JPH0941494A - Construction method of building structure - Google Patents

Construction method of building structure

Info

Publication number
JPH0941494A
JPH0941494A JP21552795A JP21552795A JPH0941494A JP H0941494 A JPH0941494 A JP H0941494A JP 21552795 A JP21552795 A JP 21552795A JP 21552795 A JP21552795 A JP 21552795A JP H0941494 A JPH0941494 A JP H0941494A
Authority
JP
Japan
Prior art keywords
diagonal
truss
temporary support
core portion
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP21552795A
Other languages
Japanese (ja)
Other versions
JP3546225B2 (en
Inventor
Masaki Ikeda
正基 池田
Mitsushi Suda
充司 須田
Kenichi Akiba
堅一 秋場
Osamu Yoda
修 依田
Akira Tanabe
昭 田邊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP21552795A priority Critical patent/JP3546225B2/en
Publication of JPH0941494A publication Critical patent/JPH0941494A/en
Application granted granted Critical
Publication of JP3546225B2 publication Critical patent/JP3546225B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To stabilize a frame under erection particularly to wind and horizontal force at the time of an earthquake and heighten construction accuracy. SOLUTION: A steel framed core part 1 supports a support base end part 2a of a truss beam 2. A shed 3 corresponding to the application of an observatory, a restaurant or the like is constructed on the upper part of the truss beam 2. A diagonal truss 4 is built up diagonally between the base part of the steel framed core part 1 and a free tip part 2b of the truss beam 2 so as to support the free tip parts of the truss beam 2 and shed 3. A diagonal member 5 formed of a pipe or the like is built up in such a way as to intersect the middle part of the diagonal truss 4 and to be integrally connected thereto, with the upper end part connected to the upper end part of the steel framed core part 1.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、建築構造物、特に大規
模な片持梁形式の建築構造物を構築する方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a building structure, particularly a large-scale cantilever type building structure.

【0002】[0002]

【従来の技術】一般に、大規模な片持梁形式の建築構造
物は、梁状建築部分の下方にこれを支持するための構造
物を構築する土地や空間が確保できない場合や、博覧会
等のイベント会場に斬新な建築物として構築される場合
が多く、不安定な構造であるため、特に構築方法に工夫
を要する。
2. Description of the Related Art Generally, a large-scale cantilever type building structure cannot be secured when a land or space for constructing a structure for supporting the cantilever beam structure can be secured below the beam-shaped building portion or at an exhibition or the like. In many cases, it is constructed as a novel building at the event venue, and the structure is unstable.

【0003】従来、この種の建築構造物の構築方法とし
ては、仮設の支柱や構台により支持しながら1部材ずつ
組み立てる工法が採用されていた。
Conventionally, as a method of constructing this type of building structure, a method of assembling one member at a time while supporting it by a temporary support column or a gantry has been adopted.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、上記従
来の構築方法は、次のような解決すべき課題を有してい
る。 1)途中段階の架構が非常に不安定になり、また、小部
材を高所で組み立てるので、作業能率が悪く、しかも建
物の精度を確保することが難しい。 2)仮設支柱頂部と建築構造物との取合い部や仮設支柱
脚部にピンローラーを設けているため、水平力を負担す
ることができず、その結果、架構が不安定になり易い。
従って、水平力を負担するためのトラワイヤー等を張る
場所が確保できない場合が多い。 3)斜材により梁状建築部分を支持させる場合が多い
が、該斜材の組み立て及び組み付け作業用の吊足場が設
置し難い。
However, the above-mentioned conventional construction method has the following problems to be solved. 1) The frame in the middle of the process becomes very unstable, and since small members are assembled at high places, work efficiency is poor and it is difficult to secure the accuracy of the building. 2) Since a pin roller is provided at the connection between the top of the temporary support column and the building structure or the leg of the temporary support column, horizontal force cannot be applied, and as a result, the frame tends to become unstable.
Therefore, in many cases, it is not possible to secure a place to stretch a traverse wire or the like to bear the horizontal force. 3) In many cases, the beam-like building part is supported by diagonal members, but it is difficult to install a suspension scaffold for assembling and assembling the diagonal members.

