment is that the floor and wall construction work starts in each area of the turbine building interior,
Mainly, equipment and piping are pre-loaded.
【0032】タービン建屋の各エリアにおいては床,壁
工事等の建築工事が行われ、ある程度完了したエリア毎
に機電工事側の機械・電気工事を開始するという、いわ
ゆるエリア引き渡しが行われ、本格的な機器据付、配管
布設等の機電工事がその他のエリアのタービン建屋建築
工事と並行して行われる。In each area of the turbine building, construction work such as floor and wall work is performed, and mechanical and electrical work on the mechanical and electrical work side is started in each completed area. Electrical and electrical work such as equipment installation and pipe laying will be performed in parallel with turbine building construction work in other areas.
【0033】つぎに、図4(a)に示すように中央マッ
ト部にはT/Gペデスタル11が立ち上げられ、T/Gペ
デスタル11の工事の完了を待って、復水器12の据付工事
が行われ、その後、図4(b)に示すようにタービン・
発電機13の組立,調整へと機電工事は進み、燃料装荷ま
でに工事を完了させる。Next, as shown in FIG. 4 (a), the T / G pedestal 11 is started up in the central mat portion, and after the completion of the construction of the T / G pedestal 11, the condenser 12 is installed. Then, as shown in FIG. 4 (b), the turbine
The electromechanical work proceeds to the assembly and adjustment of the generator 13, and the work is completed before the fuel is loaded.
【0034】しかして、本実施の形態によれば、天井走
行クレーン14の早期搭載,稼働によりタービン建屋構築
物の建設および設置されるタービン,発電機,復水器,
その他の据付工事に建設の初期の段階から有効に利用で
き、大型揚重機の使用および費用を低減できる。また、
建屋を構成する主柱や主梁を使用して建屋外壁部を覆う
ことで外部の影響を低減できる。Therefore, according to the present embodiment, the turbine, the generator, the condenser, which is constructed and installed in the turbine building structure by the early loading and operation of the overhead traveling crane 14,
It can be effectively used for other installation work from the early stage of construction, and the use and cost of large lifting machines can be reduced. Also,
It is possible to reduce external influences by covering the exterior wall of the building using the main columns and main beams that make up the building.
【0035】つぎに図5(a),(b)および図6
(a),(b)により本発明に係る原子力発電所タービ
ン建屋の第2の実施の形態を説明する。なお、図5およ
び図6においては図2および図4と同一部分には同一符
号を付して重複する部分の説明は省略する。Next, FIGS. 5 (a), 5 (b) and 6
A second embodiment of a nuclear power plant turbine building according to the present invention will be described with reference to (a) and (b). In FIGS. 5 and 6, the same parts as those in FIGS. 2 and 4 are designated by the same reference numerals, and the description of the overlapping parts will be omitted.
【0036】なお、図5(a)は第2の実施の形態にお
ける鉄骨建方完了後の状態、図5(b)は同じく走行レ
ール18に天井走行クレーン14を搭載完了後の状態、図6
(a)は図5(a)から機電設備搬入および機電工事開
始の状態、図6(b)はタービン・発電機据付完了後の
状態を示す概略断面図である。FIG. 5 (a) is a state after the steel frame construction is completed in the second embodiment, FIG. 5 (b) is a state after the overhead traveling crane 14 is similarly mounted on the traveling rail 18, and FIG.
FIG. 6A is a schematic cross-sectional view showing a state of carrying in the mechanical and electrical equipment and starting the mechanical and electrical work from FIG. 5A, and FIG. 6B is a state after completion of the turbine / generator installation.
【0037】図5(a)において、主柱5,主梁6およ
び壁,屋根等16の鉄骨建方完了と同じくして荷取りエリ
ア床21を地面(G.L)と同レベルに設置する。荷取り
エリア床21は主柱5および主梁6によって支えられてい
る。図5(b)に示すように荷取りエリア床21にはトラ
ック等の車輌22が走行する。車輌22には搬入機器配管等
7を積載し、荷取りエリア内部23まで走行する。In FIG. 5A, the loading area floor 21 is installed at the same level as the ground (GL) in the same manner as the completion of the steel frame erection of the main pillars 5, the main beams 6 and the walls, the roof 16 and the like. . The loading area floor 21 is supported by the main columns 5 and the main beams 6. As shown in FIG. 5B, a vehicle 22 such as a truck runs on the floor 21 of the loading area. Carry-on equipment pipes 7 and the like are loaded on the vehicle 22 and run to the inside 23 of the unloading area.