【0005】本発明は、上記従来の課題を解決するため
になされたもので、その目的とするところは、建方中の
架構を特に風や地震時の水平力に対して安定させると共
に、施工精度を高めることができ、特に斜めトラス用の
足場の取付・撤去作業の安全性と、該足場による構築
(本締・溶接・塗装等)作業の安全性や作業能率を向上
させることができる建築構造物の構築方法を提供するこ
とにある。
The present invention has been made in order to solve the above-mentioned conventional problems, and an object thereof is to stabilize the frame structure during construction, particularly against wind and horizontal force during an earthquake, and to carry out construction. Construction that can improve accuracy, especially the safety of work for attaching and removing scaffolds for diagonal trusses, and the safety and work efficiency of construction (main tightening, welding, painting, etc.) work using the scaffolds It is to provide a method for constructing a structure.

【0006】[0006]

【課題を解決するための手段】本発明の建築構造物の構
築方法は、コア部を所定高さに構築し、該コア部の構築
作業と並行あるいは前後して中間仮設支柱を立設し、該
中間仮設支柱に関して上記コア部の反対側に位置する基
盤から該コア部の上端部に向けて斜材を建て込むと共に
該斜材を上記中間仮設支柱の頂部に接続固定し、上記コ
ア部の基部から上記斜材と交差するように斜めトラスを
建て込むと共に上記中間仮設支柱の頂部に接続固定し、
上記斜材や斜めトラスの建て込み作業と並行あるいは前
後して上記斜材の基部付近から端部仮設支柱を立設して
その頂部に上記斜めトラスの上端部を接続固定し、さら
に上記コア部の上端部と斜めトラスの上端部の間にトラ
ス梁を組み付け、該トラス梁の上部に上屋を構築し、最
後に上記中間仮設支柱および端部仮設支柱の頂部を上記
斜材および斜めトラスから切り離して撤去することを特
徴とする。上記コア部は、鉄骨造、鉄筋コンクリート
造、鉄骨鉄筋コンクリート造等いずれの構造であっても
よい。また、上記中間仮設支柱あるいは上記端部仮設支
柱の頂部にジャッキボックスを設けて介挿部材を介して
上記斜材あるいは斜めトラスを接続固定し、上記切り離
し撤去作業の際に、上記ジャッキボックスの間にジャッ
キおよびキャンバーを設置して、該ジャッキを伸縮操作
しながら上記介挿部材の背丈およびキャンバーの枚数を
交互に順次低くあるいは減じて切り離しを行うことも特
徴とする。さらに、上記斜めトラスを地組みする際に足
場を取り付けることも特徴とする。
A method for constructing a building structure according to the present invention comprises constructing a core portion at a predetermined height and arranging an intermediate temporary support column in parallel with or before or after the construction work of the core portion. A diagonal member is built from the base located on the opposite side of the core portion with respect to the intermediate temporary support column toward the upper end of the core portion, and the diagonal member is connected and fixed to the top of the intermediate temporary support column. Build a diagonal truss from the base so as to intersect with the diagonal member, and connect and fix it to the top of the intermediate temporary column,
In parallel with or before or after the work of building the diagonal member or diagonal truss, an end temporary support pillar is erected from the vicinity of the base of the diagonal member, and the upper end of the diagonal truss is connected and fixed to the top of the pillar, and the core portion is further added. The truss beam is assembled between the upper end of the diagonal truss and the upper end of the diagonal truss, and a shed is constructed on the upper part of the truss beam, and finally the tops of the intermediate temporary support column and the end temporary support column are separated from the diagonal member and the diagonal truss. It is characterized by separating and removing. The core portion may have any structure such as a steel frame structure, a reinforced concrete structure, or a steel frame reinforced concrete structure. In addition, a jack box is provided on the top of the intermediate temporary support pillar or the end temporary support pillar to connect and fix the diagonal member or the diagonal truss via an interposing member, and the space between the jack boxes during the detaching and removing work. It is also characterized in that a jack and a camber are installed in the jack and the height of the insertion member and the number of the camber are alternately lowered or reduced while performing the expansion and contraction of the jack to perform the separation. Further, it is also characterized in that a scaffold is attached when the diagonal truss is grounded.

【0007】[0007]

【実施例】以下、本発明の一実施例について図面を参照
しながら説明する。図1において、1は鉄骨コア部であ
って、トラス梁2の支持基端部2aを支持する。該鉄骨
コア部1は、エレベータや非常階段等の移動用空間、及
び設備配管等のサービス空間を提供する。1aは上記鉄
骨コア部1の基礎部である。上記トラス梁2の上部に
は、上屋3が構築されている。該上屋3は展望室やレス
トラン等の使用目的に応じた利用空間を提供する。な
お、上記鉄骨コア部1は、これに限定するものではな
く、鉄筋コンクリートコア部、鉄骨鉄筋コンクリートコ
ア部等であってもよい。
An embodiment of the present invention will be described below with reference to the drawings. In FIG. 1, reference numeral 1 is a steel frame core portion, which supports a support base end portion 2 a of the truss beam 2. The steel core portion 1 provides a moving space such as an elevator and an emergency staircase, and a service space such as facility piping. Reference numeral 1a is a base portion of the steel core portion 1. A shed 3 is constructed above the truss beam 2. The shed 3 provides a use space according to the purpose of use such as an observation room and a restaurant. The steel core portion 1 is not limited to this, and may be a reinforced concrete core portion, a steel reinforced concrete core portion, or the like.

【0008】4は斜めトラスであって、上記鉄骨コア部
1の基部とトラス梁2の自由先端部2bとの間に斜めに
建込まれ、上記トラス梁2及び上屋3の自由先端部を支
持している。5はパイプ等より成る斜材であって、上記
斜めトラス4の中間部と交差して、これに一体的に連結
されると共に、その上端部は上記鉄骨コア部1の上端部
に連結するように建込まれている。Gは基盤である。
Reference numeral 4 denotes an oblique truss, which is installed obliquely between the base of the steel frame core 1 and the free tip 2b of the truss beam 2 so that the free tips of the truss beam 2 and the shed 3 are connected to each other. I support you. Reference numeral 5 denotes a diagonal member made of a pipe or the like, which intersects with the intermediate portion of the diagonal truss 4 and is integrally connected thereto, and its upper end portion is connected to the upper end portion of the steel frame core portion 1. Built in. G is the foundation.

【0009】次に、上記実施例の建築構造物の構築方法
について説明する。まず、図2に示すように、鉄骨コア
部1を低層部から構築する。本実施例においては、鉄骨
コア部1の各節部分を地組して、1節ずつ吊り上げて組
み上げ接続することにより構築する。該鉄骨コア部1の
構築作業と並行あるいは前後して中間仮設支柱6を設置
する。
Next, a method of constructing the building structure of the above embodiment will be described. First, as shown in FIG. 2, the steel frame core portion 1 is constructed from the lower layer portion. In this embodiment, each node of the steel core portion 1 is grounded, and the nodes are lifted one by one and assembled and connected. The intermediate temporary support column 6 is installed in parallel with or before or after the construction work of the steel frame core portion 1.

【0010】続いて、図3に示すように、上記斜材5の
下半部を建て込む。該斜材5の基部は上記基盤Gに定着
せしめ、上部は上記中間仮設支柱6の頂部に支持せしめ
る。
Subsequently, as shown in FIG. 3, the lower half of the diagonal member 5 is built. The base of the diagonal member 5 is fixed to the base G, and the upper portion is supported on the top of the intermediate temporary support column 6.