【0038】すなわち、本実施の形態は第1の実施の形
態と同様にタービン建屋1の工事着工後、直ちぐにター
ビン建屋の主柱5,主梁6となる鉄骨および屋根16を立
ち上げ、図5(b)に示すように走行レール18を設置
し、早期に天井走行クレーン14を搭載,稼働させる。That is, in this embodiment, as in the case of the first embodiment, immediately after the construction of the turbine building 1 is started, the steel frame and the roof 16 which will be the main pillars 5 and the main beams 6 of the turbine building are immediately raised, As shown in FIG. 5B, the traveling rail 18 is installed, and the overhead traveling crane 14 is installed and operated at an early stage.
【0039】つぎに、タービン建屋1の外部に設置した
荷取りエリア19をタービン建屋1を構成する主柱5,主
梁6となる鉄骨を利用して図6(a)に示すように走行
クレーン14の可動範囲内に早期より車輌22の乗り込みが
できる荷取りエリア床21を本設あるいは仮設により構築
する。荷取りエリア内部23はタービン建屋1の内部にま
でわたって設けられる。Next, in the loading area 19 installed outside the turbine building 1, a traveling crane is used as shown in FIG. 6 (a) by utilizing the steel frames which are the main pillars 5 and the main beams 6 constituting the turbine building 1. A unloading area floor 21 that allows vehicles 22 to be loaded into the movable range of 14 from an early stage is constructed by permanent construction or temporary construction. The inside 23 of the loading area extends to the inside of the turbine building 1.
【0040】以下、第1の実施例の形態と同様に図6
(b)に示す工事を行い燃料装荷までに完了させる。本
実施の形態は荷取りエリア床21をタービン建屋1内に延
長して設け、車輌22をタービン建屋1内に走行できるよ
うにして搬入機器配管等7を運搬できるようにしたこと
にあり、その他の作用効果は第1の実施例に準じている
ので、その説明は省略する。Hereinafter, as in the case of the first embodiment, FIG.
The work shown in (b) will be performed and completed by loading fuel. In the present embodiment, the loading area floor 21 is provided so as to extend inside the turbine building 1 so that the vehicle 22 can travel inside the turbine building 1 so that the carrying-in equipment pipes 7 can be carried. Since the function and effect of are similar to those of the first embodiment, the description thereof will be omitted.
【0041】[0041]
【発明の効果】本発明によれば、原子力発電所のタービ
ン建屋を構成する主柱や主梁となる鉄骨,屋根をタービ
ン建屋を構成する床や壁よりも先行して組み立て、ター
ビン建屋建設の初期段階から天井走行クレーンを搭載,
稼働させることによりタービン建屋の床や壁等の構築物
の建設およびタービン建屋に設置されるタービン・発電
機および付属設備などの据付工事に、タービン建屋の建
設初期の段階から天井走行クレーンを使用することがで
きる。According to the present invention, the main pillars and the main beams constituting the turbine building of the nuclear power plant, the roof and the roof are assembled prior to the floors and walls of the turbine building, and the initial construction of the turbine building is completed. Equipped with overhead traveling crane from the stage,
It is possible to use an overhead traveling crane from the initial stage of construction of the turbine building for construction of structures such as floors and walls of the turbine building and installation of turbines / generators and auxiliary equipment installed in the turbine building by operating the turbine building. it can.
【0042】これにより、従来の工法で使用していた機
電設備搬入用の大型揚重機の準備およびその費用が不要
となり、その結果、大型揚重機設置のために必要とされ
た組立,解体スペースは不要となる。また、タービン建
屋建築工事用と機電工事用の大型揚重機の干渉も発生す
ることがなくなる。そして、機器搬入の際の地耐圧は、
機械設備およびその積載車輌または、コロ引き時等の耐
力のみとなり、よって構台の補強も不要となる。This eliminates the need for the preparation and cost of a large-sized lifting machine for carrying in the mechanical and electrical equipment used in the conventional construction method. As a result, the assembly and dismantling space required for the installation of the large-sized lifting machine is reduced. It becomes unnecessary. Further, the interference between the large-scale lifting machine for the turbine building construction work and the electric machinery work will not occur. And the earth pressure at the time of equipment loading is
Only the mechanical equipment and its loading vehicle, or the proof stress at the time of rolling the roller, etc., and therefore the reinforcement of the gantry are not necessary.