【0011】さらに、図4に示すように、上記斜めトラ
ス4の下半部を建て込む。該斜めトラス4の基部は上記
鉄骨コア部1の基部に連結せしめ、上部は上記中間仮設
支柱6の頂部に支持せしめる。
Further, as shown in FIG. 4, the lower half of the diagonal truss 4 is built. The base portion of the diagonal truss 4 is connected to the base portion of the steel frame core portion 1, and the upper portion is supported on the top portion of the intermediate temporary support column 6.

【0012】図5は、上記中間仮設支柱6の頂部におけ
る、上記斜材5と斜めトラス4の支持状態を示すもの
で、これらの斜材5と斜めトラス4の交差連結部分の下
側にジョイント部材6aを一体的に取り付け、該ジョイ
ント部材6aを、上記中間仮設支柱6の頂部に一体的に
取り付けたジャッキボックス6bにより支持している。
図6に拡大して示すように、これらのジャッキボックス
6bとジョイント部材6aの間には、H型鋼からなる介
挿部材6cが介挿されている。該介挿部材6cは、ボル
ト等の固定金具により取外し可能に取り付けられてい
る。
FIG. 5 shows the supporting state of the diagonal member 5 and the diagonal truss 4 at the top of the intermediate temporary support column 6. A joint is provided below the cross-connecting portion of the diagonal member 5 and the diagonal truss 4. The member 6a is integrally attached, and the joint member 6a is supported by the jack box 6b integrally attached to the top of the intermediate temporary column 6.
As shown in an enlarged manner in FIG. 6, an insertion member 6c made of H-shaped steel is inserted between the jack box 6b and the joint member 6a. The insertion member 6c is detachably attached by a fixing member such as a bolt.

【0013】再び、図4において、7は端部仮設支柱で
あって、上記中間仮設支柱6を中心に上記鉄骨コア部1
のほぼ対称位置に設置する。また、上記作業に並行ある
いは前後して上記鉄骨コア部1の上部も構築する。
Referring again to FIG. 4, reference numeral 7 denotes a temporary end support, which is centered around the intermediate temporary support 6 and has the steel core 1
Install at approximately symmetrical positions. Further, the upper part of the steel frame core portion 1 is also constructed in parallel with or before or after the above work.

【0014】次に、図7に示すように、上記斜材5の上
半部を建て込んで、その上端を上記鉄骨コア部1の上端
部に接続する。また、上記斜めトラス4の上半部も建て
込んで、その上端を上記端部仮設支柱7の上端部に接続
する。該端部仮設支柱7の頂部と斜めトラス4との取合
い部も、上記ジョイント部材6a、ジャッキボックス6
b、介挿部材6cと同様の構成により連結支持されてい
る。
Next, as shown in FIG. 7, the upper half of the diagonal member 5 is built up and its upper end is connected to the upper end of the steel frame core 1. Further, the upper half of the diagonal truss 4 is also built in and its upper end is connected to the upper end of the end temporary support column 7. The joint between the apex of the end temporary support column 7 and the diagonal truss 4 is also the joint member 6a and the jack box 6 described above.
It is connected and supported by the structure similar to b and the insertion member 6c.

【0015】続いて、図8に示すように、上記鉄骨コア
部1の上端部と斜めトラス4の上端部の間に、トラス梁
2を構築して、それぞれ一体的に接続する。該トラス梁
2上には上屋3を構築する。
Subsequently, as shown in FIG. 8, a truss beam 2 is constructed between the upper end of the steel frame core 1 and the upper end of the diagonal truss 4, and they are integrally connected to each other. A shed 3 is constructed on the truss beam 2.

【0016】上記建築構造物の構築が完了したら、上記
中間仮設支柱6及び端部仮設支柱7を撤去する。例え
ば、上記中間仮設支柱6を撤去するには、まず、図9に
示すように、上記ジャッキボックス6bの間にジャッキ
8をセットして、キャンバー9を数枚(本実施例では4
枚)載置しておく。
When the construction of the building structure is completed, the intermediate temporary support column 6 and the end temporary support column 7 are removed. For example, in order to remove the intermediate temporary support column 6, first, as shown in FIG. 9, the jack 8 is set between the jack boxes 6b, and several cambers 9 (in this embodiment, 4).
Place one).

【0017】上記準備が完了したら、上記介挿部材6c
をジョイント部材6aから切り離してから、上記ジャッ
キ8を作動させて、図10に示すように、上記キャンバ
ー9を介してジョイント部材6aを僅かに持ち上げる。
その結果、上記介挿部材6cとジョイント部材6aとの
間には、僅かな隙間Sが形成される。
When the above preparation is completed, the interposing member 6c
Is separated from the joint member 6a, the jack 8 is operated, and the joint member 6a is slightly lifted via the camber 9 as shown in FIG.
As a result, a slight gap S is formed between the insertion member 6c and the joint member 6a.

【0018】上記ジャッキアップした状態で、図11に
示すように、上記介挿部材6cをジャッキボックス6b
から切り離して、撤去する。介挿部材6cを撤去したあ
とには、図12に示すように、別の介挿部材6c′をセ
ットして、ジャッキダウウンする。上記介挿部材6c′
は上記介挿部材6cより背丈が低い。
In the jacked up state, as shown in FIG. 11, the insertion member 6c is inserted into the jack box 6b.
Separate from and remove. After removing the insertion member 6c, as shown in FIG. 12, another insertion member 6c 'is set and jack down is performed. The insertion member 6c '
Is shorter than the insertion member 6c.

【0019】次に、上記キャンバー9を1枚取り除いて
から(本実施例では3枚にする)、再び、上記ジャッキ
8を作動させて上記ジョイント部材6aをジャッキアッ
プし、図13に示すように、上記介挿部材6c′からジ
ョイント部材6aを浮かした状態で該介挿部材6c′を
撤去し、そのあとに、図14に示すように、更に別の介
挿部材6c″を介挿させる。該介挿部材6c″は上記介
挿部材6c′より更に背丈が低くなっている。
Next, after removing one camber 9 (three in this embodiment), the jack 8 is actuated again to jack up the joint member 6a, as shown in FIG. The insertion member 6c 'is removed with the joint member 6a floating from the insertion member 6c', and then another insertion member 6c "is inserted as shown in FIG. The insertion member 6c ″ is shorter than the insertion member 6c ′.

【0020】上記ジョイント部材6aは、上記斜めトラ
ス4や斜材5と一体となっているので、以上のジャッキ
ダウン操作を数回繰り返すうちに、上記ジョイント部材
6aの降下が停止する。すなわち、ジョイント部材6a
はジャッキ8で支持しておく必要はなくなり、上記中間
仮設支柱6から完全に切り離される。切り離された中間
仮設支柱6は解体撤去する。なお、上記端部仮設支柱7
も同様にジャッキダウン操作を繰り返して切り離した
後、解体撤去する。
Since the joint member 6a is integrated with the slant truss 4 and the slant member 5, the lowering of the joint member 6a is stopped while the above jack down operation is repeated several times. That is, the joint member 6a
Does not need to be supported by the jack 8, and is completely separated from the intermediate temporary support column 6. The separated intermediate temporary support column 6 is dismantled and removed. In addition, the end temporary support column 7
Similarly, repeat the jack-down operation to separate and then dismantle and remove.

【0021】図15は上記トラス梁4の作業用の足場1
0の取付状態を示すもので、該トラス梁4の地組みの際
に、これに斜め(本実施例では、約45°)に取り付け
られる。各足場10は適宜間隔に平行に配置されてい
て、その一側端部は上部の足場10から吊りチェーン1
0aにより保持されるようになっている。10bは手
摺、11は安全ネットである。
FIG. 15 shows a scaffold 1 for working the truss beam 4 described above.
The installation state of 0 is shown, and the truss beam 4 is obliquely (at this embodiment, about 45 °) attached to the truss beam 4 when it is erected. The scaffolds 10 are arranged in parallel at appropriate intervals, and one side end of the scaffold 10 is suspended from the upper scaffold 10 by the chain 1.
It is held by 0a. 10b is a handrail and 11 is a safety net.