【0043】天井走行クレーンを使用する際、搬入物の
荷取りのためには、天井走行クレーンの走行レールを荷
取り可能な位置まで延長し、仮設の壁および屋根を構築
することで雨,風等の天候の影響を防ぐことができる荷
取り(または荷受け、荷捌き)エリアを外部に設置する
か、またはタービン建屋を構成する主柱,主梁を利用し
て、タービン建屋内部の天井走行クレーンの稼働範囲内
に早期より車輌等の乗り込みのできる床を本設あるいは
仮設にて構築する。これにより、いずれの場合も雨,風
等の天候に左右されることなく機電設備の搬入・据付工
事等の作業を行うことができる。When using the overhead traveling crane, in order to unload the cargo, it is necessary to extend the traveling rail of the overhead traveling crane to a position where it can be loaded and construct a temporary wall and roof to prevent rain and wind. An overhead traveling crane inside the turbine building using a main pillar and a main beam that make up the turbine building by installing a unloading (or receiving and handling) area that can prevent the effects of weather, etc. A floor where vehicles can be boarded from the early stage within the operating range will be constructed by permanent construction or temporary construction. As a result, in any case, it is possible to carry out work such as carrying-in / installation work of the electric / mechanical equipment without being affected by weather such as rain and wind.
【0044】さらに、タービン建屋を構成する主柱や主
梁となる鉄骨を利用して、タービン建屋外壁部を覆設シ
ートまたはパネル等を用いて覆設することで建屋内作業
および搬入した機電設備の養生において、雨,風,外気
温度等の天候の影響を緩和することができる。特に寒冷
地においては外気との遮断ができることから、作業環境
の向上も図れる。また、この時、採光性の良い覆設材を
用いることで太陽光で作業をすることもできる。Further, by using steel frames which are main pillars and main beams constituting the turbine building, the turbine building outdoor wall portion is covered with a covering sheet or panel, etc. to carry out the work inside the building and carry-in electrical equipment. In curing, the effects of weather such as rain, wind, and outside temperature can be mitigated. Especially in a cold region, the work environment can be improved because the air can be shielded from the outside air. At this time, it is also possible to work with sunlight by using a covering material with good lighting properties.
【図1】本発明に係る原子力発電所タービン建屋の建設
工法の第1の実施の形態を説明するための工程図。FIG. 1 is a process diagram for explaining a first embodiment of a construction method for a turbine building of a nuclear power plant according to the present invention.
【図2】図1の工程により構築される建設中のタービン
建屋を示す概略断面図。FIG. 2 is a schematic cross-sectional view showing a turbine building under construction constructed by the process of FIG.
【図3】(a)は図1の工程において、岩盤上に全天候
鉄骨材を組立てた鉄骨建方後の状態を示す概略断面図、
(b)は同じく走行レールに天井クレーン搭載完了後の
状態を示す概略断面図。FIG. 3 (a) is a schematic cross-sectional view showing a state after the steel frame is erected by assembling the weatherproof steel aggregate on the rock in the step of FIG.
FIG. 6B is a schematic sectional view showing a state after the overhead crane is completely mounted on the traveling rail.
【図4】(a)は図1の工程において、機電設備搬入お
よび機電工事開始の状態を示す概略断面図、(b)は同
じくタービン・発電機据付完了後の状態を示す概略断面
図。4 (a) is a schematic cross-sectional view showing a state of carrying in mechano-electric equipment and starting mechanic work in the step of FIG. 1, and FIG. 4 (b) is a schematic cross-sectional view showing a state after completion of installation of the turbine / generator.
【図5】(a)は本発明に係る原子力発電所タービン建
屋の建設工法の第2の実施の形態を説明するためのター
ビン建屋の鉄骨建方完了後の状態を示す断面図、(b)
は同じく走行レールに天井走行クレーン搭載完了後の状
態を示す概略断面図。5A is a cross-sectional view showing a state after completion of steel frame erection of a turbine building for explaining a second embodiment of a construction method for a nuclear power plant turbine building according to the present invention; FIG.
Is a schematic cross-sectional view showing a state after the overhead traveling crane is completely mounted on the traveling rail.
【図6】(a)は図5(b)から引き続き、機電設備搬
入および機電工事開始の状態をも示す概略断面図、
(b)は同じくタービン・発電機据付完了後の状態を示
す概略断面図。FIG. 6 (a) is a schematic cross-sectional view showing the state of carrying in mechanic equipment and starting mechanic work, continuing from FIG.
FIG. 3B is a schematic sectional view showing a state after the completion of the turbine / generator installation.
【図7】従来の原子力発電所タービン建屋の建設工法を
説明するための工程図。FIG. 7 is a process diagram for explaining a conventional construction method for a nuclear power plant turbine building.
【図8】(a)は図7の工程において岩盤掘削からター
ビン建屋マットを敷設したマット工事および初期の建築
工事の状態を示す概略断面図、(b)は同じく大型揚重
機による機械,電気設備搬入状態を示す概略断面図、
(c)は同じく天井クレーン稼働後の状態を示す概略断
面図。8 (a) is a schematic cross-sectional view showing a state of a mat construction in which a rock building is laid from a rock excavation mat and an initial construction work in the process of FIG. 7, and FIG. A schematic cross-sectional view showing a loading state,
(C) is a schematic sectional view showing a state after the operation of the overhead crane.
1…タービン建屋、2…岩盤、3…人工的な岩盤(MM
R)、4…マット、5…主柱、6…主梁、7…搬入機器
・配管等、8…タワークレーン、9…クローラクレー
ン、10…構台、11…タービン・発電機基礎台(T/Gペ
デスタル)、12…復水器、13…タービン・発電機、14…
天井走行クレーン、15…オペレーティングフロア、16…
壁,屋根等、17…採光性シートまたはパネル、18…走行
レール、19…荷取りエリア、20…荷取りエリアの仮設
壁,屋根、21…荷取りエリア床、22…車輌、23…荷取り
エリア内部。1 ... Turbine building, 2 ... Bedrock, 3 ... Artificial bedrock (MM
R), 4 ... Mat, 5 ... Main pillar, 6 ... Main beam, 7 ... Carry-in equipment / piping, 8 ... Tower crane, 9 ... Crawler crane, 10 ... Stand, 11 ... Turbine / generator foundation stand (T / G pedestal), 12 ... condenser, 13 ... turbine / generator, 14 ...
Overhead traveling crane, 15 ... Operating floor, 16 ...
Walls, roofs, etc. 17… Lighting sheets or panels, 18… Traveling rails, 19… Loading area, 20… Temporary walls and roofs in the loading area, 21… Loading area floors, 22… Vehicles, 23… Loading Inside the area.
Claims (6)
主柱や主梁となる鉄骨および屋根を、タービン建屋を構
成する床や壁よりも先行して組み立てるとともに、前記
タービン建屋建設の初期段階から天井走行クレーンを走
行レールに搭載し稼働させることを特徴とする原子力発
電所タービン建屋の建設工法。1. A main pillar and a main beam constituting a turbine building of a nuclear power plant, a steel frame and a roof are assembled prior to a floor or a wall constituting the turbine building, and the ceiling is constructed from the initial stage of the construction of the turbine building. A construction method for a turbine building of a nuclear power plant characterized by mounting a traveling crane on a traveling rail and operating it.
建設およびタービン建屋に設置されるタービンや発電機
および付属設備などの据付工事に、タービン建屋建設の
初期段階から天井走行クレーンを使用することを特徴と
する請求項1記載の原子力発電所タービン建屋の建設工
法。2. The use of an overhead traveling crane from the initial stage of turbine building construction for construction of structures such as floors and walls of the turbine building and installation of turbines, generators and auxiliary equipment installed in the turbine building. The construction method for a nuclear power plant turbine building according to claim 1.
載した天井走行クレーンの走行レールをタービン建屋の
外部に延長し、荷取りエリアをタービン建屋外部に設置
することを特徴とする請求項1記載の原子力発電所ター
ビン建屋の建設工法。3. The traveling rail of an overhead traveling crane installed from the initial stage of the construction of the turbine building is extended to the outside of the turbine building, and the unloading area is installed outside the turbine building. Construction method for a turbine building of a nuclear power plant.
利用して、天井走行クレーンの稼働範囲内に車両が乗込
みできる床を本設または仮設し、荷取りエリアをタービ
ン建屋内部に設置することを特徴とする請求項1記載の
原子力発電所タービン建屋の建設工法。4. The steel frame serving as the main pillars and main beams constructed as described above is used to permanently or temporarily install a floor on which a vehicle can be loaded within an operating range of an overhead traveling crane, and a loading area is provided inside a turbine building. The method for constructing a turbine building of a nuclear power plant according to claim 1, wherein
使用して、タービン建屋外壁部を覆うことを特徴とする
請求項1記載の原子力発電所タービン建屋の建設工法。5. The method for constructing a turbine building of a nuclear power plant according to claim 1, wherein an outer wall of the turbine building is covered by using the steel frame that serves as the main pillar or main beam that has been constructed.