【0022】[0022]

【発明の効果】【The invention's effect】

1)斜材および斜めトラスを仮設支柱の頂部に接続固定
して構築するので、特に水平力に対する架構が非常に安
定し、構築作業の能率および精度が向上する。 2)ジャッキダウンを安定かつ能率良く行うことができ
る。 3)斜めトラスの足場を安全かつ能率良く組み付けるこ
とができる。
1) Since the diagonal member and the diagonal truss are connected and fixed to the top of the temporary support column, the frame structure is extremely stable especially against horizontal force, and the efficiency and accuracy of the construction work are improved. 2) The jack down can be performed stably and efficiently. 3) The scaffold of the diagonal truss can be assembled safely and efficiently.

【図面の簡単な説明】[Brief description of drawings]

【図1】建築構造物の一実施例を示す側面図である。FIG. 1 is a side view showing an embodiment of a building structure.

【図2】図1の建築構造物の構築方法の説明図である。FIG. 2 is an explanatory diagram of a method for constructing the building structure of FIG.

【図3】図2に続く建築構造物の構築方法の説明図であ
る。
FIG. 3 is an explanatory diagram of a method of constructing a building structure subsequent to FIG.

【図4】図3に続く建築構造物の構築方法の説明図であ
る。
FIG. 4 is an explanatory diagram of a method of constructing a building structure subsequent to FIG.

【図5】中間仮設支柱による斜めトラスの支持状態の説
明図である。
FIG. 5 is an explanatory diagram of a supporting state of an oblique truss by an intermediate temporary support column.

【図6】図5の要部の拡大説明図である。FIG. 6 is an enlarged explanatory view of a main part of FIG.

【図7】図4に続く建築構造物の構築方法の説明図であ
る。
FIG. 7 is an explanatory diagram of a method of constructing a building structure following FIG.

【図8】図7に続く建築構造物の構築方法の説明図であ
る。
8 is an explanatory diagram of a method of constructing a building structure following FIG. 7. FIG.

【図9】中間仮設支柱による斜めトラスの支持部におけ
るジャッキダウンの説明図である。
FIG. 9 is an explanatory view of jacking down on a support portion of an oblique truss by an intermediate temporary support column.

【図10】図9に続くジャッキダウンの説明図である。FIG. 10 is an explanatory diagram of jacking down following FIG.

【図11】図10に続くジャッキダウンの説明図であ
る。
FIG. 11 is an explanatory diagram of the jackdown following FIG.

【図12】図11に続くジャッキダウンの説明図であ
る。
FIG. 12 is an explanatory diagram of jacking down following FIG. 11.

【図13】図12に続くジャッキダウンの説明図であ
る。
FIG. 13 is an explanatory diagram of jacking down following FIG.

【図14】図13に続くジャッキダウンの説明図であ
る。
FIG. 14 is an explanatory diagram of jacking down following FIG.

【図15】トラス梁の足場の取付状態を示す説明図であ
る。
FIG. 15 is an explanatory diagram showing a mounting state of the scaffold of the truss beam.

【符号の説明】[Explanation of symbols]

1 鉄骨コア部 1a 基礎部 2 トラス梁 2a 支持基端部 2b 自由先端部 3 上屋 4 斜めトラス 5 斜材 6 中間仮設支柱 6a ジョイント部材 6b ジャッキボックス 6c 介挿部材 6c′介挿部材 6c″介挿部材 7 端部仮設支柱 8 ジャッキ 9 キャンバー 10 足場 10a 吊りチェーン 10b 手摺 11 安全ネット G 基盤 S 隙間 DESCRIPTION OF SYMBOLS 1 Steel core part 1a Foundation part 2 Truss beam 2a Supporting base end part 2b Free tip part 3 Shedhouse 4 Oblique truss 5 Oblique member 6 Intermediate temporary support pillar 6a Joint member 6b Jack box 6c Inserting member 6c 'Inserting member 6c ″ Insert member 7 Temporary end support 8 Jack 9 Camber 10 Scaffold 10a Suspended chain 10b Handrail 11 Safety net G Base S S Gap

フロントページの続き (72)発明者 依田 修 東京都渋谷区渋谷一丁目16番14号 東急建 設株式会社内 (72)発明者 田邊 昭 東京都渋谷区渋谷一丁目16番14号 東急建 設株式会社内Front page continuation (72) Inventor Osamu Yoda 1-16-14 Shibuya, Shibuya-ku, Tokyo Tokyu Construction Co., Ltd. (72) Inventor Akira Tanabe 1-16-14 Shibuya, Shibuya-ku, Tokyo Tokyu Construction Shares In the company

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 コア部を所定高さに構築し、該コア部の
構築作業と並行あるいは前後して中間仮設支柱を立設
し、該中間仮設支柱に関して上記コア部の反対側に位置
する基盤から該コア部の上端部に向けて斜材を建て込む
と共に該斜材を上記中間仮設支柱の頂部に接続固定し、
上記コア部の基部から上記斜材と交差するように斜めト
ラスを建て込むと共に上記中間仮設支柱の頂部に接続固
定し、上記斜材や斜めトラスの建て込み作業と並行ある
いは前後して上記斜材の基部付近から端部仮設支柱を立
設してその頂部に上記斜めトラスの上端部を接続固定
し、さらに上記コア部の上端部と斜めトラスの上端部の
間にトラス梁を組み付け、該トラス梁の上部に上屋を構
築し、最後に上記中間仮設支柱および端部仮設支柱の頂
部を上記斜材および斜めトラスから切り離して撤去する
ことを特徴とする建築構造物の構築方法。
1. A base structure in which a core portion is constructed at a predetermined height, an intermediate temporary support pillar is erected in parallel with or before or after the construction work of the core portion, and the intermediate temporary support pillar is located on the opposite side of the core portion. From the above to the upper end of the core portion of the diagonal member and the diagonal member is connected and fixed to the top of the intermediate temporary support,
The diagonal truss is built from the base of the core portion so as to intersect with the diagonal member, and is connected and fixed to the top of the intermediate temporary support, and the diagonal member is installed in parallel with or before or after the diagonal member or diagonal truss building work. End tentative struts are erected from the vicinity of the base of the above, and the upper end of the diagonal truss is connected and fixed to the top thereof, and a truss beam is assembled between the upper end of the core and the upper end of the diagonal truss. A method for constructing a building structure, comprising constructing a shed on an upper part of a beam, and finally removing the tops of the intermediate temporary support pillar and the end temporary support pillar by separating them from the diagonal member and the diagonal truss.
【請求項2】 上記中間仮設支柱あるいは上記端部仮設
支柱の頂部にジャッキボックスを設けて介挿部材を介し
て上記斜材あるいは斜めトラスを接続固定し、上記切り
離し撤去作業の際に、上記ジャッキボックスの間にジャ
ッキおよびキャンバーを設置して、該ジャッキを伸縮操
作しながら上記介挿部材の背丈およびキャンバーの枚数
を交互に順次低くあるいは減じて切り離しを行うことを
特徴とする請求項1に記載の建築構造物の構築方法。
2. A jack box is provided on the top of the intermediate temporary strut or the end temporary strut to connect and fix the diagonal member or the diagonal truss via an interposing member, and the jack is used in the detaching work. The jack and the camber are installed between the boxes, and the height of the insertion member and the number of the camber are alternately lowered or reduced while performing the expansion and contraction operation of the jack to perform the separation. Construction method of building structure.
【請求項3】 上記斜めトラスを地組みする際に足場を
取り付けることを特徴とする請求項1に記載の建築構造
物の構築方法。
3. The method for constructing a building structure according to claim 1, wherein a scaffold is attached when the diagonal truss is grounded.
JP21552795A 1995-08-02 1995-08-02 How to build building structures Expired - Fee Related JP3546225B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21552795A JP3546225B2 (en) 1995-08-02 1995-08-02 How to build building structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21552795A JP3546225B2 (en) 1995-08-02 1995-08-02 How to build building structures