トまたはパネルで覆うことを特徴とする請求項1記載の
原子力発電所タービン建屋の建設工法。6. The construction method for a turbine building of a nuclear power plant according to claim 1, wherein an outer wall portion of the turbine building is covered with a daylighting sheet or panel.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8094953A JPH09281268A (en) | 1996-04-17 | 1996-04-17 | Nuclear power plant turbine building construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8094953A JPH09281268A (en) | 1996-04-17 | 1996-04-17 | Nuclear power plant turbine building construction method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH09281268A true JPH09281268A (en) | 1997-10-31 |
Family
ID=14124314
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP8094953A Pending JPH09281268A (en) | 1996-04-17 | 1996-04-17 | Nuclear power plant turbine building construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH09281268A (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102184747A (en) * | 2011-03-18 | 2011-09-14 | 山东核电设备制造有限公司 | Modular steel containment vessel annular hanging beam and assembling method thereof |
| CN102184748A (en) * | 2011-03-18 | 2011-09-14 | 山东核电设备制造有限公司 | Integrated steel containing vessel annular suspension beam and assembling method thereof |
| CN106939642A (en) * | 2017-04-25 | 2017-07-11 | 中国建筑第八工程局有限公司 | Under hanging packway davit structure and its installation forming method |
| JP2019015077A (en) * | 2017-07-06 | 2019-01-31 | 大成建設株式会社 | Building construction method |
-
1996
- 1996-04-17 JP JP8094953A patent/JPH09281268A/en active Pending
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102184747A (en) * | 2011-03-18 | 2011-09-14 | 山东核电设备制造有限公司 | Modular steel containment vessel annular hanging beam and assembling method thereof |
| CN102184748A (en) * | 2011-03-18 | 2011-09-14 | 山东核电设备制造有限公司 | Integrated steel containing vessel annular suspension beam and assembling method thereof |
| CN106939642A (en) * | 2017-04-25 | 2017-07-11 | 中国建筑第八工程局有限公司 | Under hanging packway davit structure and its installation forming method |
| CN106939642B (en) * | 2017-04-25 | 2019-05-10 | 中国建筑第八工程局有限公司 | Under hanging riding track davit structure and its installation forming method |
| JP2019015077A (en) * | 2017-07-06 | 2019-01-31 | 大成建設株式会社 | Building construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP0480683A1 (en) | Erection workbench and construction process | |
| EP4100595B1 (en) | Modular structure for providing on-site protection | |
| CN109025388B (en) | A construction device and construction method for a movable and expandable canopy that can be opened | |
| CN115749298A (en) | Construction method for steel structure of main body of high-speed rail station house | |
| JPH07292986A (en) | Long span roof construction equipment and construction method | |
| JP3078805B1 (en) | Construction method of nuclear power facilities | |
| JP3212233B2 (en) | Power plant construction method using overhead crane | |
| CN107503522A (en) | Portable suitable for metro station construction covers canopy and construction method | |
| JPH0782897A (en) | All weather type building method of building | |
| JP2011052512A (en) | Roof repair construction method and structure | |
| JP3888564B2 (en) | Construction method of underground structure | |
| JPH01263334A (en) | Core part precedence type construction method | |
| JP2779998B2 (en) | Lifting device for temporary tents | |
| JP3212231B2 (en) | Plant construction method and construction equipment | |
| JP6893134B2 (en) | Building construction method | |
| JPH05171817A (en) | Temporary house for all-weather type execution | |
| JP2638725B2 (en) | Construction method of refuse incinerator facilities | |
| JP2000098079A (en) | Nuclear power plant construction method | |
| JPS62228974A (en) | Method of construction of housing for nuclear power plant | |
| JPH08218628A (en) | Construction of roof for cylindrical structure | |
| CN206521967U (en) | A kind of Novel mobile communication base station computer room | |
| JP3290307B2 (en) | Building with curing roof | |
| JPH06307097A (en) | Opening/closing type film roof structure for curing | |
| JPH0112889B2 (en) | ||
| JP2522494B2 (en) | Nuclear power plant construction method |