Publications (2)

Publication Number Publication Date
JPH0941494A true JPH0941494A (en) 1997-02-10
JP3546225B2 JP3546225B2 (en) 2004-07-21

Family

ID=16673907

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21552795A Expired - Fee Related JP3546225B2 (en) 1995-08-02 1995-08-02 How to build building structures

Country Status (1)

Country Link
JP (1) JP3546225B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102022002A (en) * 2009-09-22 2011-04-20 中冶成工上海五冶建设有限公司 Method for transferring hoisting-point loads
CN104975721A (en) * 2014-12-03 2015-10-14 中国航空规划建设发展有限公司 Installing and monitoring method of roof embedded steel beam

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102022002A (en) * 2009-09-22 2011-04-20 中冶成工上海五冶建设有限公司 Method for transferring hoisting-point loads
CN102022002B (en) * 2009-09-22 2016-01-13 五冶集团上海有限公司 Method for transferring hoisting-point loads
CN104975721A (en) * 2014-12-03 2015-10-14 中国航空规划建设发展有限公司 Installing and monitoring method of roof embedded steel beam
CN104975721B (en) * 2014-12-03 2017-02-01 中国航空规划建设发展有限公司 Installing and monitoring method of roof embedded steel beam

Also Published As

Publication number Publication date
JP3546225B2 (en) 2004-07-21

Similar Documents

Publication Publication Date Title
CN112814395B (en) Construction method of suspended steel structure
JPH04111829A (en) Construction method for large span roofs
CN110512523B (en) Construction method of large-span door type upper cross beam split support
CN112482795A (en) Supporting structure of prefabricated concrete structure and construction method
JP2000352017A (en) Bridge construction method
CN206554487U (en) A kind of roofing hanging basket
JP4279189B2 (en) Temporary strut and its construction method
CN115787996A (en) Overhung construction method and overhung frame for super-high building
JP7500408B2 (en) Pre-construction method for interior stairs of buildings
JPH0941494A (en) Construction method of building structure
CN112983013A (en) Construction method of large-span net frame walking frame
JP2950726B2 (en) Construction method of multi-layer suspension structure
JP3303218B2 (en) Reconstruction method
JPH0730637B2 (en) Building demolition method
JP2527686B2 (en) Tower-suspended building construction method
JP3328790B2 (en) High-rise building assembly method
JP7390733B2 (en) Construction method and hollow parts for scaffolding truss beams
CN111042577B (en) Method for dismantling plane-intersected truss
JP2595614Y2 (en) Push-up rack for large span structures
WO2002086250A1 (en) Method of constructing dome, and jig and connection device for constructing dome
JP3115942B2 (en) Building construction method
JPH07259191A (en) All-weather construction method for structures
JPH1046838A (en) Demolition method of building
JP2776140B2 (en) Temporary beam assembly equipment for building construction
CN120331488A (en) A method for installing a steel canopy for a gymnasium with a facade grid and steel truss system

Legal Events

Date Code Title Description
A977 Report on retrieval

Effective date: 20040115

Free format text: JAPANESE INTERMEDIATE CODE: A971007

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040217

RD04 Notification of resignation of power of attorney

Effective date: 20040220

Free format text: JAPANESE INTERMEDIATE CODE: A7424

A521 Written amendment

Effective date: 20040224

Free format text: JAPANESE INTERMEDIATE CODE: A821

A61 First payment of annual fees (during grant procedure)

Effective date: 20040317

Free format text: JAPANESE INTERMEDIATE CODE: A61

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees